Professional Documents
Culture Documents
00 30-Jun-16
HAWIYAH AND HARADH DEVELOPMENT SATELLITE GAS COMPRESSION 10 - 01996 / 0007 MOFAREHH AL-HARBI & PARTNERS
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
3.6
SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL
W H
ITEM RE-INSP
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No. DATE
Uncompacted asphalt concrete samples shall be taken daily for extraction, gradation and
Marshall properties at the following rates of production:
Quantity (tons) Extraction/Grading Marshall Properties SAES-Q-006
A2
0 to 500 1 sample per 200 tons 1 sample per 250 tons Sec. 5.4.4.2
501 to 800 1 sample per 250 tons 1 sample per 300 tons
801 & above 1 sample per 300 tons 1 sample per 400 tons
Temperature of mixtures without sulfur shall be between 139°C and 163°C when it leaves SAES-Q-006
B1
the plant and at least 139°C at the time of spreading and compaction at the site. Sec. 5.4.4.A
The hot mix asphalt concrete material has a temperature of at least 115°C at the time of SAES-Q-006
C1
spreading and compaction. Sec. 5.4.4.A
The polymer modified asphalt mix shall placed and compacted at a temperature
SAES-Q-006
D1 determined from the viscosity-temperature relationship which is estimated to be in the
Sec. 5.4.3.A
range of 155 to 165°C.
The hot mix asphalt concrete shall be placed only when the atmospheric temperature is
SAES-Q-006
E1 4°C or above, & when the weather is not foggy or rainy & when the existing surface is free
Sec. 5.4.4.A
from moisture.
Any existing pavement shall be saw-cut, primed and tacked prior to placing new hot mix SAES-Q-006
E2
asphalt. Sec. 5.4.3.B
Steel skid equipment shall not be used for placing hot mix asphalt until after the first layer SAES-Q-006
E3
is placed. Sec. 5.4.3.B
Bituminous mixture shall be placed so that after rolling, the nominal thickness of the SAES-Q-006
E4
compacted bituminous material shall not be more than 70mm per layer. Sec. 5.4.3.B
Greater than 70mm thick layers may be implemented if approved by the Company
representative after the contractor has proven that he can achieve the requirements by
SAES-Q-006
E5 field trials, using the compacting equipment and rolling patterns that he intends to use.
Sec. 5.4.4.B
Note: Approval of thicker lift by the S.A. representative does not relieve the Contractor's
responsibility to meet the project requirements.
In no case shall thin layers of fine materials be added to the top of the wearing course in SAES-Q-006
E6
order to achieve the required thickness or specified tolerances. Sec. 5.4.4.C
Longitudinal joints shall be rolled first, then rolling shall begin at the lower edge and SAES-Q-006
E7
proceed towards the highest portion. (MOT GS, Par. 4.05.6.8) Sec. 3.2
SAUDI ARAMCO ID/PIEU - 15-Nov-2017 - REV. 2016.06.00 (Standards Cutoff -June 30, 2016) Rev. 2016.06.00 30-Jun-16
HAWIYAH AND HARADH DEVELOPMENT SATELLITE GAS COMPRESSION 10 - 01996 / 0007 MOFAREHH AL-HARBI & PARTNERS
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
3.6
SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL
W H
ITEM RE-INSP
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No. DATE
Each asphalt paving layer shall be placed as continuously as possible to keep the number
SAES-Q-006
E8 of joints between old and new pavements, between successive day's work, or when the
Sec. 5.6.1
mixture has become cold (less than 90°C) to a minimum.
Joints shall be made in such a manner as to create a continuous bond between the old SAES-Q-006
E9
and new pavement construction courses. Sec. 5.6.5
When the pavement construction involves two or more courses, successive courses shall SAES-Q-006
E10
be offset by at least 150 mm. Sec. 5.6.3
If the placing of material is discontinued or if material in place becomes cold (less than
90°C), a joint running perpendicular to the direction traveled by the paver shall be made.
SAES-Q-006
E11 Before placement continues, the edge of the previously placed pavement shall be trimmed
Sec. 5.6.4
to a straight line perpendicular to the paver and cut back to expose an even vertical
surface for the full thickness of the course.
When the roller is within sixty (60) centimeters of either edge, it shall proceed by lapping
the uncompacted mixture by not more than thirty (30) centimeters per coverage. A SAES-Q-006
E12
coverage consists of one pass of the roller over any portion of the layer being placed. Sec. 3.2
(MOT GS, Par. 4.05.6.8)
SAES-Q-006
E13 All compaction shall be completed before the temperature of the mix falls below 90 0C.
Sec. 5.6.1
SAES-Q-006
E14 The finished surface shall be free of open-textured areas of asphalt.
Sec. 5.4.4.B
Areas of asphalt which fail to meet the required tolerances and/or compaction shall be
SAES-Q-006
E15 removed by saw cutting to the full depth of the wearing course and base course, forming
Sec. 5.4.4.D
parallel and perpendicular lines extending to the architectural features where practical.
Areas cut out for repair shall receive additional prime coat prior to placing asphalt SAES-Q-006
E16
materials. Sec. 5.4.4.D
Newly placed sections are protected from traffic by barricades or other suitable method.
SAES-Q-006
E17 After final rolling, vehicular traffic on asphalt concrete pavement are not permitted until it
Sec. 5.4.4.E
has hardened properly.
SAES-Q-006
E18 Asphalt pavement shall not be in contact with pipelines that are catholically protected.
Sec. 5.4.4.F
At the time of spreading and compaction, the conventional hot mix asphalt concrete SAES-Q-006
F1
material shall be at least 139°C. Sec. 5.4.4.B
Polymer modified asphalt mix shall be placed and compacted at a temperature determined
SAES-Q-006
G1 from the viscosity-temperature relationship which is estimated to be in the range of 155°C
Sec. 5.5.4.
to 165°C.
At the time of spreading and compaction, the sulfur extended asphalt concrete material is SAES-Q-006
H1
at least 115°C. Sec. 5.4.4
SAUDI ARAMCO ID/PIEU - 15-Nov-2017 - REV. 2016.06.00 (Standards Cutoff -June 30, 2016) Rev. 2016.06.00 30-Jun-16
HAWIYAH AND HARADH DEVELOPMENT SATELLITE GAS COMPRESSION 10 - 01996 / 0007 MOFAREHH AL-HARBI & PARTNERS
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
3.6
SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL
W H
ITEM RE-INSP
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No. DATE
Rolling and compaction is carried out immediately after the Sulfur Extended Asphalt
SAES-Q-006
H2 Concrete (SEAC) mix is placed and is completed within 100 m of the paver. (SABP-Q-010,
Sec. 3.1
Sec. 8.2)
Compaction is maximized while the mix is hot, in the 140 to 120°C range. (SABP Q-010, SAES-Q-006
H3
Sec. 8.2) Sec. 3.1
SAES-Q-006
H4 Rubber-tired rollers is not used for finish rolling of SEAC mix.(SABP Q-010, Sec. 8.2)
Sec. 3.1
The base shall be primed and the edges of the existing pavement shall be tacked in SAES Q-006
I1
accordance with paragraph 5.4. Section 5.6.6
Asphalt concrete materials and mix design shall be in accordance with paragraphs 5.5.1 SAES Q-006
I2
and 5.5.2 or 5.6. Section 5.5
Asphalt concrete shall be placed in a minimum two lifts and compacted in accordance with
SAES Q-006
I3 paragraph 5.5.3 to a thickness equivalent to the original pavement or 100 mm, whichever
Section 5.6
is greater.
J Laboratory Testing
All quality tests and sampling on raw materials shall be performed by a Saudi Aramco
SAES Q-006
J1 approved independent laboratory in the presence of Contractor and Saudi Aramco
Section 5.4.5
Representatives.
Third Party Agency's Quality Personnel assigned to the Work must be technically
Schedule "Q"
J2 competent to perform their duties and shall have a recommendation for approval from
Section 5.5
Saudi Aramco to perform applicable Tests.
Tests performed in accordance to applicable Standards in the presence of Contractor and Schedule "Q"
J3
Saudi Aramco Representatives. Section 1.4
REMARKS:
REFERENCE DOCUMENTS:
1- SAES-Q-006 -- Asphalt and Sulfur Extended Asphalt Concrete Paving, 22 May 2016
2- Schedule "Q" -- Project Quality Requirements
3- General Specifications for Road and Bridge Construction, Ministry of Transport (MOT) -- November 1998
HAWIYAH AND HARADH DEVELOPMENT SATELLITE GAS COMPRESSION 10 - 01996 / 0007 MOFAREHH AL-HARBI & PARTNERS
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
3.6
SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL
W H
ITEM RE-INSP
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No. DATE
Name, Initials and Date: Name, Initials and Date:
Mr.Abdul Hannan Mr. ADNAN
QC Supervisor Proponent and Others
Quality Record Approved: Work
T&I Witnessed QC Record Reviewed
Name, Organization, Verified
Name, Sign and Date:
Mohammaed Zubair Initials and Date:
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
In no case shall thin layers of fine materials be added to the top of the
SAES-Q-006
E6 wearing course in order to achieve the required thickness or specified
Sec. 5.4.4.C
tolerances.
Longitudinal joints shall be rolled first, then rolling shall begin at the lower SAES-Q-006
E7
edge and proceed towards the highest portion. (MOT GS, Par. 4.05.6.8) Sec. 3.2
When the roller is within sixty (60) centimeters of either edge, it shall
proceed by lapping the uncompacted mixture by not more than thirty (30) SAES-Q-006
E12
centimeters per coverage. A coverage consists of one pass of the roller Sec. 3.2
over any portion of the layer being placed. (MOT GS, Par. 4.05.6.8)
All compaction shall be completed before the temperature of the mix falls SAES-Q-006
E13
below 900C. Sec. 5.6.1
SAES-Q-006
E14 The finished surface shall be free of open-textured areas of asphalt.
Sec. 5.4.4.B
Areas cut out for repair shall receive additional prime coat prior to placing SAES-Q-006
E16
asphalt materials. Sec. 5.4.4.D
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Asphalt pavement shall not be in contact with pipelines that are SAES-Q-006
E18
catholically protected. Sec. 5.4.4.F
At the time of spreading and compaction, the conventional hot mix asphalt SAES-Q-006
F1
concrete material shall be at least 139°C. Sec. 5.4.4.B
At the time of spreading and compaction, the sulfur extended asphalt SAES-Q-006
H1
concrete material is at least 115°C. Sec. 5.4.4
Compaction is maximized while the mix is hot, in the 140 to 120°C range. SAES-Q-006
H3
(SABP Q-010, Sec. 8.2) Sec. 3.1
Rubber-tired rollers is not used for finish rolling of SEAC mix.(SABP Q- SAES-Q-006
H4
010, Sec. 8.2) Sec. 3.1
The base shall be primed and the edges of the existing pavement shall be SAES Q-006
I1
tacked in accordance with paragraph 5.4. Section 5.6.6
Asphalt concrete materials and mix design shall be in accordance with SAES Q-006
I2
paragraphs 5.5.1 and 5.5.2 or 5.6. Section 5.5
J Laboratory Testing
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
REMARKS:
REFERENCE DOCUMENTS:
1- SAES-Q-006 -- Asphalt and Sulfur Extended Asphalt Concrete Paving, 22 May 2016
2- Schedule "Q" -- Project Quality Requirements
3- General Specifications for Road and Bridge Construction, Ministry of Transport (MOT) -- November 1998