JOB NO:SPTL-L&T-AC

HVAC DRAWING SUBMITTAL SCHEDULE / STATUS


DATE: 25.06.21

PROJECT : L&T (S1 BLOCK)

APPROVED / APPROVED WITH SUBMITTED FOR


TOTAL NO OF DRAWINGS RESUBMIT TO BE SUBMITTED INPUT AWAITED
COMMENTS APPROVAL
SUMMARY OF DRAWING
SUBMITTAL STATUS:
26 0 0 26 0 0

Actual receipt date Submission & Approval status(R0)


Sl.N Planned Sub.
Drg Ref. No. DEPENDENCY
o Architectural Date
GFC RCP R0 R1 R2 R3
Layout

Actual sub Date


CHW & CDW Schematic Layout
1 SPTL-L&T-S1-AC-01 28.05.21 29.06.21 Return Date
(High & Low side)
Status
Actual sub Date CHILLER & PUMP,EXPANSION TANK AND
2 SPTL-L&T-S1-AC-02 Plant room layout for Terrace floor 28.05.21 Return Date AIRSEPARATOR GA DWG DETAIL INPUT
Status AWAITED
Actual sub Date
Hvac layout for Basement-1
3 SPTL-L&T-S1-AC-03 28.05.21 30.06.21 Return Date
(Staircase & lobby Pressurization & Lobby Ducting )
Status
Actual sub Date
STP Ducting layout for Basement-1
4 SPTL-L&T-S1-AC-04 28.05.21 Return Date ARCHITECH SECTION DETAIL INPUT AWAITED
Status
Actual sub Date
Hvac layout for Basement-2
5 SPTL-L&T-S1-AC-05 28.05.21 30.07.21 Return Date
(Staircase & lobby Pressurization & Lobby Ducting )
Status
Actual sub Date
Hvac layout for Basement-3
7 SPTL-L&T-S1-AC-06 28.05.21 30.07.21 Return Date
(Staircase & lobby Pressurization & Lobby Ducting )
Status
Actual sub Date
Hvac layout for Basement-4
9 SPTL-L&T-S1-AC-07 28.05.21 30.07.21 Return Date
(Staircase & lobby Pressurization & Lobby Ducting )
Status
Actual sub Date
HVAC Layout for Ground Floor
11 SPTL-L&T-S1-AC-08 28.05.21 03.07.21 Return Date
(AHU room, Toliet ,Staircase & lobby Pressurization)
Status
Actual sub Date
HVAC Layout for First floor
12 SPTL-L&T-S1-AC-09 28.05.21 07.07.21 Return Date
(AHU room, Toliet ,Staircase & lobby Pressurization)
Status
Actual sub Date
HVAC Layout for 2nd floor
13 SPTL-L&T-S1-AC-10 28.05.21 08.07.21 Return Date
(AHU room, Toliet ,Staircase & lobby Pressurization)
Status
Actual sub Date
HVAC Layout for Typical floor -3rd & 4th floor
14 SPTL-L&T-S1-AC-11 28.05.21 09.07.21 Return Date
(AHU room, Toliet ,Staircase & lobby Pressurization)
Status
Actual sub Date
HVAC Layout for 5th floor
15 SPTL-L&T-S1-AC-12 28.05.21 12.07.21 Return Date
(AHU room, Toliet ,Staircase & lobby Pressurization)
Status
Actual sub Date
HVAC Layout for 6th floor
16 SPTL-L&T-S1-AC-13 28.05.21 13.07.21 Return Date
(AHU room, Toliet ,Staircase & lobby Pressurization)
Status
Actual sub Date
HVAC Layout for 7th floor
17 SPTL-L&T-S1-AC-14 28.05.21 14.07.21 Return Date
(AHU room, Toliet ,Staircase & lobby Pressurization)
Status
Actual sub Date
HVAC Layout for 8th floor
18 SPTL-L&T-S1-AC-15 28.05.21 15.07.21 Return Date
(AHU room, Toliet ,Staircase & lobby Pressurization)
Status
Actual sub Date
HVAC Layout for 9th floor
19 SPTL-L&T-S1-AC-16 28.05.21 16.07.21 Return Date
(AHU room, Toliet ,Staircase & lobby Pressurization)
Status
Actual sub Date
HVAC Layout for 10th floor
20 SPTL-L&T-S1-AC-17 28.05.21 17.07.21 Return Date
(AHU room, Toliet ,Staircase & lobby Pressurization)
Status
Actual sub Date
21 SPTL-L&T-S1-AC-18 Equipment layout for Terrace Floor 28.05.21 21.07.21 Return Date
Status
Actual sub Date
Staircase & Lift Lobby pressurization
22 SPTL-L&T-S1-AC-19 INPUT AWAITED 22.07.21 Return Date SECTION INPUT AWAITED
riser & AHU room fresh air riser Layout
Status
Actual sub Date
23 SPTL-L&T-S1-AC-20 Toilet Duct & STP riser Layout INPUT AWAITED 23.07.21 Return Date SECTION INPUT AWAITED
Status
Actual sub Date
24 SPTL-L&T-S1-AC-21 HVAC Ducting standard layout 28.05.21 29.07.21 Return Date
Status
Actual sub Date
25 SPTL-L&T-S1-AC-22 HVAC Piping standard layout 28.05.21 29.07.21 Return Date
Status
CAR PARK VENTILATION
Ventilation layout for Basement-1-sheet-1 of 2,sheet 2of 2 Actual sub Date
SHOP DWG SHALL BE SUBIMIT AFTER CFD
1 SPTL-L&T-S1& S2-AC-01 (Car park ventilation S1 & S2 Block) 28.05.21 Return Date
ANALYSIS
Status
Ventilation layout for Basement-2-sheet-1 of 2,sheet 2of 2 Actual sub Date
SHOP DWG SHALL BE SUBIMIT AFTER CFD
2 SPTL-L&T-S1& S2-AC-02 (Car park ventilation S1 & S2 Block) 28.05.21 Return Date
ANALYSIS
Status
Ventilation layout for Basement-3-sheet-1 of 2,sheet 2of 2 Actual sub Date
SHOP DWG SHALL BE SUBIMIT AFTER CFD
3 SPTL-L&T-S1& S2-AC-03 (Car park ventilation S1 & S2 Block) 28.05.21 Return Date
ANALYSIS
Status
Ventilation layout for Basement-4-sheet-1 of 2,sheet 2of 2 Actual sub Date
SHOP DWG SHALL BE SUBIMIT AFTER CFD
4 SPTL-L&T-S1& S2-AC-04 (Car park ventilation S1 & S2 Block) 28.05.21 Return Date
ANALYSIS
Status
JOB NO:SPTL-L&T-AC
HVAC DRAWING SUBMITTAL SCHEDULE / STATUS
DATE: 25.06.21

PROJECT : L&T (S2 BLOCK)

APPROVED / APPROVED WITH SUBMITTED FOR


TOTAL NO OF DRAWINGS RESUBMIT TO BE SUBMITTED INPUT AWAITED
COMMENTS APPROVAL
SUMMARY OF DRAWING
SUBMITTAL STATUS:
21 0 0 21 0 0

Actual receipt date Submission & Approval status(R0)


Sl.N Planned Sub.
Drg Ref. No. DEPENDENCY
o Architectural Date
GFC RCP R0 R1 R2 R3
Layout

Actual sub Date


CHW & CDW Schematic Layout
1 SPTL-L&T-S2-AC-01 28.05.21 29.06.21 Return Date
(High & Low side)
Status
Actual sub Date CHILLER & PUMP,EXPANSION TANK AND
2 SPTL-L&T-S2-AC-02 Plant room layout for Terrace floor 28.05.21 Return Date AIRSEPARATOR GA DWG DETAIL INPUT
Status AWAITED
Actual sub Date
Hvac layout for Basement-1
3 SPTL-L&T-S2-AC-03 28.05.21 30.06.21 Return Date
(Staircase & lobby Pressurization & Lobby Ducting )
Status
Actual sub Date
Hvac layout for Basement-2
4 SPTL-L&T-S2-AC-04 28.05.21 Return Date
(Staircase & lobby Pressurization & Lobby Ducting )
Status
Actual sub Date
Hvac layout for Basement-3
5 SPTL-L&T-S2-AC-05 28.05.21 30.07.21 Return Date
(Staircase & lobby Pressurization & Lobby Ducting )
Status
Actual sub Date
Hvac layout for Basement-4
6 SPTL-L&T-S2-AC-06 28.05.21 30.07.21 Return Date
(Staircase & lobby Pressurization & Lobby Ducting )
Status
Actual sub Date
HVAC Layout for Ground Floor
7 SPTL-L&T-S2-AC-07 28.05.21 30.07.21 Return Date
(AHU room, Toliet ,Staircase & lobby Pressurization)
Status
Actual sub Date
HVAC Layout for First floor
8 SPTL-L&T-S2-AC-08 28.05.21 03.07.21 Return Date
(AHU room, Toliet ,Staircase & lobby Pressurization)
Status
Actual sub Date
HVAC Layout for 2nd floor
9 SPTL-L&T-S2-AC-09 28.05.21 07.07.21 Return Date
(AHU room, Toliet ,Staircase & lobby Pressurization)
Status
Actual sub Date
HVAC Layout for Typical floor -3rd & 4th floor
10 SPTL-L&T-S2-AC-10 28.05.21 08.07.21 Return Date
(AHU room, Toliet ,Staircase & lobby Pressurization)
Status
Actual sub Date
HVAC Layout for 5th floor
11 SPTL-L&T-S2-AC-11 28.05.21 09.07.21 Return Date
(AHU room, Toliet ,Staircase & lobby Pressurization)
Status
Actual sub Date
HVAC Layout for 6th floor
12 SPTL-L&T-S2-AC-12 28.05.21 12.07.21 Return Date
(AHU room, Toliet ,Staircase & lobby Pressurization)
Status
Actual sub Date
HVAC Layout for 7th floor
13 SPTL-L&T-S2-AC-13 28.05.21 13.07.21 Return Date
(AHU room, Toliet ,Staircase & lobby Pressurization)
Status
Actual sub Date
HVAC Layout for 8th floor
14 SPTL-L&T-S2-AC-14 28.05.21 14.07.21 Return Date
(AHU room, Toliet ,Staircase & lobby Pressurization)
Status
Actual sub Date
HVAC Layout for 9th floor
15 SPTL-L&T-S2-AC-15 28.05.21 15.07.21 Return Date
(AHU room, Toliet ,Staircase & lobby Pressurization)
Status
Actual sub Date
HVAC Layout for 10th floor
16 SPTL-L&T-S2-AC-16 28.05.21 16.07.21 Return Date
(AHU room, Toliet ,Staircase & lobby Pressurization)
Status
Actual sub Date
17 SPTL-L&T-S2-AC-17 Equipment layout for Terrace Floor 28.05.21 17.07.21 Return Date
Status
Actual sub Date
Staircase & Lift Lobby pressurization
18 SPTL-L&T-S2-AC-18 INPUT AWAITED 21.07.21 Return Date SECTION INPUT AWAITED
riser & AHU room fresh air riser Layout
Status
Actual sub Date
19 SPTL-L&T-S2-AC-19 Toilet Duct riser Layout INPUT AWAITED 22.07.21 Return Date SECTION INPUT AWAITED
Status
Actual sub Date
20 SPTL-L&T-S2-AC-20 HVAC Ducting standard layout 28.05.21 23.07.21 Return Date
Status
Actual sub Date
21 SPTL-L&T-S2-AC-21 HVAC Piping standard layout 28.05.21 29.07.21 Return Date
Status