Republic of the Philippines

Department of Education
Region V
Division of Camarines Sur
Frredom Sports Complex,San Jose, Pili,Camarines Sur

PROJECT PROPOSAL
SCHOOL: BULAGWIN ELEMENTARY SCHOOL
MUNICIPALITY/ DISTRICT : LUPI
CONGRESSIONAL DISTRICT: 1st
A. Project Title: Schedule of Implementation: B. Proponent:
Improvement of steel gate July 16-21,2019 ROSALIE A. NAPA
signage and landscaping School Head
C. Project Location: Bulagwin Elementary School
La Purisima, Lupi, Camarines Sur
D. Participants: School Head,Teachers , BAC members & Inspectorate Team
E. Overview,Rationale and Objectives:

1. To improve the steel gate signage.


2. To have beautiful and attractive facilities in the school.

The improvement of steel gate signage in the school can be great help to the pupils and
teachers not to accident due to falling of rusted steel/debris. And the development of
concrete and attractive landscaping in the school, it serves as inspiration to the pupils
entering the school regularly.

F. Goal and Scope:


1. Help the pupils and teachers not to accident for the falling of rusted steel /debris.
2. Serves as inspiration to the pupils and teachers.
G. Work Programs /Activities:
ACTIVITIES TIME FRAME PERSON’S EXPECTED
INVOLVED OUTCOMES
A. Pre-Implementation
1. Conduct Teachers June 10,2019 School Head & Conducted Teachers
Meeting Teachers Meeting
2. Prepare and submit June 11,2019 School Head Approved Project Proposal
project proposal
3. Conduct Pre-Repair June 12,2019 School Physical Reported the findings on
Inspection Facilities inspection
coordinator
4. Listing down the June 12,2019 School Head & Listed the materials needed
materials needed BAC
B. Actual Implementation
1. Canvass Hardware June 13,2019 BAC Members Requested for quotation
materials
2. Purchase Hardware June 20,2019 BAC members Purchased hardware
materials materials
3. Implementation of JULY 16,2019 School Head & Pictures,Program of Works
Project Laborer
4. Request for post July 23,2019 School Physical Documented/Reported the
Inspection Facilities results
coordinator
C. Post Implementation
1. Submit of July 31,2019 School Head Submitted the liquidation on
Liquidation Reports time
H. Funding Source: MOOE 2019
I. Budgetary Requirements: Please see attached bill of materials
J. Reporting and Evaluation :
a. Documentation
b. Liquidation Reports
Prepared by: Reviewed by: Recommending Approved:
Approval:
ROSALIE A. NAPA VIRGILIO B. BANCASO DOLORES Q.
School Head OIC DIV. ENGR. PEDRO J. PELONIO MAPUSAO
SGOD CHIEF ASDS
(The budget on this proposal is included in MDP S/Y 2019-2020)

Republic of the Philippines


Department of Education
Region V
Division of Camarines Sur
Freedom Sports Complex, San Jose, Pili, Camarines Sur

School: BULAGWIN ELEMENTARY SCHOOL


Address: La Purisima, Lupi, Camarines Sur
Project Title: Improvement of School Gate signage and Landscaping
(Repair and maintenance -Other structures)
Allocation : PHP. 38,000.00
Source of Fund : MOOE 2019
Mode of Implementation: By Administration
Project Duration: July 16,2019 – July 21,2019

PROGRAM OF WORKS

ITEM NO. DESCRIPTI % TOTAL QUANTITY UNITS COST


ON
I Construction 76.92 1 Lot 28,390.00
Works
II Labor 23.08 1 Lot 8,517.00

Total: 100% Php.36,907.0


0

Prepared By:

ELIZABETH C. LORIO
School Physical Facilities Coordinator

Approved:

ROSALIE A. NAPA
School Head

Checked / Reviewed: Concurred:

NICOLAS L. REBELLON JR. ENGR.


VIRGILO B. BANCASO
In- Charge of Division Congressional District Division Engineer II
DepEd
Camarines Sur
Education Facilities
Unit (EFU )

Republic of the Philippines


Department of Education
Region V
Division of Camarines Sur
Freedom Sports Complex, San Jose, Pili, Camarines Sur

School: BULAGWIN ELEMENTARY SCHOOL


Address: La Purisima, Lupi, Camarines Sur
Project Title: Improvement of School Gate Signage and Landscaping
(Repairs and maintenance-Other structures)
Allocation : PHP. 38,000.00
Source of Fund : MOOE 2019
Mode of Implementation: By Administration
Project Duration: July 16, 2019 – July 21, 2019
_____________________________________________________________________________________
________________________________

BILL OF MATERIALS AND COST ESTIMATES

QUANTITY UNIT DESCRIPTION UNIT PRICE COST


A- MATERIALS
COST
2 Truckloa Sand 2,800.00 5,600.00
d
2 Pcs. Ordinary Plywood 350.00 700.00
2 Kl. Tie Wire 90.00 180.00
2 Kl. Nail ‘3 80.00 160.00
10 Pcs. RSB 10mm 170.00 1,700.00
6 Pcs. RSB 12mm 200.00 1,200.00
10 Pcs. RSB 8mm 110.00 1,100.00
500 Pcs. CHB 4’ 13.00 6,500.00
45 Bags Cement 250.00 11,250.00
TOTAL: Php.28,390.00
B-LABOR 8,517.00
A+B TOTAL: Php. 36,907.00

Prepared By:

ELIZABETH C. LORIO
School Physical Facilities Coordinator

Approved:
ROSALIE A. NAPA
School Head

Checked & Reviewed: Concurred:

NICOLAS L. REBELLON JR. ENGR.


VIRGILIO B. BANCASO
In- Charge of Division Congressional District Division Engineer II
DepEd
Camarines Sur
Education Facilities
Unit (EFU )