Professional Documents
Culture Documents
SWITCHBOARD INSTALLATION
DAR NUMBER:
METHOD STATEMENT
Author Checked Checked Approved
Name
Position
Signature
Date
METHOD STATEMENT FOR 600V
SWITCHBOARD INSTALLATION
A 31/05/2021 N/A
Page 2 of 29
METHOD STATEMENT FOR 600V
SWITCHBOARD INSTALLATION
TABLE OF CONTENTS
Purpose of Document ........................................................................................... 5
Abbreviations ..................................................................................................................... 6
Reference Documents ....................................................................................................... 7
Safety, Health and Environment ........................................................................... 8
Replacement of 600V Switchgear....................................................................... 10
Equipment Dimensions .................................................................................................... 10
Installation Team, Equipment & Tools ............................................................... 14
Site Organization Chart .................................................................................................... 14
Handling Equipment ......................................................................................................... 14
Tools ................................................................................................................................ 14
Testing Equipment’s ........................................................................................................ 14
Materials and Supplies ..................................................................................................... 14
Installation and Removal Methodology ............................................................. 15
Preparation for Temporary 600V Switchboard Installation................................................ 15
Facilitating Works for Temporary 600V Switchboard Installation ...................................... 16
Temporary (& New Final) 600V Switchgear Installation.................................................... 19
Preparation Works for Existing 600V Switchboard Removal ............................................ 21
Facilitating Works for Existing 600V Switchboard Removal.............................................. 21
Existing 600V switchboard Removal ................................................................................ 22
Preparation Works for New 600V Switchboard Installation............................................... 23
Facilitating Works for New 600V Switchboard Installation ................................................ 23
New 600V Switchgear Installation .................................................................................... 24
Preparation Works for Temporary 600V Switchboard Removal........................................ 24
Facilitating Works for Temporary 600V Switchboard Removal ......................................... 24
Temporary 600V Switchboard Removal ........................................................................... 24
PICO Inspection ............................................................................................................... 24
Testing and Commissioning ............................................................................................. 24
Risk and Mitigation Plan ..................................................................................... 24
Contingency Plan ............................................................................................................. 25
Update Existing As-built Drawings and O&M Manuals ..................................................... 25
Emergency Personnel Contact List ................................................................... 25
Emergency Assembly Point................................................................................ 29
Construction Interfaces....................................................................................... 29
Typical Risk Assessments .................................................................................. 29
Appendices .......................................................................................................... 29
Appendix A Hazard Identification, Risk Assessment and Risk Control Procedure ......................... 30
Appendix B Typical Microplanning ................................................................................................ 31
Appendix C Tools and Equipment Checklist.................................................................................. 32
Appendix D Safe Management Plan Covid-19 Safe Start.............................................................. 33
Page 3 of 29
METHOD STATEMENT FOR 600V
SWITCHBOARD INSTALLATION
Appendix E GSM Handling & Installation Instructions 600VAC (and 415VAC Switchgear) ........... 34
Appendix F Existing 600V
Switchboard GA ............................................................................................................................ 35
Appendix G GSM Temporary
600V Switchboard GA................................................................................................................... 36
Appendix H GSM New 600V
Switchboard GA ............................................................................................................................ 37
Page 4 of 29
METHOD STATEMENT FOR 600V
SWITCHBOARD INSTALLATION
Purpose of Document
The Purpose of this document is to define the method & requirements for the installation of Temporary
Traction Equipment (600V Switchboard), removal of Existing Traction Equipment & installation of New
Traction Equipment (600V Switchboard) at Bukit Panjang Light Rapid Transit’s (BPLRT) PDS stations.
This installation method statement is specific to Choa Chu-Kang, Keat Hong, Phoenix, Bukit Panjang,
Pending, Fajar, Jelapang BPLRT stations
It will be reviewed accordingly to suit each specific BPLRT station/site constraints during the installation
of the equipment from temporary to New and the removal of the existing 600V switchboard.
Qualified persons familiar with standard electrical construction practices, electrical equipment, and safety
should perform the work described.
This procedure is developed based on the site survey conducted and discussed with
and
A joint inspection between of the delivery route will be carried out a day before the actual delivery to
ensure that the delivery route is obstruction free.
Page 5 of 29
METHOD STATEMENT FOR 600V
SWITCHBOARD INSTALLATION
Abbreviations
Abbreviation Description
AC Alternating Current
ACDB Alternating Current Distribution Boards
DCDB Direct Current Distribution Boards
BPLRT Bukit Panjang Light Rapid Transit
BP01 Bukit Panjang Station 01
CCK Chua Chu Kang
CT Current Transformer
DC Direct Current
EWR Engineering Works
FO Fiber Optic
kV Kilo Volt
LEW Licensed Electrical Worker
MCC Motor Control Centre
OTDR Optical Time Domain Reflectometer
PDS Power Distribution Substation
PTW Permit to Work
SPPG Singapore Power Grid
TMJ Ten Mile Junction
TBD To be determined
TCS Trip circuit supervision
VT Voltage Transformer
Page 6 of 29
METHOD STATEMENT FOR 600V
SWITCHBOARD INSTALLATION
Reference Documents
The present document is mainly based upon and refers to the following documents:
Page 7 of 29
METHOD STATEMENT FOR 600V
SWITCHBOARD INSTALLATION
will identify potential noise nuisance and will arrange for any required measurements to be made as per
the Noise Management Plan [5]. Where it is impractical to reduce noise levels below 85dB (A), hearing
protection and noise prevention measures will be made available.
All construction activities shall be carried out in such a manner to avoid, minimize, or prevent injury to
persons and damage to property, both on the site and off the site. The potential hazards and
recommended actions identified shall be always paid attention to by the supervisors. Details from the
Risk Assessments (RA) shall form part of the safety induction to be given by the safety officer or
delegated Manager prior to work activities commencing.
The safety induction courses, and training will be conducted to all labour teams and each employee will
be issued appropriate Personal Protective Equipment (PPE) for their work activities. PPE issued will be
Page 8 of 29
METHOD STATEMENT FOR 600V
SWITCHBOARD INSTALLATION
used by all personnel and as detailed in the JSA. In general, the following types of PPE will be worn
during construction activities.
In alignment with National efforts, l has put in place a protocol regarding Covid-19 pandemic, refer to
Safe Management Plan in Appendix D.
Any potential hazards arising from Power Supply installation works shall be mitigated or prevented
by:
Hazard Analysis and Mitigation identifies the anticipated potential hazards arising from the
construction activities involved in this Methodology and identifies the recommended actions which
can be taken prior to or during execution of such construction activity to reduce or mitigate each
hazard to the maximum extent. The Risk Assessments may require revisions as activities changes,
accident, incident, or close call occurrences and/or periodical review is due.
Each Supervisor will implement and enforce the recommended actions and check the safety
requirements in the Safety Work procedures applicable to this Methodology to ensure that the work
is performed in a safe manner.
Risk assessment for the works will be addressed in each individual method statement. The method
for risk assessment of a particular work will be given in the reference document.
Page 9 of 29
METHOD STATEMENT FOR 600V
SWITCHBOARD INSTALLATION
Due to the nature of the equipment and the fact that they are required to operate during
normal revenue services, a temporary board will be used to replace the existing one. It will
be installed in the LT room. By using a temporary board, the existing can be taken offline
creating a green-field worksite without having to impact the revenue operations.
Equipment Dimensions
The Temporary and New switchboards shall be sourced from GSM Pt. Ltd. Below are the
switchboards’ dimensions, and sample GA and floor frame, for illustration purposes, BP12 600V
equipment were used. For actual execution of installation refer to respective correct, latest issued
drawings.
Switchboard Dimension
Page 10 of 29
METHOD STATEMENT FOR 600V
SWITCHBOARD INSTALLATION
Temporary 600V switchboard will be installed in the LT room. For additional details on this
equipment, refer to the specific vendor (GSM) general arrangement drawings and singe
line diagrams.
Page 11 of 29
METHOD STATEMENT FOR 600V
SWITCHBOARD INSTALLATION
As an example: SB-BP12-2 :
As an example: SB-BP12-1:
Page 12 of 29
METHOD STATEMENT FOR 600V
SWITCHBOARD INSTALLATION
As an example: SB-BP12-2 :
As an example: SB-BP12-1:
PLC
Figure 3-1-5 – BP12 600V Existing Switchboard (GA), for Removal
Page 13 of 29
METHOD STATEMENT FOR 600V
SWITCHBOARD INSTALLATION
For the roles and responsibilities of site personnel, refer to Installation Plan [7].
For the list of Competency Certificates, refer to Appendix XX.
Handling Equipment
Hand Pallet Truck
Crow bars
Transport devices (rollers, cylindrical pipe etc.)
Pallet Jacks
Wooden Block
Lorry Crane, Tailgate lorry, Forklift
Tools
Hand tools set
Screwdriver set
Spanner set.
Torque Wench set, Ratchet wrench set
Cordless Impact Driver
Battery Operated Hammer Drill
300mm spirit level, Measuring tape
2 set Platform ladders
Touch-up material, paint, and brush
Testing Equipment’s
Digital Multimeter
Insulation & Continuity Tester
Digital Low Resistance OHM Meter
Page 14 of 29
METHOD STATEMENT FOR 600V
SWITCHBOARD INSTALLATION
LT room work area should be checked for hazard frees and cleanliness.
Page 15 of 29
METHOD STATEMENT FOR 600V
SWITCHBOARD INSTALLATION
The panel lamp seem to indicate that it is already de-energized which must be verified and
decommissioned before we start to removal works.
Another factor is before the installation of 600V switchboard, protection/control interface between
22kV switchgear and existing 600V switchboard may be rewired through this ITB as an option to have
an easier approach to multiple migration between 22kV switchgear and 600V switchboard.
Installation of cable containment for the temporary to cover the ff temporary power cables:
Power cables from 22kV/600V Traction Transformers TT501 & TT502 to temporary 600V
switchboard SB-TA10
Power cables from temporary 600V switchboard’s six track feeders to JB-101 to 103 & JB-201
to JB-203 plus power cables to JB-104 & JB-204 adjacent gap stations BPN+1 & BPN-1.
Power cables from temporary 600V switchboard to existing service transformers A10T4 & A10t5
& guideway transformer A10T3
For an illustration of the approximate minimum cable containment works required, the Power
cable route is highlighted yellow in the below Power Cable Containment and Support illustration.
Page 16 of 29
METHOD STATEMENT FOR 600V
SWITCHBOARD INSTALLATION
Installation of cable containment for the temporary and new control cables from ITBs to existing
equipment and temporary equipment (i.e. 600V switchboard, ETS & Vital Relay panel, battery, and
charger etc.) and later new equipment (PSCADA etc)
For an illustration of the minimum approximate cable containment works required, the control
cable route is highlighted green in the below control Cable Containment and Support illustration
Page 17 of 29
METHOD STATEMENT FOR 600V
SWITCHBOARD INSTALLATION
After the installation of the cable containment both for power and control we procced with installation
of temporary 600V switchgear at LT room. (refer to section 5.2))
After the installation of the temporary 600V switchgear at LT room, proceed with temporary 600V
Switchboard Site Acceptance Test (refer to DAR/R801/SAT/6025)
Installation of 600V Junction Boxes for traction feeders and adjacent stations’ service transformers
feeders. * (see note 1)
Installing these 600V Junction Boxes at the mezzanine would allow traction feeders and adjacent
stations’ service transformers’ feeders to transfer/migrate one by one form existing to temporary board.
600V switchboard’s six track feeder JB-101 to 103 & JB-201 to JB-203
Adjacent gap service stations BPN+1 & BPN-1 transformer feeder JB-104 & JB-204
(Note 1: Can be done prior to, in parallel to or after installation of temporary 600V switchboard, before migration.)
Installation of outdoor temporary 600V cable containment for traction feeders and adjacent stations’
service transformers feeders’ cables to 600V JBs at mezzanine (see note 1)
(Note 1: Can be done prior to, in parallel to or after installation of temporary 600V switchboard, before migration.)
Page 18 of 29
METHOD STATEMENT FOR 600V
SWITCHBOARD INSTALLATION
Temporary
600V cable from 1st
Temporary Cable storey LT room
Containment (600V)
Doghouse
450 mm 3800 mm
Figure 5-2-3 Area at mezzanine for the 600V JB and cable containment (BP12)
Page 19 of 29
METHOD STATEMENT FOR 600V
SWITCHBOARD INSTALLATION
Note: Refer to vendor (GSM) Handling and Installation instructions for details
Degree of Protection
Depending on the degree of protection, measures are required to be taken at the erection site to seal
the sections to comply to IP rating.
Page 20 of 29
METHOD STATEMENT FOR 600V
SWITCHBOARD INSTALLATION
At the end of the work remove all barricades, signage, tools, and materials from the workplace.
Housekeeping shall be done after completing task activities on working area.
After the installation of the temporary 600V switchgear at LT room, refer with temporary 600V
Switchboard Site Acceptance Test (refer to DAR/R801/SAT/2004.)
Page 21 of 29
METHOD STATEMENT FOR 600V
SWITCHBOARD INSTALLATION
Step-04
Page 22 of 29
METHOD STATEMENT FOR 600V
SWITCHBOARD INSTALLATION
At the end of the work remove all barricades, signage, tools, and materials from the workplace.
Housekeeping shall be done after completing task activities on working area.
Figure 5-6-2 Existing 600V Switchboard for Removal as Shown in the Plan (BP12)
For PDS stations with Guideway Switch Transformer, the incomer to the Guideway Transformer shall
be secured by two redundant feeders from the new 600V switchboard. The two redundant incoming
supplies shall be managed by an Automatic Transfer Switch Panel.
Page 23 of 29
METHOD STATEMENT FOR 600V
SWITCHBOARD INSTALLATION
The new NGR will be connected to traction transformer secondary star point and subsequently to
earth. An NGR monitoring relay be installed (by the new 600Vac switchboard manufacturer) in their
panel.
Installation of Auxiliary 230VAC and 110VDC cable containment and cable laying
Cable containment for the Auxiliary 230VAC and 110VDC, to be installed and cables can be pre-laid
before or after installation of new 600V switchboard.
PICO Inspection
Check and verify against the approved reference drawing.
Conduct a visual inspection on all installed cubicles when handling.
Page 24 of 29
METHOD STATEMENT FOR 600V
SWITCHBOARD INSTALLATION
Contingency Plan
To avoid any disruption to power supply system while carrying out the replacement works; the following
measures must be complied:
1) Critical spares to be available all the time.
2) Provide adequate spare termination kit and accessories
3) Authorized Personnel (AP), 2 Grade 9 Licensed Electrical Worker (LEW) and Testing Engineer and
testing team full time on Site during Migration works
4) Appoint 24 hours on-call personnel to attend to fault
Proposed
Personnel Name Contact Number
Response Time
During the migration period, the Authorized personnel (AP), Licensed Electrical Worker (LEW), the
testing engineer and Installation Supervisor will be full time on site during the working hours. If any fault
occurs, it will be immediately attended by at least the one of above-mentioned personnel who will decide
whether required any further action.
Above proposed response times are for illustration and based on time to site from any notification,
everyone will respond immediately to call and will be briefed by the Project Manager prior start of
migration.
Tabletop exercise shall be conducted to brief ERT team on their roles and responsibility in the event of
Fire and Explosion.
Page 25 of 29
METHOD STATEMENT FOR 600V
SWITCHBOARD INSTALLATION
- Explosion or fire damage to the structure of any room or place in which persons are at work, or
to any machinery or plant contained therein, and resulting in the complete suspension of
ordinary work in the room or place or stoppage of machinery or plant for not less than 5 hours,
where the explosion or fire is due to the ignition of dust, gas or vapor, or the ignition of celluloid
or substance composed wholly or in part of celluloid.
- Electrical short circuit or failure of electrical machinery, plant, or apparatus, attended by
explosion or fire or causing structural damage thereto, and involving its stoppage or disuse for
not less than 5 hours.
- Explosion or fire affecting any room in which persons are at work and causing complete
suspension of ordinary work therein for not less than 24 hours.
Page 26 of 29
METHOD STATEMENT FOR 600V
SWITCHBOARD INSTALLATION
Fire / Explosion
Observer’s shout
‘Help, Help, Help’
Inform MD
First-aid assess the
severity of the injury.
Inform
Conduct
CRSPL will inform Situation under
investigation for the
areas that can control
causes within the
resume work.
affected area.
Page 27 of 29
METHOD STATEMENT FOR 600V
SWITCHBOARD INSTALLATION
Incident occurs
Assess the
damage
Arrival of Police/SCDF to
take charge of the situation
and send injured to hospital
via ambulance.
Page 28 of 29
METHOD STATEMENT FOR 600V
SWITCHBOARD INSTALLATION
Construction Interfaces
The construction interface during the operation between the equipment deliveries and other’s activities
are:
Appendices
Page 29 of 29
METHOD STATEMENT FOR 600V
SWITCHBOARD INSTALLATION
Appendix A
Hazard Identification, Risk Assessment and Risk Control Procedure
Appendix B
Typical Microplanning
Appendix C
Tools and Equipment Checklist
Appendix D
Safe Management Plan Covid-19 Safe Start
Appendix E
GSM Handling & Installation Instructions 600VAC (and 415VAC
Switchgear)
Appendix F
Existing 600V Switchboard GA
Appendix G
GSM Temporary 600V Switchboard GA
Appendix H
GSM New 600V Switchboard GA