You are on page 1of 6

Karian Dam ( Karian Barat )

21. Potential Involuntary Resettlement


Based on the sub-project identification which have been established by RWS Consultant
then potential Involuntary Resettlement per sub-project starting from source to main
distribution pipeline can be explained as follows:

Table. Land Requirements for Pice Besar Wier


Name of Location Land Use Required Area
Potential RWS
No.
Infrastructure name of villages Subdistrict Regency Length Width Area
Component (M) (M) (M2)
E. Karian Dam
(Karian Barat)
1. Intake Panyabrangan Cikeusal Kab Pemukiman 80 60 2400
Serang
2. WTP Panyabrangan Cikeusal Kab sawah 225 192 43184
Serang
3. Reservoir Panyabrangan Cikeusal Kab Sawah
Serang
4. Underground Panyabrangan, Dahu, Cikeusal, Kab Sawah 21285
Transmission Bantarpanjang, Cikeusal, Kragilan, Serang
Piping (offtake Sukamaju, Cilayangguha, Ciruas
1) Mongpok (Kec Cikeusal, Kab
Serang), Pematang,
Kramatjati, Kendayakan,
Sentul (Kec Kragilan, Kab
Serang), Citerep, Kaserangan
(Kec Ciruas, Kab Serang)
Underground Citerep, Pelawad (Kec Ciruas, Ciruas, Kab Pemukiman 7351
Transmission Kab Serang) Walantaka, Serang
Piping (offtake Kalodran (Kec Walantaka, Cipocokjay dan Kota
2) Kota Serang), Penancangan a, Serang Serang
(Kec Cipocokjaya, Kota
Serang), Kaligandu (Kec
Serang, Kota Serang)
Underground Kaligandu, Cimuncang, Serang, Kota Pemukiman 14201
Transmission Lopang, Unyur, Kagungan Kasemen, Serang,
Piping (offtake (Kec Serang, Kota Serang), Taktakan, Kab
3) Kasemen (Kec Kasemen, Kota Kramatwat Serang,
Serang), Drangong, Taman u, Cibeber Kota
Baru (Kec Taktakan, Kota Cilegon
Serang)
Pelamunan, Kramatwatu,
Pejaten, Wanayasa, Serdang
(Kec Kramatwatu, Kab
Serang)
Kedaleman (Kec Cibeber, Kota
Cilegon)
Underground Kedaleman (Kec Cibeber, Kota Cibeber, Kota Pemukiman 6111
Transmission Cilegon), Gedongdalem (Kec Jombang, Cilegon,
Piping (offtake Jombang, Kota Cilegon) Bojonegara Kab
4) Kertasana, Mangkunegara, Serang
Bojonegara, Karangkepuh
Name of Location Land Use Required Area
Potential RWS
No.
Infrastructure name of villages Subdistrict Regency Length Width Area
Component (M) (M) (M2)
(Kec Bojonegara, Kab Serang)
21.1. Dam
Karian Dam can control the Ciberang river flood of 60.80 million cubic meters. When the
Ciberang river overflowed and caused flooding and landslides in six sub districts, Cipanas,
Lebakgedong, Sajira, Curugbitung, Maja, and Cimarga.

In addition to controlling floods, the Karian Dam will be a source of raw water in nine cities /
regencies in Banten and Jakarta.

"To distribute raw water to these areas, a 47.90 kilometer long water pipe is required to
serve more than 5 million people. The Karian Dam began construction in October 2015.
Construction of the dam, which costs Rp1.30 trillion

The LARAP document in this project has never been planned, DED, AMDAL, and LARAP
will be prepared under ESP in 2020-2021. Land acquisition might be conducted in 2021-
2022. The Karian Dam STT likely will start in 2022 and followed by the downstream system
in 2022 until 2025.

Works 2022 2023 2024 2025 2026 2027


Land Acquisition

Water Supply System AMDAL and LARAP study


preparation under APBN/APBD
RWS Intake and Transmission Construction by
BBWS Cidanau Ciujung Cidurian
Water Supply Production and Distribution System
Construction by DGHS

The schedule above is excluding the implementation schedule for house connection. RWS
consultant will complete this schedule.

21.2. Intake
This is the proposed intake. The Intake location will be in Panyabrangan village Cikeusal
Sub-district as well and near the Dam (see Figure below). To date has been completed the
process of land acquisition for dam construction then for the proposed intake location will
not require the land acquisition anymore. The area for the Intake building is planned
approximately 2,400 m2 with capacity of 1700 lps.

21.3. WTP
This is a proposed WTP. The WTP location proposed by the RWS Consultant is located in
Panyabrangan Village Ckeusal Sub-district. This location is paddies field owned by the
communities and there are no settlements in this location (see Figure below). A number of
landowners need to identified. The area for the WTP building is planned approximately
43184 m2 with capacity of 1500 lps. To obtain the required land area to be used as a WTP
area and access road to WTP, a land acquisition process is required through a mechanism
that refers to stipulate in the regulations.

21.4. Transmission and Main Distribution Pipeline


This is a proposed main distribution pipeline by RWS Consultant will pass several villages
and sub-district as follows:

Table XX. Location to be crossed by the proposed Main Distribution Pipeline


1. Underground Panyabrangan, Dahu, Bantarpanjang, Cikeusal, Cikeusal, Kab Serang
Transmission Piping Sukamaju, Cilayangguha, Mongpok
(offtake 1) Pematang, Kramatjati, Kendayakan, Sentul Kragilan,
Citerep, Kaserangan Ciruas
2. Underground Citerep, Pelawad Ciruas, Kab Serang
Transmission Piping Kalodran Walantaka,
(offtake 2) Penancangan Cipocokjaya Kota Serang
Kaligandu Serang
3. Underground Kaligandu, Cimuncang, Lopang, Unyur, Kagungan Serang, Kota Serang,
Transmission Piping Kasemen Kasemen,
(offtake 3) Drangong, Taman Baru Taktakan,
Pelamunan, Kramatwatu, Pejaten, Wanayasa, Kramatwatu, Kab Serang,
Serdang
Kedaleman Cibeber Kota Cilegon
4. Underground Kedaleman Cibeber, Kota Cilegon,
Transmission Piping Gedongdalem Jombang,
(offtake 4) Kertasana, Mangkunegara, Bojonegara, Bojonegara Kab Serang
Karangkepuh
Source: RWS Consultant Analysis, 2020

Type of occupation and school participation level of the communities along the transmission
and main distribution pipeline are are generally farmers or farm workers and Elementery
School graduate respectively.

The transmission pipeline will be planned to follow the main road from Intake to Reservoir
and WTP as well as among Reservoirs and pass through residential areas and agricultural
land. The same thing will be applied for the main distribution pipeline (see Figure below).
The impact of this sub-project work will be received by residents whose houses and land will
be passed by these pipeline. There is no need for involuntary resettlement due to the
installation of raw water supply pipeline. The impact that will be received by the residents
along the path is the obstruction of the movement of goods and people and other
environmental impacts such as dust and noise. But to mitigate the impact on the socio-
economic and cultural surrounding communities there will be an amount of things that need
to be considered by the project impelementer as follows:
a. The project implementer should have a close relationship with the surrounding
community,
b. Carry out safe development and does not cause the restlessness for the surrounding
community,
c. As much as possible to involve people who have the skills needed as workers at the
construction phase,
d. Establish intense communication to stakeholders such as village / sub-district officials
and community leaders.
21.5. Reservoir
This is a proposed reservoir where the location is the same as the location of the WTP,
which is located in Panyabrangan Village Cikeusal Sub-district with total capacity of 1500 lps
and require total land area of around 43,184 m2. This location is paddies field and there is
no settlement (see Figure below). A number of landowners need to be identified. To obtain
the land area that will be used as an area and access road to the reservoir, a land
acquisition process is needed through a mechanism that refers to stipulate in the
regulations.

The map below describes the potential RWS System and land cover for RWS Karian Dam:
Figure XX. The Potential RWS System and Land Cover for RWS Karian Dam
22. Potential Indigenous people impact
Based on the definitions either ADB’s SPS (2009) and GoI regulation as well as AMAN no
IPs is found / identified in this RWS subproject of RWS Semantok Dam either in or having a
collective being bound to the subproject area so that the subproject will be considered as
category C for the protection of indigenous peoples.

You might also like