Professional Documents
Culture Documents
SiSa COS-RA - Corrected by AE - 06.05.2020-1
SiSa COS-RA - Corrected by AE - 06.05.2020-1
2.02 Providing and Construction of Embankment with approved materials Ref. RA Item No.
from borrow areas Cum 230.34 - 3.16
6.01 a Excavation for Structures in Ordinary Soil upto 3 m depth (By
Mechanical Means) Ref. RA Item No.
Earth work in excavation of foundation of structures as per drawing Cum 57.66 - 12.01 I-B
and technical specification.
6.02 a Providing and laying PCC for leveling course below foundation &
Ref. RA Item No.
approach slab Cum 7,175.76 - 12.04 (i)
PCC Grade M-10
6.02 b Providing and laying PCC for leveling course below foundation &
Ref. RA Item No.
approach slab Cum 7,313.46 - 12.08 A (ii)
PCC Grade M-15
6.20 c Structural Cement Concrete in Open Foundation for piers,
abutments, wing walls, retaining walls etc including formwork,
excluding reinforcement complete as per drawing & Technical Ref. RA Item No.
Cum 7,848.07 - 12.08 G-(ii)
Specification.
RCC Grade M-30
6.20 d Structural Cement Concrete in Open Foundation for piers,
abutments, wing walls, retaining walls etc including formwork,
excluding reinforcement complete as per drawing & Technical Ref. RA Item No.
Cum 7,941.88 - 12.08 H-(ii)
Specification.
RCC Grade M-35
6.22 c Structural Cement Concrete in Substructure for piers, abutments,
wing walls, retaining walls, etc. including formwork, excluding
reinforcement complete as per drawing & Technical Specification. Ref. RA Item No.
Cum 8,341.94 - 13.05 G-(p) II
RCC Grade M-30
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.080 284.10 22.73 L-12
Mazdoor day 2.000 263.05 526.10 L-13
b) Machinery
Hydraulic excavator 0.9 cum bucket hour 6.000 1554.00 9324.00 P&M-026
capacity @ 60 cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 16.000 370.00 5920.00 P&M-048
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 284.10 11.36 L-12
Mazdoor day 1.000 263.05 263.05 L-13
b) Machinery
Hydraulic Excavator1 cum bucket hour 1.670 1554.00 2595.18 P&M-026
capacity @ 60 cum per hour
Tipper 10 tonne capacity Lead L = 8 km t.km 160 x L 2.96 3788.80 P&M-058
Add 10 per cent of cost of carriage to 378.88
cover cost of loading and unloading
Dozer 80 HP for spreading @ 200 cum hour 0.500 4440.00 2220.00 P&M-014
per hour
Motor grader for grading @ 100 cum per hour 1.000 2858.25 2858.25 P&M-032
hour
Water tanker6 KL capacity hour 4.000 370.00 1480.00 P&M-060
Vibratory roller 8 -10 tonnes @ 100 cum hour 1.000 1838.90 1838.90 P&M-059
per hour
c) Material
Cost of water KL 24.000 50.00 1200.00 M-189
Compensation for earth taken from cum 100.000 35.00 3500.00 M-092
private land
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 284.10 11.36 L-12
Mazdoor day 1.000 263.05 263.05 L-13
b) Machinery
Hydraulic excavator1 cum bucket hour 1.670 1554.00 2595.18 P&M-026
capacity @ 60 cum per hour
Tipper 10 tonne capacity Lead L = 11 km t.km 175 x L 2.96 5698.00 P&M-058
Add 10 per cent of cost of carriage to 569.80
cover cost of loading and unloading
Dozer 80 HP for spreading @ 200 cum hour 0.500 4440.00 2220.00 P&M-014
per hour
Motor grader for grading @ 50 cum per hour 2.000 2858.25 5716.50 P&M-032
hour
Water tanker with 6 km lead hour 4.000 370.00 1480.00 P&M-060
Vibratory roller 8-10 tonnes @ 80 cum hour 1.250 1838.90 2298.63 P&M-059
per hour
c) Material
Cost of water KL 24.000 50.00 1200.00 M-189
Compensation for earth taken from cum 100.000 35.00 3500.00 M-092
private land
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.400 284.10 113.64 L-12
Mazdoor skilled day 2.000 278.84 557.68 L-15
Mazdoor day 8.000 263.05 2104.40 L-13
b) Machinery
Mortar Grader 110 HP @ 50 cum per hour 6.000 2858.25 17149.50 P&M-032
hour
Vibratory roller 8 -10 tonne hour 6.000 1838.90 11033.40 P&M-059
Water tanker 6 KL capacity hour 7.700 370.00 2849.00 P&M-060
c) Material
Grading-IV - As per Design Mix (For One Cum) 2.148 7.13
Shieve Size (mm) % Retained Cum Wt Retained % Passing
53.00 tonne 0.00% 0.000 100.00%
26.50 tonne 35.10% 64.90%
9.50 tonne 68.08% 1.462 31.92%
4.75 tonne 77.29% 22.71%
2.36 tonne 89.22% 1.916 10.78%
0.75 tonne 97.25% 2.75%
0.00 tonne 100.00% 2.148 0.00%
Material for 300 cum (Density = 1.548 MT/Cum)
GSB 53 mm to 9.5 mm cum 283.387 2186.20 619539.62 DM-20
GSB 9.5 mm to 2.36 mm cum 88.001 1913.43 168384.57 DM-22
2.36 mm below cum 44.891 1867.12 83817.11 DM-24
Cost of water KL 45.946 50.00 2297.29 M-189
Unit = cum
Taking output = 495 tonnes
a) Labour
Mate day 0.480 284.10 136.37 L-12
Mazdoor skilled day 2.000 278.84 557.68 L-15
Mazdoor day 10.000 263.05 2630.50 L-13
b) Machinery
Wet mix plant of 75 tonne hourly hour 9.000 1437.45 12937.05 P&M-094
capacity
Electric generator 125 KVA hour 6.000 832.50 4995.00 P&M-018
Front end loader 1 cum capacity hour 6.000 962.00 5772.00 P&M-017
Paver finisher hour 6.000 1163.65 6981.90 P&M-035
Vibratory roller 8 - 10 tonne hour 6x0.65 1838.90 7171.71 P&M-059
or
Smooth 3 wheeled steel roller @ 8-10 hour 12.000
tonnes.
Water tanker 6 KL capacity hour 5.500 370.00 2035.00 P&M-060
Tipper tonne.k 495 x L 2.96 7809.52 P&M-058
m
Add 10 per cent of cost of carriage to 780.95
cover cost of loading and unloading
c) Material - As per Design Mix (For One MT) Density Lab Density = 2.195
Aggregate 40 mm tonne 0.340 1.299 MT/cum 34.00%
Aggregate 20 mm tonne 0.180 1.322 MT/cum 18.00%
Aggregate 10 mm tonne 0.185 1.338 MT/cum 18.50%
Stone Dust tonne 0.295 1.485 MT/cum 29.50%
Water tonne 0.067 6.68%
Material (for 495 MT)
Aggregate 40 mm cum 129.561 3101.00 401769.28 DM-30
Aggregate 20 mm cum 67.398 3637.85 245183.39 DM-35
Aggregate 10 mm cum 68.442 3317.81 227076.57 DM-46
Stone Dust cum 98.333 2956.47 290719.55 DM-55
Water KL 33.066 50.00 1653.30 M-189
Unit = cum
Taking output = 450 tonnes MT 450.000
a) Labour
Mate day 0.840 284.10 238.64 L-12
Mazdoor working with HMP, mechanical day 16.000 263.05 4208.80 L-13
broom, paver, roller, asphalt cutter and
assistance for setting out lines, levels
and layout of construction
Skilled mazdoor for checking line & day 5.000 278.84 1394.20 L-15
b) levels
Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 20658.95 123953.70 P&M-022
Paver finisher hydrostatic with sensor hour 6.000 3191.25 19147.50 P&M-034
control @ 75 cum per hour
Generator 250 KVA hour 6.000 832.50 4995.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 962.00 5772.00 P&M-017
Tipper 10 tonne capacity tonne.k 450 x L 2.96 14212.44 P&M-058
m
Add 10 per cent of cost of carriage to cover 1421.24
cost of loading and unloading
smooth wheeled roller 8-10 tonnes for hour 6.00x0.65* 549.45 2142.86 P&M-044
initial break down rolling.
Vibratory roller 8 tonnes for intermediate hour 6.00x0.65* 1838.90 7171.71 P&M-059
rolling.
Finish rolling with 6-8 tonnes smooth hour 6.00x0.65* 1365.30 5324.67 P&M-045
wheeled tandem roller.
c) Material (Grading-I), As per Design Mix (for 1.00 MT) Density Lab Density = 2.484
Aggregate - 40 mm to 25 mm tonne 0.209 1.365 MT/cum 20.94%
Aggregate - 25 mm to 16 mm tonne 0.124 1.390 MT/cum 12.38%
Aggregate - 16 mm to 12 mm tonne 0.076 1.390 MT/cum 7.62%
Aggregate - 12 mm to 6 mm tonne 0.157 1.374 MT/cum 15.71%
Aggregate - 6 mm passing tonne 0.347 1.457 MT/cum 34.75%
Filler (Stone Dust) tonne 0.038 1.539 MT/cum 3.81%
Bitumen (VG-40) tonne 0.048 4.80%
Unit = cum
Taking output = 450 tonnes MT 450.000
a) Labour
Mate day 0.840 284.10 238.64 L-12
Mazdoor working with HMP, mechanical day 16.000 263.05 4208.80 L-13
broom, paver, roller, asphalt cutter and
assistance for setting out lines, levels
and layout of construction
Skilled mazdoor for checking line & day 5.000 278.84 1394.20 L-15
b) levels
Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 20658.95 123953.70 P&M-022
Paver finisher hydrostatic with sensor hour 6.000 3191.25 19147.50 P&M-034
control @ 75 cum per hour
Generator 250 KVA hour 6.000 832.50 4995.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 962.00 5772.00 P&M-017
Tipper 10 tonne capacity tonne.k 450 x L 2.96 14212.44 P&M-058
m
Add 10 per cent of cost of carriage to cover 1421.24
cost of loading and unloading
smooth wheeled roller 8-10 tonnes for hour 6.00x0.65* 549.45 2142.86 P&M-044
initial break down rolling.
Vibratory roller 8 tonnes for intermediate hour 6.00x0.65* 1838.90 7171.71 P&M-059
rolling.
Finish rolling with 6-8 tonnes smooth hour 6.00x0.65* 1365.30 5324.67 P&M-045
wheeled tandem roller.
c) Material (Grading-I), As per Design Mix (for 1.00 MT) Density Lab Density = 2.456
Aggregate - 37.5 mm to 25 mm tonne 0.053 1.365 MT/cum 5.25%
Aggregate - 25 mm to 16 mm tonne 0.162 1.390 MT/cum 16.24%
Aggregate - 16 mm to 12 mm tonne 0.143 1.390 MT/cum 14.33%
Aggregate - 12 mm to 6 mm tonne 0.201 1.374 MT/cum 20.05%
Aggregate - 6 mm passing tonne 0.363 1.457 MT/cum 36.29%
Filler (Stone Dust) tonne 0.033 1.539 MT/cum 3.34%
Bitumen (VG-40) tonne 0.045 4.50%
c) Material (Grading-2), As per Design Mix (for 1.00 MT) Bulk Density of Aggregate Lab Density = 2.533
Aggregate - 18 mm to 4 mm tonne 0.104 1.390 MT/cum 10.41%
Aggregate - 12 mm to 4 mm tonne 0.213 1.374 MT/cum 21.28%
Aggregate - 8 mm to 4 mm tonne 0.166 1.374 MT/cum 16.56%
Aggregate - 4 mm tonne 0.426 1.374 MT/cum 42.57%
Filler (Stone Dust) tonne 0.038 1.539 MT/cum 3.78%
Bitumen (VG-40) tonne 0.054 5.40%
12.04 (i) Plain Cement Concrete in Levelling Course - Analysis of PCC Using
Using Batching Plant, Transit Mixer and Batching Plant &
Concrete Pump ₹ 7,175.76 Transit Mixer is based
PCC Grade M-10 on Item no. 12.08 D-
(iii)
Unit = cum
Taking Output = 120 cum
a) Material
Material - As per Design Mix (For One Cum)
Cement kg 220.000
Coarse sand kg 829.000 1.575 MT/cum Density
20 mm Aggregate kg 737.000 1.322 MT/cum Density
10 mm Aggregate kg 492.000 1.338 MT/cum Density
Admixture kg 2.530 1.15%
Water Lit 127.600 0.580 W/C ratio
Material (for 120 Cum)
Cement tonne 26.40 4932.28 130212.19 M-081
Coarse sand cum 63.16 2301.50 145367.12 M-004
20 mm Aggregate cum 66.90 3637.85 243367.21 DM-35
10 mm Aggregate cum 44.13 3317.81 146400.23 DM-46
Admixture kg 303.60 53.00 16090.80 M-180
Water KL 15.31 50.00 765.60 M-189
b) Labour
Mate day 0.84 284.10 238.64 L-12
Mason day 3.00 368.28 1104.84 L-11
Mazdoor day 18.00 263.05 4734.90 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2664.00 15984.00 P&M-002
Generator 100 KVA hour 6.00 832.50 4995.00 P&M-080
Loader 1 cum capacity 1 cum hour 6.00 962.00 5772.00 P&M-017
Transit Mixer 4 cum capacity for lead hour 15.00 1110.00 16650.00 P&M-049
upto 1 km.
Transit Mixer 4 cum capacity lead tonne.k 300 x L 12.00 19188.00 P&M-050
beyond 1 Km, L - lead in Kilometer m
Concrete Pump hour 6.00 305.25 1831.50 P&M-007
Per Cum Basic Cost of Labour, Material & 6273.00
Machinery (a+b+c)
d) Formwork @ 0 % on cost of concrete 0.00 0.00
i.e. cost of material, labour and machinery
12.08 A (ii) Plain Cement Concrete in Levelling Course - Analysis of PCC Using
Using Batching Plant, Transit Mixer and Batching Plant &
Concrete Pump ₹ 7,313.46 Transit Mixer is based
PCC Grade M-15 on Item no. 12.08 D-
(iii)
Unit = cum
Taking Output = 120 cum
a) Material
Material - As per Design Mix (For One Cum)
Cement kg 250.000
Coarse sand kg 822.000 1.575 MT/cum Density
20 mm Aggregate kg 731.000 1.322 MT/cum Density
10 mm Aggregate kg 487.000 1.338 MT/cum Density
Admixture kg 2.750 1.10%
Water Lit 125.000 0.500 W/C ratio
Material (for 120 Cum)
Cement tonne 30.00 4932.28 147968.40 M-081
Coarse sand cum 62.63 2301.50 144139.66 M-004
20 mm Aggregate cum 66.35 3637.85 241385.93 DM-35
10 mm Aggregate cum 43.68 3317.81 144912.42 DM-46
Admixture kg 330.00 53.00 17490.00 M-180
Water KL 15.00 50.00 750.00 M-189
b) Labour
Mate day 0.84 284.10 238.64 L-12
Mason day 3.00 368.28 1104.84 L-11
Mazdoor day 18.00 263.05 4734.90 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2664.00 15984.00 P&M-002
Generator 100 KVA hour 6.00 832.50 4995.00 P&M-080
Loader 1 cum capacity 1 cum hour 6.00 962.00 5772.00 P&M-017
Transit Mixer 4 cum capacity for lead hour 15.00 1110.00 16650.00 P&M-049
upto 1 km.
Transit Mixer 4 cum capacity lead tonne.k 300 x L 12.00 19188.00 P&M-050
beyond 1 Km, L - lead in Kilometer m
Concrete Pump hour 6.00 305.25 1831.50 P&M-007
Per Cum Basic Cost of Labour, Material & 6393.00
Machinery (a+b+c)
d) Formwork @ 0 % on cost of concrete 0.00 0.00
i.e. cost of material, labour and machinery
Unit = cum
Taking Output = 120 cum
a) Material
Material - As per Design Mix (For One Cum)
Cement kg 340.000
Coarse sand kg 770.000 1.575 MT/cum Density
20 mm Aggregate kg 685.000 1.322 MT/cum Density
10 mm Aggregate kg 456.000 1.338 MT/cum Density
Admixture kg 3.230 0.95%
Water Lit 146.200 0.430 W/C ratio
Material (for 120 Cum)
Cement tonne 40.80 4932.28 201237.02 M-081
Coarse sand cum 58.67 2301.50 135021.33 M-004
20 mm Aggregate cum 62.18 3637.85 226196.12 DM-35
10 mm Aggregate cum 40.90 3317.81 135688.01 DM-46
Admixture kg 387.60 53.00 20542.80 M-180
Water KL 17.54 50.00 877.20 M-189
b) Labour
Mate day 0.84 284.10 238.64 L-12
Mason day 3.00 368.28 1104.84 L-11
Mazdoor day 18.00 263.05 4734.90 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2664.00 15984.00 P&M-002
Generator 100 KVA hour 6.00 832.50 4995.00 P&M-080
Loader 1 cum capacity 1 cum hour 6.00 962.00 5772.00 P&M-017
Transit Mixer 4 cum capacity for lead hour 15.00 1110.00 16650.00 P&M-049
upto 1 km.
Transit Mixer 4 cum capacity lead tonne.k 300 x L 12.00 19188.00 P&M-050
beyond 1 Km, L - lead in Kilometer m
Concrete Pump hour 6.00 305.25 1831.50 P&M-007
Per Cum Basic Cost of Labour, Material & 6583.85
Machinery (a+b+c)
d) Formwork @ 3.75 per cent on cost of 29627.30
concrete i.e. cost of material, labour and
machinery
Unit = cum
Taking output = 120 cum
a) Material
Material - As per Design Mix (For One Cum)
Cement kg 365.000
Coarse sand kg 758.000 1.575 MT/cum Density
20 mm Aggregate kg 674.000 1.322 MT/cum Density
10 mm Aggregate kg 450.000 1.338 MT/cum Density
Admixture kg 2.920 0.80%
Water Lit 149.650 0.410 W/C ratio
Material (for 120 Cum)
Cement tonne 43.80 4932.28 216033.86 M-081
Coarse sand cum 57.75 2301.50 132917.10 M-004
20 mm Aggregate cum 61.18 3637.85 222563.77 DM-35
10 mm Aggregate cum 40.36 3317.81 133902.65 DM-46
Admixture kg 350.40 53.00 18571.20 M-180
Water KL 17.96 50.00 897.90 M-189
b) Labour
Mate day 0.84 284.10 238.64 L-12
Mason day 3.00 368.28 1104.84 L-11
Mazdoor day 18.00 263.05 4734.90 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2664.00 15984.00 P&M-002
Generator 100 KVA hour 6.00 832.50 4995.00 P&M-080
Loader 1 cum capacity hour 6.00 962.00 5772.00 P&M-017
Transit Mixer 4 cum capacity for lead hour 15.00 1110.00 16650.00 P&M-049
upto 1 km.
Transit Mixer 4 cum capacity lead tonne.k 300 x L 12.00 19188.00 P&M-050
beyond 1 Km, L - lead in Kilometer m
Concrete Pump hour 6.00 305.25 1831.50 P&M-007
Per Cum Basic Cost of Labour, Material & 6629.00
Machinery (a+b+c)
d) Formwork @ 3.5 per cent of cost of 27838.49
concrete i.e. cost of material, labour and
machinery
Unit ; cum
Taking Output = 120 cum
a) Material
Material - As per Design Mix (For One Cum)
Cement kg 400.000
Coarse sand kg 744.000 1.575 MT/cum Density
20 mm Aggregate kg 662.000 1.322 MT/cum Density
10 mm Aggregate kg 441.000 1.338 MT/cum Density
Admixture kg 3.200 0.80%
Water Lit 152.000 0.380 W/C ratio
Material (for 120 Cum)
Cement tonne 48.00 4932.28 236749.44 M-081
Coarse sand cum 56.69 2301.50 130462.17 M-004
20 mm Aggregate cum 60.09 3637.85 218601.21 DM-35
10 mm Aggregate cum 39.55 3317.81 131224.59 DM-46
Admixture kg 384.00 53.00 20352.00 M-180
Water KL 18.24 50.00 912.00 M-189
b) Labour
Mate day 0.84 284.10 238.64 L-12
Mason day 3.00 368.28 1104.84 L-11
Mazdoor day 18.00 263.05 4734.90 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2664.00 15984.00 P&M-002
Generator 100 KVA hour 6.00 832.50 4995.00 P&M-080
Loader1 cum capacity hour 6.00 962.00 5772.00 P&M-017
Transit Mixer 4 cum capacity for lead hour 15.00 1110.00 16650.00 P&M-049
upto 1 km.
Transit Mixer 4 cum capacity lead tonne.k 300 x L 12.00 19188.00 P&M-050
beyond 1 Km, L - lead in Kilometer m
Concrete Pump hour 6.00 305.25 1831.50 P&M-007
Per Cum Basic Cost of Labour, Material & 6741.00 Conc. cost, Item no:
Machinery (a+b+c) 12.08 H-(ii)
d) Formwork @ 3 per cent on cost of 24264.01
concrete i.e. cost of material, labour and
machinery
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including5 per cent tonne 1.05 35668.46 37451.88 M-082
overlaps and wastage
Binding wire Kg 6.00 53.51 321.06 M-072
b) Labour for cutting, bending, shifting to
site, tying and placing in position
Height upto 5m
Per Cum Basic Cost of Labour, Material & 6583.85
Machinery (a+b+c) of Item 12.08 E-(ii)
d) formwork
Add 10 per cent of cost of material, 10.00 658.39
labour and machinery (a+b+c) for
Formwork
Height upto 5m
Per Cum Basic Cost of Labour, Material & 6629.00
Machinery (a+b+c) of Item 12.08 G-(ii)
d) formwork
Add 10 per cent of cost of material, 10.00 662.90
labour and machinery (a+b+c) for
Formwork
13.05 G-(p) II
13.05 H-(p) II Plain/Reinforced Cement Concrete in Sub-
Structure - Using Batching Plant, Transit
Mixer and Concrete Pump ₹ 8,482.87
RCC Grade M-35
Height upto 5m
Per Cum Basic Cost of Labour, Material & 6741.00
Machinery (a+b+c) of Item 12.08 H-(ii)
d) formwork
Add 10 per cent of cost of material, 10.00 674.10
labour and machinery (a+b+c) for
Formwork
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including5 per cent tonne 1.05 35668.46 37451.88 M-082
overlaps and wastage
Binding wire Kg 6.00 53.51 321.06 M-072
b) Labour for cutting, bending, shifting to
site, tying and placing in position
13.08 A Providing weep holes with 100 mm dia PVC Ref: STD data Book
pipe in Plain/ Reinforced concrete abutment, Item No. 13.08
wing wall/ return wall, extending through the
full width of the structure with slope of 1V : ₹ 540.78
20H towards drawing foce. Complete as per
drawing and Technical Specifications
Unit = Nos.
Taking output = 30 Nos.
a) Material
PVC pipe 100 mm dia. (including metre 31.50 442.00 13923.00 M-056
wastage @ 5 per cent )
Average length of weep hole is taken as one
metre for the purpose of estimating.
b) Labour
Mate day 0.03 284.10 8.52 L-12
Mason day 0.50 368.28 184.14 L-11
Mazdoor day 0.25 263.05 65.76 L-13
13.10 A Providing and laying of Filter media with Geo- Ref: STD data Book
Composite provided over the entire surface Item No. 13.10 G-(ii) &
behind abutment, wing wall and return wall to ₹ 201.40 15.06
the full height complete as per drawing and
technical specification.
Unit = sqm
Taking output = 10 sqm.
a) Labour
Mate day 0.02 284.10 5.68 L-12
Mazdoor day 0.30 263.05 78.92 L-13
Mazdoor (Skilled) day 0.10 278.84 27.88 L-15
b) Material
Permeable geo-composite sheet sqm 10.30 160.00 1648.00 M-109
including 3% for overlap and wastage
Height upto 5m
For Solid Slab Super-Structure
Unit = cum
Taking output = 120 cum
a) Material
Material - As per Design Mix (For One Cum)
Cement kg 340.000
Coarse sand kg 770.000 1.575 MT/cum Density
20 mm Aggregate kg 685.000 1.322 MT/cum Density
10 mm Aggregate kg 456.000 1.338 MT/cum Density
Admixture kg 3.230 0.95%
Water Lit 146.200 0.430 W/C ratio
Material (for 120 Cum)
Cement tonne 40.80 4932.28 201237.02 M-081
Coarse sand cum 58.67 2301.50 135021.33 M-004
20 mm Aggregate cum 62.18 3637.85 226196.12 DM-35
10 mm Aggregate cum 40.90 3317.81 135688.01 DM-46
Admixture kg 387.60 53.00 20542.80 M-180
Water KL 17.54 50.00 877.20 M-189
b) Labour
Mate day 0.84 284.10 238.64 L-12
Mason day 3.00 368.28 1104.84 L-11
Mazdoor day 18.00 263.05 4734.90 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2664.00 15984.00 P&M-002
Generator 100 KVA hour 6.00 832.50 4995.00 P&M-080
Loader hour 6.00 962.00 5772.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead hour 15.00 1110.00 16650.00 P&M-049
upto1 Km
Lead beyond 1 Km, L - lead in tonne.k 300 x L 12.00 19188.00 P&M-050
Kilometer m
Concrete Pump hour 6.00 305.25 1831.50 P&M-007
Basic Cost of Labour, Material & Machinery 790062.00
(a+b+c) for 120 cum
d) Formwork and staging 20 percent of 20.00 158012.28
(a+b+c)
Height upto 5m
For Solid Slab Super-Structure
Unit = cum
Taking output = 120 cum
a) Material
Material - As per Design Mix (For One Cum)
Cement kg 400.000
Coarse sand kg 744.000 1.575 MT/cum Density
20 mm Aggregate kg 662.000 1.322 MT/cum Density
10 mm Aggregate kg 441.000 1.338 MT/cum Density
Admixture kg 3.200 0.80%
Water Lit 152.000 0.380 W/C ratio
Material (for 120 Cum)
Cement tonne 48.00 4932.28 236749.44 M-081
Coarse sand cum 56.69 2301.50 130462.17 M-004
20 mm Aggregate cum 60.09 3637.85 218601.21 DM-35
10 mm Aggregate cum 39.55 3317.81 131224.59 DM-46
Admixture kg 384.00 53.00 20352.00 M-180
Water KL 18.24 50.00 912.00 M-189
b) Labour
Mate day 0.88 284.10 250.01 L-12
Mason day 3.00 368.28 1104.84 L-11
Mazdoor day 19.00 263.05 4997.95 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2664.00 15984.00 P&M-002
Generator 100 KVA hour 6.00 832.50 4995.00 P&M-080
Loader hour 6.00 962.00 5772.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead hour 15.00 1110.00 16650.00 P&M-049
upto1 Km
Lead beyond 1 Km, L - lead in t.km 300 x L 12.00 19188.00 P&M-050
Kilometer
Concrete Pump hour 6.00 305.25 1831.50 P&M-007
Basic Cost of Labour, Material & Machinery 809075.00
(a+b+c) for 120 cum
d) Formwork and staging 18 percent of 18.00 145633.45
(a+b+c)
say 9101.55
RATE ANALYSIS
Std. Data
Book Description Unit Quantity Rate Rs Cost Rs Remarks
Item No.
Height upto 5m
For Solid Slab Super-Structure
Unit = cum
Taking output = 120 cum
a) Material
Material - As per Design Mix (For One Cum)
Cement kg 415.000
Coarse sand kg 742.000 1.575 MT/cum Density
20 mm Aggregate kg 660.000 1.322 MT/cum Density
10 mm Aggregate kg 440.000 1.338 MT/cum Density
Admixture kg 3.320 0.80%
Water Lit 149.400 0.360 W/C ratio
Material (for 120 Cum)
Cement tonne 49.80 4932.28 245627.54 M-081
Coarse sand cum 56.53 2301.50 130111.47 M-004
20 mm Aggregate cum 59.91 3637.85 217940.79 DM-35
10 mm Aggregate cum 39.46 3317.81 130927.03 DM-46
Admixture kg 398.40 53.00 21115.20 M-180
Water KL 17.93 50.00 896.40 M-189
b) Labour
Mate day 0.94 284.10 267.05 L-12
Mason day 3.50 368.28 1288.98 L-11
Mazdoor day 20.00 263.05 5261.00 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2664.00 15984.00 P&M-002
Generator 100 KVA hour 6.00 832.50 4995.00 P&M-080
Loader hour 6.00 962.00 5772.00 P&M-017
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead hour 15.00 1110.00 16650.00 P&M-049
upto1 Km
Lead beyond 1 Km, L - lead in tonne.k 300 x L 12.00 19188.00 P&M-050
Kilometer m
Concrete Pump hour 6.00 305.25 1831.50 P&M-007
Basic Cost of Labour, Material & Machinery 817856.00
(a+b+c) for 120 cum
d) Formwork and staging 18 percent of 18.00 147214.07
(a+b+c)
say 9200.33
RATE ANALYSIS
Std. Data
Book Description Unit Quantity Rate Rs Cost Rs Remarks
Item No.
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including5 per cent tonne 1.05 35668.46 37451.88 M-082
overlaps and wastage
Binding wire Kg 8.00 53.51 428.08 M-072
b) Labour for cutting, bending, shifting to
site, tying and placing in position
Unit = cum
(I) Cost of M-30 grade concrete Ref: STD data Book Item No. 12.08 G-(ii)
Taking output = 120 cum
a) Material
Material - As per Design Mix (For One Cum)
Cement kg 365.000
Coarse sand kg 758.000 1.575 MT/cum Density
20 mm Aggregate kg 674.000 1.322 MT/cum Density
10 mm Aggregate kg 450.000 1.338 MT/cum Density
Admixture kg 2.920 0.80%
Water Lit 149.650 0.410 W/C ratio
Material (for 120 Cum)
Cement tonne 43.80 4932.28 216033.86 M-081
Coarse sand cum 57.75 2301.50 132917.10 M-004
20 mm Aggregate cum 61.18 3637.85 222563.77 DM-35
10 mm Aggregate cum 40.36 3317.81 133902.65 DM-46
Admixture kg 350.40 53.00 18571.20 M-180
Water KL 17.96 50.00 897.90 M-189
b) Labour
Mate day 0.84 284.10 238.64 L-12
Mason day 3.00 368.28 1104.84 L-11
Mazdoor day 18.00 263.05 4734.90 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2664.00 15984.00 P&M-002
Generator 100 KVA hour 6.00 832.50 4995.00 P&M-080
Loader 1 cum capacity hour 6.00 962.00 5772.00 P&M-017
Transit Mixer 4 cum capacity for lead hour 15.00 1110.00 16650.00 P&M-049
upto 1 km.
Transit Mixer 4 cum capacity lead tonne.k 300 x L 12.00 19188.00 P&M-050
beyond 1 Km, L - lead in Kilometer m
Concrete Pump hour 6.00 305.25 1831.50 P&M-007
d) Formwork @ 2 per cent of cost of
concrete i.e. cost of material, labour and 2.00 15907.71
machinery
(II) Cost of Reinforcement Steel Ref: STD Data Book Item No. 14.02
Taking output = 1 MT
a) Material
HYSD bars including5 per cent tonne 1.05 35668.46 37451.88 M-082
overlaps and wastage
Binding wire Kg 8.00 53.51 428.08 M-072
b) Labour for cutting, bending, shifting to
site, tying and placing in position
Unit = Cum
Taking output = 1 Cum
a) Labour
For carrying, placing & fixing.
Mate day 0.050 392.00 19.60 L-12
Mazdoor day 0.250 350.00 87.50 L-13
Mazdoor (Skilled) day 1.000 410.00 410.00 L-15
b) Material
Stone weighing not less than 40kg cum 1.00 1846.20 1846.20 M-003
Stone spalls of minimum 25 mm size cum 0.20 1846.20 369.24 M-003
Unit = sqm
Taking output = 1 sqm
a) Cost of Panel Facia sqm 1.00 1496.71 1496.71 Item no: 7.05 II
b) Cost of Geogrid Reinforcement sqm 3.50 123.89 433.62 Item no: 7.05 (i)-B
c) Cost of Geo-composite (Filter Media) sqm 1.00 176.05 176.05 Item no: 7.05 (i)-C
Unit = sqm
Taking output = 300 sqm
a) Labour
Mate day 0.360 284.10 102.28 L-12
Mazdoor day 6.000 263.05 1578.30 L-13
Mazdoor skilled day 3.000 278.84 836.52 L-15
b) Material
Synthetic Geogrids as per clause sqm 300.000 105.00 31500.00 M-181
3102.8 and approved design and
specifications.
Add 10 per cent of the cost of 3150.00
reinforcing elements (synthetic
geogrids) for accessories like tie-
strips, nuts and bolts and loops/lugs
for joining reinforcing elements with
the facia pannels, overlaps and other
protective elements for synthetic
geogrids.
RATE ANALYSIS
Std. Data
Book Description Unit Quantity Rate Rs Cost Rs Remarks
Item No.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.120 284.10 34.09 L-12
Mazdoor for preparation of ground and day 3.000 263.05 789.15 L-13
fetching of sods
b) Machinery
Water tanker including watering for 3 hour 2.000 370.00 740.00 P&M-060
months
Tractor-trolley hour 1.000 432.90 432.90 P&M-053
c) Material
Farm yard manure @ 0.18 cum per 100 cum 0.180 202.79 36.50 M-167
sqm at site of work
Cost of water KL 12.000 50.00 600.00 M-189
12.08 B (ii) PCC / RCC in Open Foundation - Using Batching Analysis of PCC Using
Plant, Transit Mixer and Concrete Pump Batching Plant &
PCC Grade M 20 ₹ 7,534.27 Transit Mixer is based
on Item no. 12.08 D-
(iii)
Unit = cum
Taking Output = 120 cum cum 120.00
a) Material
Material - As per Design Mix (For One Cum)
Cement kg 280.000
Coarse sand kg 811.000 1.575 MT/cum Density
20 mm Aggregate kg 721.000 1.322 MT/cum Density
10 mm Aggregate kg 481.000 1.338 MT/cum Density
Admixture kg 2.940 1.05%
Water Lit 126.000 0.450 W/C ratio
Material (for 120 Cum)
Cement tonne 33.60 4932.28 165724.61 M-081
Coarse sand cum 61.79 2301.50 142210.78 M-004
20 mm Aggregate cum 65.45 3637.85 238083.80 DM-35
10 mm Aggregate cum 43.14 3317.81 143127.05 DM-46
Admixture kg 352.80 53.00 18698.40 M-180
Water KL 15.12 50.00 756.00 M-189
b) Labour
Mate day 0.84 284.10 238.64 L-12
Mason day 3.00 368.28 1104.84 L-11
Mazdoor day 18.00 263.05 4734.90 L-13
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 2664.00 15984.00 P&M-002
Generator 100 KVA hour 6.00 832.50 4995.00 P&M-080
Loader 1 cum capacity 1 cum hour 6.00 962.00 5772.00 P&M-017
Transit Mixer 4 cum capacity for lead upto 1 hour 15.00 1110.00 16650.00 P&M-049
km.
Transit Mixer 4 cum capacity lead beyond 1 tonne.k 300 x L 12.00 0.00 P&M-050
Km, L - lead in Kilometer m
Concrete Pump hour 6.00 305.25 1831.50 P&M-007
Per Cum Basic Cost of Labour, Material & 6333.00
Machinery (a+b+c)
d) Formwork @ 4 % on cost of concrete i.e. cost 4.00 30396.46
of material, labour and machinery
Unit = sqm
Taking output = 1 sqm
a) Supply of Morth approved HDPE Geocell Sqm 1.000 80.00 80.00
Material Quotation of M/s Terrain
Infratech
b) Installation of Geocell Sqm 1.000 50.00 50.00
c) Providing and Filling M15 grade concrete Cum 0.100 6392.88 639.29 Ref: RA of Item No.
between the cells 12.08 A (ii)
Unit = sqm
Taking output = 1 sqm
a) Supply of Morth approved HDPE Geocell Sqm 1.000 80.00 80.00
Material
b) Installation of Geocell Sqm 1.000 50.00 50.00
Quotation of M/s
c) Soil filling between the cells & plantation of Sqm 1.000 35.00 35.00 Terrain Infratech
Doob Grass
d) Maintanance of Growth of vegetation till six Sqm 1.000 5.00 5.00
months
say 2746.07
Std. Data
Book Description Unit Quantity Rate Rs Cost Rs Remarks
Item No.
8.13 ₹ 524.47
Road Marking with Hot Applied Thermoplastic
Compound with Reflectorising Glass Beads on
Bituminous Surface
Unit = sqm
Taking output = Details of cost for 200 sqm (Area
covered on one day):-
MATERIAL
Thermoplastic paint screeded in paint
form for 2.5 mm thick road making
stripe including glass beads etc. as per
specifications
200 sqm @ 5kg/ sqm = 1000 kg
Wastage @ 5% = 50kg
Total = 1050 kg
8687 Thermoplastic paint kg 1050.000 65.00 68250.00
Glass beads (B-class) to be sprayed
over the paint stripe @ 250 gms. Per
sqm = 100x0.25=25 kg
8688 Glass beads day 50.000 70.00 3500.00
MACHINERY
0033 Paint applicator. day 1.000 750.00 750.00
0083 Hire charges of TATA 407 or equivalent day 1.000 1200.00 1200.00
for local shifting.
1241 Commercial LPG in cylinder. kg 142.000 82.00 11644.00
LABOUR
0157 Operator (Pile/ Special machine) day 1.000 738.00 738.00
0139 Skilled Beldar (for floor rubbing etc.) day 4.000 617.00 2468.00
0114 Beldar day 4.000 558.00 2232.00
TOTAL 90782.00 W
Add 1 % Water charges on "W" 907.82
TOTAL 91689.82 X
4.0% Gross OH (8%) - VAT
i) Add Overhead @ 4% on base rate 3667.59 (4%) = 4% Net OH
3 P&M-002 Batching and Mixing Plant (a) 30 cum capacity hour 2001-02 2001 1,440.00 2019-20 2019 85% 1,224.00 2,664.00 Sl.-31, Pg-557 MoRTH Std. Data Book
4 P&M-004 Bitumen Pressure Distributor hour 2001-02 2001 692.00 2019-20 2019 85% 588.20 1,280.20 Sl.-16, Pg-556 MoRTH Std. Data Book
5 P&M-007 Concrete Pump of 45 & 30 cum capacity hour 2001-02 2001 165.00 2019-20 2019 85% 140.25 305.25 Sl.-33, Pg-557 MoRTH Std. Data Book
6 P&M-009 Concrete Mixer (a) 0.4/0.28 cum hour 2001-02 2001 150.00 2019-20 2019 85% 127.50 277.50 Sl.-37, Pg-557 MoRTH Std. Data Book
7 P&M-013 Cranes (c) 3 tonnes hour 2001-02 2001 230.00 2019-20 2019 85% 195.50 425.50 Sl.-34, Pg-557 MoRTH Std. Data Book
8 P&M-014 Dozer D - 80 - A 12 hour 2001-02 2001 2,400.00 2019-20 2019 85% 2,040.00 4,440.00 Sl.-01, Pg-555 MoRTH Std. Data Book
9 P&M-017 Front End loader 1 cum bucket capacity hour 2001-02 2001 520.00 2019-20 2019 85% 442.00 962.00 Sl.-05, Pg-555 MoRTH Std. Data Book
10 P&M-018 Generator (a) 125 KVA hour 2001-02 2001 450.00 2019-20 2019 85% 382.50 832.50 Sl.-42, Pg-558 MoRTH Std. Data Book
11 P&M-019 Generator (b) 63 KVA hour 2001-02 2001 240.00 2019-20 2019 85% 204.00 444.00 Sl.-42, Pg-558 MoRTH Std. Data Book
12 P&M-022 Hotmix Plant - 100 TPH capacity hour 2001-02 2001 11,167.00 2019-20 2019 85% 9,491.95 20,658.95 Sl.-19, Pg-556 MoRTH Std. Data Book
13 P&M-026 Hydraulic Excavator of 1 cum bucket hour 2001-02 2001 840.00 2019-20 2019 85% 714.00 1,554.00 Sl.-04, Pg-555 MoRTH Std. Data Book
14 P&M-031 Mechanical Broom Hydraulic hour 2001-02 2001 230.00 2019-20 2019 85% 195.50 425.50 Sl.-15, Pg-556 MoRTH Std. Data Book
15 P&M-032 Motor Grader 3.35 mtr blade hour 2001-02 2001 1,545.00 2019-20 2019 85% 1,313.25 2,858.25 Sl.-03, Pg-555 MoRTH Std. Data Book
16 P&M-034 Paver Finisher Hydrostatic with sensor control 100 TP hour 2001-02 2001 1,725.00 2019-20 2019 85% 1,466.25 3,191.25 Sl.-22, Pg-556 MoRTH Std. Data Book
17 P&M-035 Paver Finisher Mechanical 100 TPH hour 2001-02 2001 629.00 2019-20 2019 85% 534.65 1,163.65 Sl.-23, Pg-556 MoRTH Std. Data Book
18 P&M-044 Smooth Wheeled Roller 8 tonne hour 2001-02 2001 297.00 2019-20 2019 85% 252.45 549.45 Sl.-08, Pg-555 MoRTH Std. Data Book
19 P&M-045 Tandem Road Roller hour 2001-02 2001 738.00 2019-20 2019 85% 627.30 1,365.30 Sl.-25, Pg-557 MoRTH Std. Data Book
20 P&M-048 Tipper - 5 cum hour 2001-02 2001 200.00 2019-20 2019 85% 170.00 370.00 Sl.-06, Pg-555 MoRTH Std. Data Book
21 P&M-049 Transit Mixer 4.0/4.5 cum hour 2001-02 2001 600.00 2019-20 2019 85% 510.00 1,110.00 Sl.-32, Pg-557 MoRTH Std. Data Book
22 P&M-050 Transit Mixer 4/4.5 cum tonne.km 2019-20 2019 12.00 2019-20 2019 0% - 12.00 Sl.-029, Pg-3 Basic Rates, DSR (CPWD)-2019
23 P&M-053 Tractor hour 2001-02 2001 234.00 2019-20 2019 85% 198.90 432.90 Sl.-10, Pg-556 MoRTH Std. Data Book
24 P&M-058 Truck 5.5 cum per 10 tonnes tonne.km 2001-02 2001 1.60 2019-20 2019 85% 1.36 2.96 Sl.-44, Pg-558 MoRTH Std. Data Book
25 P&M-059 Vibratory Roller 8 tonne hour 2001-02 2001 994.00 2019-20 2019 85% 844.90 1,838.90 Sl.-07, Pg-555 MoRTH Std. Data Book
26 P&M-060 Water Tanker hour 2001-02 2001 200.00 2019-20 2019 85% 170.00 370.00 Sl.-09&06, Pg-555 MoRTH Std. Data Book
27 P&M-079 Generator 33 KVA hour 2001-02 2001 240.00 2019-20 2019 85% 204.00 444.00 Sl.-42, Pg-558 MoRTH Std. Data Book
28 P&M-080 Generator 100 KVA hour 2001-02 2001 450.00 2019-20 2019 85% 382.50 832.50 Sl.-42, Pg-558 MoRTH Std. Data Book
29 P&M-081 Generator 250 KVA hour 2001-02 2001 450.00 2019-20 2019 85% 382.50 832.50 Sl.-42, Pg-558 MoRTH Std. Data Book
30 P&M-094 Wet Mix Plant 75 TPH hour 2001-02 2001 777.00 2019-20 2019 85% 660.45 1,437.45 Sl.-14, Pg-556 MoRTH Std. Data Book
30 P&M-043 Road Marking machine 100 SQM/Hour hour 2001-02 2001 60.00 2019-20 2019 85% 51.00 111.00 Sl.-45, Pg-558 MoRTH Std. Data Book
om Sidhi Ganeshpur to Sansarpur km 121+600 to km 164+300 in the state of Uttar Pradesh
ATERIALS, MACHINERY AND LABOUR
Sl. Material Rate at Source Haulage Cost Reference (Base Rate)
Cost at Project
Item No. Description Price Adj Updated Price Adj Updated Remarks
No. Unit Rate Base Month Basic Cost Base Month Site w/o taxes Sl No, page SOR, Other
Factor Rate Factor Cost
1 2 3 4 5 6 7 8 9 10 11 12
1 (B) Labour
2 L-02 Blacksmith (Ist class) day 340.00 Sep-17 1.052 357.75 - - - 357.75 Sl.-5, Pg-28 SOR-16.10.2017, PWD, Sultanpur, UP
3 L-11 Mason (Ist class) day 350.00 Sep-17 1.052 368.28 - - - 368.28 Sl.-49, Pg-28 SOR-16.10.2017, PWD, Sultanpur, UP
4 L-12 Mate / Supervisor day 270.00 Sep-17 1.052 284.10 - - - 284.10 Sl.-13, Pg-28 SOR-16.10.2017, PWD, Sultanpur, UP
5 L-13 Mazdoor day 250.00 Sep-17 1.052 263.05 - - - 263.05 Sl.-15, Pg-28 SOR-16.10.2017, PWD, Sultanpur, UP
6 L-15 Mazdoor/Dresser/Sinker (Skilled) day 265.00 Sep-17 1.052 278.84 - - - 278.84 Sl.-14, Pg-28 SOR-16.10.2017, PWD, Sultanpur, UP
1 (C) Material
2 M-004 Coarse sand at Quarry Cum 950.00 1.00 950.00 1,351.50 1.000 1,351.50 2,301.50 SOR-, PWD, Kaushambi, UP Mahewaghat
3 M-005 Coarse sand at Quarry Cum 950.00 1.00 950.00 1,351.50 1.000 1,351.50 2,301.50 SOR-, PWD, Kaushambi, UP Mahewaghat
4 M-056 PVC pipe 100 mm dia metre 442.00 1.00 442.00 442.00 Sl.-7758, Pg-42 Basic Rates, DSR (CPWD)-2019
Base rate excl. GST
5 M-072 Binding wire kg 50.85 Sep-17 1.052 53.51 53.51 Sl.-21(f), Pg-21 SOR-16.10.2017, PWD, Sultanpur, UP
@ 18%
6 M-074 Bitumen (60-70 grade) Ex- Mathura tonne 29,710.00 1.00 29,710.00 2,315.72 1.000 2,315.72 32,025.72 IOCL-Mathura (Jan-19 Average) VG-40
7 M-077 Bitumen (Emulsion) Ex- Jhansi tonne 23,700.00 1.00 23,700.00 2,084.46 1.000 2,084.46 25,784.46 IOCL-Haldia (Jan-19 Average) MS
DM-20 GSB Material 53 mm to 9.5 mm Cum 650.00 Feb-18 1.029 669.04 1,517.16 1.000 1,517.16 2,186.20 Sl.-4 d(i), Pg-14 SOR-01.02.2018, Allahabad, UP Meja
DM-22 GSB Material 9.5 mm to 2.36 mm Cum 385.00 Feb-18 1.029 396.27 1,517.16 1.000 1,517.16 1,913.43 Sl.-4 d(ii), Pg-14 SOR-01.02.2018, Allahabad, UP Meja
DM-24 GSB Material 2.36 mm & below at Quarry Cum 340.00 Feb-18 1.029 349.96 1,517.16 1.000 1,517.16 1,867.12 Sl.-4 d(iii), Pg-14 SOR-01.02.2018, Allahabad, UP Meja
DM-30 Aggregates 40 mm at Quarry Cum 820.00 Apr-18 1.032 846.56 2,254.44 1.000 2,254.44 3,101.00 Sl.-3(1i),b(i), Pg-10 SOR-24.04.2018, Banda, UP Kabrai
DM-35 Aggregates 20 mm at Quarry Cum 1,340.00 Apr-18 1.032 1,383.41 2,254.44 1.000 2,254.44 3,637.85 Sl.-3(1i),e(ii), Pg-10 SOR-24.04.2018, Banda, UP Kabrai
DM-36 Aggregates 19 mm at Quarry Cum 1,340.00 Apr-18 1.032 1,383.41 2,254.44 1.000 2,254.44 3,637.85 Sl.-3(1i),f(ii), Pg-10 SOR-24.04.2018, Banda, UP Kabrai
DM-40 Aggregates 13.2 mm at Quarry Cum 1,070.00 Apr-18 1.032 1,104.66 2,254.44 1.000 2,254.44 3,359.10 Sl.-3(1i),g(ii), Pg-10 SOR-24.04.2018, Banda, UP Kabrai
DM-41 Aggregates 13 mm at Quarry Cum 1,030.00 Apr-18 1.032 1,063.37 2,254.44 1.000 2,254.44 3,317.81 Sl.-3(1i),h(i), Pg-10 SOR-24.04.2018, Banda, UP Kabrai
DM-45 Aggregates 11.2 mm at Quarry Cum 1,030.00 Apr-18 1.032 1,063.37 2,254.44 1.000 2,254.44 3,317.81 Sl.-3(1i),i(i), Pg-10 SOR-24.04.2018, Banda, UP Kabrai
DM-46 Aggregates 10 mm at Quarry Cum 1,030.00 Apr-18 1.032 1,063.37 2,254.44 1.000 2,254.44 3,317.81 Sl.-3(1i),j(i), Pg-10 SOR-24.04.2018, Banda, UP Kabrai
DM-50 Aggregates 6.7 mm at Quarry Cum 760.00 Apr-18 1.032 784.62 2,254.44 1.000 2,254.44 3,039.06 Sl.-3(1i),k(ii), Pg-10 SOR-24.04.2018, Banda, UP Kabrai
DM-55 Stone Dust 2.8 mm down at Quarry Cum 680.00 Apr-18 1.032 702.03 2,254.44 1.000 2,254.44 2,956.47 Sl.-3(1i),l(ii), Pg-10 SOR-24.04.2018, Banda, UP Kabrai
DM-32 Aggregate - 40 mm to 25 mm Cum 1,080.00 Apr-18 1.032 1,114.99 2,254.44 1.000 2,254.44 3,369.43 Average (DM-30, 35) Kabrai
DM-33 Aggregate - 25 mm to 16 mm Cum 1,205.00 Apr-18 1.032 1,244.04 2,254.44 1.000 2,254.44 3,498.48 Average (DM-35, 36, 40) Kabrai
DM-38 Aggregate - 16 mm to 12 mm Cum 1,117.50 Apr-18 1.032 1,153.70 2,254.44 1.000 2,254.44 3,408.14 Average (DM-36,40,41, 45) Kabrai
DM-43 Aggregate - 12 mm to 6 mm Cum 915.00 Apr-18 1.032 944.64 2,254.44 1.000 2,254.44 3,199.08 Average (DM-41, 46, 50) Kabrai
DM-51 Aggregate - 6 mm passing Cum 760.00 Apr-18 1.032 784.62 2,254.44 1.000 2,254.44 3,039.06 Sl.-3(1i),k(ii), Pg-10 SOR-24.04.2018, Banda, UP Kabrai
DM-57 Filler (Stone Dust) Cum 680.00 Apr-18 1.032 702.03 2,254.44 1.000 2,254.44 2,956.47 Sl.-3(1i),l(ii), Pg-10 SOR-24.04.2018, Banda, UP Kabrai
Carriage of Materials
Item Description Unit Quantity Rate Rs Cost Rs Remarks
A3 Cost of Haulage of Aggregate, Sand & GSB Material from Source to Project Site.
a Cost of Haulage of Stone Aggregate from Quarry at Kabrai (UP) to Hot Mix Plant
i Distance from Quarry to Plant HMP at km 143+500 Ref: Material Source
km 304.00
(Nidura) & Lead
ii Cost of Haulage
Cost of Haulage - 1st to 30 km cum 1.00 468.00 468.00 PWD, Lucknow
Cost of Haulage - 31st to 40 km cum 1.00 90.00 90.00 Eff: 26.06.2018
Cost of Haulage - 41st to 50 km cum 1.00 90.00 90.00
Cost of Haulage - 51st to 75 km cum 1.00 225.00 225.00
Cost of Haulage - 76th to 100 km cum 1.00 200.00 200.00
Cost of Haulage - 101st to 200 km cum 1.00 750.00 750.00
Cost of Haulage - 201st to 304 km cum 1.00 676.00 676.00
Add 33.3% on cartage (excl. loading/
Unloading) of 1st km for Kuchha cum 1.00 15.88 15.88
Road.
Carriage of Materials
Item Description Unit Quantity Rate Rs Cost Rs Remarks
b Cost of Haulage of Stone Aggregate from Quarry at Kabrai (UP) to WMM & RMC Plant
i Distance from Quarry to Plant WMM & RMC Plant at
Ref: Material Source
km 308.50 km 143+500 (Nidura)
& Lead
& 153+700 (Dostpur)
ii Cost of Haulage
Cost of Haulage - 1st to 30 km cum 1.00 468.00 468.00 PWD, Lucknow
Cost of Haulage - 31st to 40 km cum 1.00 90.00 90.00 Eff: 26.06.2018
Cost of Haulage - 41st to 50 km cum 1.00 90.00 90.00
Cost of Haulage - 51st to 75 km cum 1.00 225.00 225.00
Cost of Haulage - 76th to 100 km cum 1.00 200.00 200.00
Cost of Haulage - 101st to 200 km cum 1.00 750.00 750.00
Cost of Haulage - 201st to 308.5 km
cum 1.00 705.25 705.25
Add 33.3% on cartage (excl. loading/
Unloading) of 1st km for Kuchha cum 1.00 15.88 15.88
Road.
Carriage of Materials
Item Description Unit Quantity Rate Rs Cost Rs Remarks
d Cost of Haulage of GSB & Stone Boulder for Pitching from Meja Quarry to Project Site
i Distance from Quarry to Project Site Ref: Material Source
km 182.68
& Lead
ii Cost of Haulage
Cost of Haulage - 1st to 30 km cum 1.00 468.00 468.00 PWD, Lucknow
Cost of Haulage - 31st to 40 km cum 1.00 90.00 90.00 Eff: 26.06.2018
Cost of Haulage - 41st to 50 km cum 1.00 90.00 90.00
Cost of Haulage - 51st to 75 km cum 1.00 225.00 225.00
Cost of Haulage - 76th to 100 km cum 1.00 200.00 200.00
Cost of Haulage - 101st to 182.675
cum 1.00 615.00 615.00
km
Add 33.3% on cartage (excl. loading/
Unloading) of 1st km for Kuchha cum 1.00 15.88 15.88
Road.
Carriage of Materials
Item Description Unit Quantity Rate Rs Cost Rs Remarks
Carriage of Materials
Item Description Unit Quantity Rate Rs Cost Rs Remarks
A4 Cost of Transportation of Bitumen from IOCL Refinery at Mathura to Hot Mix Plant
i Distance from IOCl, Mathura to HMP HMP at km 143+500 Ref: Material Source
km 554.00
Location (Nidura) & Lead
Carriage of Materials
Item Description Unit Quantity Rate Rs Cost Rs Remarks
8 Coarse Sand (FM > 2.25) Mahewaghat (UP) xxx Lead from Source to Site