CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February 2021

Gas Transmission Company Ltd. (GTCL)


Engineering Services Division
Pipeline Integrity Department
Plot no: F-18/A, Sher-E-Bangla Nagar, Administrative Area,
Agargaon, Dhaka-1207

CP SYSTEM OPERATION AND MAINTENANCE


REPORT OF GTCL PIPELINES (PART-A)

Contract Name: Operation and Maintenance works of the Cathodic


Protection (CP) System of GTCL operated High Pressure Gas
Transmission Pipelines under PART-A.

Contract No: 28.14.0000.234.16.008.19; Dated: 19th December 2019

Reported Month: FEBRUARY 2020

SUBMITTED BY:

TOTAL ENERGY SERVICES LIMITED


333/3, Segunbagicha, Ramna, Dhaka-1000
Phone: 8332891, 01814962853
Email: total.energy02@gmail.com
total.energy1@hotmail.com

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department Page |1


CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February 2021

CP SYSTEM OPERATION AND MAINTENANCE REPORT


OF GTCL PIPELINES (PART-A)
Contract Name: Operation and Maintenance works of the Cathodic Protection (CP) System of
GTCL operated High Pressure Gas Transmission Pipelines under PART-A.

Contract No: 28.14.0000.234.16.008.19; Dated: 19th December 2019

CONTENTS
Sl. No Description Page No.
1 FORWARDING LETTER 03
CP STATIONS MONTHLY OPERATION AND MAINTENANCE REPORT 04
(a) ASHUGANJ- MONOHORDI (A-M) PIPELINE 05
(b) ASHUGANJ- ELANGA (B,B) (A-E) PIPELINE 06
(c) MONOHORDI-DHANUA (M-D) PIPELINE 07
(d) DHANUA- SAVAR (D-S) PIPELINE 08
2 (e) DHANUA- ELANGA (D-E) PIPELINE
(f) BEANIBAZAR-KALISHTILA (BB-KTL) PIPELINE 09
(g) NOUTH-SOUTH (N-S) PIPELINE 10-12
(h) RASHIDPUR-ASHUGANJ (R-A) PIPELINE
(i) ASHUGANJ- BAKHRABAD1 (A-B1) PIPELINE 13
(j) ASHUGANJ- BAKHRABAD2 (A-B2) PIPELINE
(k) BIBIYANA-DHANUA (B-D) PIPELINE 14
MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT 15
(a) ASHUGANJ- MONOHORDI (A-M) PIPELINE 16
(b) ASHUGANJ- ELANGA (B,B) (A-E) PIPELINE 17
(c) MONOHORDI-DHANUA (M-D) PIPELINE 18
(d) DHANUA- SAVAR (D-S) PIPELINE 19
(e) DHANUA- ELANGA (D-E) PIPELINE 20
(f) BEANIBAZAR-KALISHTILA (BB-KTL) PIPELINE 21
3
(g) NOUTH-SOUTH (N-S) PIPELINE 22
(h) RASHIDPUR-ASHUGANJ (R-A) PIPELINE 23
(i) ASHUGANJ- BAKHRABAD1 (A-B1) PIPELINE 24
(j) ASHUGANJ- BAKHRABAD2 (A-B2) PIPELINE 25
(k) BIBIYANA-DHANUA (B-D) PIPELINE 26
(l) TITAS-AB PIPELINE 27
(m) SRIKAIL-AB PIPELINE 28
(n) TITAS-KHATIHATA- MALIHATA PIPELINE 29
(o) TITAS-CBA PIPELINE 30
4 MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY GRAPHICAL 31-45
REPORT
5 SUMMARY OF WORK PROGRESS AS OF FEBRUARY 2021 46-47
6 CONCLUSION 48

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department Page |2


CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February 2021

Date:

Deputy General Manager,


Pipeline Integrity Department
Engineering Services Division (ESD)
Gas Transmission Company Limited (GTCL)
Plot no: F-18/A, Sher-E-Bangla Nagar, Administrative Area,
Agargaon, Dhaka-1207

Subject: Monthly CP system Maintenance report for the month of February 2021

Your Ref: Operation and Maintenance works of the Cathodic Protection (CP) System of GTCL
operated High Pressure Gas Transmission Pipelines under PART-A.

CONTRACT NO: 28.14.0000.234.16.008.19; Dated: 19th December 2019

Dear Sir,

Reference to the above-mentioned works, we hereby submit 03 (three) copies of our Monthly
CP System Monitoring report for the month of February 2021 as per Section (f): Technical
Specifications (scope of work) of the contract.

We therefore request your kind acceptance of the report as it conforms to stipulation of the
Contract meeting your requirements.

Yours Sincerely

Md. Saiful Harun


Project Manager
O.M & Development works of the CP
system of GTCL Operated Pipelines
for Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department Page |3


CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February 2021

OPERATION AND MAINTENANCE REPORT OF GTCL


PIPELINES (PART-A) CP SYSTEM

Reporting Month: FEBRUARY; Year: 2021


CP STATIONS MONTHLY OPERATION AND
MAINTENANCE REPORT
List of Pipelines (PART-A)
(a) ASHUGANJ- MONOHORDI (A-M) PIPELINE

(b) ASHUGANJ- ELANGA (B,B) (A-E) PIPELINE

(c) MONOHORDI-DHANUA (M-D) PIPELINE

(d) DHANUA- SAVAR (D-S) PIPELINE

(e) DHANUA- ELANGA (D-E) PIPELINE

2 (f) BEANIBAZAR-KALISHTILA (BB-KTL) PIPELINE


PART-A
(g) NORTH-SOUTH (N-S) PIPELINE

(h) RASHIDPUR-ASHUGANJ (R-A) PIPELINE

(i) ASHUGANJ- BAKHRABAD1 (A-B1) PIPELINE

(j) ASHUGANJ- BAKHRABAD2 (A-B2) PIPELINE

(k) BIBIYANA-DHANUA (B-D) PIPELINE

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department Page |4


CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February 2021

CP STATIONS MONTHLY OPERATION AND MAINTENANCE REPORT


PIPELINE NAME : ASHUGANJ-MONOHORDI (A-M) HIGH PRESSURE GAS TRANSMISSION PIPELINE (30″ OD, 37 Km)
CP Station Maintenance Information
Before Maintenance After Maintenance
TEG No. CP Station Fuel TEG G.B V. TEG G.B V.
SI Description Drain Drain
(Model 5120 Observation Present Pressure Without Input Without Input Inspection
No. Completed work Output Point Output Point
& 5220 Status (psi) Reg. Drop Ampere Reg. Drop Amper Month
Voltage PSP Voltage PSP -
Voltage (A) Voltage e (A)
(V) (mV) (V) (mV)
(V) (V)
CP Station-1: Lakpur, Norshindi
9447- POD Found Standby Standby TEG Filter Cleaning,
1 6 Necessary servicing and 12.30 1.20 1.5 1210 11.34 3.20 1.25 1215 01.02.21
4113-Y1J Found Running Running voltage adjustment done

CP Station-2: Monohordi, Narshindi


3856- TIK Found Running Running TEG Filter Cleaning,
2 5 Necessary servicing and 12.62 3.20 3.62 1470 12.62 3.20 3.62 1470 01.02.21
3897-TIK Found Standby Standby voltage adjustment done
CP Station Maintenance Description:
• Measured and recorded before output voltage, Anode and Cathode current & Pipe to Soil Potential (PSP).
• Changed Air Intake Flame Arrestors and Exhaust Flame Arrestor.
• Measured the voltage Vset, across the Precision Load.
• Then Measured the Rated Power (W).
• Measured and recorded after output voltage, Anode and Cathode current and Pipe to Soil Potential (PSP) in CP Station.
• All cleaning work done inside the CP Station.

Remarks: CP Stations Working Effectively.


Mansur Ali Md. Saiful Harun
CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department Page |5


CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February 2021

CP STATIONS MONTHLY OPERATION AND MAINTENANCE REPORT


PIPELINE NAME : ASHUGANJ- ELANGA B.B (A-E) HIGH PRESSURE GAS TRANSMISSION PIPELINE (24″ OD, 125 Km)
CP Station Maintenance Information
Before Maintenance After Maintenance
CP Station Fuel TEG G.B V. TEG G.B V.
SI TR No. Description Drain Drain
Observation Present Pressure Without Input Without Input Inspection
No. (Model ) Completed work Output Point Output Point
Status (psi) Reg. Drop Ampere Reg. Drop Amper Month
Voltage PSP Voltage PSP -
Voltage (A) Voltage e (A)
(V) (mV) (V) (mV)
(V) (V)
CP Station-1: Ashuganj, Brahmanbaria
TR Cleaning, Necessary
1 TR Found Running Running servicing and voltage 5.42 - 2.95 1539 5.42 - 2.95 1498 01.02.21
adjustment done
CP Station-2: Monohordi, Narshingdi
TR Cleaning, Necessary
2 TR Found Running Running servicing and voltage 1.50 - 0.10 1168 1.50 - 0.10 1168 01.02.21
adjustment done
CP Station-3: Dhanua, Gazipur
TR Cleaning, Necessary
3 TR Found Running Running servicing and voltage 3.20 - 0.80 1391 3.20 - 0.80 1391 03.02.21
adjustment done
CP Station-4: Sakhipur, Tangail
TR Cleaning, Necessary
4 TR Found Running Running servicing and voltage 2.0 - 0.10 1276 2.0 - 0.10 1276 05.02.21
adjustment done
CP Station Maintenance Description: • Then Measured the Rated Power (W).
• Measured and recorded before output voltage, Anode and Cathode current & Pipe to • Measured and recorded after output voltage, Anode and Cathode current and Pipe to Soil
Soil Potential (PSP). Potential (PSP) in CP Station.
• Changed Air Intake Flame Arrestors and Exhaust Flame Arrestor. • All cleaning work done inside the CP Station.
• Measured the voltage Vset, across the Precision Load.

Remarks: CP Stations Working Effectively.


Mansur Ali Md. Saiful Harun
CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department Page |6


CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February 2021

CP STATIONS MONTHLY OPERATION AND MAINTENANCE REPORT


PIPELINE NAME : MONOHORDI -DHANUA (M-D) HIGH PRESSURE GAS TRANSMISSION PIPELINE (30″ OD, 37 Km)
CP Station Maintenance Information
Before Maintenance After Maintenance
TEG No. CP Station Fuel TEG G.B V. TEG G.B V.
SI Description Drain Drain
(Model 5120 Observation Present Pressure Without Input Without Input Inspection
No. Completed work Output Point Output Point
& 5220 Status (psi) Reg. Drop Ampere Reg. Drop Amper Month
Voltage PSP Voltage PSP -
Voltage (A) Voltage e (A)
(V) (mV) (V) (mV)
(V) (V)
CP Station-1: Sreepur, Gazipur
3891-T1k Found Standby Standby TEG Filter Cleaning,
1 5 Necessary servicing and 10.66 1.99 0.14 1426 10.66 1.99 0.14 1426 02.02.21
3911-U1k Found Running Running voltage adjustment done

CP Station-2: Dhanua, Gazipur


3901- TIK Found Running Standby TEG Filter Cleaning,
2 5.5 Necessary servicing and 12.12 2.32 0.89 1840 15.32 6.40 0.11 1445 02.02.21
3898-UIK Found Standby Running voltage adjustment done
CP Station Maintenance Description:
• Measured and recorded before output voltage, Anode and Cathode current & Pipe to Soil Potential (PSP).
• Changed Air Intake Flame Arrestors and Exhaust Flame Arrestor.
• Measured the voltage Vset, across the Precision Load.
• Then Measured the Rated Power (W).
• Measured and recorded after output voltage, Anode and Cathode current and Pipe to Soil Potential (PSP) in CP Station.
• All cleaning work done inside the CP Station.

Remarks: CP Stations Working Effectively.


Mansur Ali Md. Saiful Harun
CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department Page |7


CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February 2021

CP STATIONS MONTHLY OPERATION AND MAINTENANCE REPORT


PIPELINE
: DHANUA- SAVAR (D-S) HIGH PRESSURE GAS TRANSMISSION PIPELINE (20″ OD, 60 Km)
NAME

Before Maintenance After Maintenance


CP G.B V. G.B V.
SI TEG No. Fuel TEG Drain TEG Drain
Station Description Without Input Without Input
No (Model Observation Pressure Output Point Output Point Inspection
Present Completed work Reg. Drop Amper Reg. Drop Ampe Date
. 1120) (psi) Voltage PSP - Voltage PSP -
Status Voltage e (A) Voltage re (A)
(V) (V) (mV) (V) (V) (mV)
CP Station-1: Panshail, Mirzapur, Gazipur
9449-POD Found Standby Standby TEG Filter Cleaning,
1 6 Necessary servicing and 7.90 1.62 0.25 1342 7.90 1.62 0.25 1347 03.02.21
9448-POD Found Running Running voltage adjustment done
CP Station-2: Kodda, Gazipur

4039- Y1J Found Standby Running TEG Filter Cleaning,


2 6 Necessary servicing and 13.73 2.13 1.26 1373 6.52 2.10 0.34 1275 03.02.21
4041-Y1J Found Running Standby voltage adjustment done

CP Station-3: Ashulia, Savar, Dhaka


TR Cleaning, Necessary
3 TR Found Running Running servicing and voltage - 3.44 1.29 1629 2.82 - 0.78 1445 03.02.21
adjustment done
CP Station Maintenance Description:
• Measured and recorded before output voltage, Anode and Cathode current & Pipe to Soil Potential (PSP).
• Changed Air Intake Flame Arrestors and Exhaust Flame Arrestor.
• Measured the voltage Vset, across the Precision Load.
• Then Measured the Rated Power (W).
• Measured and recorded after output voltage, Anode and Cathode current and Pipe to Soil Potential (PSP) in CP Station.
• All cleaning work done inside the CP Station.

Remarks: CP Stations Working Effectively. Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department Page |8


CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February 2021

CP STATIONS MONTHLY OPERATION AND MAINTENANCE REPORT


PIPELINE NAME : BEANIBAZAR- KALISHTILA HIGH PRESSURE GAS TRANSMISSION PIPELINE (20″ OD, 18 Km)
CP Station Maintenance Information
Before Maintenance After Maintenance
CP Station Fuel TEG G.B V. TEG G.B V.
SI TEG No. Description Drain Drain
Observation Present Pressure Without Input Without Input Inspection
No. (Model 5120 Completed work Output Point Output Point
Status (psi) Reg. Drop Ampere Reg. Drop Amper Month
Voltage PSP Voltage PSP
Voltage (A) Voltage e (A)
(V) (mV) (V) (mV)
(V) (V)
CP Station-1: Kadamrasul, Goapgonj, Sylhet
9436- NOD Found Standby Standby TEG Filter Cleaning,
1 5 Necessary servicing and 9.00 8.00 4.00 1345 9.00 8.00 4.00 1348 07.02.21
9437- NOD Found Running Running voltage adjustment done

CP Station Maintenance Description:


• Measured and recorded before output voltage, Anode and Cathode current & Pipe to Soil Potential (PSP).
• Changed Air Intake Flame Arrestors and Exhaust Flame Arrestor.
• Measured the voltage Vset, across the Precision Load.
• Then Measured the Rated Power (W).
• Measured and recorded after output voltage, Anode and Cathode current and Pipe to Soil Potential (PSP) in CP Station.
• All cleaning work done inside the CP Station.

Remarks: CP Stations Working Effectively.


Mansur Ali Md. Saiful Harun
CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department Page |9


CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February 2021

CP STATIONS MONTHLY OPERATION AND MAINTENANCE REPORT

NORTH - SOUTH (24” DIA. X 175 KM LONG), RASHIDPUR – ASHUGANJ (30” DIA. X 82 KM LONG) HIGH
PIPELINE NAME :
PRESSURE GAS AND NORTH – SOUTH (6” DIA. X 175 KM LONG) CONDENSATE TRANSMISSION PIPELINE.
CP Station Maintenance Information
Before Maintenance After Maintenance
CP Station Fuel TEG G.B V. TEG G.B V.
SI TEG No. Description Drain Drain
Observation Present Pressure Without Input Without Input
No. (Model 1120) Completed work Output Point Output Point Inspection Date
Status (psi) Reg. Drop Ampere Reg. Drop Amper
Voltage PSP Voltage PSP
Voltage (A) Voltage e (A)
(V) (mV) (V) (mV)
(V) (V)
CP Station-1: Kailashtilla-2, Golapganj, Sylhet.
5418-Q9k Found Running Running TEG Filter Cleaning,
1. 5 Necessary servicing and 5.92 4.92 3.00 1068 5.92 4.92 3.00 1068 07.02.21
5418-Q9k Found Standby Inactive
voltage adjustment done
CP Station-2: Chowdhury Bazar, Golapganj, Sylhet.
5449-O9K Found Standby Standby
5450-Q9K Found Standby Standby
5451-O9K Found Standby Standby
5452-Q9K Found Standby Standby TEG Filter Cleaning,
2 5454-Q9K Found Running Running 6 Necessary servicing and 3.40 - 0.81 1206 3.40 - 0.81 1206 07.02.21
voltage adjustment done
5455-O9K Found Standby Standby
5456-Q9K Found Standby Standby
5457-Q9K Found Running Running
5458-O9K Found Standby Standby
CP Station-3: Fenchugonj, Sylhet.
5409-Q9K Found Standby Standby
5410-Q9K Found Standby Standby
5412-Q9K Found Standby Standby TEG Filter Cleaning,
3 5414-Q9K Found Standby Standby 5.2 Necessary servicing and 6.76 - 0.60 1245 6.76 - 0.60 1245 08.02.21
voltage adjustment done
5415-Q9K Found Running Running
5416-Q9K Found Standby Standby
5417-Q9K Found Standby Standby
CP Station-4: Mostafapur, Moulavibazar
4 5420-Q9k Found Standby Standby 5.6 TEG Filter Cleaning, 7.39 - 3.03 1395 7.39 - 3.03 1395 08.02.21
Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 10
CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February 2021

5421-Q9k Found Standby Standby Necessary servicing and


voltage adjustment done
5423-Q9k Found Standby Standby
5427-Q9k Found Standby Running
5428-Q9k Found Running Standby
CP Station-5: Musai, Bahubal, Hobiganj
5419-Q9k Found Running Running TEG Filter Cleaning,
5 5 Necessary servicing and 11.55 3.50 0.60 1814 11.55 3.50 0.60 1814 08.02.21
5422-Q9k Found Standby Inactive voltage adjustment done
CP Station-6: Notunbazar, Mirpur, Hobiganj.
5429-Q9K Inactive Inactive
5430-Q9K Found Standby Standby
5432-Q9K Found Standby Standby
5433-Q9k Inactive Inactive TEG Filter Cleaning,
6 5434-Q9K Found Inactive Inactive 5.50 Necessary servicing and 8.67 - 0.54 1412 8.67 - 0.54 1472 08.02.21
5435-Q9K Found Standby Standby voltage adjustment done
5436-Q9K Found Running Running
5437-Q9k Found Inactive Inactive
5438-Q9K Found Inactive Inactive
CP Station-7: Raghunandan, Hobiganj.
7014-Q9D Found Standby Standby TEG Filter Cleaning,
7 5 Necessary servicing and 9.78 1.75 0.40 1315 9.78 1.75 0.40 1315 09.02.21
7016-Q9D Found Running Running voltage adjustment done
CP Station-8: Madavpur, Hobiganj.
5381-Q9k Found Standby Standby
5382-Q9k Found Standby Standby
5383-Q9K Found Standby Standby
5384-Q9K Found Standby Standby
5385-Q9K Found Standby Standby
5386-Q9K Found Standby Inactive TEG Filter Cleaning,
8 7 Necessary servicing and 7.42 - 3.02 1305 7.42 - 3.02 1312 09.02.21
5387-Q9K Found Standby Inactive voltage adjustment done
5388-Q9K Found Running Standby
5389-Q9K Found Standby Running
5390-Q9K Found Standby Standby
5391-Q9K Found Standby Standby
5392-Q9K Found Standby Inactive

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 11


CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February 2021

5393-Q9K Found Standby Inactive


5394-Q9K Found Standby Inactive
CP Station-9: Khatihata, B.Baria
5405-Q9K Found Standby Standby
5395-Q9K Found Standby Standby
5396-Q9K Found Standby Standby
5397-Q9K Found Standby Standby
5398-Q9K Found Standby Inactive
5399-Q9K Found Standby Standby
5400-Q9K Found Standby Inactive TEG Filter Cleaning,
6 Necessary servicing and 6.18 - 3.20 1020 6.18 - 3.20 1020 09.02.21
5401-Q9K Found Running Running
voltage adjustment done
5402-Q9K Found Standby Standby
5403-Q9K Found Standby Inactive
5404-Q9K Found Standby Inactive
5406-Q9K Found Standby Inactive
5407-Q9K Found Standby Standby
5408-Q9K Found Standby Standby
CP Station Maintenance Description: • Then Measured the Rated Power (W).
• Measured and recorded before output voltage, Anode and Cathode current & • Measured and recorded after output voltage, Anode and Cathode current and Pipe to
Pipe to Soil Potential (PSP). Soil Potential (PSP) in CP Station.
• Changed Air Intake Flame Arrestors and Exhaust Flame Arrestor. • All cleaning work done inside the CP Station.
• Measured the voltage Vset, across the Precision Load.

Remarks: CP Stations Working Effectively.


Mansur Ali Md. Saiful Harun
CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 12


CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February 2021

CP STATIONS MONTHLY OPERATION AND MAINTENANCE REPORT


ASHUGANJ - BAKHRABAD (30” DIA. X 58.5 KM LONG), GTCE A-B (30” DIA. X 61 KM LONG), TITAS-AB (24” DIA. X 7.5
PIPELINE NAME : KM LONG), TITAS CBA-SOYBARIA OFFTAKE (10.75” DIA. X 7.7 KM LONG), SRIKAIL-AB (20” DIA. X 1.2 KM LONG))
HIGH PRESSURE GAS TRANSMISSION PIPELINE.
CP Station Maintenance Information
Before Maintenance After Maintenance
CP Station Fuel TEG G.B V. TEG G.B V.
SI TEG No. Description Drain Drain
Observation Present Pressure Without Input Without Input Inspection
No. (Model 1120) Completed work Output Point Output Point
Status (psi) Reg. Drop Ampere Reg. Drop Amper Month
Voltage PSP Voltage PSP
Voltage (A) Voltage e (A)
(V) (mV) (V) (mV)
(V) (V)
CP Station-1: Adampur, B. Baria
7007-Q9D Found Standby Standby
TEG Filter Cleaning,
7010-Q9D Found Standby Running
1 5.5 Necessary servicing and 0.84 1.00 0.12 962 9.84 4.28 3.98 1498 10.02.21
7011-Q9D Found Standby Standby voltage adjustment done
7012-Q9D Found Running Standby
CP Station-2: Koraibari , Muradnagar, Cumilla
7017-Q9D Found Running Standby
7021-Q9D Found Standby Standby
7022-Q9D Found Standby Standby TEG Filter Cleaning,
2 7023-Q9D Found Standby Standby 5 Necessary servicing and 9.25 1.82 7.57 1276 9.25 1.82 7.57 1282 10.02.21
7026-Q9D Found Standby Standby voltage adjustment done

7027-Q9D Found Standby Running


7028-Q9D Found Standby Standby
CP Station Maintenance Description: • Then Measured the Rated Power (W).
• Measured and recorded before output voltage, Anode and Cathode current & Pipe to • Measured and recorded after output voltage, Anode and Cathode current and Pipe to Soil
Soil Potential (PSP). Potential (PSP) in CP Station.
• Changed Air Intake Flame Arrestors and Exhaust Flame Arrestor. • All cleaning work done inside the CP Station.
• Measured the voltage Vset, across the Precision Load.

Remarks: CP Stations Working Effectively.


Mansur Ali Md. Saiful Harun
CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 13


CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February 2021

CP STATIONS MONTHLY OPERATION AND MAINTENANCE REPORT


PIPELINE NAME : BIBIYANA- DHANUA HIGH PRESSURE GAS TRANSMISSION PIPELINE. ( 36” DIA, 137KM LONG)
CP Station Maintenance Information
Before Maintenance After Maintenance
CP Station Fuel TEG G.B V. TEG G.B V.
SI TEG No. Description Drain Drain
Observation Present Pressure Without Input Without Input Inspection
No. (Model 1120) Completed work Output Point Output Point
Status (psi) Reg. Drop Ampere Reg. Drop Amper Month
Voltage PSP - Voltage PSP -
Voltage (A) Voltage e (A)
(V) (mV) (V) (mV)
(V) (V)
CP Station-1: Bibiyana, Hobiganj
4114- Y1J Found Running Standby TEG Filter Cleaning,
1 6 Necessary servicing and 13.98 4.00 1.84 1359 13.98 4.00 1.84 1359 14.02.21
4123-Y1J Found Standby Running
voltage adjustment done
CP Station-1: Noyagaor Hobiganj
4106-Y1J Found Standby Standby TEG Filter Cleaning,
2 5 Necessary servicing and 13.58 4.00 1.84 1359 13.58 4.00 1.84 1359 15.02.21
4134- Y1J Found Running Running
voltage adjustment done
CP Station-3: Bogadia, Kishoreganj
4128- Y1J Found Standby Running TEG Filter Cleaning,
3 6 Necessary servicing and - - - 1255 16.25 1.53 0.55 1485 16.02.21
4129- Y1J Found Standby Standby voltage adjustment done
CP Station-4: Nandala, Kishoreganj
4115- Y1J Found Standby Running TEG Filter Cleaning,
4 5 Necessary servicing and 13.12 2.2 0.29 1225 13.12 2.2 0.29 1225 16.02.21
4125- Y1J Found Running Standby voltage adjustment done
CP Station-5: Nigory, Mymensingh
4127- Y1J Found Standby Standby TEG Filter Cleaning,
5 5 Necessary servicing and 13.97 3.07 1.28 1575 13.64 2.23 0.79 1329 17.02.21
4137-Y1J Found Running \ Running voltage adjustment done
CP Station Maintenance Description: • Then Measured the Rated Power (W).
• Measured and recorded before output voltage, Anode and Cathode current & Pipe to • Measured and recorded after output voltage, Anode and Cathode current and Pipe to Soil
Soil Potential (PSP). Potential (PSP) in CP Station.
• Changed Air Intake Flame Arrestors and Exhaust Flame Arrestor. • All cleaning work done inside the CP Station.
• Measured the voltage Vset, across the Precision Load.

Remarks: CP Stations Working Effectively. Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 14


CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February, 2021

Page-
OPERATION AND MAINTENANCE REPORT OF GTCL
PIPELINES (PART-A) CP SYSTEM

Reporting Month: FEBRUARY; Year: 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY


REPORT

List of Pipelines (PART-A)

(a) ASHUGANJ- MONOHORDI (A-M) PIPELINE

(b) ASHUGANJ- ELANGA (B,B) (A-E) PIPELINE

(c) MONOHORDI-DHANUA (M-D) PIPELINE

(d) DHANUA- SAVAR (D-S) PIPELINE

(e) DHANUA- ELANGA (D-E) PIPELINE

(f) BEANIBAZAR-KALISHTILA (BB-KTL) PIPELINE

(g) NOUTH-SOUTH (N-S) PIPELINE

2
(h) RASHIDPUR-ASHUGANJ (R-A) PIPELINE
PART-A
(i) ASHUGANJ- BAKHRABAD1 (A-B1) PIPELINE

(j) ASHUGANJ- BAKHRABAD2 (A-B2) PIPELINE

(k) TITAS-AB PIPELINE

(l) SRIKAIL-AB PIPELINE

(m) TITAS-KHATIHATA- MALIHATA PIPELINE

(n) TITAS-CBA PIPELINE

(o) BIBIYANA-DHANUA (B-D) PIPELINE

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 15


CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February, 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT


Pipeline Name: Ashuganj-Monohordi High Pressure Gas Transmission Pipeline. (30''
Dia, 37km)
Sl. Test Chain Location PSP- 30” PSP Min PSP Inspection Remarks
No Ref age km -mV Casing” req. -mV Date
No -mV
1 1 0 Ashuganj Manifold Station 1147 850 01.02.21
2 20 10.90 Lashipur Road crossing 1139 850 01.02.21
3 31 22.50 Lakpur (CP Station) 1215 850 01.02.21 CP station
4 35 28.00 Tula Mandertek 1231 850 01.02.21
5 41 36.70 Monohordi Valve Station 1470 850 01.02.21 CP station

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 16


CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February, 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT


Pipeline Name: Ashuganj- Elenga/ Brahmaputra Basin (B.B) High Pressure Gas
Transmission Pipeline. (24” Dia, 125km Long)

Sl. Test Chain Location PSP Pipe PSP Min PSP Inspection Date Remarks
No Ref age km 24” -mV Casing” req.
No -mV -mV

1 1 0.00 Ashuganj CP Station 1498 850 01.02.21 CP Station


2 13 11.50 Shahchar 1129 850 01.02.21

3 20 20.48 Lackpur MLV 1248 850 01.02.21

4 30 36.20 Monohordi CP Station 1268 850 01.02.21 CP Station


5 48 58.55 Hortoky Take 1252 850 03.02.21

6 58 75.25 Dhanua CP Station 1391 850 03.02.21 CP Station


7 73 92.05 Gojariya School 1144 850 03.02.21

8 77 95.75 Sakhipur CP Station 1469 850 04.02.21 CP Station


9 92 115.35 Kuke Daura 1120 850 04.02.21

10 101 125.00 Elanga CP Station 1225 850 04.02.21

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 17


CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February, 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT


Pipeline Name: Monohordi-Dhanua High Pressure Gas Transmission Pipeline. (30” Dia,
37km Long)

Sl. Test Chain Location PSP- 30” PSP Min PSP Inspection Remarks
No Ref age -mV Casing” req. mV Date
No km -mV
1 1 0 Monohordi (Drain Point) 1341 850 02.02.21
2 13 8.6 Changra Uttar Para 1208 850 02.02.21
3 44 28.95 Sreepur CP Station 1426 850 02.02.21 CP Station
4 54 35.75 Chatir Bazar 1226 850 02.02.21
5 56 37.5 Dhanua CP Station 1445 850 02.02.21 CP Station

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 18


CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February, 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT


Pipeline Name: Dhanua- Savar High Pressure Gas Transmission Pipeline. (20” Dia, 60 km
Long)

Sl. Test Chain age Location PSP- 20” PSP Min PSP Inspection Date Remarks
No Ref km -mV Casing” req.
No -mV -mV
1 1 0.00 Dhanua Valve Station 1329 850 04.02.21
2 22 18.50 Panshail CP Station 1347 850 04.02.21 CP station
3 25 22.50 Baroi Chala 1243 850 04.02.21
4 32 31.75 Kodda Valve Station 1275 850 04.02.21 CP station
5 40 40.00 Poiashona 1274 850 04.02.21
6 44 45.50 Ashulia CP Station 1445 850 04.02.21 CP station
7 53 60.00 Aminbazar CGS 1141 850 04.02.21

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 19


CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February, 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT


Pipeline Name: Dhanua- Elanga High Pressure Gas Transmission Pipeline. 30” Dia, 52
km Long)

Sl. Test Chain age Location PSP- 20” PSP Min PSP Inspection Date Remarks
No Ref km -mV Casing” req.
No -mV -mV
03 0.05 Dhaka- Mymensingh 04.02.21
1 1242 850
Highway Road U.S
2 15 31.60 Tonki River 1 1347 850 04.02.21
3 33 Moshinda Razabari 1243 850 04.02.21

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 20


CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February, 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT


Pipeline Name: Beanibazar - Kailastilla High Pressure Pipeline(20" Dia., × 18 Km Long) & Beanibazar-
Kailashtilla Condensate Transmission Pipeline. (4” Dia., ×18 Km Long)

Sl. Test Chain age Location PSP- PSP- 4” Min PSP Inspection Date Remarks
No Ref km 20” -mV Req.
No -mV -mV
1 1 0.00 Inside of Beanibazar Gas Field 1011 956 850 07.02.21
2 6 5.20 Nalful- Beanibazar road D.S 1261 1272 850 07.02.21 CP Station
3 10 13.10 Kadam Rasul CP Station 1348 1279 850 07.02.21
4 16 18.00 Inside of KTL-2 1158 1160 850 07.02.21

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 21


CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February, 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT


Pipeline Name: North - South (24” dia. × 175 km Long), High Pressure Gas and North –
South (6” dia. × 175 km Long) Condensate Transmission Pipeline.
Test Chain PSP- (mV) Min PSP Inspection Remarks
SL.
Post age Location 24” 6” Req. Date
No.
Ref. (KM) -mV
01 01 00 Inside KTL-2 1068 1065 850 07.02.21 CP Station
02 10 2 North of Golapgonj Upzilla 1163 1122 850 07.02.21
03 18 9 Chowdury Bazar, CP Station 1206 1212 850 07.02.21 CP Station
04 30 24 Hawor Thola 4 Lamaganga 1195 1179 850 07.02.21
05 38 27 Fenchungonj, CP Station 1245 1235 850 08.02.21 CP Station
06 48 36 Haipur, Rajnagor 1119 1119 850 08.02.21
07 68 63 Mostafapur, CP Station 1395 1348 850 08.02.21 CP Station
08 77 69 Kodupur, Moulavibazar 1283 1283 850 08.02.21
09 96 93 Muchai CP Station 1498 1485 850 08.02.21 CP Station
10 107 97 Amtholi-2 1155 1156 850 08.02.21
11 115 102 Notunbazar CP Station 1412 1472 850 09.02.21 CP Station
12 129 113 Deundi Tea Garden Road 1261 1232 850 09.02.21
13 134 122 Ragunandan CP 1315 1301 850 09.02.21 CP Station
14 144 132 Narayonpur Village 1056 1051 850 09.02.21
15 143 139 Madavpur CP Station 1245 1276 850 09.02.21 CP Station
16 157 149 Chandura-Akhaura Road 1011 1000 850 09.02.21
17 163 162 Khatihata CP Station 1094 1125 850 09.02.21 CP Station
18 179 175 ASH. MPS 1041 1036 850 09.02.21

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 22


CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February, 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT


Pipeline Name: Rashidpur – Ashuganj (30” Dia. × 82 Km Long) High Pressure Gas
Transmission Pipeline.

Test PSP Minimum


SL. Chainage Inspection
Post Location (mV) Required Remarks
No. (KM) Month
Ref. 30” PSP (mV)

01 1 0.00 Muchai MLV 1238 850 09.02.21

02 18 17.00 Shimulthola Road 1038 850 09.02.21

03 35 34.30 Doctor Bari Gate, Rathanpur 1075 850 09.02.21

04 54 70.00 Khatihata CP Station 1181 850 09.02.21

05 65 82.00 AGMS 1131 850 09.02.21

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 23


CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February, 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT


Pipeline Name: Titas- Khatihata-Malikhata High Pressure Gas Transmission Pipeline.
.Sl. No Test Chain age Location PSP 20” PSP Min PSP Inspection Date Remarks
Ref km -mV Casing” req.
No -mV -mV
01 02 2.00 West of Malihata 1342 850 14.02.21

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 24


CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February, 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT


Pipeline Name: Ashuganj - Bakhrabad High Pressure Gas Transmission Pipeline. (30”
Dia. × 58.5 Km Long)
.Sl. Test Chain age Location PSP 30” PSP Min PSP Inspection Date Remarks
No Ref No km -mV Casing req.
-mV -mV
01 1 0.00 Ashugonj Metering Station 1129 850 14.02. 21
02 9 10.00 Adampur CP Station 1498 850 14.02. 21 CP Station
03 12 23.00 Dhonashai (Sarper) Road 1121 850 14.02. 21
04 16 35.00 Muradnagar CP Station-02 1282 850 14.02. 21 CP Station
05 21 48.00 Neamatpur Pacca Road 1170 850 14.02. 21
06 26 58.00 Bakhrabad Gas Field 1098 850 14.02. 21

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 25


CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February, 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT


Pipeline Name: GTCE A-B High Pressure Gas Transmission Pipeline. (30” Dia., × 61
Km Long)
.Sl. Test Chain age Location PSP 30” PSP Min PSP Inspection Date Remarks
No Ref No km -mV Casing req.
-mV -mV
01 1 0.00 Ashuganj Manifold Station 1162 850 14.02. 21
02 23 13.00 Islampur Road (D.S) 1112 850 14.02. 21
03 41 29.00 Akobpur Village 1225 850 14.02. 21
04 81 61.00 Bakhrabad Gas Station 1065 850 14.02. 21

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 26


CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February, 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT


Pipeline Name: Titas– AB High Pressure Gas Transmission Pipeline. (24” Dia. × 7.5
Km Long)
.Sl. No Test Chain age Location PSP 24” PSP Min PSP Inspection Date Remarks
Ref km -Mv Casing” req.
No -mV -mV
01 1 0.00 Bhadugar 1118 850 15.02. 21
02 12 5.00 Kalishma Village AP-8 1175 850 15.02. 21
03 20 7.50 Adampur Valve Station 1132 850 15.02. 21

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 27


CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February, 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT


Pipeline Name: Srikail– Ab High Pressure Gas Transmission Pipeline. (20” Dia. × 1.2
Km Long)
.Sl. No Test Chain age Location PSP 20” PSP Min PSP Inspection Date Remarks
Ref km -mV Casing” req.
No -mV -mV
01 01 0.20 Srikail Gas Field Road Crossing (US) 1024 971 850 15.02. 21

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 28


CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February, 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT


Pipeline Name: Titas CBA-Soybaria (10.75” Dia, 7.7 Km Long) High Pressure Gas
Transmission Pipeline
.Sl. Test Chain Location PSP PSP Min Inspection Remarks
No Ref age km 10.75” Casing” PSP Date
No -mV -mV req.
-mV
01 08 2.15 TGF Location-1 Entrance of Rising 1245 1120 850 15.02. 21
02 16 7.00 Near Dariapur Pukur Road Casing 1298 1082 850 15.02. 21

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 29


CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February, 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT


Pipeline Name: Bibiyana- Dhanua High Pressure Gas Transmission Pipeline. (36” Dia,
137km Long)
.Sl. No Test Chain age Location PSP 30” PSP Min PSP Inspection Date Remarks
Ref km -mV Casing” req.
No -mV -mV
1 1 0.00 Bibiyana CP Station 1359 850 16.02.21 CP Station

2 6 3.42 Madhabpur Village 1319 850 16.02.21


3 8 6.74 Shingly River Down Steam 1387 850 16.02.21
4 20 30.08 Noagaor CP Station 1338 850 17.02.21 CP Station

5 22 36.62 Shibpasha Khacha Road 1284 850 17.02.21


6 23 40.93 Kalni River Crossing Up Steam 1302 850 17.02.21
7 31 55.66 Bogadia CP Station 1485 850 17.02.21 CP Station

8 46 84.42 Nikli Rail Crossing Down Steam 1228 850 18.02.21


9 51 91.37 Nandala CP Station 1225 850 18.02.21 CP Station

10 59 95.83 Chandnipasha Village 1227 850 18.02.21


11 71 107.18 Brahmaputra-2 River Crossing D.S. 1315 850 19.02.21 CP Station

12 80 118.58 Nigoiry CP Station 1329 850 19.02.21


13 100 136.00 Dhanua CP Station 1261 850 19.02.21

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 30


Operation and Maintenance works of the Cathodic Protection System of GTCL Operated Pipelines. PART-A February 2021

Pipeline Name: Ashuganj-Monohordi High Pressure Gas Transmission Pipeline. (30'' Dia, 37km)
1600

1400

1200

1000
PSP (mV)

800
Pipe 30"

600 Minimum PSP

400

200

0
0 10.9 22.5 28 36.7
Chainage (km)

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company limited (GTCL) Pipeline Integrity Department P a g e |31


Operation and Maintenance works of the Cathodic Protection System of GTCL Operated Pipelines. PART-A February 2021

Pipeline Name: Ashuganj- Elenga/ Brahmaputra Basin (B.B) High Pressure Gas Transmission Pipeline.
(24” Dia, 125km Long)
1600

1400

1200

1000
PSP (mV)

800
Pipe 24"

600 Minimum PSP

400

200

0
0 11.50 20.48 36.2 58.55 75.25 92.05 95.75 115.35 125
Chainage (km)

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company limited (GTCL) Pipeline Integrity Department P a g e |32


Operation and Maintenance works of the Cathodic Protection System of GTCL Operated Pipelines. PART-A February 2021

Pipeline Name: Monohordi-Dhanua High Pressure Gas Transmission Pipeline. (30” Dia, 37km Long)
1600

1400

1200

1000
PSP (mV)

800
Pipe 30"

600 Minimum PSP

400

200

0
0 8.6 28.95 35.75 37.5
Chainage (km)

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company limited (GTCL) Pipeline Integrity Department P a g e |33


Operation and Maintenance works of the Cathodic Protection System of GTCL Operated Pipelines. PART-A February 2021

Pipeline Name: Dhanua- Savar High Pressure Gas Transmission Pipeline. (20” Dia, 60 km Long)
1600

1400

1200

1000
PSP (mV)

800
Pipe 20"

600 Minimum PSP

400

200

0
0 18.5 22.5 31.75 40 45.5 60
Chainage (km)

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company limited (GTCL) Pipeline Integrity Department P a g e |34


Operation and Maintenance works of the Cathodic Protection System of GTCL Operated Pipelines. PART-A February 2021

Pipeline Name: Dhanua- Elanga High Pressure Gas Transmission Pipeline. 30” Dia, 52 km Long)
1600

1400

1200

1000
PSP (mV)

800
Pipe 30
600 Minimum PSP

400

200

0
0.05 31.6 50
Chainage (km)

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company limited (GTCL) Pipeline Integrity Department P a g e |35


Operation and Maintenance works of the Cathodic Protection System of GTCL Operated Pipelines. PART-A February 2021

Pipeline Name: Beanibazar - Kailastilla High Pressure Pipeline(20" Dia., × 18 Km Long) & Beanibazar-
Kailashtilla Condensate Transmission Pipeline. (4” Dia., ×18 Km Long)
1600

1400

1200

1000
PSP (mV)

800 Pipe 20"


Pipe 4"
600 Minimum PSP

400

200

0
0 5.2 13.1 18
Chainage (km)

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company limited (GTCL) Pipeline Integrity Department P a g e |36


Operation and Maintenance works of the Cathodic Protection System of GTCL Operated Pipelines. PART-A February 2021

Pipeline Name: North - South (24” dia. × 175 km Long), High Pressure Gas and North – South (6” dia. ×
175 km Long) Condensate Transmission Pipeline.
1600

1400

1200

1000
PSP (mV)

800 Pipe 24"


Pipe 6"
600
Minimum PSP

400

200

0
0 2 9 24 27 36 63 69 93 97 102 113 122 132 139 149 162 175
Chainage (km)

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited
Gas Transmission Company limited (GTCL) Pipeline Integrity Department P a g e |37
Operation and Maintenance works of the Cathodic Protection System of GTCL Operated Pipelines. PART-A February 2021

Pipeline Name: Rashidpur – Ashuganj (30” Dia. × 82 Km Long) High Pressure Gas Transmission Pipeline.
1400

1200

1000

800
PSP (mV)

Pipe 30"
600
Minimum PSP

400

200

0
0 17 34.3 70 82
Chainage (km)

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company limited (GTCL) Pipeline Integrity Department P a g e |38


Operation and Maintenance works of the Cathodic Protection System of GTCL Operated Pipelines. PART-A February 2021

Pipeline Name: Titas- Khatihata-Malikhata High Pressure Gas Transmission Pipeline


1600

1400

1200

1000
PSP (mV)

800
Pipe 20"
Minimum PSP
600

400

200

0
2
Chainage (km)

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited
Gas Transmission Company limited (GTCL) Pipeline Integrity Department P a g e |39
Operation and Maintenance works of the Cathodic Protection System of GTCL Operated Pipelines. PART-A February 2021

Pipeline Name: Ashuganj - Bakhrabad High Pressure Gas Transmission Pipeline. (30” Dia. × 58.5
Km Long)
1600

1400

1200

1000
PSP (mV)

800
Pipe 30"
600 Minimum PSP

400

200

0
0 10 23 35 48 58
Chainage (km)

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited
Gas Transmission Company limited (GTCL) Pipeline Integrity Department P a g e |40
Operation and Maintenance works of the Cathodic Protection System of GTCL Operated Pipelines. PART-A February 2021

Pipeline Name: GTCE A-B High Pressure Gas Transmission Pipeline. (30” Dia., × 61 Km Long)
1400

1200

1000

800
PSP (mV)

Pipe 30"
600
Minimum PSP

400

200

0
0 13 29 61
Chainage (km)

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited
Gas Transmission Company limited (GTCL) Pipeline Integrity Department P a g e |41
Operation and Maintenance works of the Cathodic Protection System of GTCL Operated Pipelines. PART-A February 2021

Pipeline Name: Titas– AB High Pressure Gas Transmission Pipeline. (24” Dia. × 7.5 Km Long)
1400

1200

1000

800
PSP (mV)

Pipe 20"
600
Minium PSP

400

200

0
0 5 7.5
Minimum PSP

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company limited (GTCL) Pipeline Integrity Department P a g e |42


Operation and Maintenance works of the Cathodic Protection System of GTCL Operated Pipelines. PART-A February 2021

Pipeline Name: Srikail– Ab High Pressure Gas Transmission Pipeline. (20” Dia. × 1.2 Km Long)
1200

1000

800
PSP (mV)

600
Pipe 20"
Minimum PSP
400

200

0
0.2
Chainage (km)

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company limited (GTCL) Pipeline Integrity Department P a g e |43


Operation and Maintenance works of the Cathodic Protection System of GTCL Operated Pipelines. PART-A February 2021

Pipeline Name: Titas CBA-Soybaria (10.75” Dia, 7.7 Km Long) High Pressure Gas Transmission
Pipeline
1400

1200

1000

800
PSP (mV)

Pipe 20"
600
Minimum PSP

400

200

0
2.15 7
Chainage (km)

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company limited (GTCL) Pipeline Integrity Department P a g e |44


Operation and Maintenance works of the Cathodic Protection System of GTCL Operated Pipelines. PART-A February 2021

Pipeline Name: Bibiyana- Dhanua High Pressure Gas Transmission Pipeline. (36” Dia, 137km Long)
1600

1400

1200

1000
PSP (mV)

800
Pipe 36"
Minimum PSP
600

400

200

0
0 3.42 6.74 30.08 36.62 40.93 55.66 84.42 91.37 95.83 107.18 118.58 136
Chainage (km)

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company limited (GTCL) Pipeline Integrity Department P a g e |45


CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February 2021

OPERATION AND MAINTENANCE REPORT OF GTCL PIPELINES


(PART-A) CP SYSTEM

Reporting Month: FABRUARY; Year: 2021

SUMMARY OF MONTHLY CP STATION MAINTENANCE


AND
PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 45


CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February 2021

SUMMARY OF MONTHLY CP STATION MAINTENANCE


AND
PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT

SI Total Completed Quantity Progress


Items Pipeline Name
No. Qty. Previous Current Total (%)
Ashugonj-Monohordi
Ashugonj- Elenga
Monohordi-Dhanua
Dhanua- Savar
Monthly
Dhanua- Elenga
Operation
and Beanibazar- Kalishtila
1 1032 280 28 308
Maintenance
of CP Nouth – South
Stations Rashidpur- Ashuganj
Ashuganj- Bakhrabad 1
Ashuganj- Bakhrabad 2
Bibiyana- Dhanua
Ashugonj-Monohordi
Ashugonj- Elenga
Monohordi-Dhanua
Dhanua- Savar
Dhanua- Elenga
Beanibazar- Kalishtila
Monthly Pipe Nouth – South
to Soil
2 Rashidpur- Ashuganj 1800 480 51 531
Potential
(PSP) Survey Ashuganj- Bakhrabad 1
Ashuganj- Bakhrabad 2
Bibiyana- Dhanua
Titas-AB Pipeline
Srikail-AB Pipeline
Titas-Khatihata-Malihata
Titas-CBA Pipeline

3 Support of Transport Vehicle 360 100 10 110

4 Accommodation 324 90 09 99

Remarks:

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 46


CP System Maintenance Report of GTCL Pipelines (PART-A) Month: February 2021

Contract Name: Operation and Maintenance works of the Cathodic


Protection (CP) System of GTCL operated High Pressure Gas
Transmission Pipelines under PART-A.

Contract No: 28.14.0000.234.16.008.19; Dated: 19th December 2019

Conclusion: Pipe to Soil Potential (PSP) readings were found within the
acceptable level which indicates Pipelines are well protected with the
Operational CP System.

Reported by:

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

TOTAL ENERGY SERVICES LIMITED


333/3, Segunbagicha, Ramna, Dhaka-1000
Phone: 8332891, 01814962853
Email: total.energy1@hotmail.com
total.energy02@gmail.com

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 47


CP System Maintenance Report of GTCL Pipelines (PART-B) Month: February, 2021

Gas Transmission Company Ltd. (GTCL)


Engineering Services Division
Pipeline Integrity Department
Plot no: F-18/A, Sher-E-Bangla Nagar, Administrative Area,
Agargaon, Dhaka-1207

CP SYSTEM OPERATION AND MAINTENANCE


REPORT OF GTCL PIPELINES (PART-B)

Contract Name: Operation and Maintenance works of the Cathodic


Protection (CP) System of GTCL operated High Pressure Gas
Transmission Pipelines under PART-B.

Contract No: 28.14.0000.234.18.001.19; Dated: 17th December 2019

Reported Month: FEBRUARY 2021

SUBMITTED BY:

M/S. ABUL HOSSAIN,


20/1, Bagichartak, Wapdha Road, Rampura, Dhaka
Phone: 01688739302,01811011909
Email: ms.abulhossain302@gmail.com

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department Page |1


CP System Maintenance Report of GTCL Pipelines (PART-B) Month: February, 2021

CP SYSTEM OPERATION AND MAINTENANCE


REPORT OF GTCL PIPELINES (PART-B)

Contract Name: Operation and Maintenance works of the Cathodic Protection (CP) System of
GTCL operated High Pressure Gas Transmission Pipelines under PART-B.

Contract No: 28.14.0000.234.18.001.19; Dated: 17th December 2019

CONTENTS
Sl. No Description Page No.
1 FORWARDING LETTER 03
CP STATIONS MONTHLY OPERATION AND MAINTENANCE REPORT 04
(a) ELANGA-JAMUNA (E-J) PIPELINE 05
2 (b) ELANGA-BAGHABARI (E-B) PIPELINE 06
(c) NALKA- BOGURA (N-B) PIPELINE 07
(d) HATIKUMRUL-BHERAMARA (H-B) PIPELINE 08
(e) BONPARA-RAJSHAHI (B-R) PIPELINE 09
(f) BHERAMARA-KHULNA (B-K) PIPELINE 10
(g) BOGURA-SAYEDPUR( B-S) PIPELINE 11
3 TRANSFORMER RECTIFIER REPORT 12-14
MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT
(a) ELANGA-JAMUNA (E-J) PIPELINE 14
(b) ELANGA-BAGHABARI (E-B) PIPELINE 15
4
(c) NALKA- BOGURA (N-B) PIPELINE 16
(d) HATIKUMRUL-BHERAMARA (H-B) PIPELINE 17
(e) BONPARA-RAJSHAHI (B-R) PIPELINE 18
(f) BHERAMARA-KHULNA (B-K) PIPELINE 19
(g) BOGURA-SAYEDPUR( B-S) PIPELINE 20
5 MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY GRAPHICAL REPORT 22-28
6 SUMMARY OF WORK PROGRESS AS OF FEBRUARY 2021 29-30
7 CONCLUSION 31

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department Page |2


CP System Maintenance Report of GTCL Pipelines (PART-B) Month: February, 2021

Date:

Deputy General Manager,


Pipeline Integrity Department
Engineering Services Division (ESD)
Gas Transmission Company Limited (GTCL)
Plot no: F-18/A, Sher-E-Bangla Nagar, Administrative Area,
Agargaon, Dhaka-1207

Subject: Monthly CP system Maintenance report for the month of February 2021

Your Ref: Operation and Maintenance works of the Cathodic Protection (CP) System of GTCL
operated High Pressure Gas Transmission Pipelines under PART-B.

CONTRACT NO: 28.14.0000.234.18.001.19; Dated: 17th December 2019

Dear Sir,

Reference to the above-mentioned works, we hereby submit 03 (three) copies of our


Monthly CP System Monitoring report for the month of February 2021 as per Section (f):
Technical Specifications (scope of work) of the contract.

We therefore request your kind acceptance of the report as it conforms to stipulation of the
Contract meeting your requirements.

Yours Sincerely

Md. Mohim Uddin


Project Manager
O.M & Development works of the CP
system of GTCL Operated Pipelines
for M/s. Abul Hossain

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department Page |3


CP System Maintenance Report of GTCL Pipelines (PART-B) Month: February, 2021

OPERATION AND MAINTENANCE REPORT OF GTCL


PIPELINES (PART-B) CP SYSTEM

Reporting Month: FEBRUARY; Year: 2021

CP STATIONS MONTHLY OPERATION AND


MAINTENANCE REPORT
List of Pipelines (PART-B)
(a) ELANGA-JAMUNA (E-J) PIPELINE

(b) ELANGA-BAGHABARI (E-B) PIPELINE

(c) NALKA- BOGURA (N-B) PIPELINE

2 (d) HATIKUMRUL-BHERAMARA (H-B) PIPELINE


PART-B
(e) BONPARA-RAJSHAHI (B-R) PIPELINE

(f) BHERAMARA-KHULNA (B-K) PIPELINE

g) TRANSGFORMER RECTIFIER REPORT

Page |4
CP System Maintenance Report of GTCL Pipelines (PART-B) Month: February, 2021

CP STATIONS MONTHLY OPERATION AND MAINTENANCE REPORT


PIPELINE NAME : ELENGA-JAMUNA HIGH PRESSURE GAS TRANSMISSION PIPELINE. (30” DIA, 10KM LONG)
CP Station Maintenance Information
Before Maintenance After Maintenance
CP G.B V. G.B V.
SI TEG No. Fuel TEG Drain TEG Drain
Station Description Without Input Without Input
No (Model Observation Pressure Output Point Output Point Inspection
Present Completed work Reg. Drop Amper Reg. Drop Ampere
. 5220 (psi) Voltage PSP - Voltage PSP - Date
Status Voltage e (A) Voltage (A)
(V) (V) (mV) (V) (V) (mV)
CP Station-1: Elanga, Tangail
3905-U1K Found Running Standby TEG Filter Cleaning,
1 5 Necessary servicing and 1.60 1.50 0.05 1230 6.70 1.40 1.65 1340 11.02.2021
3892-TIK Found Standby Running voltage adjustment done

CP Station Maintenance Description:


• Measured and recorded before output voltage, Anode and Cathode current & Pipe to Soil Potential (PSP).
• Changed Air Intake Flame Arrestors and Exhaust Flame Arrestor.
• Measured the voltage Vset, across the Precision Load.
• Then Measured the Rated Power (W).
• Measured and recorded after output voltage, Anode and Cathode current and Pipe to Soil Potential (PSP) in CP Station.
• All cleaning work done inside the CP Station.

Remarks: CP Stations Working Effectively. Golam Mowla Md. Mohim Uddin


Site Supervisor Project Manager
M/S Abul Hossain M/S Abul Hossain

Page |5
CP System Maintenance Report of GTCL Pipelines (PART-B) Month: February, 2021

CP STATIONS MONTHLY OPERATION AND MAINTENANCE REPORT


ELENGA-BAGHABARI (ELENGA-J, RIVER EAST, J RIVER WEST-NALKA (24” DIA, 28.50KM
PIPELINE
: LONG,BRIDGE SECTION 30” DIA, 9KM LONG & NALKA – BAGABARI 20” DIA, 35.50KM LONG,
NAME
TOTAL =73 KM LONG) HIGH PRESSURE GAS TRANSMISSION PIPELINE.
CP Station Maintenance Information
Before Maintenance After Maintenance
CP G.B V. G.B V.
SI TEG Fuel TEG Drain TEG Drain
Station Description Without Input Without Input
No (Model ) Observation Pressure Output Point Output Point Inspection
Present Completed work Reg. Drop Amper Reg. Drop Ampere
. 1120, 5220 (psi) Voltage PSP Voltage PSP - Date
Status Voltage e (A) Voltage (A)
(V) (V) (mV) (V) (V) (mV)
CP Station-1: Nalka, Sirajgonj
Installed clean Changed
1 7025-Q9D Found Standby Running Air Filter, Exhaust
Filter & Resistance
5 10.4 4.40 5.40 1200 10.50 6.10 1.95 1280 10.02.2021
checked all connection
7030-Q9D Found Running Standby continuity

CP Station-2: Baghabari, Sirajgonj

4034-T1J Found Standby Standby


TEG Filter Cleaning,
2 6 Necessary servicing and 14.00 2.50 0.10 1670 14.00 2.30 0.10 1400 11.02.2021
voltage adjustment done
4037- T1J Found Running Running

CP Station Maintenance Description: • Then Measured the Rated Power (W).


• Measured and recorded before output voltage, Anode and Cathode current • Measured and recorded after output voltage, Anode and Cathode current and Pipe
& Pipe to Soil Potential (PSP). to Soil Potential (PSP) in CP Station.
• Changed Air Intake Flame Arrestors and Exhaust Flame Arrestor. • All cleaning work done inside the CP Station.
• Measured the voltage Vset, across the Precision Load.

Remarks: CP Stations Working Effectively. Golam Mowla Md. Mohim Uddin


Site Supervisor Project Manager
M/S Abul Hossain M/S Abul Hossain

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department Page |6


CP System Maintenance Report of GTCL Pipelines (PART-B) Month: February, 2021

CP STATIONS MONTHLY OPERATION AND MAINTENANCE REPORT


NALKA – BOGRA (NALKA-HATIKUMRUL 30” DIA, 6.20KM LONG & HATIKUMRUL-BOGRA 20”
PIPELINE NAME :
DIA, 53.8KM LONG, TOTAL =60 KM LONG ) HIGH PRESSURE GAS TRANSMISSION PIPELINE.
CP Station Maintenance Information
Before Maintenance After Maintenance
CP G.B V. G.B V.
SI TEG Fuel TEG Drain TEG Drain
Station Description Without Input Without Input
No (Model ) Observation Pressure Output Point Output Point Inspection
Present Completed work Reg. Drop Amper Reg. Drop Ampere
. 1120, 5220 (psi) Voltage PSP Voltage PSP - Date
Status Voltage e (A) Voltage (A)
(V) (V) (mV) (V) (V) (mV)
CP Station-1: Hatikumrul, Sirajgonj

1 3904- U1K Found Standby Standby TEG Filter Cleaning,


Necessary servicing and
5 15.80 3.90 1.53 1200 3.90 3.90 1.53 1200 10.02.2021
voltage adjustment done
3910-U1K Found Running Running

CP Station-2: Sherpur, Bogura

5413-Q9k Found Standby Standby Installed clean Changed


Air Filter, Exhaust
2 5 Filter & Resistance 10.80 1.70 0.52 1212 10.80 2.40 0.52 1200 10.02.21
checked all connection
5431-Q9k Found Running Running continuity

CP Station Maintenance Description: • Then Measured the Rated Power (W).


• Measured and recorded before output voltage, Anode and Cathode current • Measured and recorded after output voltage, Anode and Cathode current and Pipe
& Pipe to Soil Potential (PSP). to Soil Potential (PSP) in CP Station.
• Changed Air Intake Flame Arrestors and Exhaust Flame Arrestor. • All cleaning work done inside the CP Station.
• Measured the voltage Vset, across the Precision Load.

Remarks: CP Stations Working Effectively. Golam Mowla Md. Mohim Uddin


Site Supervisor Project Manager
M/S Abul Hossain M/S Abul Hossain

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department Page |7


CP System Maintenance Report of GTCL Pipelines (PART-B) Month: February, 2021

CP STATIONS MONTHLY OPERATION AND MAINTENANCE REPORT


PIPELINE NAME : HATIKUMRUL-BHERAMARA HIGH PRESSURE GAS TRANSMISSION PIPELINE. (30” DIA, 82KM LONG)
CP Station Maintenance Information
Before Maintenance After Maintenance
CP G.B V. G.B V.
SI Fuel TEG Drain TEG Drain
TEG No. Station Description Without Input Without Input
No Observation Pressure Output Point Output Point Inspection
(Model 5220 Present Completed work Reg. Drop Amper Reg. Drop Ampe
. (psi) Voltage PSP - Voltage PSP - Date
Status Voltage e (A) Voltage re (A)
(V) (V) (mV) (V) (V) (mV)
CP Station-1: Khalkula, Natore
3907-UIK Found Standby Standby TEG Filter Cleaning,
1 6 Necessary servicing and 10.70 4.50 0.10 1400 10.00 4.30 0.10 1380 11.02.21
3909-UIK Found Running Running voltage adjustment done
CP Station-2: Bonpara, Natore
3857-TIK Found Running Running TEG Filter Cleaning,
2 5 Necessary servicing and 20.00 2.60 0.95 1360 20.00 2.60 0.95 1360 25.02.21
3858-TIK Found Standby Standby voltage adjustment done
CP Station-3: Ishwardi, Pabna
3896-TIK Found Standby Standby TEG Filter Cleaning,
3 Necessary servicing and - - - 1385 - - - 1385 24.02.21
3913-TIK Found Standby Standby voltage adjustment done
CP Station-4: Bheramara, Khustia
3902-UIK Found Running Running TEG Filter Cleaning,
4 5 Necessary servicing and 17.00 2.2 0.25 1308 17.00 2.2 0.25 1308 24.02.21
voltage adjustment done
CP Station Maintenance Description:
• Measured and recorded before output voltage, Anode and Cathode current & Pipe to Soil Potential (PSP).
• Changed Air Intake Flame Arrestors and Exhaust Flame Arrestor.
• Measured the voltage Vset, across the Precision Load.
• Then Measured the Rated Power (W).
• Measured and recorded after output voltage, Anode and Cathode current and Pipe to Soil Potential (PSP) in CP Station.
• All cleaning work done inside the CP Station.

Remarks: CP Stations Working Effectively. Golam Mowla Md. Mohim Uddin


Site Supervisor Project Manager
M/S Abul Hossain M/S Abul Hossain

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department Page |8


CP System Maintenance Report of GTCL Pipelines (PART-B) Month: February, 2021

CP STATIONS MONTHLY OPERATION AND MAINTENANCE REPORT


PIPELINE NAME : BONPARA- RAJSHAHI HIGH PRESSURE GAS TRANSMISSION PIPELINE. (12.75” DIA, 52KM LONG,)
CP Station Maintenance Information
Before Maintenance After Maintenance
CP G.B V. G.B V.
SI TEG No. Fuel TEG Drain TEG Drain
Station Description Without Input Without Input
No (Model Observation Pressure Output Point Output Point Inspection
Present Completed work Reg. Drop Amper Reg. Drop Ampe
. 1120) (psi) Voltage PSP - Voltage PSP - Date
Status Voltage e (A) Voltage re (A)
(V) (V) (mV) (V) (V) (mV)
CP Station-1: Tamaltala, Natore
3853-TIK Found Running Running TEG Filter Cleaning,
1 5 Necessary servicing and 4.00 1.70 0.10 1440 4.00 1.70 0.10 1440 24.02.21
3900-TIK Found Standby Standby voltage adjustment done
CP Station-2: Belpukur, Rajshshi
3901-U1K Found Standby Running TEG Filter Cleaning,
2 3893-U1K Found Running Standby 5 Necessary servicing and 10.00 1.70 0.11 1315 17.00 1.75 0.35 1280 24.02.21
voltage adjustment done
CP Station Maintenance Description: • Then Measured the Rated Power (W).
• Measured and recorded before output voltage, Anode and Cathode • Measured and recorded after output voltage, Anode and Cathode current
current & Pipe to Soil Potential (PSP). and Pipe to Soil Potential (PSP) in CP Station.
• Changed Air Intake Flame Arrestors and Exhaust Flame Arrestor. • All cleaning work done inside the CP Station.
• Measured the voltage Vset, across the Precision Load.

Remarks: CP Stations Working Effectively. Golam Mowla Md. Mohim Uddin


Site Supervisor Project Manager
M/S Abul Hossain M/S Abul Hossain

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department Page |9


CP System Maintenance Report of GTCL Pipelines (PART-B) Month: February, 2021

CP STATIONS MONTHLY OPERATION AND MAINTENANCE REPORT


PIPELINE NAME : BHERAMARA-KHULNA HIGH PRESSURE GAS TRANSMISSION PIPELINE( 20” DIA, 163KM LONG,)
CP Station Maintenance Information
Before Maintenance After Maintenance
CP Station Fuel TEG G.B V. TEG G.B V.
SI TEG No. Description Without Input Drain Without Input Drain
Observation Present Pressure Output Point Output Point Inspection
No. (Model 5220) Completed work Reg. Drop Ampere Reg. Drop Amper
Status (psi) Voltage PSP - Voltage PSP - Date
Voltage (A) (mV) Voltage e (A) (mV)
(V) (V) (V) (V)
CP Station-1: Kushtia
4042-T1J Found Standby Standby TEG Filter Cleaning,
1 5 Necessary servicing and 17.50 2.20 0.22 1520 17.50 2.20 0.22 1520 24.02.21
4048-T1J Found Running Running voltage adjustment done
CP Station-2: Dulalpur, Jhenidah
4043-T1J Found Standby Standby TEG Filter Cleaning,
2 5.1 Necessary servicing and 14.00 2.30 0.65 1470 14.00 2.30 0.65 1470 23.02.21
4047-T1J Found Running Running voltage adjustment done
CP Station-3: Jhenidah,
4033-T1J Found Standby Standby TEG Filter Cleaning,
3 5 Necessary servicing and - - - 1575 - - - 1575 23.02.21
4045-T1J Found Standby Standby voltage adjustment done
CP Station-4: Cantonment TBS, Jessore
4038-T1J Found Running Running TEG Filter Cleaning,
4 5 Necessary servicing and 17 2.2 0.26 1320 17 2.2 0.26 1320 23.02.21
4046-T1J Found Standby Standby voltage adjustment done
CP Station-5: Rupdia, Jessore
4035-T1J Found Standby Running TEG Filter Cleaning,
5 Necessary servicing and 17.00 1.70 0.11 1408 15.60 1.90 0.20 1460 23.02.21
4040-T1J Found Running Standby voltage adjustment done
CP Station-6: Fultala, Khulna
4049-T1J Found Running Running TEG Filter Cleaning,
6 5 Necessary servicing and 16.50 1.20 0.77 1310 16.50 1.20 0.77 1310 23.02.21
4050-T1J Found Standby Standby voltage adjustment done
CP Station Maintenance Description: • Then Measured the Rated Power (W).
• Measured and recorded before output voltage, Anode and Cathode current & Pipe to Soil Potential (PSP). • Measured and recorded after output voltage, Anode and Cathode current and Pipe to Soil Potential (PSP) in CP
• Changed Air Intake Flame Arrestors and Exhaust Flame Arrestor. Station.
• Measured the voltage Vset, across the Precision Load. • All cleaning work done inside the CP Station.

Remarks: CP Stations Working Effectively. Golam Mowla Md. Mohim Uddin


Site Supervisor Project Manager
M/S Abul Hossain M/S Abul Hossain

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 10


CP System Maintenance Report of GTCL Pipelines (PART-B) Month: February, 2021

CP STATIONS TWO MONTHLY OPERATION AND MAINTENANCE REPORT


Transformer Rectifier based CP station of different TBS & CGS
CP Station Maintenance Information
CP Station Before Maintenance After Maintenance
Description Output Input Drain Output Input
Observation Present Drain Point Inspection Date
Completed work Voltage Ampere Point PSP Voltage Ampere
Status -(mV)
PSP -(mV)
(V) (A) (V) (A)
CP Station-1: Rajshahi TBS
Found Running Running TR Cleaning, Necessary servicing and voltage adjustment done 2.00 0.8 2.00 0.8

Sl. Location PSP Min PSP Inspection Date Sl. Location PSP Min PSP Inspection Date
No (-mV) -mV No (-mV) -mV
1 KOD Condensate Dram 6 Hater Outlet line
2 Filter Condensate Dram 7 DRS Metering Unit
3 Filter Outlet Line 8 Liquid Separator Condensate Dram
4 Hater Fuel line 9 Condensate Dram
5 Hater Inlet line 10 Generator Fuel line
CP Station-2: PutiaTBS
Found Running Running TR Cleaning, Necessary servicing and voltage adjustment done 2.00 0.38 2.00 0.38

Sl. Location PSP Min PSP Inspection Date Sl. Location PSP Min PSP Inspection Date
No (-mV) -mV No (-mV) -mV
1 KOD Condensate Dram 6 Hater Outlet line
2 Filter Condensate Dram 7 DRS Metering Unit
3 Filter Outlet Line 8 Liquid Separator Condensate Dram
4 Hater Fuel line 9 Condensate Dram
5 Hater Inlet line 10 Generator Fuel line
CP Station-3: Tamaltala TBS
Found Running Running TR Cleaning, Necessary servicing and voltage adjustment done

Sl. Location PSP Min PSP Inspection Date Sl. Location PSP Min PSP Inspection Date
No (-mV) -mV No (-mV) -mV
1 KOD Condensate Dram 6 Hater Outlet line
2 Filter Condensate Dram 7 DRS Metering Unit
3 Filter Outlet Line 8 Liquid Separator Condensate Dram
4 Hater Fuel line 9 Condensate Dram
5 Hater Inlet line 10 Generator Fuel line

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 11


CP System Maintenance Report of GTCL Pipelines (PART-B) Month: February, 2021

CP Station-4: Bheramara TBS


Found Running Running TR Cleaning, Necessary servicing and voltage adjustment done

Sl. Location PSP Min PSP Inspection Date Sl. Location PSP Min PSP Inspection Date
No (-mV) -mV No (-mV) -mV
1 KOD Condensate Dram 6 Hater Outlet line
2 Filter Condensate Dram 7 DRS Metering Unit
3 Filter Outlet Line 8 Liquid Separator Condensate Dram
4 Hater Fuel line 9 Condensate Dram
5 Hater Inlet line 10 Generator Fuel line
CP Station-5: Kushtia TBS
Found Running Running TR Cleaning, Necessary servicing and voltage adjustment done 5 0.09 6 0.12

Sl. Location PSP Min PSP Inspection Date Sl. Location PSP Min PSP Inspection Date
No (-mV) -mV No (-mV) -mV
1 KOD Condensate Dram 6 Hater Outlet line
2 Filter Condensate Dram 7 DRS Metering Unit
3 Filter Outlet Line 8 Liquid Separator Condensate Dram
4 Hater Fuel line 9 Condensate Dram
5 Hater Inlet line 10 Generator Fuel line
CP Station-6: Zhenidah TBS
Found Running Running TR Cleaning, Necessary servicing and voltage adjustment done

Sl. Location PSP Min PSP Inspection Date Sl. Location PSP Min PSP Inspection Date
No (-mV) -mV No (-mV) -mV
1 KOD Condensate Dram 6 Hater Outlet line
2 Filter Condensate Dram 7 DRS Metering Unit
3 Filter Outlet Line 8 Liquid Separator Condensate Dram
4 Hater Fuel line 9 Condensate Dram
5 Hater Inlet line 10 Generator Fuel line

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 12


CP System Maintenance Report of GTCL Pipelines (PART-B) Month: February, 2021

CP Station-7: Jessore TBS


Found Running Running TR Cleaning, Necessary servicing and voltage adjustment done 2.00 0.05 2.00 0.05

Sl. Location PSP Min PSP Inspection Date Sl. Location PSP Min PSP Inspection Date
No (-mV) -mV No (-mV) -mV
1 KOD Condensate Dram 6 Hater Outlet line
2 Filter Condensate Dram 7 DRS Metering Unit
3 Filter Outlet Line 8 Liquid Separator Condensate Dram
4 Hater Fuel line 9 Condensate Dram
5 Hater Inlet line 10 Generator Fuel line

CP Station 8: Khulna TBS


Found Running Running TR Cleaning, Necessary servicing and voltage adjustment done 4 0.79 4 0.79

Sl. Location PSP Min PSP Inspection Date Sl. Location PSP Min PSP Inspection Date
No (-mV) -mV No (-mV) -mV
1 KOD Condensate Dram 6 Hater Outlet line
2 Filter Condensate Dram 7 DRS Metering Unit
3 Filter Outlet Line 8 Liquid Separator Condensate Dram
4 Hater Fuel line 9 Condensate Dram
5 Hater Inlet line 10 Generator Fuel line

Remarks: CP Stations Working Effectively. Golam Mowla Md. Mohim Uddin


Site Supervisor Project Manager
M/S Abul Hossain M/S Abul Hossain

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 13


CP System Maintenance Report of GTCL Pipelines (PART-B) Month: February, 2021

Page-
OPERATION AND MAINTENANCE REPORT OF GTCL
PIPELINES (PART-B) CP SYSTEM

Reporting Month: February; Year: 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY


REPORT

List of Pipelines (PART-B)


(a) ELANGA-JAMUNA (E-J) PIPELINE

(b) WEST SIDE JAMMUNA BRIDGE – NALKA PIPELINE

(c) ELANGA-BAGHABARI (E-B) PIPELINE

(d) NALKA- BOGURA (N-B) PIPELINE


2
PART-B
(e) HATIKUMRUL-BHERAMARA (H-B) PIPELINE

(f) BONPARA-RAJSHAHI (B-R) PIPELINE

(g) BHERAMARA-KHULNA (B-K) PIPELINE


(h) BOGURA-SAYEDPUR ( B-S) PIPELINE

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 14


CP System Maintenance Report of GTCL Pipelines (PART-B) Month: February, 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT


Pipeline Name: Elenga-Jamuna High Pressure Gas Transmission Pipeline. (30”
Dia, 13km Long)

PSP Min
SI. Test Chainage PSP Pipe Casing PSP
Location Inspection Date Remarks
No No (km) 30” -mV ” req.
-mV -mV
1 1 0.00 Elenga CP Station 1340 850 11.02.2021 CP station

2 900 850 11.02.2021


19 12.00 Jamuna Bridge Valve Station

Golam Mowla Md. Mohim Uddin


Site Supervisor Project Manager
M/S Abul Hossain M/S Abul Hossain

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 15


CP System Maintenance Report of GTCL Pipelines (PART-B) Month: February, 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT


Pipeline Name: West Side Jumana Bridge - Nalka High Pressure Gas Transmission
Pipeline. (30” Dia, 13km Long)

PSP Min
SI. Test Chainage PSP Pipe Casing PSP
Location Inspection Date Remarks
No No (km) 30” -mV ” req.
-mV -mV
1 05 1.79 Saydabad Road Crossing D.S. 1100 1200 850 11.02.2021 CP station

2 24 15.50 Nalka MLV Road 1050 850 11.02.2021

1070 850

Golam Mowla Md. Mohim Uddin


Site Supervisor Project Manager
M/S Abul Hossain M/S Abul Hossain

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 16


CP System Maintenance Report of GTCL Pipelines (PART-B) Month: February, 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT


Pipeline Name: Elenga-Baghabari (Elenga-J, River East, J River West-Nalka (24”
dia, 28.50km Long, Bridge Section 30” dia, 9km Long & Nalka – Bagabari 20” dia,
35.50km Long, Total =73 Km Long) High Pressure Gas Transmission Pipeline

Min
Test PSP
SI. Location PSP Pipe PSP Inspection
Post Location Casing Remarks
No (km) 24” -mV req. Date
No. -mV
-mV
1 1 0.00 Elenga Metering Station 1000 850 11.02.2021

2 25 28.50 Asam City 1050 850 11.02.2021

3 29 35.00 Kona Bari College More 1137 850 11.02.2021

4 32 42.00 Nalka CP Station 1280 850 11.02.2021 CP Station

6 36 47.00 Nagar Bari Road U.S 1155 850 11.02.2021


7 50 73.00 Bagabari CP Station 1400 850 11.02.2021 CP Station

Golam Mowla Md. Mohim Uddin


Site Supervisor Project Manager
M/S Abul Hossain M/S Abul Hossain

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 17


CP System Maintenance Report of GTCL Pipelines (PART-B) Month: February, 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT


Pipeline Name: Nalka – Bogra (Nalka-Hatikumrul 30” dia, 6.20km long &
Hatikumrul-Bogra 20” dia, 53.8km long, Total =60km long) High Pressure Gas
Transmission Pipeline

Min
Test PSP
SI. Location PSP Pipe PSP Inspection
Post Location Casing” Remarks
No (km) 30” -mV req. Date
No. -mV
-mV
1 1 0.00 Nalka Valve Station 1205 850 10.02.2021

2 16 6.20 Hatikamrul CP Station 1200 850 10.02.2021 CP Station

3 44 31.45 Mirzapur-Ranirhat Road 1248 850 10.02.2021

4 52 38.20 Sherpur CP Station 1200 850 10.02.2021 CP Station

5 79 60.00 Bogra TBS 1350 850 10.02.2021

Golam Mowla Md. Mohim Uddin


Site Supervisor Project Manager
M/S Abul Hossain M/S Abul Hossain

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 18


CP System Maintenance Report of GTCL Pipelines (PART-B) Month: February, 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT


Pipeline Name: Hatikumrul-Bheramara High Pressure Gas Transmission
Pipeline (30” dia, 82km long)
Sl. Test Chain Location PSP- 30” PSP Min PSP Inspection Date Remarks
No Ref age km -mV Casing” req.
No -mV -mV
1 2 0 Hatikumrul DRS (Outlet) 1125 850 11.02.2021
2 6 8 No Sholonga Union Parisad 1326 850 11.02.2021
3.8
3 16 Khalkhulla Valve CP Station 1380 850 11.02.2021 CP station
12.9
4 Borai Gram-2(Near Mob. 850 11.02.2021
42 1360
40.0 Tawar) Razakar More
5 Bonpara TBS CP Station 1360 850 25.02.2021 CP station
47 44.3
6 Bonpara-Dashuria Road 850 24.02.2021
1340 1300
56 52.3 Crossing(Up)
7 72 66.4 Iswardi CGS CP Station 1385 850 24.02.2021 CP station

8 Iswardi-Pakshi Road 850 24.02.2021


1358
79 69.35 Crossing(Dw)
98 82 Bheramara CP Station 1308 850 24.02.2021 CP station

Golam Mowla Md. Mohim Uddin


Site Supervisor Project Manager
M/S Abul Hossain M/S Abul Hossain

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 19


CP System Maintenance Report of GTCL Pipelines (PART-B) Month: February, 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT


Pipeline Name: Bonpara- Rajshahi High Pressure Gas Transmission Pipeline.
(12.75” dia, 52km long,)

Sl. Test Chain Location PSP- PSP- Min Inspection Date Remarks
No Ref age km 12.75” Casing PSP
No -mV -mV Req.
-mV
1 1 0.00 Boanpara CP Station 1440 850 24.02.2021
2 26 17.327 Tomal Tola CP Station 1440 850 24.02.2021 CP station
3 43 28.076 Putia-Anari Road (D.S) 1300 850 24.02.2021
4 65 41.844 Belpukuria CP Station 1280 850 24.02.2021 CP station

6 Rajshai Bypass Highway 850 24.02.2021


75 1330
47.848 Road (U.S)
7 82 52.00 Rajshahi CGS 1560 850 24.02.2021

Golam Mowla Md. Mohim Uddin


Site Supervisor Project Manager
M/S Abul Hossain M/S Abul Hossain

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 20


CP System Maintenance Report of GTCL Pipelines (PART-B) Month: February, 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT


Pipeline Name: Bheramara-Khulna High Pressure Gas Transmission Pipeline.
(20” dia, 163km long,)
Sl. Test Chain Location PSP- PSP- Min Inspection Date Remarks
No Ref age km 12.75” Casing PSP
No -mV -mV Req.
-mV
1 1 0 Bheramara CGS 1550 850 22.02.2021
2 21 23 Kushtia T.B.S (CP station) 1520 850 22.02.2021 CP station
3 33 38 Laxmipur bazaar road U.S 1405 850 22.02.2021
4 39 44 CP Station Drain point 1470 850 23.02.2021 CP station
5 50 55.01 Vatibazar mohabbatpur road D.s 1383 850 23.02.2021
6 59 66 CP station Drain Point 1575 850 23.02.2021 CP station
7 65 71 Boro kamar kundo village road 1300 850 23.02.2021
8 97 101 Barinagor bazaar road U.S 1400 850 23.02.2021
9 101 102 CP station Drain Point 1320 850 23.02.2021 CP station
10 108 109 Jessore TBS road crossing U.S 1485 1388 850 23.02.2021
11 131 123 Rupdia cp station Drain point 1460 850 23.02.2021 CP station
12 163 149 Juglipasa village road U.S 1550 1308 850 23.02.2021
13 175 156 CP Station Drain Point 1310 850 23.02.2021 CP station
14 181 161.5 Teligati village-2 1440 850 23.02.2021
16 183 163 Arongghata CGS 1390 850 23.02.2021

Golam Mowla Md. Mohim Uddin


Site Supervisor Project Manager
M/S Abul Hossain M/S Abul Hossain

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 21


Operation and Maintenance works of the Cathodic Protection System of GTCL Operated Pipelines. PART –B February, 2021

Pipeline Name: Elenga-Jamuna High Pressure Gas Transmission Pipeline. (30” Dia, 13km Long)
1600

1400

1200

1000
PSP (mV)

800
Pipe 30"

600 Minimum PSP

400

200

0
0 12 15
Chainage (km)

Golam Mowla Md. Mohim Uddin


Site Supervisor Project Manager
M/S Abul Hossain M/S Abul Hossain

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e 22


Operation and Maintenance works of the Cathodic Protection System of GTCL Operated Pipelines. PART –B February, 2021

Pipeline Name: West Side Jumana Bridge - Nalka High Pressure Gas
Transmission Pipeline. (30” Dia, 13km Long)
1200

1000

800
PSP (mV)

600
Pipe 30"
Minimum PSP
400

200

0
1.79 15.5
Chainage (km)

Golam Mowla Md. Mohim Uddin


Site Supervisor Project Manager
M/S Abul Hossain M/S Abul Hossain

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e 23


Operation and Maintenance works of the Cathodic Protection System of GTCL Operated Pipelines. PART –B February, 2021

Pipeline Name: Elenga-Baghabari (Elenga-J, River East, J River West-Nalka (24” dia, 28.50km Long,
Bridge Section 30” dia, 9km Long & Nalka – Bagabari 20” dia, 35.50km Long, Total =73 Km Long)
High Pressure Gas Transmission Pipeline
1600

1400

1200

1000
Axis Title

800
Pipe 24" 20"
600 Minimum PSP

400

200

0
0 28.5 35 42 47 73
Axis Title

Golam Mowla Md. Mohim Uddin


Site Supervisor Project Manager
M/S Abul Hossain M/S Abul Hossain

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e 24


Operation and Maintenance works of the Cathodic Protection System of GTCL Operated Pipelines. PART –B February, 2021

Pipeline Name: Nalka – Bogra (Nalka-Hatikumrul 30” dia, 6.20km long & Hatikumrul-Bogra 20”
dia, 53.8km long, Total =60km long) High Pressure Gas Transmission Pipeline
1600

1400

1200

1000
PSP (mV)

800
Pipe 30" & 20"

600 Minimum PSP

400

200

0
1 2 Chainage (km) 3 4 5

Golam Mowla Md. Mohim Uddin


Site Supervisor Project Manager
M/S Abul Hossain M/S Abul Hossain
Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e 25
Operation and Maintenance works of the Cathodic Protection System of GTCL Operated Pipelines. PART –B February, 2021

Pipeline Name: Hatikumrul-Bheramara High Pressure Gas Transmission Pipeline (30” dia, 82km
long)
1600

1400

1200

1000
PSP mV)

800
Pipe 30"

600 Minimum PSP

400

200

0
0 3.8 12.9 40 44.3 52.3 66.4 69.35 82
Chainage (km)

Golam Mowla Md. Mohim Uddin


Site Supervisor Project Manager
M/S Abul Hossain M/S Abul Hossain

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e 26


Operation and Maintenance works of the Cathodic Protection System of GTCL Operated Pipelines. PART –B February, 2021

Pipeline Name: Bonpara- Rajshahi High Pressure Gas Transmission Pipeline. (12.75” dia, 52km
long,)
1800

1600

1400

1200
PSP (mV)

1000

Pipe 12.75"
800
Minimum PSP
600

400

200

0
0 17.327 28.076 41.844 47.848 52
Chainage (km)

Golam Mowla Md. Mohim Uddin


Site Supervisor Project Manager
M/S Abul Hossain M/S Abul Hossain

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e 27


Operation and Maintenance works of the Cathodic Protection System of GTCL Operated Pipelines. PART –B February, 2021

Pipeline Name: Bheramara-Khulna High Pressure Gas Transmission Pipeline. ( 20” dia, 163km long,)
1800

1600

1400

1200

1000
PSP (mV)

Pipe 20"
800
Minimum PSP
600

400

200

0
0 23 38 44 55.01 66 71 101 102 109
Chainage (km)

Golam Mowla Md. Mohim Uddin


Site Supervisor Project Manager
M/S Abul Hossain M/S Abul Hossain
Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e 28
Operation and Maintenance works of the Cathodic Protection System of GTCL Operated Pipelines. PART –B February, 2021

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e 29


CP System Maintenance Report of GTCL Pipelines (PART-B) Month: February, 2021

OPERATION AND MAINTENANCE REPORT OF GTCL


PIPELINES (PART-B) CP SYSTEM

Reporting Month: FEBRUARY; Year: 2021

SUMMARY OF MONTHLY CP STATION MAINTENANCE


AND
PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e |29


CP System Maintenance Report of GTCL Pipelines (PART-B) Month: February, 2021

SUMMARY OF MONTHLY CP STATION MAINTENANCE


AND
PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT

SI Total Completed Quantity Progress


Items Pipeline Name
No. Qty. Previous Current Total (%)
Elanga-Jamuna
Monthly Elanga-Baghabari
Operation
Nalka- Bogura
and 696 17
1 Hatikumrul-Bheramara 170 187
Maintenanc
Bonpara-Rajshahi
e of CP
Bheramara-Khulna
Stations
Bogura-Sayedpur
Two
Monthly Rajshahi CGS, Tamaltala
Operation TBS, Ishawardi TBS,
and Bheramara CGS, Kushtia
2 Maintenanc TBS, Jhenaidaha TBS, 144 48 00 48
e of TR Jessore TBS and khulna
Based CP CGS
Station of
CGS/TBS
Elanga-Jamuna
Monthly Elanga-Baghabari
Pipe to Soil Nalka- Bogura
3 Potential Hatikumrul-Bheramara 1068 253 28 281
(PSP) Bonpara-Rajshahi
Survey Bheramara-Khulna
Bogura-Sayedpur
4 Support of Transport Vehicle 360 51 09 60
5 Accommodation 324 46 08 54
Remarks

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e |30


CP System Maintenance Report of GTCL Pipelines (PART-B) Month: February, 2021

Contract Name: Operation and Maintenance works of the Cathodic


Protection (CP) System of GTCL operated High Pressure Gas
Transmission Pipelines under PART-B.

Contract No: 28.14.0000.234.16.008.19; Dated: 19th December 2019

Conclusion: Pipe to Soil Potential (PSP) readings were found within the
acceptable level which indicates Pipelines are well protected with the
Operational CP System.

Reported by:

Golam Mowla Md. Mohim Uddin


Site Supervisor Project Manager
M/S Abul Hossain M/S Abul Hossain

M/S. ABUL HOSSAIN,


20/1, Bagichartak, Wapdha Road, Rampura, Dhaka
Phone: 01688739302,01811011909
Email: ms.abulhossain302@gmail.com

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e |31


CP System Maintenance Report of GTCL Pipelines (PART-C) Month February, 2021

Gas Transmission Company Ltd. (GTCL)


Engineering Services Division
Pipeline Integrity Department
Plot no: F-18/A, Sher-E-Bangla Nagar, Administrative Area,
Agargaon, Dhaka-1207

CP SYSTEM OPERATION AND MAINTENANCE


REPORT OF GTCL PIPELINES (PART-C)

Contract Name: Operation and Maintenance works of the Cathodic


Protection (CP) System of GTCL operated High Pressure Gas
Transmission Pipelines under PART-C.

Contract No: 28.14.0000.234.17.003.19; Dated: 19th December 2019

Reported Month: FEBRUARY 2021

SUBMITTED BY:

TOTAL ENERGY SERVICES LIMITED


333/3, Segunbagicha, Ramna, Dhaka-1000
Phone: 8332891, 01814962853
Email: total.energy1@hotmail.com
total.energy02@gmail.com

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department Page |1


CP System Maintenance Report of GTCL Pipelines (PART-C) Month: February, 2021

CP SYSTEM OPERATION AND MAINTENANCE REPORT


OF GTCL PIPELINES (PART-C)
Contract Name: Operation and Maintenance works of the Cathodic Protection (CP) System of
GTCL operated High Pressure Gas Transmission Pipelines under PART-C.

Contract No: 28.14.0000.234.17.003.19; Dated: 19th December 2019

CONTENTS
SI No. Description Page No.

1 FORWARDING LETTER 03

CP STATIONS MONTHLY OPERATION AND MAINTENANCE REPORT 04


(a) BAKHRABAD-DEMRA (BKB-D) PIPELINE 05
(b) BAKHRABAD-CHATTOGRAM (BKB-CHT) PIPELINE 06
(c) BAKHRABAD-SHIDDHIRGONJ (B-S) PIPELINE 07
2
(d) ANOWARA- FOUZDARHAT (A-F) PIPELINE 08
10
(e) MAHESHKHALI-ANOWARA (M-A) PIPELINE 09
(f) CHATTOGRAM- FENI- BAKHRABAD (C-F-B) PIPELINE 10-11
(g) MAHESHKHALI-ANOWARA (M-A) PARALLEL PIPELINE 12
(h) ZERO POINT-CTMS PIPELINE 13
MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT 14
(a) BAKHRABAD-DEMRA (BKB-D) PIPELINE 15
(b) BAKHRABAD-CHATTOGRAM (BKB-CHT) PIPELINE 16
(c) BAKHRABAD-SHIDDHIRGONJ (B-S) PIPELINE 17
3 (d) ANOWARA- FOUZDARHAT (A-F) PIPELINE 18
(e) MAHESHKHALI-ANOWARA (M-A) PIPELINE 19
(f) CHATTOGRAM- FENI- BAKHRABAD (C-F-B) PIPELINE 20
(g) MAHESHKHALI-ANOWARA (M-A) PARALLEL PIPELINE 21
(h) ZERO POINT-CTMS PIPELINE 22
4 MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY GRAPHICAL REPORT 23-30
5 SUMMARY OF WORK PROGRESS AS OF FEBRUARY 2020 31-32
6 CONCLUSION 33

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department Page |2


CP System Maintenance Report of GTCL Pipelines (PART-C) Month: February, 2021

Date:

Deputy General Manager,


Pipeline Integrity Department
Engineering Services Division (ESD)
Gas Transmission Company Limited (GTCL)
Plot no: F-18/A, Sher-E-Bangla Nagar, Administrative Area,
Agargaon, Dhaka-1207

Subject: Monthly CP system Maintenance report for the month of February 2021

Your Ref: Operation and Maintenance works of the Cathodic Protection (CP) System of GTCL
operated High Pressure Gas Transmission Pipelines under PART-C.

CONTRACT NO: 28.14.0000.234.17.003.19; Dated: 19th December 2019

Dear Sir,

Reference to the above-mentioned works, we hereby submit 03 (three) copies of our Monthly
CP System Monitoring report for the month of February 2021 as per Section (f): Technical
Specifications (scope of work) of the contract.

We therefore request your kind acceptance of the report as it conforms to stipulation of the
Contract meeting your requirements.

Yours Sincerely

Md. Saiful Harun


Project Manager
O.M & Development works of the CP
system of GTCL Operated Pipelines
for Total Energy Services Limited
Page-

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department Page |3


CP System Maintenance Report of GTCL Pipelines (PART-C) Month: February, 2021

OPERATION AND MAINTENANCE REPORT OF GTCL


PIPELINES (PART-C) CP SYSTEM

Reporting Month: FEBRUARY; Year: 2021

CP STATIONS MONTHLY OPERATION AND


MAINTENANCE REPORT
List of Pipelines (PART-C)
(a) BAKHRABAD-DEMRA (BKB-D) PIPELINE

(b) BAKHRABAD-CHATTOGRAM (BKB-CHT) PIPELINE

(c) BAKHRABAD-SHIDDHIRGONJ (B-S) PIPELINE

(d) ANOWARA- FOUZDARHAT (A-F) PIPELINE


2
PART-C
(e) MAHESHKHALI-ANOWARA (M-A) PIPELINE

(f) CHATTOGRAM- FENI- BAKHRABAD (C-F-B) PIPELINE

(g) MAHESHKHALI-ANOWARA (M-A) PARALLEL PIPELINE

(h) ZERO POINT-CTMS PIPELINE

Page |4
CP System Maintenance Report of GTCL Pipelines (PART-C) Month: February, 2021

CP STATIONS MONTHLY OPERATION AND MAINTENANCE REPORT


PIPELINE
: BAKHRABAD-DEMRA (BKB-D) HIGH PRESSURE GAS TRANSMISSION PIPELINE (20″ OD, 68.72 Km)
NAME
CP Station Maintenance Information
Before Maintenance After Maintenance
CP G.B V. G.B V.
SI TEG No. Fuel TEG Drain TEG Drain
Station Description Without Input Without Input
No (Model Observation Pressure Output Point Output Point Inspection
Present Completed work Reg. Drop Amper Reg. Drop Ampe
. 1120) (psi) Voltage PSP - Voltage PSP - Month
Status Voltage e (A) Voltage re (A)
(V) (V) (mV) (V) (V) (mV)
CP Station-1: Bakhrabad Gas Field, Muradnagar, Cumilla
7004-Q9D Inactive TEG Filter Cleaning,
February
1 7005-Q9D Found Running Running 6 Necessary servicing and 11.00 8.92 8.02 1184 11.00 8.92 8.02 1184
21
7015-Q9D Found Running Running voltage adjustment done

CP Station-2: Gouripur Cumilla


7003-Q9D Inactive Standby TEG Filter Cleaning,
February
2 7009-Q9D Found Standby Running 6 Necessary servicing and - - - 974 9.23 2.12 2.91 1490
21
7013-Q9D Found Running Standby voltage adjustment done

CP Station-3: Dewanbag, Sonargaon, Narayangonj


7006-Q9D Found Standby Standby TEG Filter Cleaning,
February
3 7 Necessary servicing and - - - 775 4.25 3.20 4.12 1025
21
7008-Q9D Found Standby Running voltage adjustment done
CP Station Maintenance Description:
• Measured and recorded before output voltage, Anode and Cathode current & Pipe to Soil Potential (PSP).
• Changed Air Intake Flame Arrestors and Exhaust Flame Arrestor.
• Measured the voltage Vset, across the Precision Load.
• Then Measured the Rated Power (W).
• Measured and recorded after output voltage, Anode and Cathode current and Pipe to Soil Potential (PSP) in CP Station.
• All cleaning work done inside the CP Station.

Remarks: CP Stations Working Effectively. Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Page |5
CP System Maintenance Report of GTCL Pipelines (PART-C) Month: February, 2021

CP STATIONS MONTHLY OPERATION AND MAINTENANCE REPORT


PIPELINE
: BAKHRABAD-CHATTOGRAM (BKB-CHT) HIGH PRESSURE GAS TRANSMISSION PIPELINE (24″ OD, 178 Km)
NAME
CP Station Maintenance Information
Before Maintenance After Maintenance
CP G.B V. G.B V.
SI TEG No. Fuel TEG Drain TEG Drain
Station Description Without Input Without Input
No (Model Observation Pressure Output Point Output Point Inspection
Present Completed work Reg. Drop Amper Reg. Drop Ampe
. 1120) (psi) Voltage PSP - Voltage PSP - Month
Status Voltage e (A) Voltage re (A)
(V) (V) (mV) (V) (V) (mV)
CP Station-1: Laksham, Cumilla.
7018-Q9D Found Running Running TEG Filter Cleaning,
February
1 5.5 Necessary servicing and 9.87 4.25 0.75 1378 9.87 4.25 0.78 1378
7024-Q9D Found Standby Standby 21
voltage adjustment done
CP Station-2: Feni ICS

1 9446-POD Found Running Running TEG Filter Cleaning,


February
6 Necessary servicing and 7.90 2.12 0.34 1355 7.90 2.12 0.34 1355
21
2 9534 –U1C Found Standby Standby voltage adjustment done

CP Station-3: Mithachara, Mirsari Chattogram


TEG Filter Cleaning,
February
3 5120 Found Running Running 8 Necessary servicing and 7.56 1.09 0.70 1368 7.56 1.09 0.70 1368
21
voltage adjustment done
CP Station-4: Barobkunda TBS Sitakunda, Chattogram
3855-T1K Found Standby Standby TEG Filter Cleaning,
February
4 6.2 Necessary servicing and 17.70 2.62 0.42 1425 17.70 2.62 0.42 1425
3903-U1K Found Running Running 21
voltage adjustment done
CP Station Maintenance Description: • Then Measured the Rated Power (W).
• Measured and recorded before output voltage, Anode and Cathode current & • Measured and recorded after output voltage, Anode and Cathode current and
Pipe to Soil Potential (PSP). Pipe to Soil Potential (PSP) in CP Station.
• Changed Air Intake Flame Arrestors and Exhaust Flame Arrestor. • All cleaning work done inside the CP Station.
• Measured the voltage Vset, across the Precision Load.

Remarks: CP Stations Working Effectively. Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited
Gas Transmission Company Limited (GTCL) Pipeline Integrity Department Page |6
CP System Maintenance Report of GTCL Pipelines (PART-C) Month: February, 2021

CP STATIONS MONTHLY OPERATION AND MAINTENANCE REPORT


BAKHRABAD-SHIDDHIRGONJ (B-S) PIPELINE HIGH PRESSURE GAS TRANSMISSION PIPELINE (30″ OD, 60
PIPELINE NAME :
Km)
CP Station Maintenance Information
Before Maintenance After Maintenance
CP G.B V. G.B V.
SI TEG No. Fuel TEG Drain TEG Drain
Station Description Without Input Without Input
No (Model Observation Pressure Output Point Output Point Inspection
Present Completed work Reg. Drop Amper Reg. Drop Ampe
. 1120) (psi) Voltage PSP Voltage PSP - Month
Status Voltage e (A) Voltage re (A)
(V) (V) (mV) (V) (V) (mV)
CP Station-1: Uttar Nasruddi, Daudkandi (VS-2), Cumilla
8958-SIG Found Standby Standby
8959-SIG Found Standby Standby
8960-SIG Found Standby Running
8961-SIG Found Running Standby TEG Filter Cleaning,
February
1 5 Necessary servicing and 4.16 - 2.78 1539 4.93 - 0.78 1267
8962-SIG Found Standby Standby 21
voltage adjustment done
8963-SIG Found Standby Standby
8964-SIG Found Standby Standby
8965-SIG Found Standby Standby

CP Station-2: Shashaner Bag , Barpara (VS-6), Narayanganj


8953-SIG Found Standby Standby
Found Standby Standby TEG Filter Cleaning,
8954-SIG February
2 5.3 Necessary servicing and 7.12 - 0.13 1348 8.15 - 0.13 1467
8955-SIG Found Running Running 21
voltage adjustment done
8957-SIG Found Standby Standby
CP Station Maintenance Description: • Then Measured the Rated Power (W).
• Measured and recorded before output voltage, Anode and Cathode current & • Measured and recorded after output voltage, Anode and Cathode current and
Pipe to Soil Potential (PSP). Pipe to Soil Potential (PSP) in CP Station.
• Changed Air Intake Flame Arrestors and Exhaust Flame Arrestor. • All cleaning work done inside the CP Station.
• Measured the voltage Vset, across the Precision Load.

Remarks: CP Stations Working Effectively. Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department Page |7


CP System Maintenance Report of GTCL Pipelines (PART-C) Month: February, 2021

CP STATIONS MONTHLY OPERATION AND MAINTENANCE REPORT


PIPELINE
: ANOWARA - FOUZDARHAT (A-F) HIGH PRESSURE GAS TRANSMISSION PIPELINE (42″ OD, 30 Km)
NAME
CP Station Maintenance Information
Before Maintenance After Maintenance
CP G.B V. G.B V.
SI TEG No. Fuel TEG Drain TEG Drain
Station Description Without Input Without Input
No (Model Observation Pressure Output Point Output Point Inspection
Present Completed work Reg. Drop Amper Reg. Drop Ampere
. 1120) (psi) Voltage PSP - Voltage PSP - Month
Status Voltage e (A) Voltage (A)
(V) (V) (mV) (V) (V) (mV)
CP Station-1: Anowara, Chattogram
10000-Y1C Found Running Running TEG Filter Cleaning,
1 6 Necessary servicing and 13.00 3.5 2.1 1119 13.00 3.4 2.00 1210 February 21
10001-Y1C Found Standby Standby voltage adjustment done

CP Station-2: Salimpur, Fauzderhat, Chattogram


9999- Y1C Found Standby Standby TEG Filter Cleaning,
2 5 Necessary servicing and 10.00 2.3 0.50 1197 9.72 2.4 0.53 1227 February 21
10003-Y1C Found Running Running voltage adjustment done

CP Station Maintenance Description: • Then Measured the Rated Power (W).


• Measured and recorded before output voltage, Anode and Cathode current & • Measured and recorded after output voltage, Anode and Cathode current and Pipe
Pipe to Soil Potential (PSP). to Soil Potential (PSP) in CP Station.
• Changed Air Intake Flame Arrestors and Exhaust Flame Arrestor. • All cleaning work done inside the CP Station.
• Measured the voltage Vset, across the Precision Load.

Remarks: CP Stations Working Effectively. Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department Page |8


CP System Maintenance Report of GTCL Pipelines (PART-C) Month: February, 2021

CP STATIONS MONTHLY OPERATION AND MAINTENANCE REPORT


PIPELINE
: MAHESHKHALI- ANOWARA (M-A) HIGH PRESSURE GAS TRANSMISSION PIPELINE (30″ OD, 91 Km)
NAME
CP Station Maintenance Information
Before Maintenance After Maintenance
CP G.B V. G.B V.
SI TEG No. Fuel TEG Drain TEG Drain
Station Description Without Input Without Input
No (Model Observation Pressure Output Point Output Point Inspection
Present Completed work Reg. Drop Amper Reg. Drop Ampe
. 5220) (psi) Voltage PSP Voltage PSP Month
Status Voltage e (A) Voltage re (A)
(V) (V) (mV) (V) (V) (mV)
CP Station-1: CTMS Mashkhali, Coxbazzar
5167-P1D Found Standby Standby
TEG Filter Cleaning,
February
1 5173-P1D Found Running Running 7.5 Necessary servicing and 14.20 2.1 0.7 1220 14.32 2.2 0.7 1360
21
5178-P1D Found Standby Standby voltage adjustment done

CP Station-2: Napura Banskhali, Chattogram


5174-P1D Found Standby Standby
TEG Filter Cleaning,
February
2 5176-P1D Found Standby Standby 7 Necessary servicing and 13.25 2.4 5.7 1239 13.25 2.4 5.7 1239
21
Found Running Running voltage adjustment done
5177-P1D
CP Station-3: Banigram Banskhali, Chattogram
5169-P1D Found Running Running TEG Filter Cleaning,
Found Standby Standby February
3 5171-P1D 6.8 Necessary servicing and 12.62 4.1 2.0 1446 12.62 3.8 1.9 1366
21
5172-P1D Found Standby Standby voltage adjustment done
CP Station Maintenance Description: • Then Measured the Rated Power (W).
• Measured and recorded before output voltage, Anode and Cathode current & • Measured and recorded after output voltage, Anode and Cathode current and
Pipe to Soil Potential (PSP). Pipe to Soil Potential (PSP) in CP Station.
• Changed Air Intake Flame Arrestors and Exhaust Flame Arrestor. • All cleaning work done inside the CP Station.
• Measured the voltage Vset, across the Precision Load.

Remarks: CP Stations Working Effectively. Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department Page |9


CP System Maintenance Report of GTCL Pipelines (PART-C) Month: February, 2021

CP STATIONS MONTHLY OPERATION AND MAINTENANCE REPORT


PIPELINE
: CHATTOGRAM-FENI-BAKHRABAD (CFB) HIGH PRESSURE GAS TRANSMISSION PIPELINE (36″ OD, 178 Km)
NAME
CP Station Maintenance Information
Before Maintenance After Maintenance
CP G.B V. G.B V.
SI TEG No. Fuel TEG Drain TEG Drain
Station Description Without Input Without Input
No (Model Observation Pressure Output Point Output Point Inspection
Present Completed work Reg. Drop Amper Reg. Drop Ampe
. 1120) (psi) Voltage PSP Voltage PSP Month
Status Voltage e (A) Voltage re (A)
(V) (V) (mV) (V) (V) (mV)
CP Station-1: Sonaichari, Sitakunda, Chattogram
9540-U1C Found Standby Standby
TEG Filter Cleaning,
1 9553-U1C Found Running Running 5 Necessary servicing and 12.11 2.41 2.88 1278 12.11 2.41 2.88 1278 February 21
9554-U1C Found Standby Standby voltage adjustment done

CP Station-2: Mirsari, Chattogram


9548-U1C Found Standby Standby
TEG Filter Cleaning,
2 9576-U1C Found Running Running 5.5 Necessary servicing and 11.25 1.89 0.79 1248 11.25 1.89 0.79 1248 February 21
9577-U1C Found Standby Standby voltage adjustment done

CP Station-3: Chandpur, Feni


9533-U1C Found Standby Standby TEG Filter Cleaning,
3 9550-U1C Found Standby Standby 5 Necessary servicing and 9.89 2.09 1.51 1373 9.89 2.09 1.51 1373 February 21
9578-U1C Found Running Running voltage adjustment done
CP Station-4: Jumarail,Chhudgram, Cumilla
9537-U1C Found Running Running TEG Filter Cleaning,
4 9581-U1C Found Standby Standby 5.5 Necessary servicing and 10.16 3.95 0.19 1442 10.16 3.95 0.19 1448 February 21
voltage adjustment done
CP Station-5: Joynagar, Barura, Cumilla
9536-U1C Found Standby Standby TEG Filter Cleaning,
5 9552-U1C Found Standby Standby 6 Necessary servicing and 10.00 2.00 2.12 1375 10.00 2.00 2.12 1378 February 21
9577-U1C Found Running Running voltage adjustment done

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 10


CP System Maintenance Report of GTCL Pipelines (PART-C) Month: February, 2021

CP Station-6: Bakhrabad, Cumilla


9538-U1C Found Running Running TEG Filter Cleaning,
6 9551-U1C Found Standby Standby 5 Necessary servicing and 10.00 2.12 0.19 1345 10.00 2.12 0.19 1345 February 21
9588-U1C Found Standby Standby voltage adjustment done
CP Station Maintenance Description: • Then Measured the Rated Power (W).
• Measured and recorded before output voltage, Anode and Cathode • Measured and recorded after output voltage, Anode and Cathode current
current & Pipe to Soil Potential (PSP). and Pipe to Soil Potential (PSP) in CP Station.
• Changed Air Intake Flame Arrestors and Exhaust Flame Arrestor. • All cleaning work done inside the CP Station.
• Measured the voltage Vset, across the Precision Load

Remarks: CP Stations Working Effectively. Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 11


CP System Maintenance Report of GTCL Pipelines (PART-C) Month: February, 2021

CP STATIONS MONTHLY OPERATION AND MAINTENANCE REPORT

MAHESHKHALI- ANOWARA (M-A) HIGH PRESSURE GAS TRANSMISSION PIPELINE( PARALAL) (42″
PIPELINE NAME :
OD, 79 Km)

CP Station Maintenance Information


Before Maintenance After Maintenance
CP G.B V. G.B V.
SI TEG No. Fuel TEG Drain TEG Drain
Station Description Without Input Without Input
No (Model Observation Pressure Output Point Output Point Inspection
Present Completed work Reg. Drop Amper Reg. Drop Ampere
. 1120) (psi) Voltage PSP - Voltage PSP - Date
Status Voltage e (A) Voltage (A)
(V) (V) (mV) (V) (V) (mV)

CP Station-1: Uttarnalvilla, Moheshkhali, Cox’sbazzar


9995-Y1C Found Standby Standby TEG Filter Cleaning,
1 6 Necessary servicing and 18.4 3.2 2.12 1275 18.4 3.4 2.20 1333 February 21
9988-Y1C Found Running Running voltage adjustment done

CP Station Maintenance Description: • Then Measured the Rated Power (W).


• Measured and recorded before output voltage, Anode and Cathode • Measured and recorded after output voltage, Anode and Cathode current
current & Pipe to Soil Potential (PSP). and Pipe to Soil Potential (PSP) in CP Station.
• Changed Air Intake Flame Arrestors and Exhaust Flame Arrestor. • All cleaning work done inside the CP Station.
• Measured the voltage Vset, across the Precision Load.

Remarks: CP Stations Working Effectively. Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 12


CP System Maintenance Report of GTCL Pipelines (PART-C) Month: February, 2021

CP STATIONS MONTHLY OPERATION AND MAINTENANCE REPORT

PIPELINE NAME : ZEROPOINT-CTMS HIGH PRESSURE GAS TRANSMISSION PIPELINE(42″ OD, 6 Km)

CP Station Maintenance Information


Before Maintenance After Maintenance
CP G.B V. G.B V.
SI Fuel TEG Drain TEG Drain
Transformer Station Description Without Input Without Input
No Observation Pressure Output Point Output Point Inspection
Rectifier Present Completed work Reg. Drop Amper Reg. Drop Ampere
. (psi) Voltage PSP - Voltage PSP - Date
Status Voltage e (A) Voltage (A)
(V) (V) (mV) (V) (V) (mV)

CP Station-1: CTMS, Moheshkhali, Coxs’bazzar


TEG Filter Cleaning,
1 TR Found Running Running 6 Necessary servicing and 1.10 - 0.30 1395 1.10 - 0.30 1395 February 21
voltage adjustment done

CP Station Maintenance Description:


• Measured and recorded before output voltage, Anode and Cathode • Then Measured the Rated Power (W).
current & Pipe to Soil Potential (PSP). • Measured and recorded after output voltage, Anode and Cathode current
• Changed Air Intake Flame Arrestors and Exhaust Flame Arrestor. and Pipe to Soil Potential (PSP) in CP Station.
• Measured the voltage Vset, across the Precision Load. • All cleaning work done inside the CP Station.

Remarks: CP Stations Working Effectively. Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e | 13


CP System Maintenance Report of GTCL Pipelines (PART-C) Month: February, 2021

OPERATION AND MAINTENANCE


Page- REPORT OF GTCL
PIPELINES (PART-C) CP SYSTEM

Reporting Month: February; Year: 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY


REPORT

List of Pipelines (PART-C)

(a) BAKHRABAD-DEMRA (BKB-D) PIPELINE

(b) BAKHRABAD-CHATTOGRAM (BKB-CHT) PIPELINE

(c) BAKHRABAD-SHIDDHIRGONJ (B-S) PIPELINE

(d) ANOWARA- FOUZDARHAT (A-F) PIPELINE


2
PART-C
(e) MAHESHKHALI-ANOWARA (M-A) PIPELINE

(f) CHATTOGRAM- FENI- BAKHRABAD (C-F-B) PIPELINE

(g) MAHESHKHALI-ANOWARA (M-A) PARALLEL PIPELINE

(h) ZERO POINT-CTMS PIPELINE

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e /14


CP System Maintenance Report of GTCL Pipelines (PART-C) Month: February, 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT

Pipeline Name: Bakhrabad-Demra (BKB-D) High Pressure Gas Transmission Pipeline


(20″ od, 68.72km)
Min
PSP
SI. Test Location PSP Pipe PSP
Location Casing” Inspection Date Remarks
No Ref No (km) 24” -mV req.
-mV
-mV
1 01 0.00 Bakhrabad Gas Field 1184 850 14.02. 2021 CP Station

2 16 15.50 Malikhi 1220 850 14.02. 2021

3 20 20.75 Goripur TBS & CPS-02 1490 850 14.02. 2021 CP Station

4 28 34.75 Baushiya - 2 1321 850 14.02. 2021

Dewanbag TBS & CPS- 14.02. 2021


5 46 59.00 1025 850 CP Station
03
CGS Demra Test Post- 14.02. 2021
6 56 68.00 1072 850
06

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e /15


CP System Maintenance Report of GTCL Pipelines (PART-C) Month: February, 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT

Pipeline Name: Bakhrabad-Chattogram (BKB-CHT) High Pressure Gas Transmission Pipeline


(24″ od, 178km)
Test PSP Min PSP
SI. Location PSP Pipe
Post Location Casing req. Inspection Date Remarks
No (km) 24” -mV
No. -mV -mV
1 1 0.00 Bakhrabad Gas Field-1 1205 850 15.02. 2021

2 11 10.50 Gandra 1184 850 15.02. 2021

3 28 44.90 Bijra Road Crossing 1276 850 15.02. 2021

4 30 50.00 Laksham TBS CP Station 1378 850 15.02. 2021 CP station


5 39 56.00 South Nor-Potti 1291 850 15.02. 2021

6 47 73.50 Gonoboti MLV-7 1221 850 15.02. 2021


7 53 89.00 Feni CP Station 1355 850 15.02. 2021 CP station

8 59 102.50 Lemua Bridge 1296 850 16.02. 2021


Mitachora TBS & CP 16.02. 2021
9 73 126.00 1368 850 CP station
Station
10 82 147.00 Mirer hat 1321 850 16.02. 2021

11 85 152.00 Barob kunda TBS/Offtake 1425 850 16.02. 2021 CP station


12 88 157.30 Basbaria Bazar 1292 850 16.02. 2021

13 92 164.80 Fokir Hat Jalypalli 1282 850 16.02. 2021

14 99 178.00 Chittagong CGS 1188 850 16.02. 2021

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited
Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e /16
CP System Maintenance Report of GTCL Pipelines (PART-C) Month: February, 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT

Pipeline Name: Bakhrabad-Shiddhirgonj (B-S) High Pressure Gas Transmission Pipeline (30″ od, 60 Km)

Min
Test PSP
SI. Location PSP Pipe PSP Inspection
Post Location Casing” Remarks
No (km) 30” -mV req. Date
No. -mV
-mV
1 01 0.00 Take Off Point Bakhrabad 1155 850 17.02.21

2 14 8.845 Panch-Pukuria Road 1205 850 17.02.21


3 38 30.00 Uttar Nasruddi CP Station 1264 850 17.02.21 CP Station
Shashaner Bag CPS, N.
4 71 55.50 1467 850 17.02.21 CP Station
ganj
5 82 59.823 Inside Siddirganj P.S 1282 850 17.02.21

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited
Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e /17
CP System Maintenance Report of GTCL Pipelines (PART-C) Month: February, 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT

Pipeline Name: Anowara - Fouzdarhat (A-F) High Pressure Gas Transmission Pipeline
(42″ OD, 30km)
PSP
Test PSP Min PSP
SI. Location Pipe Inspection
Post Location Casing” req. Remarks
No (km) 42” - Month
No. -mV -mV
mV
1 1 0.00 Drain Point (Anowara) 1210 850 18.02.21 CP station

2 13 4.04 CUFL Road (US) 1241 1132 850 18.02.21


3 35 16.04 Anando Bazar Road (DS) 1192 850 18.02.21

4 47 23.08 Test post (Petrol Pump) 1262 850 18.02.21


5 53 28.00 Drain point (Salimpur) 1227 850 18.02.21 CP station

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e /18


CP System Maintenance Report of GTCL Pipelines (PART-C) Month: February, 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT

Pipeline Name: Maheshkhali- Anowara (M-A) High Pressure Gas Transmission Pipeline
(30″ od, 91 km)
PSP Min
Test PSP
SI. Location Pipe PSP Inspection
Post Location Casing” Remarks
No (km) 30” - req. Date
No. -mV
mV -mV
1 1 0.00 Zero Popint,Maheshkhali (SP) 1221 850 22.02.21

2 4 4.55 Paiga Bari Khal (SP) 1211 850 22.02.21

3 6 6.75 CTMS Valve Station 1360 850 22.02.21 CP Station

4 17 17.16 Nuna Chara Mat Bazar Road (SP) 1169 850 22.02.21
5 31 28.17 Uzantia River Crossing (DS) 1172 850 22.02.21

6 43 47.42 Napura Valve Station 1239 850 22.02.21 CP Station


7 53 55.44 Ashkaria Road, South Joldi 1232 850 22.02.21

8 62 64.78 Kalipur Road Crossing (DS) 1232 850 22.02.21

9 64 70.46 Banigram Valve Station 1366 850 22.02.21 CP Station

10 77 80.00 Barumchara Road Crossing (US) 1227 850 22.02.21


11 88 91.00 Shah-Mirpur Off-take, Anowara 1176 850 22.02.21

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e /19


CP System Maintenance Report of GTCL Pipelines (PART-C) Month: February, 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT

Pipeline Name: Chattogram-Feni- Bakhrabad (CFB) High Pressure Gas Transmission Pipeline
(36″ od, 178km)
Test PSP Min PSP
SI. Location PSP Pipe Inspection
Post Location Casing req. Remarks
No (km) 24” -mV Date
No. -mV -mV
1 01 0.00 Salimpur Valve Station 1202 850 16.02.21

2 21 7.42 Kadam Rasul Road D.S 1189 850 16.02.21

3 57 14.50 Sonaichari CP Station 1278 850 16.02.21 CP station

4 74 24.25 Barob kunda TBS Road 1357 850 16.02.21


5 92 30.92 Mirherhat Road US 1292 850 16.02.21
6 112 45.00 Mirsari CP Station 1248 850 16.02.21 CP station

7 115 50.00 Mitachora TBS Road 1342 850 16.02.21


8 147 72.02 Uttar Farad Nagar 1291 850 16.02.21

9 155 77.00 Chandpur CP Station 1373 850 16.02.21 CP station

10 157 78.50 Sonagazi Road 1222 850 16.02.21


11 170 84.68 Dagunbhuiyan Road 1272 850 15.02.21
12 199 107.30 Jumarail CP Station 1448 850 15.02.21 CP station

13 232 129 South Perul 1289 850 15.02.21


14 274 150 Jaynagar CP Station 1378 850 15.02.21 CP station
15 291 165 Kutumbopur 1208 850 15.02.21

16 311 181 Bakhrabad CP Station 1345 850 15.02.21 CP station

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e /20


CP System Maintenance Report of GTCL Pipelines (PART-C) Month: February, 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT

Pipeline Name: Maheshkhali- Anowara (M-A) High Pressure Gas Transmission Pipeline
Parallel (42″ od, 79 km)
Min
Test PSP PSP
SI. Location PSP
Post Location Pipe Casing” Inspection Date Remarks
No (km) req.
No. 30” -mV -mV
-mV
1 1 0 CTMS Valve Station 1238 850 23.02.21

2 8 6.78 Time Bazar Chara 1244 850 23.02.21

3 21 16.76 Uttoronolbila CP Station (42”) 1333 850 23.02.21 CP Station


36 24.67 Kamal Chairman Road
4 1292 850 23.02.21
Crossing Down Steam
5 50 34.42 Napura Valve Station 1228 850 23.02.21
6 65 47.25 Uttar Joldi Road 1279 850 23.02.21
79 54.15 Kalipur Road Crossing Down
7 1278 850 23.02.21
Steam
8 89 59.95 Boilgan Road 1411 850 23.02.21

9 113 79.00 Anowara Valve Station 1209 850 23.02.21

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e /21


CP System Maintenance Report of GTCL Pipelines (PART-C) Month: February, 2021

MONTHLY PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT

Pipeline Name: Zero point- CTMS High Pressure Gas Transmission Pipeline (42″ od, 6 km)

Test PSP PSP Min PSP


SI. Location Inspection
Post Location Pipe Casing” req. Remarks
No (km) Date
No. 30” -mV -mV -mV

1 1 0.00 Zero Popint,Maheshkhali (SP) 1221 850 24.02.21


Bagan Bari (Near Beoken
2 4 3.05 1218 850 24.02.21
Bridge)
Panir Chara, UP Streem of
3 6 6.20 1221 850 24.02.21
CTMS
4 8 6.75 CTMS Valve Station 1395 850 24.02.21 CP Station

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e /22


Operation and Maintenance works of the Cathodic Protection System of GTCL Operated Pipelines. PART –C February, 2021

Pipeline Name: Bakhrabad-Demra (BKB-D) High Pressure Gas Transmission Pipeline (20″ od, 68.72km)
1600

1400

1200

1000
PSP (mV)

800
Pipe 20"
Minimum PSP
600

400

200

0
0 15.5 20.75 34.75 59 68
Chainage (km)

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited
Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e /23
Operation and Maintenance works of the Cathodic Protection System of GTCL Operated Pipelines. PART –C February, 2021

Pipeline Name: Bakhrabad-Chattogram (BKB-CHT) High Pressure Gas Transmission Pipeline (24″ od,
178km)
1600

1400

1200

1000
PSP (mV)

800
Pipe 24"

600 Minimum PSP

400

200

0
0 10.5 44.9 50 56 73.5 89 102.5 126 147 152 157.3 164.8 178
Chainage (km)

Md. Saiful Harun


Mansur Ali Project Manager
CP Technician Total Energy Services Limited
Total Energy Services Limited
Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e /24
Operation and Maintenance works of the Cathodic Protection System of GTCL Operated Pipelines. PART –C February, 2021

Pipeline Name: Bakhrabad-Shiddhirgonj (B-S) High Pressure Gas Transmission Pipeline (30″ od, 60 Km)
1600

1400

1200

1000
PSP (mV)

800
Pipe 30"

600 Minimum PSP

400

200

0
0 8.845 30 55.5 59.823
Chainage (km)

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e /25


Operation and Maintenance works of the Cathodic Protection System of GTCL Operated Pipelines. PART –C February, 2021

Pipeline Name: Anowara - Fouzdarhat (A-F) High Pressure Gas Transmission Pipeline (42″ OD, 30km)
1400

1200

1000

800
PSP (mV)

Pipe 42"
600
Minimum PSP

400

200

0
0 4.04 16.04 23.08 28
Chainage (km)

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e /26


Operation and Maintenance works of the Cathodic Protection System of GTCL Operated Pipelines. PART –C February, 2021

Pipeline Name: Maheshkhali- Anowara (M-A) High Pressure Gas Transmission Pipeline (30″ od, 91 km)
1600

1400

1200

1000
PSP (mV)

800
Pipe 30"
Minimum PSP
600

400

200

0
0 4.55 6.75 17.16 28.17 47.42 55.44 64.78 70.46 80 91
Chainage (km)

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e /27


Operation and Maintenance works of the Cathodic Protection System of GTCL Operated Pipelines. PART –C February, 2021

Pipeline Name: Chattogram-Feni- Bakhrabad (CFB) High Pressure Gas Transmission Pipeline (36″ od,
178km)
1600

1400

1200

1000
PSP (mV)

800
Pipe 36"
Minimum PSP
600

400

200

0
0 7.42 14.5 24.25 30.92 45 50 72.02 77 78.5 84.68 107.3 129 150 165 181
Chainage (km)

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited
Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e /28
Operation and Maintenance works of the Cathodic Protection System of GTCL Operated Pipelines. PART –C February, 2021

Pipeline Name: Maheshkhali- Anowara (M-A) High Pressure Gas Transmission Pipeline Parallel (42″ od, 79
km)
1600

1400

1200

1000
PSP (mV)

800
Pipe 42"
Minimum PSP
600

400

200

0
0 6.78 16.76 24.67 34.42 47.25 54.15 59.95 79
Chainage (km)

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e /29


Operation and Maintenance works of the Cathodic Protection System of GTCL Operated Pipelines. PART –C February, 2021

Pipeline Name: Zero point- CTMS High Pressure Gas Transmission Pipeline (42″ od, 6 km)
1600

1400

1200

1000
PSP (mV)

800
Pipe 42"
Minimum PSP
600

400

200

0
0 3.05 6.2 6.75
Chainage (km)

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e /30


CP System Maintenance Report of GTCL Pipelines (PART-C) Month: February, 2021

OPERATION AND MAINTENANCE REPORT OF GTCL


PIPELINES (PART-C) CP SYSTEM

Reporting Month: February ; Year: 2021

SUMMARY OF MONTHLY CP STATION MAINTENANCE


AND
PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e / 31


CP System Maintenance Report of GTCL Pipelines (PART-C) Month: February, 2021

SUMMARY OF MONTHLY CP STATION MAINTENANCE


AND
PIPE TO SOIL POTENTIAL (PSP) SURVEY REPORT

SI Total Completed Quantity Progress


Items Pipeline Name
No. Qty. Previous Current Total (%)
Bakhrabad-Demra

Bakhrabad-Chattogram

Bakhrabad-Shiddhirganj
Monthly
Operation and Anowara-Fouzdarhat
1 Maintenance Maheshkhali-Anowara
736 164 22 186
of CP Stations
Chattogram-Feni-Bakhrabad

Maheshkhali-Anowara (Para.)

Zero Point-CTMS

Bakhrabad-Demra

Bakhrabad-Chattogram

Bakhrabad-Shiddhirganj
Monthly Pipe
Anowara-Fouzdarhat
to Soil
2 1560 332 48 380
Potential Maheshkhali-Anowara
(PSP) Survey
Chattogram-Feni-Bakhrabad

Maheshkhali-Anowara (Para.)

Zero Point-CTMS

3 Support of Transport Vehicle 288 80 8 88

4 Accommodation 252 70 7 77

Remarks:

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e / 32


CP System Maintenance Report of GTCL Pipelines (PART-C) Month: February, 2021

Contract Name: Operation and Maintenance works of the Cathodic


Protection (CP) System of GTCL operated High Pressure Gas
Transmission Pipelines under PART-C.

Contract No: 28.14.0000.234.17.003.19; Dated: 19th December 2019

Conclusion: Pipe to Soil Potential (PSP) readings were found within the
acceptable level which indicates Pipelines are well protected with the Operational
CP System.

Reported by:

Mansur Ali Md. Saiful Harun


CP Technician Project Manager
Total Energy Services Limited Total Energy Services Limited

TOTAL ENERGY SERVICES LIMITED


333/3, Segunbagicha, Ramna, Dhaka-1000
Phone: 8332891, 01814962853
Email: total.energy02@gmail.com
total.energy1@hotmail.com

Gas Transmission Company Limited (GTCL) Pipeline Integrity Department P a g e / 33