TOTAL NO OF DRAWINGS RESUBMIT TO BE SUBMITTED INPUT AWAITED COMMENTS APPROVAL SUMMARY OF DRAWING SUBMITTAL STATUS: 26 0 0 26 0 0
Actual receipt date Submission & Approval status(R0)
Sl.N Planned Sub. Drg Ref. No. DEPENDENCY o Architectural Date GFC RCP R0 R1 R2 R3 Layout
Actual sub Date
CHW & CDW Schematic Layout 1 SPTL-L&T-S1-AC-01 28.05.21 29.06.21 Return Date (High & Low side) Status Actual sub Date CHILLER & PUMP,EXPANSION TANK AND 2 SPTL-L&T-S1-AC-02 Plant room layout for Terrace floor 28.05.21 Return Date AIRSEPARATOR GA DWG DETAIL INPUT Status AWAITED Actual sub Date Hvac layout for Basement-1 3 SPTL-L&T-S1-AC-03 28.05.21 30.06.21 Return Date (Staircase & lobby Pressurization & Lobby Ducting ) Status Actual sub Date STP Ducting layout for Basement-1 4 SPTL-L&T-S1-AC-04 28.05.21 Return Date ARCHITECH SECTION DETAIL INPUT AWAITED Status Actual sub Date Hvac layout for Basement-2 5 SPTL-L&T-S1-AC-05 28.05.21 30.07.21 Return Date (Staircase & lobby Pressurization & Lobby Ducting ) Status Actual sub Date Hvac layout for Basement-3 7 SPTL-L&T-S1-AC-06 28.05.21 30.07.21 Return Date (Staircase & lobby Pressurization & Lobby Ducting ) Status Actual sub Date Hvac layout for Basement-4 9 SPTL-L&T-S1-AC-07 28.05.21 30.07.21 Return Date (Staircase & lobby Pressurization & Lobby Ducting ) Status Actual sub Date HVAC Layout for Ground Floor 11 SPTL-L&T-S1-AC-08 28.05.21 03.07.21 Return Date (AHU room, Toliet ,Staircase & lobby Pressurization) Status Actual sub Date HVAC Layout for First floor 12 SPTL-L&T-S1-AC-09 28.05.21 07.07.21 Return Date (AHU room, Toliet ,Staircase & lobby Pressurization) Status Actual sub Date HVAC Layout for 2nd floor 13 SPTL-L&T-S1-AC-10 28.05.21 08.07.21 Return Date (AHU room, Toliet ,Staircase & lobby Pressurization) Status Actual sub Date HVAC Layout for Typical floor -3rd & 4th floor 14 SPTL-L&T-S1-AC-11 28.05.21 09.07.21 Return Date (AHU room, Toliet ,Staircase & lobby Pressurization) Status Actual sub Date HVAC Layout for 5th floor 15 SPTL-L&T-S1-AC-12 28.05.21 12.07.21 Return Date (AHU room, Toliet ,Staircase & lobby Pressurization) Status Actual sub Date HVAC Layout for 6th floor 16 SPTL-L&T-S1-AC-13 28.05.21 13.07.21 Return Date (AHU room, Toliet ,Staircase & lobby Pressurization) Status Actual sub Date HVAC Layout for 7th floor 17 SPTL-L&T-S1-AC-14 28.05.21 14.07.21 Return Date (AHU room, Toliet ,Staircase & lobby Pressurization) Status Actual sub Date HVAC Layout for 8th floor 18 SPTL-L&T-S1-AC-15 28.05.21 15.07.21 Return Date (AHU room, Toliet ,Staircase & lobby Pressurization) Status Actual sub Date HVAC Layout for 9th floor 19 SPTL-L&T-S1-AC-16 28.05.21 16.07.21 Return Date (AHU room, Toliet ,Staircase & lobby Pressurization) Status Actual sub Date HVAC Layout for 10th floor 20 SPTL-L&T-S1-AC-17 28.05.21 17.07.21 Return Date (AHU room, Toliet ,Staircase & lobby Pressurization) Status Actual sub Date 21 SPTL-L&T-S1-AC-18 Equipment layout for Terrace Floor 28.05.21 21.07.21 Return Date Status Actual sub Date Staircase & Lift Lobby pressurization 22 SPTL-L&T-S1-AC-19 INPUT AWAITED 22.07.21 Return Date SECTION INPUT AWAITED riser & AHU room fresh air riser Layout Status Actual sub Date 23 SPTL-L&T-S1-AC-20 Toilet Duct & STP riser Layout INPUT AWAITED 23.07.21 Return Date SECTION INPUT AWAITED Status Actual sub Date 24 SPTL-L&T-S1-AC-21 HVAC Ducting standard layout 28.05.21 29.07.21 Return Date Status Actual sub Date 25 SPTL-L&T-S1-AC-22 HVAC Piping standard layout 28.05.21 29.07.21 Return Date Status CAR PARK VENTILATION Ventilation layout for Basement-1-sheet-1 of 2,sheet 2of 2 Actual sub Date SHOP DWG SHALL BE SUBIMIT AFTER CFD 1 SPTL-L&T-S1& S2-AC-01 (Car park ventilation S1 & S2 Block) 28.05.21 Return Date ANALYSIS Status Ventilation layout for Basement-2-sheet-1 of 2,sheet 2of 2 Actual sub Date SHOP DWG SHALL BE SUBIMIT AFTER CFD 2 SPTL-L&T-S1& S2-AC-02 (Car park ventilation S1 & S2 Block) 28.05.21 Return Date ANALYSIS Status Ventilation layout for Basement-3-sheet-1 of 2,sheet 2of 2 Actual sub Date SHOP DWG SHALL BE SUBIMIT AFTER CFD 3 SPTL-L&T-S1& S2-AC-03 (Car park ventilation S1 & S2 Block) 28.05.21 Return Date ANALYSIS Status Ventilation layout for Basement-4-sheet-1 of 2,sheet 2of 2 Actual sub Date SHOP DWG SHALL BE SUBIMIT AFTER CFD 4 SPTL-L&T-S1& S2-AC-04 (Car park ventilation S1 & S2 Block) 28.05.21 Return Date ANALYSIS Status JOB NO:SPTL-L&T-AC HVAC DRAWING SUBMITTAL SCHEDULE / STATUS DATE: 25.06.21
PROJECT : L&T (S2 BLOCK)
APPROVED / APPROVED WITH SUBMITTED FOR
TOTAL NO OF DRAWINGS RESUBMIT TO BE SUBMITTED INPUT AWAITED COMMENTS APPROVAL SUMMARY OF DRAWING SUBMITTAL STATUS: 21 0 0 21 0 0
Actual receipt date Submission & Approval status(R0)
Sl.N Planned Sub. Drg Ref. No. DEPENDENCY o Architectural Date GFC RCP R0 R1 R2 R3 Layout
Actual sub Date
CHW & CDW Schematic Layout 1 SPTL-L&T-S2-AC-01 28.05.21 29.06.21 Return Date (High & Low side) Status Actual sub Date CHILLER & PUMP,EXPANSION TANK AND 2 SPTL-L&T-S2-AC-02 Plant room layout for Terrace floor 28.05.21 Return Date AIRSEPARATOR GA DWG DETAIL INPUT Status AWAITED Actual sub Date Hvac layout for Basement-1 3 SPTL-L&T-S2-AC-03 28.05.21 30.06.21 Return Date (Staircase & lobby Pressurization & Lobby Ducting ) Status Actual sub Date Hvac layout for Basement-2 4 SPTL-L&T-S2-AC-04 28.05.21 Return Date (Staircase & lobby Pressurization & Lobby Ducting ) Status Actual sub Date Hvac layout for Basement-3 5 SPTL-L&T-S2-AC-05 28.05.21 30.07.21 Return Date (Staircase & lobby Pressurization & Lobby Ducting ) Status Actual sub Date Hvac layout for Basement-4 6 SPTL-L&T-S2-AC-06 28.05.21 30.07.21 Return Date (Staircase & lobby Pressurization & Lobby Ducting ) Status Actual sub Date HVAC Layout for Ground Floor 7 SPTL-L&T-S2-AC-07 28.05.21 30.07.21 Return Date (AHU room, Toliet ,Staircase & lobby Pressurization) Status Actual sub Date HVAC Layout for First floor 8 SPTL-L&T-S2-AC-08 28.05.21 03.07.21 Return Date (AHU room, Toliet ,Staircase & lobby Pressurization) Status Actual sub Date HVAC Layout for 2nd floor 9 SPTL-L&T-S2-AC-09 28.05.21 07.07.21 Return Date (AHU room, Toliet ,Staircase & lobby Pressurization) Status Actual sub Date HVAC Layout for Typical floor -3rd & 4th floor 10 SPTL-L&T-S2-AC-10 28.05.21 08.07.21 Return Date (AHU room, Toliet ,Staircase & lobby Pressurization) Status Actual sub Date HVAC Layout for 5th floor 11 SPTL-L&T-S2-AC-11 28.05.21 09.07.21 Return Date (AHU room, Toliet ,Staircase & lobby Pressurization) Status Actual sub Date HVAC Layout for 6th floor 12 SPTL-L&T-S2-AC-12 28.05.21 12.07.21 Return Date (AHU room, Toliet ,Staircase & lobby Pressurization) Status Actual sub Date HVAC Layout for 7th floor 13 SPTL-L&T-S2-AC-13 28.05.21 13.07.21 Return Date (AHU room, Toliet ,Staircase & lobby Pressurization) Status Actual sub Date HVAC Layout for 8th floor 14 SPTL-L&T-S2-AC-14 28.05.21 14.07.21 Return Date (AHU room, Toliet ,Staircase & lobby Pressurization) Status Actual sub Date HVAC Layout for 9th floor 15 SPTL-L&T-S2-AC-15 28.05.21 15.07.21 Return Date (AHU room, Toliet ,Staircase & lobby Pressurization) Status Actual sub Date HVAC Layout for 10th floor 16 SPTL-L&T-S2-AC-16 28.05.21 16.07.21 Return Date (AHU room, Toliet ,Staircase & lobby Pressurization) Status Actual sub Date 17 SPTL-L&T-S2-AC-17 Equipment layout for Terrace Floor 28.05.21 17.07.21 Return Date Status Actual sub Date Staircase & Lift Lobby pressurization 18 SPTL-L&T-S2-AC-18 INPUT AWAITED 21.07.21 Return Date SECTION INPUT AWAITED riser & AHU room fresh air riser Layout Status Actual sub Date 19 SPTL-L&T-S2-AC-19 Toilet Duct riser Layout INPUT AWAITED 22.07.21 Return Date SECTION INPUT AWAITED Status Actual sub Date 20 SPTL-L&T-S2-AC-20 HVAC Ducting standard layout 28.05.21 23.07.21 Return Date Status Actual sub Date 21 SPTL-L&T-S2-AC-21 HVAC Piping standard layout 28.05.21 29.07.21 Return Date Status