Proposed Renovation, Refurbishment & Improvements of Existing Old MJF stores Complex, Maligawatte,

Sri Lanka

Item No
Description Unit Quantity Rate Amount

A Preliminaries

A001
Allow for the cost of construction and maintenance of
temporary sheds to accommodate the contractor's staff
Client will Provide the
and workmen, outside the site (elsewhere) during the Item 1.00
facilities
contract period and demolition and removal on practical
completion

A002
Allow for the cost of construction and maintenance of
sanitary facilities for all staffs and workmen at the site Client will Provide the
Item 1.00
during the contract period and demolition and removal on facilities
practical completion.

Client will Provide the


facilities
A003
Allow lump sum for the cost of construction and
maintenance of the contractor's temporary office Client will Provide the
Item 1.00
during the contract period and demolition and removal on facilities
practical completion.

A004 Allow for providing water and electricity for construction


Item 1.00 50,000.00 50,000.00
work during the contract period.

A005 Allow lump sum for two sets of As Built Drawings on


Item 1.00 30,000.00 30,000.00
completion of works including shop drawings.

A006 Allow for site communication facilities including


Item 1.00 15,000.00 15,000.00
telephone & Fax machine

A007 Allow for protecting and safe guarding works Item 1.00 20,000.00 20,000.00

A008 Allow for setting out of works in accordance with


drawings and other written information given by the Item 1.00 50,000.00 50,000.00
Engineer time to time.

A009 Allow for Project management Item 1.00 50,000.00 50,000.00

A010
Allow lump sum for the cost of demolishing and removal
of all temporary works, clearing and cleaning the site to a
Item 1.00 50,000.00 50,000.00
presentable manner at the time of handing over on the
practical completion of the works.

Bonds and Guarantees


Item No
Description Unit Quantity Rate Amount

A011 Allow lump sum for Providing "Contractors All Risks


Insurance " Policy including third party cover and fire, as Item 1.00 40,000.00 40,000.00
prescribed in the contract.

A012 Allow lump sum for providing "Workmen's


Item 1.00 40,000.00 40,000.00
Compensation" insurance policy.

A013
Allow lump sum for providing an approved Performance
Bond for 10% of the Contract Sum payable "on Demand"
Item 1.00 100,000.00 100,000.00
from Bank for contract period and defects liability period
of one year.

A014
Allow lump sum for providing an approved Advance
Guarantee Bond for 20% of the Contract Sum (excluding
Item 1.00 50,000.00 50,000.00
provisional sums and contingencies ) payable "on
Demand" from Bank

A015
Allow lump sum for providing any other work that the
tenderer deems necessary for the proper execution and
completion of the works but not listed above. Tenderers Item 1.00 -
shall insert below the details of, such work with costs. (If
space provided is insufficient attach separate list)

a) Bid bond Item 1.00 50,000.00 50,000.00

b) Name board Item 1.00 N/A

c) First aid facilities Item 1.00 20,000.00 20,000.00

e) Safety equipment Item 1.00 50,000.00 50,000.00

f) others if any item 1.00

Total Amount of Preliminaries Works Carried To Summary (Rs.) 615,000.00


Proposed Renovation, Refurbishment & Improvements of Existing Old MJF stores Complex, Maligawatte,
Sri Lanka

Item No Description Unit Quantity Rate Amount

B Demolition & Dismantling

Allow cost for removing existing roof structure (North,


centre & south wing) including ceiling items necessary and
-
to be handed over to the client with other all necessary
accessories.
B 001 North wing Item 1.00 588,000.00 588,000.00
B 002 Centre wing Item 1.00 470,000.00 470,000.00
B 003 South wing Item 1.00 748,000.00 748,000.00

Total Amount of Demolition and dismantling Works Carried To Summary (Rs.) 1,806,000.00
Proposed Renovation, Refurbishment & Improvements of Existing Old MJF stores Complex, Maligawatte, Sri Lanka

Item No Description Unit Quantity Rate Amount

H 001 Roof Structure

Structural steel beams as structural steel schedule the drawing.


All rate inclusive of base plate ,gusset plate, necessary haunches
sand blasting and apply two coats of approved anti corrosive
paint and two coats of approved good quality paint. All
complete works as per the structural drawings and
specifications.

Roof Beams
H 001 North wing kg 11,591.63 480.00 5,563,982.40
H 002 South wing kg 12,980.99 480.00 6,230,875.20

In Roof ,sandwich panel roofing sheet of thickness 35mm ,sheet


thickness 0.47mm and panel weight 9.69kg/m2 Rate shall also
inclusive of 0.47mm the. End cap at sandwich panel ends
,standard. tar sheet and other related works as per drawings
LYSAGHT TRIMDEK OPTIMA 0.47mm(TCT) thick roof
sheet & 0.47 LYSAGHT PANELRIB 0.47mm(TCT) thick
ceiling sheet, and galvanized "C" purlins of size 200mm x
75mm X 20mm X 2mm thick lipped channel as per the
structural drawings. .Rate for gutters and downpipes will be
paid separately. Rate is included Aluminum Foil 6mm(thick),
PE Bubbles with High Resistance Anti-Corrosive in Both
Side.

H 003 North wing m2 733.92 7,775.00 5,706,228.00


H 004 South wing m2 1,077.77 7,775.00 8,379,661.75

Do- of gutters size 300m height 250mm width given at eave


with galvanized steel brackets at 600 intervals fixed on eave
H 005 l.m. 175.67 2,650.00 465,525.50
truss as per the details given by the engineer. All complete work
as per the architectural and structural drawings

Do- of valley gutters size of 300mm height 250mm with


galvanized steel brackets at 600 intervals fixed on eave truss as
H 006 l.m. 45.28 2,450.00 110,926.20
per the details given by the engineer. All complete work as per
the architectural and structural drawings

Zinc alum valley gutter flashing (0.47mm thick) and 2'6" wide
H 007 l.m 53.96 2,450.00 132,202.00
bent to shape and fixed to wall
Supply and installation of 110mmdia Type 400 PVC Down
Pipes fixed on rain water outlets at corners of roof top .All
H 008 m 115.92 2,150.00 249,228.00
complete work as per the relevant standards and
architectural/structural drawings

Supply and installation of 110mm dia rain water outlet at roof


H 009 Nos 12.00 5,000.00 60,000.00
top. Rate shall include for all complete work.

Total Amount of Roof Works Carried To Summary (Rs.) 26,898,629.05


Proposed Renovation, Refurbishment & Improvements of Existing Old MJF stores Complex, Maligawatte,
Sri Lanka

Summary

Item No Description Details of BOQ Item Total Amount (Rs.)


A Bill No 01 Preliminaries 615,000.00
B Bill No 02 Demolition & Dismantle 1,806,000.00
C Bill No 03 Roof Work 26,898,629.05
Sub Total 29,319,629.05
10% Contingencies 2,931,962.91
Grand Summary 32,251,591.96