DATE: 28.01.

2021
DM-SO (L)

L - STATION PHASE -2
TOTAL PLANT STARTUP SCHEDULE

After completion of total shutdown jobs, L-Station Phase -2 Power & Desal plants shall be started on 29.01.2021 as
per the following program.

All timings are tentative and start up will depend on concomitant circumstances.

All systems shall be normalized after related PTWs are returned. All maintenance departments are requested to
return the PTWs by today (28.01.2021) to meet the startup program.

 Available units GT-L21 (81), L23 (83), L24 (84) and CEST-L25 (85). All units shall be on TG.
 GT-L22 (82) start up after completion of minor maintenance & FODS implementation hence line
up shall be checked thoroughly. CEST-26 (86) under annual maintenance.

28.01.2021 (Thursday)
 Service water and potable water system is in service.
 Make up water pumps are in service & system is normal.
 CCW system is normal in service. Check availability of chemical dosing system/standby equipment.
 Check instrument air system is normal and in service.
 Normalize Electrical and Firefighting system.
 Check Section isolation valves between block-1 & 2 are available.
 Normalize GT-L84, L81 & GT-L83 and CEST-L85 and keep units on TG.
 Slowly charge and normalize SW system through Desal 92 heat rejection section.
 Auxiliary SW system is normal in service and standby Aux. SW cooling pumps are available.
 Check all steam header drain valves are open to drain the header completely.
 Check & normalize clean drain system and keep in service.
 Normalize boiler feed water system.
 Drain & fill up Aux. Boilers 87 in consultation with chemist and keep ready for light up.
 Dose CCCW chemical in consultation with chemist.
 Normalize and ensure chemical dosing system is ready for available boilers and Desals.
 Fill up HRSGs-81, 83 & 84 in consultation with chemist and keep ready for start up.
 Normalize, line up and charge NG system for GT-L84, L83, L81 & Aux. Boiler-87 after all PTWs
returned.
 Line up and charge NG system for GT-84 after related PTWs are returned.

29.01.2021 (Friday)
 Start one S.W intake pump and establish flow through Desal 92 Heat Rejection Section.
 Fill up CEST-85 condenser hot well in consultation with chemist.
 Charge SW & establish flow through Desal -93 heat rejection section.
 Charge ST Condensers with SW & start one MSW cooling pump to establish flow through ST-85
condenser.
 Check Aux. boiler 87 burner availability one by one in preparation for start up
 Fill the evaporator & establish cold run of Desal-92
 Start ST-85 CEP on recirculation in preparation for HP header charging.
 Fill the evaporator & establish cold run of Desal-93

 Inform M/s DUSUP of L-Phase-2 startup.

Page 1 of 2
2

 Light up auxiliary boiler to carry out availability check. Ensure all steam header drain valves are
open and the header is completely drained.

06:00 to 14:00 hr Start Aux. Boiler for HP steam line warm up and slowly charge the HP header.
- HP/IP/LP & Start up steam headers warm up & charging. Ensure all steam header drain
valves are throttled while slowly warming the steam headers for charging.
¨ Pull ST-85 -condenser vacuum for steam header charging.
¨ Pull Desal-L92 vacuum after HP/IP header charging is completed
14:00 hr - LP steam admission to DS-92. Line up and normalize blending plant for start up.

18:30 hr - Start GT-84 on CC mode, synchronize and load up for HRSG warming/startup
19:00 hr - Pull Desal-L93 vacuum
21:00 hr - LP steam admission to Desal-93
23:30 hr - After 2nd Desal distillate recovery, take the blending plant in service.

30.01.2021 (Saturday)

00:30 hr - Start CEST-85 auto start sequence for pre warming after Desal normal in service.
05:00 hr - Charge SW & establish flow through Desal -91 heat rejection section.
06:00 hr - Fill the evaporator & establish cold run of Desal-91.

07:30 hr - Start GT-81 on CC mode, synchronize and load up for HRSG warming/startup
08:00 hr - Fill the evaporator & establish cold run of Desal-91.
08:30 hr - Synchronize and load up CEST-85.

- As per water demand, Pull Desal-L91 vacuum


- LP steam admission to Desal-91

GT-83 shall be started on CC mode, as per system requirement.


Desal-L94 shall be started as per water demand following completion of annual maintenance.

Note:

1. Auxiliary boiler shall be kept in service as per operation requirement.


2. Water & steam quality shall be checked and cleared by chemist prior to admission.
3. Clean drain system shall be closely monitored during start up and alternative arrangements for the drain pit
draining shall be kept available.
4. HP, IP & LP steam headers shall be completely drained. IP/LP header drain valves to atmosphere shall be
open until the headers are pressurized to avoid overloading the clean drain system.
5. Following start up of each system the operators shall be instructed to monitor the plant parameters closely.
The local operators shall make regular rounds of the equipment to check any abnormalities.
6. DM water tank levels shall be maintained maximum and MBF shall be kept available.

28.01.2021
Manager-Op (L)

cc: EVP (G)


VP - (P1 / P2 / PP / MM)
SM- P2 (Op. /EM / I&CM) / SM-(GT/ST&DS) / SM-OP-P1/SM-OOP.
AM- Lab (L)
All concerned : By email

L2-TPStt 2021