DESIGN & BUILT PACKAGE 4

GREEN LINE UNDERDROUND


Date-: 12-02-2019
CONSTRUCTION DAILY REPORT – GREEN LINE UNDERGROUND FIRE TELEPHONE SYSTEM
9Project : GREEN LINE UNDERGROUND
Client : Qatar Rail
PMCS : MEINHARDT (SINGAPORE) PTEL LTD QATAR
Name of Contractor : PSH
Name of Subcontractor : Q-MEP
Name of Sub-Subcontractors : HTC
Site / Location of Work : AL QADEEM *
Date : 12-02-2019 Temperature-: Day Night
Weather :

1- MAJOR ACTIIVITIES :

CONCOURSE LEVEL PLATFORM& UNDERPLATFORM 30 BACKBOX TERMINATION COMPLETED.


CONCOURSE LEVEL PLATFORM& UNDERPLATFORM 7 JACKBOX TERMINATION COMPLETED
Station 1 Al QADEEM
GRADE LEVEL

1-
2-
3
CONCORSE LEVEL
1-
2-

1
DESIGN & BUILT PACKAGE 4
GREEN LINE UNDERDROUND
Date-: 12-02-2019
CONSTRUCTION DAILY REPORT – GREEN LINE UNDERGROUND FIRE TELEPHONE SYSTEM
3
PLAT FORM LEVEL
1
2
3

UNDER PLATFORM
1
2
3

Station 2 AL SHAQAB
GRADE LEVEL

1-
2-

CONCORSE LEVEL
1-
2-

PLAT FORM LEVEL

2
DESIGN & BUILT PACKAGE 4
GREEN LINE UNDERDROUND
Date-: 12-02-2019
CONSTRUCTION DAILY REPORT – GREEN LINE UNDERGROUND FIRE TELEPHONE SYSTEM
1
2

UNDER PLATFORM
1
2
3

Station 3 QNL ST
GRADE LEVEL

1-
2-

CONCORSE LEVEL
1- Concourse level west 300meters cable pulling completed.
2- Concourse level central 540meters cable pulling completed.

PLAT FORM LEVEL


1 Platform east&west 5 jackbox&cc1 box installed.
2 Platform east 250meters cable pulling completed

UNDER PLATFORM
3
DESIGN & BUILT PACKAGE 4
GREEN LINE UNDERDROUND
Date-: 12-02-2019
CONSTRUCTION DAILY REPORT – GREEN LINE UNDERGROUND FIRE TELEPHONE SYSTEM
1 Platform east&west 6 jackbox&cc1 box installed.
2
3

2- MANPOWER DETAILS :
First Shift : Second Shift :

TOTAL

TOTAL
DESIGNATION
Q-MEP Q-MEP
SUB-CONTRACTORS SUB-CONTRACTORS

4
DESIGN & BUILT PACKAGE 4
GREEN LINE UNDERDROUND
Date-: 12-02-2019
CONSTRUCTION DAILY REPORT – GREEN LINE UNDERGROUND FIRE TELEPHONE SYSTEM

Q-MEP

Q-MEP
HTC

HTC
Project Director / Management 1 1
QA/QC 1
Engineer 2
Site Doctor
HSE Officer/Nurse 1
Land Surveyor
Doc. Controller
Survey Assistant
Management and indirect
Time Keeper
Storekeeper 1
Office Boy
Security
Visitors
Others (Admin, Account,
Designer &Planner, QS, ETC.)
Total: 3 4 7

3 FirstShift: Second Shift :

TOTAL

TOTAL
5
DESIGN & BUILT PACKAGE 4
GREEN LINE UNDERDROUND
Date-: 12-02-2019
CONSTRUCTION DAILY REPORT – GREEN LINE UNDERGROUND FIRE TELEPHONE SYSTEM

DESIGNATION
Q-MEP Q-MEP
SUB-CONTRACTORS SUB-CONTRACTORS

Q-MEP
Q-MEP

HTC
HTC
Foreman/Supervisor/CH 4
Driver/Operator 3
Scaffolder
Carpenter
Mason
Direct (site) Steel fixer / Erector
Electrician 16
Technician / Helper 28
Mechanic & Auto Elec
Plumber
Welder
Unskilled Workers
Pipe Fitter
Rigger/Flagman
Other Skilled Workers

6
DESIGN & BUILT PACKAGE 4
GREEN LINE UNDERDROUND
Date-: 12-02-2019
CONSTRUCTION DAILY REPORT – GREEN LINE UNDERGROUND FIRE TELEPHONE SYSTEM
   TOTAL 5 44
4- MATERIAL DELIVERY :
No Material Descriptions Quantity Unit Supplier Reference No
1 25mm Conduit pipe 2Nos 60Mtr
2 single way box 1Box
3 L box 20 Nos
4 Flexible cable 1 box
5 Copper push male 1box
6 Copper push big 1box
7 Coupler 2boxes
8 Jack box 12Nos
9 Back box 12Nos
10 Fire rated cable 1000 meters
11 jackbox 5 nos
12
13

5 REMARKS ANDNOTES:

1. CABLE PULLING AND JACKBOX CC1 BOX INSTALLATION GOING ON


2-
3-

7
DESIGN & BUILT PACKAGE 4
GREEN LINE UNDERDROUND
Date-: 12-02-2019
CONSTRUCTION DAILY REPORT – GREEN LINE UNDERGROUND FIRE TELEPHONE SYSTEM
4-

8
DESIGN & BUILT PACKAGE 4
GREEN LINE UNDERDROUND
Date-: 12-02-2019
CONSTRUCTION DAILY REPORT – GREEN LINE UNDERGROUND FIRE TELEPHONE SYSTEM

9
DESIGN & BUILT PACKAGE 4
GREEN LINE UNDERDROUND
Date-: 12-02-2019
CONSTRUCTION DAILY REPORT – GREEN LINE UNDERGROUND FIRE TELEPHONE SYSTEM

10
DESIGN & BUILT PACKAGE 4
GREEN LINE UNDERDROUND
Date-: 12-02-2019
CONSTRUCTION DAILY REPORT – GREEN LINE UNDERGROUND FIRE TELEPHONE SYSTEM

11
DESIGN & BUILT PACKAGE 4
GREEN LINE UNDERDROUND
Date-: 12-02-2019
CONSTRUCTION DAILY REPORT – GREEN LINE UNDERGROUND FIRE TELEPHONE SYSTEM

12