Client: M/s JINDAL STEEL & POWER LTD. Date of Insp.: 27.07.2021
Purchase Order No.4531505585 PO Line No: 20 (MACHINING BRACKET)
Contractor M/s HOWRAH MILLING INDUSTRIES Place of Inspection CHATTERJEEPARA, HOWRAH
Scope of Inspections:
01. Manuf. Progress 09. Fit-up / Alignment Check 17. Assembly 25. Completeness
02. QAP / QCP Verification 10. Dimensional Checks 18. Performance 26. Marking
03. Welder Qualification 11. Welds Edge Preparation 19. Functional Test 27. Environment-Health-Safety
OK
04.Material Identification 12. Visual Check of Welds 20. Test Run 28. Inst. calibration verified.
Not
OK
05. Lab Witness of Samples 13. NDT ULTRASONIC TEST 21. Strip Test 29. others
07. Visual Condition 15. Load Test 23. Surface Preparation 31.others
For QETO – Quality Services For Contractor / Subcontractor For Client Representative
Inspector: SUDIPTA DAS Name: KUNAL SAMANTA Name:
Test Documents
discussed not discussed
Others
Others
Others
1. Visually checked and no defect found except burrs and weld spatters at few areas. To be
removed.
2. Hydro pressure testing witnessed for 7nos fresh and 8nos. rectified (out of total 30 nos.)
brackets and found seepage in one point at weld seam in Sl. no. 26 only with no significant
fall in pressure during 10min holding in a pressure gauge of minimum division 2Kg/cm 2. The
pressure testing apparatus was not calibrated. Rest ones are acceptable.
Conclusion:
1. Seepage found in bracket sl. No. 26. Need to be rectified. Rest ones are accepted.
For QETO – Quality Services For Contractor / Subcontractor For Client Representative
Inspector: SUDIPTA DAS Name: KUNAL SAMANTA Name:
Signature: Signature: Signature:
Date: Date: Date:
Seal: Seal: Seal: