Professional Documents
Culture Documents
UNIT COST
ITEM DESCRIPTION QTY UNIT TOTAL COST
LABOR MATERIALS
1 GENERAL REQUIREMENTS
Mobilization / Demobilization 1.00 ls 68,527.74 68,527.74 212,435.98 212,435.98 280,963.72
Permits & Licenses
Barangay Clearance 1.00 ls
Building Permit & Processing 1.00 ls by owner
Sidewalk Permit 1.00 ls by owner
Excavation Permit 1.00 ls by owner
Occupancy Permit 1.00 ls by owner
City Tax/Contractors Tax, if any 1.00 ls by owner
HOA construction bond and processing 1.00 ls
Electrical Permit & Processing 1.00 ls by owner
Mechanical (Elevator) Permit & Processing 1.00 ls by owner
Fire Safety Requirements & Processing 1.00 ls by owner
Water Permit & Processing 1.00 ls by owner
Bonds & Insurances
Contractor's All-Risk Insurance 1.00 ls 207,776.10 207,776.10 207,776.10
Performance Bond 1.00 ls by owner
Guarantee Bond 1.00 ls by owner
Surety Bond 1.00 ls by owner
Warranty Bond 1.00 ls by owner
Temporary Facilities
Tools & Equipment 1.00 ls 274,110.95 274,110.95 274,110.95
Barracks 12.00 mo/s 47,969.42 575,632.99 575,632.99
Warehouse 1.00 ls 47,969.42 47,969.42 27,411.09 27,411.09 75,380.51
Portable Workers' Toilet 1.00 ls Included in tempfacil works by owner
Water Consumption 12.00 mo/s 14,185.24 170,222.90 170,222.90
Power Consumption 12.00 mo/s 23,642.07 283,704.83 283,704.83
Telephone/Internet Consumption 12.00 mo/s 4,002.39 48,028.68 48,028.68
Safety & Requirements
Board up/Safety Perimeter Fence 1.00 ls 207,776.10 207,776.10 207,776.10
PPE's & Uniforms 1.00 ls by owner
Disinfectants at site, Alcohols in complianceto IATF Guidelines 1.00 ls by owner
Gun Thermometer 1.00 ls by owner
Face Masks, Face Shields 1.00 ls by owner
Covid-19 Test Kits, Certificates 1.00 ls by owner
Housekeeping, Hauling & Disposal 1.00 ls by owner
Sub-total 2,123,596.78
EARTHWORKS
Excavation
Footing
F1 19.44 m³ 1,370.55 26,643.58 26,643.58
F2 11.52 m³ 1,370.55 15,788.79 15,788.79
F3 43.74 m³ 1,370.55 59,948.06 59,948.06
F4 21.78 m³ 1,370.55 29,850.68 29,850.68
F5 15.55 m³ 1,370.55 21,309.39 21,309.39
F6 20.70 m³ 1,370.55 28,370.48 28,370.48
F7 23.55 m³ 1,370.55 32,279.31 32,279.31
F8 24.06 m³ 1,370.55 32,981.03 32,981.03
F9 26.59 m³ 1,370.55 36,440.31 36,440.31
F10 31.10 m³ 1,370.55 42,629.73 42,629.73
F11 25.48 m³ 1,370.55 34,921.73 34,921.73
Tank
3-chamber STP 35.06 m³ 1,370.55 48,044.80 48,044.80
Gravel Bedding
Footing
F1 0.09 m³ 685.28 59.21 2,741.11 236.83 296.04
F2 0.05 m³ 685.28 35.09 2,741.11 140.34 175.43
F3 0.19 m³ 685.28 133.22 2,741.11 532.87 666.09
F4 0.10 m³ 685.28 66.33 2,741.11 265.34 331.67
F5 0.07 m³ 685.28 46.32 2,741.11 185.30 231.62
F6 0.09 m³ 685.28 61.67 2,741.11 246.70 308.37
F7 0.10 m³ 685.28 70.17 2,741.11 280.69 350.86
F8 0.10 m³ 685.28 70.17 2,741.11 280.69 350.86
F9 0.12 m³ 685.28 79.22 2,741.11 316.87 396.09
F10 0.13 m³ 685.28 88.81 2,741.11 355.25 444.06
F11 0.08 m³ 685.28 53.73 2,741.11 214.90 268.63
Slab
Main House 2.24 m³ 685.28 1,537.69 2,741.11 6,150.78 7,688.47
Outdoor 2.20 m³ 685.28 1,506.79 2,741.11 6,027.15 7,533.94
Backfilling
Footing
F1 18.92 m³ 548.22 10,372.36 10,372.36
F2 10.72 m³ 548.22 5,876.94 5,876.94
F3 42.77 m³ 548.22 23,447.45 23,447.45
F4 20.41 m³ 548.22 11,189.21 11,189.21
1 of 7
CLIENT'S COPY
Project Name PROPOSED TWO STOREY WITH ROOFDECK
Project Location TAGAYTAY
Project Name MR. JOHN CAHILIG
UNIT COST
ITEM DESCRIPTION QTY UNIT TOTAL COST
LABOR MATERIALS
2 of 7
CLIENT'S COPY
Project Name PROPOSED TWO STOREY WITH ROOFDECK
Project Location TAGAYTAY
Project Name MR. JOHN CAHILIG
UNIT COST
ITEM DESCRIPTION QTY UNIT TOTAL COST
LABOR MATERIALS
3 of 7
CLIENT'S COPY
Project Name PROPOSED TWO STOREY WITH ROOFDECK
Project Location TAGAYTAY
Project Name MR. JOHN CAHILIG
UNIT COST
ITEM DESCRIPTION QTY UNIT TOTAL COST
LABOR MATERIALS
4 of 7
CLIENT'S COPY
Project Name PROPOSED TWO STOREY WITH ROOFDECK
Project Location TAGAYTAY
Project Name MR. JOHN CAHILIG
UNIT COST
ITEM DESCRIPTION QTY UNIT TOTAL COST
LABOR MATERIALS
Second floor
Indoor 192.00 m² 170.53 32,742.58 254.69 48,901.39 81,643.98
Outdoor 89.88 m² 170.53 15,327.62 254.69 22,891.96 38,219.59
Door and Jamb painting
Ground floor
D-1 (Solid Wood Panel Door) 1.00 set 1,096.44 1,096.44 2,741.11 2,741.11 3,837.55
D-2 (Flush Panel Door) 9.00 set 1,096.44 9,867.99 2,741.11 24,669.99 34,537.98
D-3 (Flush Panel Door) 5.00 set 1,096.44 5,482.22 2,741.11 13,705.55 19,187.77
Second floor
D-2 (Flush Panel Door) 4.00 set 1,096.44 4,385.78 2,741.11 10,964.44 15,350.21
D-3 (Flush Panel Door) 2.00 set 1,096.44 2,192.89 2,741.11 5,482.22 7,675.11
D-4 (Barn Door) 2.00 set 1,096.44 2,192.89 2,741.11 5,482.22 7,675.11
D-5 (2-Leaf Door) 2.00 set 1,096.44 2,192.89 2,741.11 5,482.22 7,675.11
Cabinetry painting - ducco
Ground floor
Guest Bedroom 1.80 lm 2,741.11 4,934.00 6,852.77 12,334.99 17,268.99
Pantry Area 5.25 lm 2,741.11 14,390.82 6,852.77 35,977.06 50,367.89
Kitchen 4.13 lm 2,741.11 11,307.08 6,852.77 28,267.69 39,574.77
Dirty Kitchen 3.00 lm 2,741.11 8,223.33 6,852.77 20,558.32 28,781.65
Second floor 2,741.11 6,852.77
Bedroom 1 2.50 lm 2,741.11 6,852.77 6,852.77 17,131.93 23,984.71
Guest Bedroom 1.70 lm 2,741.11 4,659.89 6,852.77 11,649.72 16,309.60
Master Bedroom Closet 3.30 lm 2,741.11 9,045.66 6,852.77 22,614.15 31,659.81
Sub-total 544,825.27
8 ROOFING WORKS
Roof 1 200.00 m² 137.06 27,411.09 685.28 137,055.47 164,466.57
Trellis 97.82 m² 685.28 67,033.83 2,741.11 268,135.33 335,169.16
Sub-total 499,635.73
9 ELECTRICAL WORKS
Service drop to MCB
NEMA 3R, 350AT CB, Sevice entrance cap, RSC pipe and fittings,
PVC conduits, 250mm ² THHN wire, 50mm² THHN wire, Ground 1.00 ls 13,157.33 13,157.33 44,209.16 44,209.16 57,366.49
rod and clamp
Main panel
1 - Panel board 18's with 3-100A rating, 4 -40AT CB, 3 -30AT CB,
8 -20AT CB,PVC electrical pipe, 30mm² THHN wire, 8.0mm² THHN 1.00 ls 13,157.33 13,157.33 27,411.09 27,411.09 40,568.42
wire
1 - Panel board 6's with 100A rating, 3-40AT CB, 2-30AT CB, 2-
20AT CB, 1" diameter PVC electrical pipe, 32mm² THHN wire, 1.00 ls 13,157.33 13,157.33 27,411.09 27,411.09 40,568.42
8.0mm² THHN wire
1 - Panel board 20's with 100A rating, 1-50AT CB, 1-30AT CB, 13-
30AT CB, 11-20AT CB, 1" diameter PVC electrical pipe, 30mm² 1.00 ls 13,157.33 13,157.33 27,411.09 27,411.09 40,568.42
THHN wire, 8.0mm² THHN wire
1 - Panel board 10's with3-30AT CB, 13-30AT CB, 7-20AT CB, 1"
diameter PVC electrical pipe,30mm² THHN wire, 8.0mm² THHN 1.00 ls 13,157.33 13,157.33 27,411.09 27,411.09 40,568.42
wire
PVC conduits and accessories
Utility box 100.00 pcs 41.12 4,111.66 4,111.66
Junction box 150.00 pcs 41.12 6,167.50 6,167.50
Adapter locknut 400.00 pcs 20.56 8,223.33 8,223.33
1/2" PVC electrical pipe 120.00 pcs 205.58 24,669.99 24,669.99
Miscellaneuous item 1.00 ls 20,558.32 20,558.32 20,558.32
Wires
8.0mm² THHN wire 2.00 box 11,649.72 23,299.43 23,299.43
5.5mm² THHN wire 10.00 box 8,908.61 89,086.06 89,086.06
3.5mm² THHN wire 10.00 box 7,675.11 76,751.07 76,751.07
Telephone wire 1.00 box 3,426.39 3,426.39 3,426.39
Coaxial wire 1.00 box 3,426.39 3,426.39 3,426.39
Devices
Duplex Convenience outlet 64.00 sets 308.37 19,735.99 19,735.99
Range outlet 1.00 sets 376.90 376.90 376.90
Water heater outlet 5.00 sets 376.90 1,884.51 1,884.51
Refigerator outlet 2.00 sets 363.20 726.39 726.39
CATV outlet 3.00 sets 363.20 1,089.59 1,089.59
Telephone outlet 8.00 sets 363.20 2,905.58 2,905.58
Swtches
Single switch 14.00 sets 308.37 4,317.25 4,317.25
Two-gang Switch 8.00 sets 335.79 2,686.29 2,686.29
Three-gang Switch 14.00 sets 376.90 5,276.64 5,276.64
3-way Switch 2.00 sets 376.90 753.81 753.81
12W LED, Pinlight 196.00 sets 753.81 147,745.80 147,745.80
Labor
Installation 1.00 ls 552,607.67 552,607.67 552,607.67
Sub-total 1,219,466.70
10 PLUMBING WORKS
Sanittary and roof drain
5 of 7
CLIENT'S COPY
Project Name PROPOSED TWO STOREY WITH ROOFDECK
Project Location TAGAYTAY
Project Name MR. JOHN CAHILIG
UNIT COST
ITEM DESCRIPTION QTY UNIT TOTAL COST
LABOR MATERIALS
6 of 7
CLIENT'S COPY
Project Name PROPOSED TWO STOREY WITH ROOFDECK
Project Location TAGAYTAY
Project Name MR. JOHN CAHILIG
UNIT COST
ITEM DESCRIPTION QTY UNIT TOTAL COST
LABOR MATERIALS
7 of 7