Response Sheet

Project Tuas Water Reclamation Plant - Contract 2B Product Water Pumping Facilities
Document No 131222-WNS00-PG-PC-0002
Document Title C2B - Response Log - Rev 2 Baseline Programme for the Works

Item B
No. Date Commented Updated dates (If any) Document Page Reference Activity ID / Section Comment Description Action Required y Contractor Status Update Contractor Response PUB/Jacobs Remarks Contractor Response 2 PUB/Jacobs Remarks2 Contractor Response 3
Please submit the basis of the Programme for the Works. Open Basis of the Programme for the Works 1. Sequences - Please consider the use of Network Logic Diagrams 1. Network logic diagram used wherever 1. The network logic diagram provided does not show
This should include the assumptions made in developing submitted on 20 May 2021. when describing the sequence of physical works within each location. possible. clear visualization of the sequence between activities.
the programme, which includes but is not limited to: Updated revision as per the comments Please also include a description of the relationship between phases 3. Production Rates - RC Works 5. Remove those legends not in use. Ensure sharper
1. Sequences; attached with this submission from procurement to installation. Please also consider the readiness of production rates used kept conistent in quality of screen captured image. Suggest to add in
2. Quantities; C&S to install MEICA equipment Attachment 4 and Section 6. And in the storage area in the diagram as well
3. Productivity rates; 2. Quantities - No further comments summary table different RC productivity 6. Provide details on the challenges, issues and
4. Resource allocation; (labor and equipment) 3. Production Rates - Please include an additional table to show how RC rates based on their complexity of work concerns listed. Provide how CHEC is intending to
5. Site utilization and availability production rates are derived from mentioned. mitigate or reduce these challenges, issues and
6. Challenges and issues and concerns 3.Productivity Rates - Please clarify the basis of why RC work’s 4. Added with Major Machinery Plan concerns impact on the programme
production rates fluctuate at various locations 5. Site Utilization & availabilty mentioned
1 14-May-2021 Basis of the Programme for the Works - - Not included in the submission 3. Productivity Rates - Please provide the productivity rates for other in Basis of the Programme for the Works.
items (e.g. pipes, cables, valves, MEICA equipment and etc.) 6. Challenges and issues and concerns
4. Please also include the total number of each major machinery in mentioned in Basis of the Programme for
each period the Works.
5. Not mentioned in narrative. Please provide.
6. Not mentioned in narrative. Please provide.

Open Programme resource loaded with Reviewed and ensured all resource Please review all activities with resource assignment.
Manpower & Equipment Please review and ensure all resource assignment is in accordance to assignment in Programme are following For example, "C2BCN21530" has 6 carpenter in the
the description in the Basis of the Programme for the works. For Basis of the Programme for the works. progarmme while RC Works resource assignment
2 14-May-2021 Programme for the Works (XER) - Resource Loaded Please resource load the Programme for the Works example "C2BCN21510" does not have tipper truck while ERSS resource mentions 3 carpenter is required in the Basis of the
assignment mentions 2 tipper truck is required Programme for the Works.

Open Programme Cost loaded as per the Cost Loading is done based on the BQ.
comments The cost loading does not correlate back to the BQ.
3 14-May-2021 Programme for the Works (XER) - Cost Loaded Please include the cost by Bill of Quantities The cost loading does not correlate back to the BQ. We will require the We will require the cost loading to be done with
cost loading to be done with reference to the submitted BQ.
reference to the submitted BQ.

Open Critical Path provided with the Basis Critical Path is traced back using the Critical path needs to be organic. Artificial conditions
of the Programme for the Works driving activities from the Key Milestone. will impact the accuracy of reporting. We suggest
Please clarify the method used to extract the critical path in using total float as the basis of your critical path. Do
4 14-May-2021 Programme for the Works (XER) - Critical Path Please provide the Critical Path  include the justification behind why the chosen total
Attachment 1
float value is to be considered as critical

Please advise the rationale for using the Constraints in Closed Constraints minimized as per the
5 14-May-2021 16-Jul-2021 Programme for the Works (XER) Refer to "Constraints" Unless with valid reason, constraint usage should be minimized and allow logic "Constraint Activities" tab, adjust logics in Programme comments.
tab to drive the activities dates accordingly
Unless with valid reason, Project should have only 1 Start milestone with no Please advise the rationale that activities  have "No Closed Activities linked to relevant All activities have Predecessor except
Refer to "No predecessors based on the comments. Please advise the rationale that activities  have "No Predecessor" in tab, "Letter of Award"
6 14-May-2021 12-Aug-2021 Programme for the Works (XER) Predecessor" tab Predecessor. Please refer to "No Predecessor" tab, review whether any missing Predecessor" in tab, and adjust logic in Programme and adjust logic in Programme accordingly
logic accordingly
Please advise the rationale that activities  have "No Closed Activities linked to relevant successors All activities have successor except "C2B
Refer to "No Unless with valid reason, Project should have only 1 Finish milestone with no based on the comments. Please advise the rationale that activities  have "No Successor" in tab, Contract Completion"
7 14-May-2021 12-Aug-2021 Programme for the Works (XER) Successor" in tab, and adjust logic in Programme
Successors" tab Successor. Please refer to "No Successor" tab, review whether any missing logic accordingly and adjust logic in Programme accordingly

Closed Lags removed and minimized as per All lags removed and activties logically
Unless with valid reason, Project should have no lags apply, activity could be the comments. linked as per the comments.
8 14-May-2021 12-Aug-2021 Programme for the Works (XER) Refer to "Lags" tab broken down and linked by FS logic instead of  a SS logic with lag is required. Please advise the rationale of using "Lag" in tab, adjust Please advise the rationale of using "Lag" in tab, adjust logic in
logic in Programme accordingly Programme accordingly
Please refer to "Lag" tab, review whether the Lags are  necessary

Refer to "FF Open SS & FF logic minimized based on the SS & FF logic minimized based on the The SS and FF links were used due to activities having
Preferred logic type would be FS, refer to list stated in "FF Logics" tab and "SS Please advise the rationale of using "SS Logic" in tab, comments. Wherever used SS is closed Please advise the rationale of using "SS Logic" in tab, review the list and comments. Wherever used SS is closed by a long duration. These can be further reduced when
9 14-May-2021 Programme for the Works (XER) Relationship" tab Logic" tab, if possible, revise the logic and minimize the usage of FF and SS, review the list and adjust logic in Programme wherever
Refer to "SS by FF to avoid any open ended adjust logic in Programme wherever possible FF to avoid any open ended activities. activities are further detailed out.
especially SS logic that leads  to open-ended loop possible activities.
Relationship" tab

Refer to "Duration Open Majority of activities broken down Majority of activities broken down with There are still a number of activities with more than 30
10 14-May-2021 Programme for the Works (XER) with more than 30 Under G2.2.5, item (o), it is specified that duration of any activity shall not Please breakdown the activities with more than 30 Days with more than 30 days duration. Please breakdown the activities with more than 30 Days duration, if more than 30 days duration. Days duration. Please refer to "Activities more than 30
days" tab exceed 30 working days, except where otherwise agreed by S.O. duration, if applicable. applicable. days" tab
Open Programme Summary to be added at Programme Summary added on top as Please ensure LOEs are linked to all the areas instead
Add in a programme summary on top and use a level of the Top as Level of Effort type activity Add in a programme summary on top and use a level of effort to level of effort activity. of the planned location to be completed last
11 14-May-2021 Programme for the Works (XER) - Programme Summary before the detailed programme effort to summarize the programme summarize the programme
progressively.
Open Detailing for Procurement activities Please provide detail breakdown of the procurement activity. CHEC will follow up with a micro Please provide detail breakdown of the procurement
Please detail the equipment for each of the facilities and provided. programme separately with the Sub-
12 14-May-2021 Programme for the Works (XER) - Procurement details by location insufficient Additionally please ensure cost loading is following the payment activity. Additionally please ensure cost loading is
follow the payment schedule  to match cost loading schedule contractor following the payment schedule
Open Detailing for Engineering activities MEICA "Design" WBS name changed to Engineering description mentioned twice. We suggest
13 14-May-2021 Programme for the Works (XER) - Engineering details by location insufficient Please detail the engineering for each of the facilities. provided. Please consider renaming the WBS to show Engeering design "Engineering Design" to check with CHEC MEICA team on the MEICA design
consideration terminology used.
Open More details for Piling Works provided WLT/PDA/PIT durations reviewed. Please review the number of WLT/PDA/PIT within
14 14-May-2021 Programme for the Works (XER) - Piling Works to provide more details Include the reports required after piling activities as per the comments. Please review the Working Load Test/PDA/PIT durations. each month. Ensure sufficient resources and durations
are allocated to complete this task.
Open Detail Provided based on the Steel Storage Tanks installation further Please further detail out the activity. please include
15 14-May-2021 Programme for the Works (XER) - Provide more details of the sequence Please provide more details of the steel storage tank comments for Steel Storage Tanks Insufficient tank installation description. Please expand on the detailed. scaffold erection and dismantling if required
installation sequences Installation. installation components

Open Breakdown provided for activities Hydrostatic test broken down into Please review with CHEC MEICA team if the
wherever applicable. Testing, flushing & sterilization hydrostatic test will be done after each tank completes
16 14-May-2021 Programme for the Works (XER) - Hydrostatic testing activities Please breakdown the activities accordingly Insufficient breakdown of hydrostatic activities. respectively. or done during a period. Additional include further
details of hydrostatic activities

Open Piping breakdown provided based on CHEC will follow up with a micro
All activities for steel Please breakdown the piping breakdown by system and System programme separately with the Sub-
17 14-May-2021 Programme for the Works (XER) Provide more details of piping installation and valves Insufficient breakdown of piping and valve installation Insufficient breakdown of piping and valve installation.
storage tanks valves contractor
Open ICA activities detailed wherever CHEC will follow up with a micro
All activities referring Please provide a breakdown of the panels and instruments applicable and progressively more The scope of works that the subcontractors are managing would have programme separately with the Sub-
18 14-May-2021 Programme for the Works (XER) ICA details of the panels and instruments details will be provided when available been scoped out prior to awarding of subcontractor. contractor Insufficient breakdown of ICA activities
to hydrostatic test accordingly
from the Sub-Contractors.

All related piping Open Proper linkage of Interface activituies Please add in the contract package code that CHEC will be interfacing Contract Package codes added in the Please ensure appropriate C2B scope is linked to the
19 14-May-2021 Programme for the Works (XER) Interface milestones are not linked to any activities Please provide proper linkage of the activities are provided. Interfacing Milestones activities. various interfacing activities
installation activities with
Open Interface activities already inlcuded in Contract Package codes added in the Please breakup C5A interfacing to its respective room
All ICA related Rev - Submission. Please add in the contract package code that CHEC will be interfacing Interfacing Milestones activities. and ensure the appropriate rooms are linked.
20 14-May-2021 Programme for the Works (XER) activities Interface activities not included Please provide details for interface activities with Additionally please ensure accurate description of
works for C5A interfacing

Open Staging activities to be monitored CHEC will follow up with a micro Please include scaffold erection and dismantle works
21 14-May-2021 Programme for the Works (XER) Interface Milestones Staging activities Provide the staging activities based on construction when available from Sub- This is referring to locations requiring the erection of scaffolds. Please programme separately with the Sub-
sequences contractor. include scaffolding erection and tearing down. contractor
Open System-wide pre-commissioning Further breakdown for T&C activities are Please include the various testing required for each of
Provide a minimum of system-wide pre-commissioning activities already included under provided in T&C Phase. the testing and pre-commissioning activity required
22 14-May-2021 Programme for the Works (XER) Interface Activities System-wide  pre-commissioning and commissioning activities and commissioning activities Please provide more details on these pre-commissioning activities
Testing & Commissioning Phase. for interfacing works

PSR is scheduled to start 10 Jun 21, which is earlier than start of ERSS design Open PSR broken down into 3 Steps The programme still does not reflect the three step process defined in PSR included for NW, IW tanks and Crane The duration assigned is not consistent with P9.5.
which is scheduled to start on 28 Jul 2021. ERSS design should be submitted Please provide more details based on the three - step (MOS/RA/SWP). And linked logically as P9.5. Please also review the list of PSR items and ensure they are Management as per the P9.5. Please review and amend
23 14-May-2021 Programme for the Works (XER) All C&S Activities per the comments.
and reviewed by SO before PSR for ERSS. PSR is a three step process. The process required. Additionally please ensure accurate linkage of PSR approvals
programme doesn't reflect this and the commencement of related physical works
Closed Detailed list of major method Method Statement, Risk Assessment and
Please include a comprehensive schedule of all method statements to be submitted included. Please breakdown the Method Statement, Risk Assessment and Safe Safe Work Procedure will be submitted as
24 21-May-2021 12-Aug-2021 Programme for the Works (XER) All C&S Activities List of method statements seems incomplete. one package for the items listed in
statements. Work Procedure should be captured separately
Programme for the Works.

ERSS design should initially be submitted to SO for preliminary review before Closed ERSS Design process revised as per the ERSS Design process reviewed and
submission to AC to avoid abortive work by AC. If there are no major comments Please revise the process of the ERSS design review and comments amended as per the comments.
25 21-May-2021 12-Aug-2021 Programme for the Works (XER) All C&S Activities Please review the logic linking of the ERSS design
on the scheme, then detailed review by SO & AC can proceed in parallel as approval
planned.

Please include installation of ground instrumentation, by Closed Ground Instrumentation to be done by C2B is looking to allow 35days to IMC
Instrumentation & Monitoring Please provide a period that C2B is looking to allow IMC Contractor to Contractor prior to Excavation.
26 21-May-2021 12-Aug-2021 Programme for the Works (XER) All C&S Activities Ground Instrumentation is not in the programme the Instrumentation and Monitoring Contractor (IMC), complete their installation works prior to commencement of ERSS
which needs to be in place before commencement of ERSS Contractor.
excavation physical works

An overall method statement for preliminary test piles (PTPs) and a design for Open All reports included for ULT. MS/RA/SWP included for ULT Please assign to all ULTs
27 21-May-2021 Programme for the Works (XER) All C&S Activities each PTP need to be submitted for SO review and approval before installation Please include all the necessary reports for submission and These activities needs to be completed prior to commencement of ULT
of PTPs. approval prior installation and testing activities installation
Item B
Date Commented Updated dates (If any) Document Page Reference Activity ID / Section Comment Description Action Required Contractor Status Update Contractor Response PUB/Jacobs Remarks Contractor Response 2 PUB/Jacobs Remarks2 Contractor Response 3
No. y
Closed Duration increased for Testing, Appropriate review cycles considered as
Please clarify when during this period the report will be Reporting & Dismantle test pile. per our discussion.
submitted to SO for QP(D) review. Do note that SO and Detailed activities included for ULT
QP(D) will review and comment on the test report before process.
Only 30 or 21 days allocated for "Testing, Reporting & Dismantle Test Pile" approval. Depending on the results, design review may be Please add in the number of expected review cycle in the activity
28 21-May-2021 12-Aug-2021 Programme for the Works (XER) All C&S Activities between finish of test pile installation and commencement of bored piling. This required. Please be reminded that as per G3.13.8 (e) (i) 1) description
seems quite short.
no guarantee will be given of the time elapsing between
completion of the test and commencement of the working
piles. Please amend accordingly

Closed WLT, PDA, PIT included as per Please clarify if 14 days is sufficient to condust Working Load Test and 14 days are sufficient to conduct
29 21-May-2021 12-Aug-2021 Programme for the Works (XER) All C&S Activities Test on working piles (WLT, PDA, PIT) to be included Add testing activities with respect to working piles comments. WLT/PDA/PIT.
prepare PDA and PIT
Bored Piling Work (Plant, Equipment & Construction) There should be an Closed Detailed breakdown for ULT and
Provide more detailed breakdown of preparation works Mobilization works included as per
30 21-May-2021 16-Jul-2021 Programme for the Works (XER) All C&S Activities activity before the start of C2BGN11020 for the setting up of the plant and
equipment for the bored piling works. before starting the bored piling work the comments
Open Details provided as per the comment. Please provide breakdown of the installation activities for the valves, CHEC will follow up with a micro
All activities in MEICA Please provide more details of the installation of pumps, instruments, pipes, electrical and ICA components. Please also programme separately with the Sub-
31 21-May-2021 Programme for the Works (XER) items Insufficient details for MEICA equipment equipment per facility, per level and per room provide detail description of the valves, pumps, instruments, pipes, contractor This is still not detailed out
electrical and ICA components
Open Refer to External and Handing Over Interfacing discussion still ongoing please breakdown the rooms for C5A interfacing and
32 21-May-2021 Programme for the Works (XER) All activities in MEICA Include room readiness and handover dates of rooms for C5A Include milestones and room handover milestone dates. for WNS03. Activity ID Please provide C5A in your activity description ensure the appropriate rooms are linked
items "C2BCN24330"

All activities in MEICA Closed Numbering of Tanks corrected based Tank no. added in the activity description
33 21-May-2021 12-Aug-2021 Programme for the Works (XER) items Inconsistent numbering of tanks against the tender drawing provide Try to follow the labeling in the drawings on Tender drawings. Add in the Tank no. In the activity description as well.
Closed Duration of Elecrical activities "Cable Cable Works activities broken down as
Duration for electrical activities "Cable Raceways Installation and Cable Please provide a detailed breakdown the activities, i.e Raceways installation & Cable per our discussion into 1) Cable Raceway
34 21-May-2021 12-Aug-2021 Programme for the Works (XER) All Electrical activities Cable raceway installation, Cable Laying/Pulling, Cable Connection" includes termination. Provide further breakdown of the activities Installation, 2) Cable Laying, 3) Cable
Connection" includes termination? Termination, etc. Termination

Open Archtectural Works included. CHEC will follow up with a micro This is still not detailed out
Please include Ceiling, floorings, partitions, ductings, Please include ductings, insulations and other necessary items in your programme separately with the Sub-
35 21-May-2021 Programme for the Works (XER) All Architectural works Insufficient details for Architectural Works insulation, etc architectural works considerations contractor
Open Architectural works included in Detail. Painting Works are included under Please include painting activities and fire-proofing
36 21-May-2021 Programme for the Works (XER) All Architectural works Painting/Fire Proofing activities Please include any paintings/fire proofing, etc Please review and ensure painting works and fire-proofing works are Architectural Finishes such as Ceiling works in the programme
included Finishes, Wall Finishes
Closed MD3 Milestone date corrected as per
Please amend according to P1.5 of the Particular P1.5 of the Particular
37 2-Jun-2021 16-Jul-2021 Programme for the Works (XER) C2BGN23360 Incorrect Milestone date for MD3. MD3 is not on 30-Dec-24 Specifications Specifications.
Closed Activities with more than 30 days of Activities with more than 30 days of We will be closing this comment but please review
Under G2.2.5, item (o), it is specified that duration of any activity shall not Please breakdown the activities with more than 30 Days duration minimised as much as Please provide further detailing for activities with more than 30 days duration minimised as much as possible. item #17.
38 2-Jun-2021 12-Aug-2021 Programme for the Works (XER) C2BGN10180
exceed 30 working days, except where otherwise agreed by S.O. duration, if applicable. possible. duration

7d duration for SI Reports to SO seems a little short when SI report requires Closed SI Process provided in detail as per the
39 2-Jun-2021 16-Jul-2021 Programme for the Works (XER) C2BGN10200 Please provide detail on the compilation efforts comments
compilation of the entire C2B site
Closed Site Office activities breakdown Please provide detailed breakdown of hoarding erection. Additionally, Site Office works broken down further
Contractor Site Office, In particular site office setup and erection of hoardings exceeds 30 working Please breakdown the activities with more than 30 Days provided as per comments. and backfilling activity included.
40 2-Jun-2021 12-Aug-2021 Programme for the Works (XER) please ensure that the necessary backfilling activities are included in
Facilities & Access days duration, if applicable. the programme prior to Site Office setup
Earth Control Incorrect submission process for ECM & drainage plan. Including activity having Please amend Closed ECM & drainage plan process Please provide further breakdown of construction and commissioning ECM Works broken down into Zone 1 &
41 2-Jun-2021 12-Aug-2021 Programme for the Works (XER) amended as per the comments. Zone 2 as per the discussion.
Measures more than 30 working day duration of ECM
Programme for the Incorrect submission process for Programme for the Works. Including activity Closed Submission process for the Please actualize the dates of your resubmissions and ensure a logical Date of the submission and resubmissions
42 2-Jun-2021 12-Aug-2021 Programme for the Works (XER) Works having more than 30 working day duration Please amend Programme for the works corrected. forecast date actualized as per the comments.
Closed Review cycle mentioned for various Date of the submission and resubmissions
submissions as per the Please actualize the dates of your resubmissions and ensure a logical actualized as per the comments.
43 2-Jun-2021 12-Aug-2021 Programme for the Works (XER) Project Controls Plan No review cycle mentioned of the various submissions Please provide submission sequencing forecast date
comments.
Open Timeframe for all the plans increased Please advise if the submission of 4 plans concurrently are feasible. Till Submission of the Plans are actualised Please advise if these activities are part of the
44 2-Jun-2021 Programme for the Works (XER) Risk, HSE & Quality To prepare and have 4 plans approved within a 28d timeframe seems Please reconsider if this is appropriate as per the comments. date there are still submissions yet to be received. Please relook and and linked logically based on forecast. Environment Health & Safety Management Plan?
unrealistic. provide a feasible forecast date
Open Testing & Commissioning Plan Breakdown of T&C activities by System Please include the various testing required for each of
Programme for the Please include necessary plans stated in the General included. Please provide detailed breakdown for T&C actvities by each of the provided as per the comments. the testing and pre-commissioning activity for C2B's
45 2-Jun-2021 Programme for the Works (XER) Works No mention of required plans such as T&C Plan or pressure testing plans. Specifications systems work. For example SATs
Open Method Statement submission MS/RA/SWP Submissions revised to The review cycle durations are not consistent. Please
Temporary Working timeline reviewed as per the Till date there are still submissions yet to be received. Please relook and provide a feasible forecast date. review and amend
46 2-Jun-2021 Programme for the Works (XER) Similarly, simultaneously preparing of 3 MS documentation seems unrealistic. Please reconsider if this is appropriate
Areas MS comments. provide a feasible forecast date

Open Design activities now divided as per CHEC will follow up with a micro
All Design & Majority of the design activities doesnt provide details on the number of review Please provide further detailing and ensure activities does the review cycles and durations of There are still design related activities with more than 30 days. Please programme separately with the Sub- There are still design related activities with more than
47 2-Jun-2021 Programme for the Works (XER) activities kept at the limit of 28d. contractor
Engineering Phase cycles considered hence the duration assigned tends to be above 30d not exceed 30d review 30 days.

Open Fabrication in batches is considered CHEC will follow up with a micro


48 2-Jun-2021 Programme for the Works (XER) All PMF Phase Do you require completion of all fabrication before proceeding to the next Please reconsider if this is appropriate based on the comments. Please provide details of the various equipments required programme separately with the Sub- Please provide details of the various equipments
step? Have fabrication in batches been considered? contractor required

Open Materials will be delivered on site 1- Materials and equipments storage area Please review if equipments are to be delivered 1-
Majority of the materials/equipments are arriving on-site way in advance. Does Please review and reconsider if there needs to be any 3months before installation. has been considered based on that 3months ahead. Please consider if some of these
49 2-Jun-2021 Programme for the Works (XER) All PMF Phase Have all the materials and equipments storage area been considered? materials and equipments will be equipments require pre-assembly
the staging area have the capacity to store all these items? amendments to the sequencing
delivered 1-3 months before installation.

Please reconsider description naming. For example you Closed WBS description changed to MEICA
50 4-Jun-2021 16-Jul-2021 Programme for the Works (XER) All Construction Phase Inaccurate WBS description for M&E works. Child node contains ICA works. might want to rename using acronym of MEICA or its full works as per the comments.
description naming instead.
Closed Activities with more than 30 days of Activities with more than 30 days of We will be closing this comment but please review
51 4-Jun-2021 12-Aug-2021 Programme for the Works (XER) All Construction Phase Under G2.2.5, item (o), it is specified that duration of any activity shall not Please breakdown the activities with more than 30 Days duration minimised as much as There are still a number of activities showing more than 30 days. Please duration reduced further as per item #17.
exceed 30 working days, except where otherwise agreed by S.O. duration, if applicable. possible. relook comments.
Closed
52 4-Jun-2021 16-Jul-2021 Programme for the Works (XER) All Construction Phase Ideally ground slab activities should not start concurrently with drainage works. Please reconsider their sequencing during further detailing
of the activities
Closed Testing & Commissioning phase for
53 4-Jun-2021 16-Jul-2021 Programme for the Works (XER) All Testing and Consider having a testing & commissioning phase for activity id. Please provide and update the programme narrative of the activity id included in the
Commissioning Phase Testing and Commissioning phase code Programme and Narrative as well.
Open Activities with more than 30 days of Further breakdown for T&C activities are Please provide details of the names of these testing
All Testing and Under G2.2.5, item (o), it is specified that duration of any activity shall not Please breakdown the activities with more than 30 Days duration minimised as much as provided in T&C Phase. and commissioning activities required.
54 4-Jun-2021 Programme for the Works (XER) Commissioning Phase exceed 30 working days, except where otherwise agreed by S.O. duration, if applicable. Please provide breakdown for T&C actvities
possible.
Closed C2BCN43110 is removed from the
55 4-Jun-2021 16-Jul-2021 Programme for the Works (XER) C2BCN43110 What is this FAT referring to Please advise programme.
Certain locations of work only has 1-3d of total float. This does not provide Open Total Float is taken into consideration The Programme for the Works has a 1d total float. Please review Duration assigned are reviewed on This is cause by long lead O&M activities. We suggest
56 4-Jun-2021 Programme for the Works (XER) Total Float sufficient turnaround in response to potential delays and can cause the whole Please review sequence and ensure ample total float for the Programme of the activities on the longest path and review if the durations assigned are longest path. using total float as the basis to derive your critical
project to overrun. Works. logical path.
Open Excessive floats are minimised Excessive floats are minimised wherever There are still activities with large total float
Certain phases contains activities with excessive floats. Excessive floats are wherever applicable. There are still a number of activities with a ample total float remaining. applicable. remaining. We suggest to review the logic linking and
57 4-Jun-2021 Programme for the Works (XER) Total Float typically caused by illogical relationship links or front loading excessive work Please review sequence and ensure logical sequencing Please relook the logic sequence consider from both natural successor and resource
efforts at the start availability perspective

Open Noted, will be taken into consideration Interfacing contract packages added in The pipe & valves activities mentioned lacks details to
Interfacing • 1800 mm diameter NW supply pipe to DLM as per the comments. The assumed interfacing dates should be based on the logical the activity description of Interface show interfacing consideration
Considerations - NW • Pipe racks/ bridge/ footings milestone as per our discussion.
from the Domestic • Flushing & sterilising activities the ROP pipeline from the discharge of the UV sequencing of your activities to determine a readiness date for
58 4-Jun-2021 Programme for the Works (XER) Please take this into consider during the reviews interfacing works to commence. Please review and ensure
Liquids Module (DLM) treatment process in the DLM to the NW product water storage tanks considerations have been undertaken. Additionally please add in the
tertiary treatment
plant Affected Contracts: C3D1/2; C1A interfacing contract packages in the activity description

Open Noted, will be taken into Interfacing contract packages added in No inclusion of interfacing with C3B1/2
• To locate the installation of the Tee joints (plugged) - for future consideration as per the comments. the activity description of Interface
connection/extension, along IW supply pipe. milestone as per our discussion.
Interfacing The assumed interfacing dates should be based on the logical
Considerations - IW • Pipe racks/ bridge/ footings sequencing of your activities to determine a readiness date for
• IW from ILM & DLM pipework connections to the C2B static mixers
59 4-Jun-2021 Programme for the Works (XER) from a mixture of the • Flushing activity on the Industrial Water pipeline from the Membrane Filtrate Please take this into consider during the reviews interfacing works to commence. Please review and ensure
DLM and Industrial considerations have been undertaken. Additionally please add in the
tank, within the DLM, to the IW product water storage tanks
Liquids Module (ILM). interfacing contract packages in the activity description
Affected Contracts: C3B1/2; C1A

Open Noted, will be taken into Interfacing contract packages added in The pipe & valves activities mentioned lacks details to
• Pipelines connections to Near-shore Outfall & Outfall drains consideration as per the comments. The assumed interfacing dates should be based on the logical the activity description of Interface show interfacing consideration
Interfacing
• Effluent Sampling Manhole sequencing of your activities to determine a readiness date for milestone as per our discussion.
Considerations - Plant
60 4-Jun-2021 Programme for the Works (XER) • NW & IW Product Water Tanks Overflow Connection pipes to Manhole Please take this into consider during the reviews interfacing works to commence. Please review and ensure
Process/ Overflow and considerations have been undertaken. Additionally please add in the
Emergency Overflow
Affected Contracts: C1A interfacing contract packages in the activity description
Item B
Date Commented Updated dates (If any) Document Page Reference Activity ID / Section Comment Description Action Required Contractor Status Update Contractor Response PUB/Jacobs Remarks Contractor Response 2 PUB/Jacobs Remarks2 Contractor Response 3
No. y
Open Noted, will be taken into Interfacing contract packages added in The pipe & valves activities mentioned lacks details to
consideration as per the comments. The assumed interfacing dates should be based on the logical the activity description of Interface show interfacing consideration
Interfacing • Various Fire / Potable Water pipework sequencing of your activities to determine a readiness date for milestone as per our discussion.
61 4-Jun-2021 Programme for the Works (XER) Considerations - Please take this into consider during the reviews interfacing works to commence. Please review and ensure
Utilities/ services Affected Contracts: C1A; C4A considerations have been undertaken. Additionally please add in the
interfacing contract packages in the activity description
Open Noted, will be taken into Interfacing contract packages added in The pipe & valves activities mentioned lacks details to
• G1 & G2D pipework consideration as per the comments. The assumed interfacing dates should be based on the logical the activity description of Interface show interfacing consideration
Interfacing • ROP from the DLM under hydrostatic head through pipework to the C2B static sequencing of your activities to determine a readiness date for milestone as per our discussion.
62 4-Jun-2021 Programme for the Works (XER) Considerations - Plant mixers Please take this into consider during the reviews interfacing works to commence. Please review and ensure
Water considerations have been undertaken. Additionally please add in the
Affected Contracts: C1A; C3D1 interfacing contract packages in the activity description
Open Noted, will be taken into Interfacing contract packages added in The pipe & valves activities mentioned lacks details to
• Storm-water drainage pipework consideration as per the comments. the activity description of Interface show interfacing consideration
• Discharging of process water (reject) pipes/ In-ground drainage pipes The assumed interfacing dates should be based on the logical
Interfacing sequencing of your activities to determine a readiness date for milestone as per our discussion.
(discharging to sea) connections
63 4-Jun-2021 Programme for the Works (XER) Considerations - Please take this into consider during the reviews interfacing works to commence. Please review and ensure
Drainage • Main & lateral drains considerations have been undertaken. Additionally please add in the
Affected Contracts: C1A; C4A interfacing contract packages in the activity description

Open Noted, will be taken into Interfacing contract packages added in No inclusion of interfacing with C6C
consideration as per the comments. The assumed interfacing dates should be based on the logical the activity description of Interface
Interfacing • Process pipework sequencing of your activities to determine a readiness date for milestone as per our discussion.
64 4-Jun-2021 Programme for the Works (XER) Considerations - RO Please take this into consider during the reviews interfacing works to commence. Please review and ensure
Reject to WWTF Affected Contracts: C6C considerations have been undertaken. Additionally please add in the
interfacing contract packages in the activity description

Open Noted, will be taken into Interfacing contract packages added in The pipe & valves activities mentioned lacks details to
• 2200 mm diameter NW /IW pipes to WSN consideration as per the comments. the activity description of Interface show interfacing consideration
• 1200 mm diameter NW /IW pipes to WSN milestone as per our discussion.
Interfacing The assumed interfacing dates should be based on the logical
• 1200 mm diameter contingency pipe to WSN
Considerations - WSN • Surge analysis, testing all air valves on the network sequencing of your activities to determine a readiness date for
65 4-Jun-2021 Programme for the Works (XER) network Please take this into consider during the reviews interfacing works to commence. Please review and ensure
interfacing/inter- • Pumps operation & testing considerations have been undertaken. Additionally please add in the
• Tanks storage/ level testing (WSN)
connecting chamber interfacing contract packages in the activity description
Affected Contracts: WSN

Open Noted, will be taken into Interfacing contract packages added in Insufficient details of activities reflecting this
consideration as per the comments. The assumed interfacing dates should be based on the logical the activity description of Interface interfacing
Interfacing • Duct Banks/ Cables sequencing of your activities to determine a readiness date for milestone as per our discussion.
66 4-Jun-2021 Programme for the Works (XER) Considerations - Please take this into consider during the reviews interfacing works to commence. Please review and ensure
Electrical Reticulation Affected Contracts: C1A considerations have been undertaken. Additionally please add in the
interfacing contract packages in the activity description

Open Noted, will be taken into Interfacing contract packages added in Insufficient details of activities reflecting this
consideration as per the comments. the activity description of Interface interfacing
Interfacing • Duct Banks/ Cables The assumed interfacing dates should be based on the logical milestone as per our discussion.
• Data collection @WSN Scada and equipment installation at selected service sequencing of your activities to determine a readiness date for
67 4-Jun-2021 Programme for the Works (XER) Considerations - ICA reservoirs Please take this into consider during the reviews interfacing works to commence. Please review and ensure
Fibre Ring Main
Reticulation considerations have been undertaken. Additionally please add in the
Affected Contracts: C1A; C5A interfacing contract packages in the activity description

Basis of the Closed Cover Page renamed to "Basis of the


68 4-Jun-2021 16-Jul-2021 Basis of the Programme for the Works Programme for the Please rename the cover page of the basis of programme Programme for the Works"
Works - Document
Open Manpower for each team is already Resource loading in Programme is made We will be closing this comment but please review
Please provide a narrative about the sequence of tanks, provided under Section 5 : consistent with the Basis of the item #17.
Please indicate the laber of tank numbers and provide a narrative on the the duration to build each tanks, the piling productivity Resource Plan. Sequence is briefly The loaded resource are not consistent with the resource plan Programme for the Works.
69 4-Jun-2021 Basis of the Programme for the Works Section 4.4 - WNS001 included in the narrative as per the
sequence of builing the tanks. assumed and manpower for eact team. Please indicate if described in section 5 of your Basis of the Programme for the Works
the work will be carried out in two shifts comments.

Open Refer Attachment 5 - Delivery CHEC will follow up with a micro


Please provide the detailed assumption of MEICA: Schedule. Installation sequence is programme separately with the Sub-
provided in "Basis of the Programme contractor
1. Major Equipment for the Works"
70 4-Jun-2021 Basis of the Programme for the Works Section 4.4 Please provide MEICA installation sequence in the basis of the programme 2. Assumed Lead time Please provide detail breakdowns of the MEICA items Insufficient detail breakdowns of the MEICA items
3. Installation sequence
4. Required on site and installation on site dates

Please provide a flow chart of testing and commissioning Open Included as per the comments in Further breakdown for T&C activities are Insufficient breakdown. Please provide the key
Please provide a more detailed information about the testing and "Basis of the Programme for the Please provide detailed breakdown of the various testing & provided in T&C Phase. testings to be done in the Basis of the Programme for
71 4-Jun-2021 Basis of the Programme for the Works Section 4.4 with the system priorities and the duration to carry out the
commissioning. precommissioning and commissioning Works" commissioning required for each of the systems the Works
Open Engineering cycle assumption Review by SO duration for 1st submission Resubmission by contractor and review by S.O should
Please indicate the assumption for engineering approval provided in the "Basis of the The review cycle durations does not seem to be appropriate. Please made to 28 days and for subsequent have the same durations. Any particualr agreed items
72 4-Jun-2021 Basis of the Programme for the Works Section 4.4 Please provide engineering engineering section cycle including the vendor information requirement, Programme for the Works" also review and indicate the flow from engineering to commencement submissions made to 21 days as per our allows for more days for contractor to resubmit?
process flow chart of procurement. discussion.

Designs, surveys, plans and submissions uses lags to artifically induce a Closed All lags removed and logical
commencement date. The use of lags does not provide logical sequencing for Please review the logical sequencing and ensure that lags sequencing used to drive the activities
73 14-Jul-2021 12-Aug-2021 Programme for the Works (XER) General Phase
its successors to commence. Additionally there is no clear visibility of lags and are not used to drive the commencement of your activities
the purpose behind these lags
Closed WBS description changed to
Procurement of Major Procurement of Major Sub-Contractor does not contain procurement related Please review the WBS description. This WBS contains the "Appointment of Major Sub-
74 14-Jul-2021 12-Aug-2021 Programme for the Works (XER) Sub-Contractor activities process required to award a subcontractor contractor"

Attach response sheet in excel format when submitting Closed Response sheet attached in excel
75 14-Jul-2021 12-Aug-2021 Programme for the Works (XER) General - Submission Please provide a copy of the comments response in excel format through Prolog format.
Open "Construction Phase" renamed to
Please relook and rename construction phase to an "Construction, Procurement &
77 14-Jul-2021 Programme for the Works (XER) Construction Phase The Construction Phase WBS contains non-construction related activities Construction typically commences after completion of engineering.
appropriate description Engineering Phase"
Closed Backfilling works for Site Office,
78 14-Jul-2021 12-Aug-2021 Programme for the Works (XER) Prelimineries and Backfilling works at Site Office, WNS01 and WNS02 were not appropriately Please include the backfilling activities WNS01 & WNS02 included in the
General described in the programme Programme.

Review all MEICA components that requires MOM Open MOM inspection is only required for
There are no activities involving MOM inspections. Please clarify if MOM inspection and include MOM Inspection into the activity EOT Cranes that has already been Insufficient detailing of the EOT cranes at WNS03. Please ALSO advise if
79 14-Jul-2021 Programme for the Works (XER) All MEICA activities included in the Programme. it is an inspection or registration? Please also clarify if the MOM
inspection considerations for the affected MEICA components were considered. description. Please also consider logically the inspection inspection duration provided includes for both cranes
period assigned to MOM
Please review the calendar assignment. The calendar Closed Project Calendar assigned as per the
80 14-Jul-2021 12-Aug-2021 Programme for the Works (XER) Calendar Activity successors were observed to commmence on the same day. comment.
assigned should be a 8am - 4pm working hour basis
Open CHEC will follow up with a micro
81 14-Jul-2021 Programme for the Works (XER) NEWater Storage Please consider the design of the storage tank's top platform as the tank mixers Please consider this activity in the design submissions programme separately with the Sub- Please provide details in the programme
Tanks - Design are not fixed to the storage tanks contractor

Please provide detailed description of the tank level Open CHEC will follow up with a micro
All NW/IW Storage Tank level sensors, water inlet flowmeters and actuators were not mentioned programme separately with the Sub-
84 14-Jul-2021 Programme for the Works (XER) sensor, the flow meter, actuators and their installation Please provide details in the programme
Tanks in the programme sequence contractor
Open CHEC will follow up with a micro
85 14-Jul-2021 Programme for the Works (XER) WNS01 There is insufficient details on drainage works Please breakdown the details of drainage construction programme separately with the Sub- Please provide details in the programme
contractor

Please include the latching mechanism for the tank mixer Open CHEC will follow up with a micro
All NW/IW Storage Latching mechanisms for tank mixer lifting chains not included for both programme separately with the Sub-
86 14-Jul-2021 Programme for the Works (XER) Tanks NEWater and Industrial Water Storage Tanks lifting chain for both NEWater and Industrial Water Please provide details in the programme
Storage Tanks into the programme contractor

Please include the Computer Fluid Dynamics (CFD) study Open CFD study activities included for
87 14-Jul-2021 Programme for the Works (XER) All NW/IW Storage Design study of mixers to avoid thermal stratifications were not considerd in activities for both NEWater and Industrial Water Storage NEWater and Industrial Water Storage Please include the CFD studies for the Pump Station as well
Tanks this programme Tanks.
Tanks
Open Pump Suction Pipework is considered
Please include the pump suction pipework for IW Storage under aboveground Pipe and Valves Please provide details in the programme
88 14-Jul-2021 Programme for the Works (XER) All IW Storage Tanks There is no mention of pump suction activities for IW Storage Tanks Tanks Installation activity.

WNS02 - Hydrostatic Closed Amended as pe the comments.


89 14-Jul-2021 12-Aug-2021 Programme for the Works (XER) Test Incorrect storage tank description for C2BTC11020 Please review and amend
Open CHEC will follow up with a micro
90 14-Jul-2021 Programme for the Works (XER) WNS03 There are no considerations for G1, PW and FWP being mentioned Please include the G1, PW and FPW in your programme programme separately with the Sub- Please provide details in the programme
contractor

Please clarify if the surge vessels are assembled on-site or delivered in one Open Surge vessel will be delivered in one The surge vessel size may not be able to be delivered in one piece.
Please include these considerations when sequencing piece and hoisted into place.
92 14-Jul-2021 Programme for the Works (XER) WNS03 piece and hoisted into place. Please consider the overall size of the surge Please consider assembly works on-site and include them into the
vessels, the space required to conduct safe lifting and allowable access. surge vessels installation works programme
Open CHEC will follow up with a micro
Please provide detailed description of the instruments to programme separately with the Sub-
93 14-Jul-2021 Programme for the Works (XER) WNS03 - Instruments The types of instruments required in WNS03 are not mentioned be installed Please provide details in the programme
contractor
Item B
Date Commented Updated dates (If any) Document Page Reference Activity ID / Section Comment Description Action Required Contractor Status Update Contractor Response PUB/Jacobs Remarks Contractor Response 2 PUB/Jacobs Remarks2 Contractor Response 3
No. y
Open CHEC will follow up with a micro
Please add in the various room types into your activity programme separately with the Sub-
94 14-Jul-2021 Programme for the Works (XER) WNS03 There is no mention of the different room types in WNS03 description Please provide details in the programme
contractor
Open CHEC will follow up with a micro
95 14-Jul-2021 Programme for the Works (XER) Static Mixers There is no mention of static mixers in the programme Please include static mixer activities in the programme programme separately with the Sub- Please provide details in the programme
contractor
Open CHEC will follow up with a micro
There is no mention of cross connection chambers and spectacle blinds in the Please include cross connection chambers and spectable programme separately with the Sub-
96 14-Jul-2021 Programme for the Works (XER) WNS03 programme blind activities in the programme Please provide details in the programme
contractor
Open CHEC will follow up with a micro
The programme only include EOT cranes linked to WNS03's level 1 works. There Please include all required crane types and their programme separately with the Sub-
98 14-Jul-2021 Programme for the Works (XER) Cranes Please provide details in the programme
are additional crane types not mentioned in the programme installation considerations. contractor

Please ensure all piping interfaces C2B has has been Open All Piping Interfaces have been
included as an interfacing milestone. Similarly, please included and logical activities are There are still interfacing works with other contract package that has
99 14-Jul-2021 Programme for the Works (XER) Interfacing Ensure pipes are ready before interfacing works commence linked to the Interfacing milestones.
ensure that logical activities are linked to interfacing not been included. Please review row 65 - row 74
milestone

Please provie breakdown of the installation activities for Open CHEC will follow up with a micro
programme separately with the Sub-
100 14-Jul-2021 Programme for the Works (XER) All MEICA activities No clear description of the valves, pumps, instruments or pipes to be the valves, pumps, instruments and pipes. Please also contractor Please provide details in the programme
procured/manufactured/tested/shipped or installed provide detail description of the valves, pumps,
instruments and pipes
Open CHEC will follow up with a micro
Please include consideration for the chloromine mixer in programme separately with the Sub-
101 14-Jul-2021 Programme for the Works (XER) WNS04 There is no mention of chloramine mixer consideration Please provide details in the programme
the programme contractor
Open Building services already detailed into
102 14-Jul-2021 Programme for the Works (XER) All Building Services There are insufficient details of the various systems required in the building Please breakdown building services activities 4 major works i.e. ACMV System, ELV Please provide further detail of the key elements in each of these
services System, FPS and Plumbing & Sanitary systems
Open CHEC will follow up with a micro
104 14-Jul-2021 Programme for the Works (XER) WNS05 There is no mention of conveyor systems Please provide conveyor system for WNS05. programme separately with the Sub- Please provide details in the programme
contractor
Open CHEC will follow up with a micro
105 14-Jul-2021 Programme for the Works (XER) WNS05 There is no mention of hammer systems Please provide hammering system for WNS05 programme separately with the Sub- Please provide details in the programme
contractor
Open CHEC will follow up with a micro
106 14-Jul-2021 Programme for the Works (XER) WNS05 There is no mention of lime mixer Please include lime mixer in the WNS05 programme separately with the Sub- Please provide details in the programme
contractor
Open CHEC will follow up with a micro
Please include the lime weighing requirements in your programme separately with the Sub-
107 14-Jul-2021 Programme for the Works (XER) WNS05 There is no mention of lime weighing requirements Please provide details in the programme
programme contractor
Open CHEC will follow up with a micro
Please provide a breakdown of the installation items in programme separately with the Sub-
109 14-Jul-2021 Programme for the Works (XER) All Installation There are insufficient details of each location's required installation works each individual location Please provide details in the programme
contractor
Open Lime Holding Tank already mentioned
110 14-Jul-2021 Programme for the Works (XER) WNS05 There is no mention of Lime Holding Tanks Please provide Lime Holding Tank in the Programme under activity id Please detail this activity as a separate line item
"C2BIN26010"
Open Pipe Racks will be Pre-fabricated and
There are no indication of the pipe rack types (single rack or double rack), assembled on Site.
Please include the necessary activities depending on the
112 14-Jul-2021 Programme for the Works (XER) WNS00 procurement, manufacturing and delivery process. Please also clarify if the pipe procurement and installation method Please include the assembly duration in the programme
racks are prefabricated and assembled on site prior to installation works

Open Installation of pipes will be done first Installation of pipe racks and pipes & valves are shown to be done
113 14-Jul-2021 Programme for the Works (XER) WNS00 Please clarify if valve will be installed onto pipes before they are laid onto the Please ensure the appropriate sequence of works are followed by installation of valves concurrently. Please review and ensure logical sequencing has been
pipe racks reflected. separately. considered
Please provide pipe laying if it has not been considered. Open Pipe laying has been considered under
There is no mention of pipe laying activities. Are these considered in the activity id "C2BIN27310" The logic linking does not seem accurate. There is no dependecy on
114 14-Jul-2021 Programme for the Works (XER) WNS00 duration of pipe rack installation Otherwise, please provide details of pipe rack installation pipe racks as its predecessor which does not seem accurate
and pipe laying
Open Coverings for the Sump Pit at GL Tank Please clarify if the sump pit covers are manufactured off-site and
115 14-Jul-2021 Programme for the Works (XER) WNS01 There is no mention of coverings at exposed sumps at GL Tank 3/A and GL Tank Please provide consideration in the programme 3/A and GL Tank 3/B has been installed after sump pits are completed? The duration assigned looks to
3/B considered as per comments. be consistent with sump pit works that does not require covers

Procurement of Major Closed ERSS Subcontractor also included


Sub-Contractor - Please include the subcontactor appointment process for under separate WBS.
116 14-Jul-2021 12-Aug-2021 Programme for the Works (XER) The subcontractor appointment process only indicates earthworks
Earthworks & ERSS ERSS as well.
Sub-Contractor
Procurement of Major The subcontractor appointment succeeding activities were not linked to their Please review and amend the successor for appointment Closed Subcontractor appointment linked to
117 14-Jul-2021 12-Aug-2021 Programme for the Works (XER) Sub-Contractor respective appropriate physical works of sub-con their relevant physical worls
Closed Dates has been actualised in the
Programme for the completed
Activities that have been completed were not actualised in the programme. Please provide the actualized dates for activities that have activities as well as well reasonable
118 14-Jul-2021 12-Aug-2021 Programme for the Works (XER) All Additionally there are activities forecasted to complete which were not been completed and a logical forecast date for activities forecast dates have been provided for
realised. that has not been completed the activities not yet started.

Closed Productivity Rates have been reviewed


119 14-Jul-2021 12-Aug-2021 Programme for the Works (XER) All - Piling & The piling works at each locations seems to require longer time than usual to Please review the productivity rate as it is too low and CHEC considers it keeping the
Foundation complete. same.
Closed ULT method are reviewed and
Please review the ULTs method. Are all of the 12 ULTs going to be tested using Please review all of the ULT method and ensure the amended in the Programme as per the
120 14-Jul-2021 12-Aug-2021 Programme for the Works (XER) All ULT activities
Kentledge? appropriate test method and durations are assigned comments.
Open 2 Teams are considered, hence 2 Please review the method of storage tank erection and consider the
121 14-Jul-2021 Programme for the Works (XER) WNS01 & WNS02 - Taking into consideration the workspace constraint, available manpower and Please review the mentioned considerations and relook at Tanks can be completed within 4 availablity of working area, manpower availability and works supporting
Storage Tanks scaffolding works, the completion of 2 tanks within 4 months looks optimistic. the logic linking and durations assigned months. the installation process
122 14-Jul-2021 Programme for the Works (XER) WNS03 - Pump Station There is no mention of roof structure works at WNS03 pump station Please provide roof works at WNS03 pump station Open Roof Works at WNS03 added. There are still no mention of structural roof works at pump station.
The duration for six sodium hydoxide tanks are identical with the duration Please review and ensure appropriate durations have been Closed Duration for Sodium Hydroxide Tank
123 14-Jul-2021 12-Aug-2021 Programme for the Works (XER) WNS04 increased to 63 days.
assigned for two sodium hypochloride tanks assigned
Closed Cabling Works are done at later period
124 14-Jul-2021 12-Aug-2021 Programme for the Works (XER) All Please provide clarification on why are the cabling works done at a much later Please review and provide appropriate relationship linkage because of Equipment Installation are
period and durations assigned required prior to Cabling Works.
Open CHEC will follow up with a micro
125 14-Jul-2021 Programme for the Works (XER) WNS04 There is no mention of cable ductings activitis in WNS04 Please provide cable ducting activities at WNS04 programme separately with the Sub- Please provide details in the programme
contractor

There are gaps observed between completion of site establishment and ULT Closed Gaps have been removed and
Please provide a feasible forecast date for the site separate team has been considered
126 14-Jul-2021 12-Aug-2021 Programme for the Works (XER) WNS05 and completion of ULT and bored piling works. This suggest that site
establishment does not have to start that early establishment and ULTs at WNS05 for WNS05.

RC piling works and test for electrical manholes and electrical ducts are Please separate piling and foundation works for electrical Closed Separate Piling Works included for
127 14-Jul-2021 12-Aug-2021 Programme for the Works (XER) WNS01 Electrical Manholes and Ductbank
conducted should not be captured together with WNS01 bored piling works manholes and electrical ducts
Open Interfacing with C4A for the 22kV
Interfacing Milestones There is no mention of interfacing works with C4A contract for 22kV cable Please include interfacing with C4A for the 22kV cable cable laying works from WSE21 to C2B
128 14-Jul-2021 Programme for the Works (XER) - Electrical laying works from WSE21 to C2B laying works from WSE21 to C2B There is no mention of cable pulling from C2A, through to C4A into C2B
included under activity id
"C2BGN22140"
Open Equipment Tag numbers stated in the
Particular Specifications cannot be
129 14-Jul-2021 Programme for the Works (XER) All - Electrical There is no mention of equipment tag numbers for all electrical components Please include the full tag number for all of your electrical directly related to individual items in This is due to activities being a single line item. Please detail out the
components activities and provide the appropriate tag number
the Baseline Programme for the
works.
Under interface milestone dates, please include the Open Interface milestones already included
following: in Programme. CHEC to follow up with
1. Handover of rooms to C5A for access a detailed programme with the Sub-
Interfacing Milestones contractor. This dates have been shared with C4A in the interfacing meeting.
130 14-Jul-2021 Programme for the Works (XER) key interfacing milestones with C5A were not mentioned 2. Information required to C5A for hardware requirements
- ICA Please ensure the accepted dates are reflecte in the programme
3. Include the date of the hardware required from C5A to
C2B
Open Site Acceptance Test is captured under
Please provide Site Acceptance Test after installation Pre-commissioning Stage 2B - Wet
works. Please ensure proper description such that Site Testing.
131 14-Jul-2021 Programme for the Works (XER) Site Acceptance Test There is no mention of Site Acceptance Test in the programme Acceptance Test are captured within the programme. We Please further detail the SAT activities in the programme
would suggest adding an additional WBS to contain the
Site Acceptance Test at various locations

Closed No activity durations are found to be


132 14-Jul-2021 12-Aug-2021 Programme for the Works (XER) All Some activitiy durations provided contains decimal values Please review and ensure durations are in whole numbers in decimals.

4.9 Breakdown of Engineering Phase was described twice. Once at Design & Engineering Phase Open
12-Aug-2021 Basis of the Programme for the Works 65/114 Works and another at Construction, Procurement & Engineering Phase Please review and provide appropriate description.
Item B
Date Commented Updated dates (If any) Document Page Reference Activity ID / Section Comment Description Action Required Contractor Status Update Contractor Response PUB/Jacobs Remarks Contractor Response 2 PUB/Jacobs Remarks2 Contractor Response 3
No. y
4.9 Breakdown of Open
12-Aug-2021 Basis of the Programme for the Works 65/114 There is no mention of Installation Phase in the breakdown Please amend description
Works
4.13 Design & Please clarify if these dates were agreed upon as stated in Open
12-Aug-2021 Basis of the Programme for the Works 71/114 The durations stated for the cycle does seem too long
Engineering Phase P2.15.4(g)(iv)
4.13 Design & Please include a note to indicate how these calendar days Open
12-Aug-2021 Basis of the Programme for the Works 71/114 Engineering Phase The durations stated are based on calendar days and not working days were derived.
There are no Procurement Phase reflected in the Programme for the Works. Open
4.14 Appointment of
12-Aug-2021 Basis of the Programme for the Works 72/114 Major Sub-Contractors Similarly there is no Procurement, Fabrication & Delivery Phase in the Please review and amend accordingly
Programme for the Work's WBS.
4.14 Appointment of Open
12-Aug-2021 Basis of the Programme for the Works 72/114 Major Sub-Contractors Table 9 WBS ID and Name are incorrect Please review and amend accordingly

WNS01 (NEWater Open


12-Aug-2021 Programme for the Works (XER) Product Water Is there supposed to be draining works at WNS01? Please review and include if necessary
Storage)
12-Aug-2021 Programme for the Works (XER) C2BGN24850 Is there a reason why no constraint was applied to C2B Contract Completion Please review and amend if necessary Open
Please review and amend the activity linkages that are Open
12-Aug-2021 Programme for the Works (XER) General There are a significant number of linkages that are either redundant links or either redundant or inappropriate. For example, there are
activities linked inappropriately MEICA works not driven by the completion of its
respective C&S works.
NW/IW Storage Tanks Open
12-Aug-2021 Programme for the Works (XER) - Mechanical No mention of the lifting device in WNS01 and WNS02 Please review and include
12-Aug-2021 Programme for the Works (XER) WNS01 The appropriate designs are not mentioned. Please refer to P4.4.3 Please review and add Open
12-Aug-2021 Programme for the Works (XER) WNS03 The appropriate designs are not mentioned. Please refer to P4.4.3 Please review and add Open
Please identify all the respective keys designs required for each of the various Open
12-Aug-2021 Programme for the Works (XER) General - Design Please review and add
locations
Please provide the appropriate ST submission considerations in your Open
12-Aug-2021 Programme for the Works (XER) General - Design programme Please advise and add if necessary

Permanently Installed There are insufficient details of the permanently installed cranes. Please review Open
12-Aug-2021 Programme for the Works (XER) Please review and include
Cranes the requirements in Appendix P4D
12-Aug-2021 Programme for the Works (XER) C2BGN21110 Please clarify the rationale behind this activity. Open
Open
WNS03 - Pump Station Building services at WNS03 are installed at the roof level. Are these above roof
12-Aug-2021 Programme for the Works (XER) structures? If so, there is no mention of the roof structure works at WNS03
Roof pump station location.
Id
C2BGN10110
C2BGN10310
C2BGN23180
C2BGN10320
C2BGN22150
C2BGN21260
C2BGN10210
C2BGN23340
C2BGN23350
C2BGN10220
C2BGN23360
Description
Letter of Award
Site Possession: WNS01/02/03/05
Commencement of Work and Site Possession
Site Possession: WNS04
Power Turn On from C2A
Power Turn On from C2B
MS1: Completion of Works Req. to Receive MBR Filtrate & RO Permeate of Specified Quality & Qty from DL Mod 1
MD2 : NEWater into Supply
MD1 : Industrial Water into Supply
MS2: Completion of the Whole of the Works
MD3 : Completion of Phase 1
Original Duration Remaining Duration Start Finish Primary Constraint
0.00 0 6/4/2021 6/4/2021 MustFinishOn
0.00 0 4/28/2021 4/28/2021 MustFinishOn
0.00 0 4/28/2021 4/28/2021 MustFinishOn
0.00 0 9/30/2022 9/30/2022 MustFinishOn
0.00 0 12/30/2023 12/30/2023 MustFinishOn
0.00 0 2/28/2024 2/28/2024 MustFinishOn
0.00 0 9/30/2024 9/30/2024 MustFinishOn
0.00 0 11/30/2024 11/30/2024 MustFinishOn
0.00 0 11/30/2024 11/30/2024 MustFinishOn
0.00 0 1/14/2025 1/14/2025 MustFinishOn
0.00 0 12/30/2025 12/30/2025 MustFinishOn
Primary Constraint Date Jacob's Remarks Contractor's Response for reason for Constraint
6/4/2021
4/28/2021
4/28/2021
9/30/2022
12/30/2023
2/28/2024
9/30/2024
11/30/2024
11/30/2024
1/14/2025
12/30/2025
Id Description
C2BGN10110 Letter of Award
Start Finish
6/4/2021 6/4/2021
Id Description
C2BGN24850 C2B Contract Completion
Start Finish Jacob's Remarks Contractor's Response
3/14/2027 3/14/2027
Predecessor Id
Predecessor
Pred Type Successor Id
Successor
Succ Type Lag Type Contractor's Response for using Lags
Predecessor Id
C2BCN30860
C2BCN32730
C2BIN23210
C2BIN24710
C2BIN24810
C2BIN26410
C2BIN27560
C2BIN27580
C2BIN27570
C2BIN27590
C2BIN23210
C2BCN16420
C2BCN16410
C2BIN21910
C2BIN21810
C2BIN24010
C2BIN25810
C2BIN25810
C2BIN25910
C2BIN26910
C2BIN27310
C2BIN25410
C2BCN32530
C2BIN25910
C2BCN11120
C2BCN43410
C2BCN43460
C2BCN43510
C2BCN43560
C2BCN43610
C2BCN11110
C2BCN43650
C2BCN11210
C2BCN11310
C2BCN11410
C2BCN11710
C2BCN43660
C2BCN43670
C2BMF23300
C2BMF21110
C2BMF23270
C2BMF44230
C2BMF42580
C2BMF21310
C2BMF44290
C2BMF21510
C2BCN11010
C2BCN43830
C2BCN43780
C2BCN43880
C2BCN45190
C2BCN16420
C2BCN16410
C2BCN43910
C2BCN43920
C2BCN16510
C2BCN16710
C2BMF23930
C2BMF29390
C2BMF29410
C2BMF42640
C2BMF44350
C2BMF29430
C2BCN16110
C2BCN21110
C2BCN44030
C2BCN43980
C2BCN43930
C2BCN45260
C2BCN21410
C2BCN21430
C2BCN44060
C2BCN44070
C2BCN21420
C2BCN21440
C2BCN21510
C2BCN21710
C2BCN22010
C2BCN22110
C2BCN21810
C2BCN21910
C2BCN23910
C2BCN24110
C2BMF21610
C2BMF21810
C2BMF21910
C2BMF22210
C2BMF30040
C2BMF44950
C2BMF44470
C2BMF22610
C2BMF28930
C2BMF29270
C2BMF29280
C2BMF29290
C2BMF29300
C2BCN25110
C2BCN44360
C2BCN44370
C2BCN45270
C2BCN25210
C2BCN25220
C2BCN25310
C2BCN25810
C2BCN25510
C2BCN26010
C2BMF29540
C2BMF30430
C2BMF31220
C2BMF31250
C2BMF31280
C2BMF31310
C2BMF29570
C2BMF43630
C2BMF43690
C2BMF44770
C2BMF29590
C2BMF43810
C2BMF43750
C2BMF30460
C2BMF30460
C2BMF30460
C2BMF30460
C2BCN30110
C2BCN44500
C2BCN44510
C2BCN44990
C2BCN30310
C2BCN30410
C2BCN44570
C2BCN44580
C2BCN30510
C2BCN30610
C2BCN30710
C2BCN30810
C2BCN30910
C2BCN31510
C2BCN31310
C2BMF29700
C2BMF31510
C2BMF31480
C2BMF31540
C2BMF31570
C2BMF29710
C2BMF29730
C2BMF43930
C2BMF43990
C2BMF44830
C2BMF44050
C2BMF44080
C2BMF44110
C2BMF30500
C2BMF30500
C2BMF30500
C2BMF30500
C2BCN44980
C2BCN32510
C2BCN32710
C2BCN45000
C2BCN32530
C2BMF29870
C2BMF29890
C2BMF44890
C2BMF29910
C2BMF29050
C2BMF43210
C2BMF43270
Predecessor
[WNS05] [Lime Bldg] Install Roofing
[WNS00 | WNS02] Install Pipe Racks
[WNS03 | L2] Installation of RIO & UPSDB Panels
[WNS04] Installation of 2 Sodium Hypochlorite FRP Storage Tank
[WNS04] Installation of Sodium Hypochlorite Dosing System (Valves, Pumps, Instruments)
[WNS05] Installation of Transformer
[WNS04] Installation of 2 Ammonium Sulphate Storage Tank
[WNS04] Installation of 6 Sodium Hydroxide FRP Storage Tank
[WNS04] Installation of Ammonium Sulphate Dosing System (Valves, Pumps, Instruments)
[WNS04] Installation of Sodium Hydroxide Dosing System (Valves, Pumps, Instruments)
[WNS03 | L2] Installation of RIO & UPSDB Panels
[WNS02] [Tank 2 | GL2/A] Install Bored Piles (35 nos.)
[WNS02] [Tank 1 | GL1/A] Install Bored Piles (35 nos.)
[WNS03 | L1] Installation of Pumps
[WNS03 | L1] Installation of EOT Cranes
[WNS03 | L4] Cable Raceway Installation (Electrical)
[WNS05] Installation of Lime Silos
[WNS05] Installation of Lime Silos
[WNS05] Installation of Lime Saturator
[WNS05] Installation of RIO & UPSDB Panels
[WNS00] Installation of Pipes and Valves
[WNS04] Installation of RIO & UPSDB Panels
[WNS00 | WNS01] Install Pipe Racks
[WNS05] Installation of Lime Saturator
[WNS01] [TP03] Ultimate Load Test Pile Installation
[WNS01] [TP06] Ultimate Load Test Pile Installation
[WNS01] [TP02] Ultimate Load Test Pile Installation
[WNS01] [TP05] Ultimate Load Test Pile Installation
[WNS01] [TP01] Ultimate Load Test Pile Installation
[WNS01] [TP04] Ultimate Load Test Pile Installation
[WNS01] Piling Mobilisation for ULT
[WNS01] Piling Mobilisation
[WNS01] [Tank 1 | GL1/A] Install Bored Piles (36 nos.)
[WNS01] [Tank 2 | GL1/B] Install Bored Piles (36 nos.)
[WNS01] [Tank 1 | GL1/A] Excavate to FEL
[WNS01] [Tank 2 | GL1/B] Excavate to FEL
[WNS01] [Tank GL 1/A] Working Load Test / PDA / PIT
[WNS01] [Tank GL 1/B] Working Load Test / PDA / PIT
[WNS01] Prepare tender documents for Shortlisted Suppliers for NEWater Tanks
[WNS01] List of Tenderers & Tender Packages for Active Tank Mixers for NEWater Tanks
[WNS01] List of Tenderers & Tender package for Embeds & Underground Pipes
[WNS01] List of Tenderers & Tender Packages for Electrical Manhole and Duct Bank Works
[WNS01] List of Tenderers & Tender Packages for Lightning and Earthing Protection
[WNS01] List of Tenderers & Tender Packages for DB, Cable & Cable Raceway Works (Electrical)
[WNS01] List of Tenderers & Tender Packages for Lighting Works
[WNS01] List of Tenderers & Tender Packages for ICA Works
[WNS01] Earth Filling & Site Levelling
[WNS02] [TP07] Ultimate Load Test Pile Installation
[WNS02] [TP08] Ultimate Load Test Pile Installation
[WNS02] Piling Mobilisation for ULT
[WNS02] Piling Mobilisation
[WNS02] [Tank 2 | GL2/A] Install Bored Piles (35 nos.)
[WNS02] [Tank 1 | GL1/A] Install Bored Piles (35 nos.)
[WNS02] [Tank GL 1/A] Working Load Test / PDA / PIT
[WNS02] [Tank GL 2/A] Working Load Test / PDA / PIT
[WNS02] [Tank 1 | GL1/A] Excavate to FEL
[WNS02] [Tank 2 | GL2/A] Excavate to FEL
[WNS02] Prepare tender documents for Shortlisted Suppliers for Industrial Water Storage Tanks
[WNS02] List of Tenderers & Tender Packages for Pipes & Valves
[WNS02] List of Tenderers & Tender Packages for DB, Cable & Cable Raceway Works (Electrical)
[WNS02] List of Tenderers & Tender Packages for Lightning and Earthing Protection
[WNS02] List of Tenderers & Tender Packages for Lighting Works
[WNS02] List of Tenderers & Tender Packages for ICA Works
[WNS02] Earth Filling & Site Levelling
[WNS03] Earth Cutting & Site Levelling
[WNS03] Piling Mobilisation for ULT
[WNS03] [TP10] Ultimate Load Test Pile Installation
[WNS03] [TP11] Ultimate Load Test Pile Installation
[WNS03] Piling Mobilisation
[WNS03] [GLA to GLD / GL1 to GL8] Install Bored Piles (57 nos.)
[WNS03] [GLA to GLD / GL8 to GL14] Install Bored Piles (43 nos.)
[WNS03] [Tank GLA to GLD] Working Load Test / PDA / PIT
[WNS03] [Tank GLD to GLG] Working Load Test / PDA / PIT
[WNS03] [GLD to GLG / GL1 to GL7] Install Bored Piles (30 nos.)
[WNS03] [GLD to GLG / GL7 to GL13] Install Bored Piles (37 nos.)
[WNS03] [GLA to GLD / GL1 to GL8] Install Temporary ERSS
[WNS03] [GLA to GLD / GL8 to GL14] Install Temporary ERSS
[WNS03] [GLA to GLD / GL1 to GL8] Construct Ground Beams & Slabs at SFL 5.30
[WNS03] [GLA to GLD / GL8 to GL14] Construct Ground Beams & Slabs at SFL 5.30
[WNS03] [GLD to GLG / GL1 to GL7] Excavate to FEL
[WNS03] [GLD to GLG / GL7 to GL13] Excavate to FEL
[WNS03 | Pump Station] Install Internal Walls to SFL 5.30
[WNS03 | Electrical Building] Install Internal Walls to SFL 5.30
[WNS03 | L1] List of Tenderers & Tender Packages for EOT Cranes
[WNS03 | L1] List of Tenderers & Tender Packages for NEWater, IW & Sump Pumps
[WNS03 | L1] List of Tenderers & Tender Packages for Surge Vessels
[WNS03 | L1] List of Tenderers & Tender Packages for Transformer
[WNS03 | L1] List of Tenderers & Tender Packages for Pipes & Valves
[WNS03 | L1] List of Tenderers & Tender Packages for Automatic Lubrication System
[WNS03 | L1] List of Tenderers & Tender Packages for EOT Crane Temporary Power Supply Works
[WNS03 | L1] List of Tenderers & Tender Packages for Instruments
[WNS03 | L2] List of Tenderers & Tender Packages for Switchgear, MCC & MDB
[WNS03 | ROOF] List of Tenderers & Tender Packages for ACMV System
[WNS03 | ROOF] List of Tenderers & Tender Packages for Fire Protection System
[WNS03 | ROOF] List of Tenderers & Tender Packages for Plumbing and Sanitary System
[WNS03 | ROOF] List of Tenderers & Tender Packages for ELV System
[WNS04] Earth Cutting & Site Levelling
[WNS04] Piling Mobilisation for ULT
[WNS04] [TP09] Ultimate Load Test Pile Installation
[WNS04] Piling Mobilisation
[WNS04] [Sodium Hydr Bldg] Install Bored Piles (15 nos.)
[WNS04] [Amm & Elec Bldg] Install Bored Piles (19 nos.)
[WNS04] [Sodium Hydr Bldg] Construct Ground Beams & Slabs at SFL 5.30
[WNS04] [Sodium Hydr Bldg] Install External Walls
[WNS04] [Amm & Elec Bldg] Construct Ground Beams & Slabs at SFL 5.30
[WNS04] [Amm Bldg] Install External Walls
[WNS04] List of Tenderers & Tender Packages for FRP Storage Tank (Sodium Hypochlorite)
[WNS04] List of Tenderers & Tender Packages for Chemical Dosing System (Sodium Hypochlorite)
[WNS04] List of Tenderers & Tender Packages for FRP Storage Tank (Ammonium Sulphate)
[WNS04] List of Tenderers & Tender Packages for Chemical Dosing System (Ammonium Sulphate)
[WNS04] List of Tenderers & Tender Packages for FRP Storage Tank (Sodium Hydroxide)
[WNS04] List of Tenderers & Tender Packages for Chemical Dosing System (Sodium Hydroxide)
[WNS04] List of Tenderers & Tender Packages for MCC & DB
[WNS04] List of Tenderers & Tender Packages for Cable & Cable Raceway Works (Electrical)
[WNS04] List of Tenderers & Tender Packages for Lightning and Earthing Protection Works
[WNS04] List of Tenderers & Tender Packages for Lighting Works
[WNS04] List of Tenderers & Tender Packages for RIO & UPSDB Panels
[WNS04] List of Tenderers & Tender Packages for Instruments
[WNS04] List of Tenderers & Tender Packages for Cable & Cable Raceway Works (ICA)
[WNS04] List of Tenderers & Tender Packages for Building Services
[WNS04] List of Tenderers & Tender Packages for Building Services
[WNS04] List of Tenderers & Tender Packages for Building Services
[WNS04] List of Tenderers & Tender Packages for Building Services
[WNS05] Earth Cutting & Site Levelling
[WNS05] Piling Mobilisation for ULT
[WNS05] [TP12] Ultimate Load Test Pile Installation
[WNS05] Piling Mobilisation
[WNS05] [Sprinkler Tank] Install Bored Piles (8 nos.)
[WNS05] [Lime Bldg | GLA to GLC / GL1 to GL4] Install Bored Piles (36 nos.)
[WNS05] [Sprinkler Tank | Lime Tank | Elec Bldg] Working Load Test / PDA / PIT
[WNS05] [Lime Bldg] Working Load Test / PDA / PIT
[WNS05] [Sprinkler Tank] Construct Ground Beams & Slabs at SFL 5.30
[WNS05] [Elec Bldg] Construct Ground Beams & Slabs at SFL 5.30
[WNS05] [Lime Tank] Construct Ground Beams & Slabs at SFL 5.30
[WNS05] [Lime Bldg] Construct Ground Beams & Slabs at SFL 5.30
[WNS05] [Lime Silo] Construct Ground Beams & Slabs at SFL 5.30
[WNS05] [Lime Bldg] Install External Walls
[WNS05] [Elec Bldg] Install External Walls to SFL 13.850
[WNS05] List of Tenderers & Tender Packages for Lime Silos
[WNS05] List of Tenderers & Tender Packages for Lime Saturators
[WNS05] List of Tenderers & Tender Packages for Lime Slurry, Saturated Lime & Lime Sludge Holding Tanks
[WNS05] List of Tenderers & Tender Packages for Lime Slurry Transfer, Lime Sludge Transfer and Lime Dosing Pumps
[WNS05] List of Tenderers & Tender Packages for Air Compressor Package
[WNS05] List of Tenderers & Tender Packages for Lime Dosing Piping Works & Valves
[WNS05] List of Tenderers & Tender Packages for Transformer
[WNS05] List of Tenderers & Tender Packages for Cable & Cable Raceway Works (Electrical)
[WNS05] List of Tenderers & Tender Packages for Lightning and Earthing Protection
[WNS05] List of Tenderers & Tender Packages for Lighting Works
[WNS05] List of Tenderers & Tender Packages for RIO & UPSDB Panels
[WNS05] List of Tenderers & Tender Packages for Instruments
[WNS05] List of Tenderers & Tender Packages for Cable & Cable Raceway Works (ICA)
[WNS05] List of Tenderers & Tender Packages for Building Services
[WNS05] List of Tenderers & Tender Packages for Building Services
[WNS05] List of Tenderers & Tender Packages for Building Services
[WNS05] List of Tenderers & Tender Packages for Building Services
[WNS00 | WNS01] Piling Mobilisation
[WNS00 | WNS01] Install Bored Piles (26 nos.)
[WNS00 | WNS02] Install Bored Piles (14 nos.)
[WNS00 | WNS02] Piling Mobilisation
[WNS00 | WNS01] Install Pipe Racks
[WNS00] List of Tenderers & Tender Packages for Pipes & Valves
[WNS00] List of Tenderers & Tender Packages for Cable & Cable Raceway Works (Electrical)
[WNS00] List of Tenderers & Tender Packages for Bonding & Earthing Works
[WNS00] List of Tenderers & Tender Packages for Cable & Cable Raceway Works (ICA)
[WNS03 | L2] List of Tenderers & Tender Packages for Telemetry System
[WNS03 | L4] List of Tenderers & Tender Packages for Switchgear, MCC & MDB
[WNS03 | L4] List of Tenderers & Tender Packages for High Voltage & Low Voltage VFD
Pred Type Successor Id
Normal C2BCN31510
Normal C2BCN32910
Normal C2BIN23410
Normal C2BIN24810
Normal C2BIN24910
Normal C2BIN26510
Normal C2BIN27570
Normal C2BIN27590
Normal C2BIN27600
Normal C2BIN27620
Normal C2BIN23420
Normal C2BIN21510
Normal C2BIN21510
Normal C2BIN27850
Normal C2BIN27730
Normal C2BIN24120
Normal C2BIN26010
Normal C2BIN26110
Normal C2BIN26210
Normal C2BIN27010
Normal C2BTC10950
Normal C2BIN25510
Normal C2BCN32910
Normal C2BIN26310
Normal C2BSM10190
Normal C2BSM10200
Normal C2BSM10230
Normal C2BSM10240
Normal C2BSM10250
Normal C2BSM10260
Normal C2BSM10170
Normal C2BSM10320
Normal C2BSM10330
Normal C2BSM10340
Normal C2BSM10420
Normal C2BSM10420
Normal C2BSM10370
Normal C2BSM10370
Normal C2BSM10080
Normal C2BSM10280
Normal C2BSM10090
Normal C2BSM10130
Normal C2BSM10120
Normal C2BSM10160
Normal C2BSM10290
Normal C2BSM10360
Normal C2BSM10140
Normal C2BSM10500
Normal C2BSM10510
Normal C2BSM10490
Normal C2BSM10530
Normal C2BSM10540
Normal C2BSM10540
Normal C2BSM10550
Normal C2BSM10550
Normal C2BSM10560
Normal C2BSM10560
Normal C2BSM10100
Normal C2BSM10350
Normal C2BSM10410
Normal C2BSM10110
Normal C2BSM10300
Normal C2BSM10450
Normal C2BSM10480
Normal C2BSM10150
Normal C2BSM10180
Normal C2BSM10210
Normal C2BSM10220
Normal C2BSM10270
Normal C2BSM10310
Normal C2BSM10310
Normal C2BSM10390
Normal C2BSM10430
Normal C2BSM10380
Normal C2BSM10380
Normal C2BSM10400
Normal C2BSM10400
Normal C2BSM10460
Normal C2BSM10460
Normal C2BSM10440
Normal C2BSM10440
Normal C2BSM10520
Normal C2BSM10470
Normal C2BSM10000
Normal C2BSM10020
Normal C2BSM10010
Normal C2BSM10030
Normal C2BSM10570
Normal C2BSM10580
Normal C2BSM10050
Normal C2BSM10070
Normal C2BSM10590
Normal C2BSM10600
Normal C2BSM10610
Normal C2BSM10620
Normal C2BSM10630
Normal C2BSM10770
Normal C2BSM10660
Normal C2BSM10640
Normal C2BSM10670
Normal C2BSM10680
Normal C2BSM10780
Normal C2BSM10810
Normal C2BSM10830
Normal C2BSM10800
Normal C2BSM10820
Normal C2BSM10710
Normal C2BSM10720
Normal C2BSM10910
Normal C2BSM10920
Normal C2BSM10930
Normal C2BSM10940
Normal C2BSM10740
Normal C2BSM10750
Normal C2BSM10860
Normal C2BSM10950
Normal C2BSM10760
Normal C2BSM10960
Normal C2BSM10970
Normal C2BSM10870
Normal C2BSM10880
Normal C2BSM10890
Normal C2BSM10900
Normal C2BSM11080
Normal C2BSM10990
Normal C2BSM10980
Normal C2BSM11000
Normal C2BSM11010
Normal C2BSM11090
Normal C2BSM11020
Normal C2BSM11100
Normal C2BSM11120
Normal C2BSM11110
Normal C2BSM11140
Normal C2BSM11270
Normal C2BSM11280
Normal C2BSM11130
Normal C2BSM11290
Normal C2BSM11030
Normal C2BSM11040
Normal C2BSM11200
Normal C2BSM11210
Normal C2BSM11220
Normal C2BSM11230
Normal C2BSM11050
Normal C2BSM11300
Normal C2BSM11150
Normal C2BSM11240
Normal C2BSM11070
Normal C2BSM11250
Normal C2BSM11260
Normal C2BSM11160
Normal C2BSM11170
Normal C2BSM11180
Normal C2BSM11190
Normal C2BSM11330
Normal C2BSM11340
Normal C2BSM11420
Normal C2BSM11640
Normal C2BSM11430
Normal C2BSM11360
Normal C2BSM11630
Normal C2BSM11570
Normal C2BSM11590
Normal C2BSM11650
Normal C2BSM10590
Normal C2BSM11660
Successor
[WNS05] [Lime Bldg] Install External Walls
[WNS00 | C1A] Coordinated Access with C1A
[WNS03 | L2] Installation of Telemetry System to WNS JISR
[WNS04] Installation of Sodium Hypochlorite Dosing System (Valves, Pumps, Instruments)
[WNS04] Installation of Sodium Hypochlorite Dosing Pipes and Valves
[WNS05] Installation of MCC & DB
[WNS04] Installation of Ammonium Sulphate Dosing System (Valves, Pumps, Instruments)
[WNS04] Installation of Sodium Hydroxide Dosing System (Valves, Pumps, Instruments)
[WNS04] Installation of Ammonium Sulphate Dosing Pipes and Valves
[WNS04] Installation of Sodium Hydroxide Dosing Pipes and Valves
[WNS03 | L2] Installation of Telemetry System to WNS CME
[WNS02] Installation of Lightning and Earthing Protection Equipment (for IW Tank No. 1 & 2)
[WNS02] Installation of Lightning and Earthing Protection Equipment (for IW Tank No. 1 & 2)
[WNS03 | L1] Installation of Automatic Lubrication System
[WNS03 | L1] Installation of Temporary Power Supply
[WNS03 | L4] Installation of Lightning and Earthing Protection Equipment (For Electrical Building)
[WNS05] Installation of Lime Slurry, Saturated Lime and Lime Sludge Holding Tanks
[WNS05] Installation of Lime Slurry Transfer, Lime Sludge Transfer and Lime Dosing Pumps
[WNS05] Installation of Air Compressor Package
[WNS05] Installation of Instruments
[WNS00] Hydrostatic Test of Pipes
[WNS04] Installation of Instruments
[WNS00 | C1A] Coordinated Access with C1A
[WNS05] Installation of Lime Dosing Piping Works & Valves
[WNS01] Install, Testing & Report - TP03
[WNS01] Install, Testing & Report - TP06
[WNS01] Install, Testing & Report - TP02
[WNS01] Install, Testing & Report - TP05
[WNS01] Install, Testing & Report - TP01
[WNS01] Install, Testing & Report - TP04
[WNS01] Mobilisation for ULT
[WNS01] Piling Mobilisation
[WNS01] Piling at GL 1/A, 2/A & 3/A
[WNS01] Piling at GL 1/B, 2/B & 3/B
[WNS01] Ground Level Works
[WNS01] Ground Level Works
[WNS01] Working Load Test, PDA & PIT
[WNS01] Working Load Test, PDA & PIT
[WNS01] NEWater Storage Tanks, Anciliaries and Hydrostatic Testing
[WNS01] Active Tank Mixers
[WNS01] Piping & Hydrostatic Test
[WNS01] Electrical Manhole & Ductbank Works (Underground)
[WNS01] Lightning & Earthing Protection
[WNS01] DB, Cable & Cable Raceway Works
[WNS01] Lighting Works
[WNS01] ICA Works
[WNS01] Site Enabling Works
[WNS02] Install, Testing & Report - TP07
[WNS02] Install, Testing & Report - TP08
[WNS02] Mobilisation for ULT
[WNS02] Piling Mobilisation
[WNS02] Piling at GL 1/A, 2/A
[WNS02] Piling at GL 1/A, 2/A
[WNS02] Working Load Test, PDA & PIT
[WNS02] Working Load Test, PDA & PIT
[WNS02] Ground Level Works
[WNS02] Ground Level Works
[WNS02] Industrial Water Storage Tanks, Anciliaries and Hydrostatic Testing
[WNS02] Piping & Hydrostatic Test
[WNS02] DB, Cable & Cable Raceway Works
[WNS02] Lightning & Earthing Protection
[WNS02] Lighting Works
[WNS02] ICA Works
[WNS02] Site Enabling Works
[WNS03] Site Enabling Works
[WNS03] Mobilisation for ULT
[WNS03] Install, Testing & Report - TP10
[WNS03] Install, Testing & Report - TP11
[WNS03] Piling Mobilisation
[WNS03] Piling at GL A to D (Pump Station)
[WNS03] Piling at GL A to D (Pump Station)
[WNS03] Working Load Test, PDA & PIT (Pump Station)
[WNS03] Working Load Test, PDA & PIT (Electrical Building)
[WNS03] Piling at GL D to G (Electrical Building)
[WNS03] Piling at GL D to G (Electrical Building)
[WNS03] ERSS and Basement Works (Pump Station)
[WNS03] ERSS and Basement Works (Pump Station)
[WNS03] Ground Level & Superstructure Works (Pump Station)
[WNS03] Ground Level & Superstructure Works (Pump Station)
[WNS03] Ground Level & Superstructure Works (Electrical Building)
[WNS03] Ground Level & Superstructure Works (Electrical Building)
[WNS03] Partition Wall & Architectural Works (Pump Station)
[WNS03] Partition Wall & Architectural Works (Electrical Building)
[WNS03] EOT Cranes
[WNS03] NEWater, IW & Sump Pumps
[WNS03] Surge Vessels
[WNS03] Transformer
[WNS03] Piping Works
[WNS03] Automatic Lubrication System
[WNS03] EOT Crane Temporary Power Supply
[WNS03] Instruments
[WNS03] Switchgear, MCC & MDB
[WNS03] ACMV System
[WNS03] Fire Protection System
[WNS03] Plumbing & Sanitary System
[WNS03] ELV System
[WNS04] Site Enabling Works
[WNS04] Mobilisation for ULT
[WNS04] Install, Testing & Report - TP09
[WNS04] Piling Mobilisation
[WNS04] Piling at Sodium Hydroxide Building
[WNS04] Piling at Ammonium Sulphate & Electrical Building
[WNS04] Ground Level & Superstructure Works (Sodium Hydroxide Building)
[WNS04] Partition Wall & Architectural Works (Sodium Hydroxide Building)
[WNS04] Ground Level & Superstructure Works (Ammonium Sulphate & Electrical Building)
[WNS04] Partition Wall & Architectural Works (Ammonium Sulphate & Electrical Building)
[WNS04] Sodium Hypochlorite FRP Storage Tank
[WNS04] Chemical Dosing System (Sodium Hypochlorite)
[WNS04] Ammonium Sulphate FRP Storage Tank
[WNS04] Chemical Dosing System (Ammonium Sulphate)
[WNS04] Sodium Hydroxide FRP Storage Tank
[WNS04] Chemical Dosing System (Sodium Hydroxide)
[WNS04] MCC & DB
[WNS04] Cable & Cable Raceway Works (Electrical)
[WNS04] Lightning & Earthing Protection
[WNS04] Lighting Works
[WNS04] RIO & UPSDB Panels
[WNS04] Instruments
[WNS04] Cable & Cable Raceway Works (ICA)
[WNS04] ACMV System
[WNS04] Fire Protection System
[WNS04] Plumbing & Sanitary System
[WNS04] ELV System
[WNS05] Site Enabling Works
[WNS05] Mobilisation for ULT
[WNS05] Install, Testing & Report - TP12
[WNS05] Piling Mobilisation
[WNS05] Piling at Sprinkler Tank, Lime Tank, Electrical Building & Lime Silo
[WNS05] Piling at Lime Building
[WNS05] Working Load Test, PDA & PIT (Sprinkler Tank, Lime Tank, Electrical Building & Lime Silo)
[WNS05] Working Load Test, PDA & PIT (Lime Building)
[WNS05] Ground Level Works (Sprinkler Tank)
[WNS05] Ground Level & Superstructure Works (Electrical Building)
[WNS05] Ground Level Works (Lime Tank)
[WNS05] Ground Level & Superstructure Works (Lime Building)
[WNS05] Ground Level Works (Lime Silo)
[WNS05] Partition Wall & Architectural Works (Lime Building)
[WNS05] Partition Wall & Architectural Works (Electrical Building)
[WNS05] Lime Silos
[WNS05] Lime Saturator
[WNS05] Lime Slurry, Saturated Lime & Lime Sludge Holding Tanks
[WNS05] Lime Slurry Transfer, Lime Sludge Transfer & Lime Dosing Pumps
[WNS05] Air Compressor Package
[WNS05] Piping & Valves
[WNS05] Transformer
[WNS05] Cable and Cable Raceway (Electrical)
[WNS05] Lightning & Earthing Protection
[WNS05] Lighting Works
[WNS05] RIO & UPSDB Panels
[WNS05] Instruments
[WNS05] Cable & Cable Raceway Works (ICA)
[WNS05] ACMV System
[WNS05] Fire Protection System
[WNS05] Plumbing & Sanitary System
[WNS05] ELV System
[WNS00 | WNS01] Piling Mobilisation
[WNS00 | WNS01] Piling & Foundation
[WNS00 | WNS02] Piling & Foundation
[WNS00 | WNS02] Piling Mobilisation
[WNS00] Install Pipe Rack
[WNS00] Piping & Valves
[WNS00] Cable and Cable Raceway (Electrical)
[WNS00] Bonding & Earthing Works
[WNS00] Cable & Cable Raceway Works (ICA)
[WNS03] Telemetry System
[WNS03] Switchgear, MCC & MDB
[WNS03] High Voltage & Low Voltage VFD
Succ Type Total Finish Float Lag Type Jacob's Remarks
Normal 162 0 StartToStart
LevelOfEffort 226 0 StartToStart
Normal 154 0 StartToStart
Normal 128 0 StartToStart
Normal 128 0 StartToStart
Normal 53 0 StartToStart
Normal 99 0 StartToStart
Normal 107 0 StartToStart
Normal 99 0 StartToStart
Normal 107 0 StartToStart
Normal 154 0 StartToStart
Normal 259 0 StartToStart
Normal 259 0 StartToStart
Normal 92 0 StartToStart
Normal 92 0 StartToStart
Normal 14 0 StartToStart
Normal 170 0 StartToStart
Normal 171 0 StartToStart
Normal 70 0 StartToStart
Normal 56 0 StartToStart
Normal 148 0 StartToStart
Normal 43 0 StartToStart
LevelOfEffort 226 0 StartToStart
Normal 7 0 StartToStart
LevelOfEffort 283 0 StartToStart
LevelOfEffort 283 0 StartToStart
LevelOfEffort 186 0 StartToStart
LevelOfEffort 186 0 StartToStart
LevelOfEffort 79 0 StartToStart
LevelOfEffort 79 0 StartToStart
LevelOfEffort 79 0 StartToStart
LevelOfEffort 79 0 StartToStart
LevelOfEffort 79 0 StartToStart
LevelOfEffort 79 0 StartToStart
LevelOfEffort 207 0 StartToStart
LevelOfEffort 207 0 StartToStart
LevelOfEffort 239 0 StartToStart
LevelOfEffort 239 0 StartToStart
LevelOfEffort 228 0 StartToStart
LevelOfEffort 305 0 StartToStart
LevelOfEffort 186 0 StartToStart
LevelOfEffort 258 0 StartToStart
LevelOfEffort 351 0 StartToStart
LevelOfEffort 175 0 StartToStart
LevelOfEffort 146 0 StartToStart
LevelOfEffort 145 0 StartToStart
LevelOfEffort 79 0 StartToStart
LevelOfEffort 5 0 StartToStart
LevelOfEffort 5 0 StartToStart
LevelOfEffort 5 0 StartToStart
LevelOfEffort 5 0 StartToStart
LevelOfEffort 5 0 StartToStart
LevelOfEffort 5 0 StartToStart
LevelOfEffort 5 0 StartToStart
LevelOfEffort 5 0 StartToStart
LevelOfEffort 5 0 StartToStart
LevelOfEffort 5 0 StartToStart
LevelOfEffort 54 0 StartToStart
LevelOfEffort 5 0 StartToStart
LevelOfEffort 28 0 StartToStart
LevelOfEffort 259 0 StartToStart
LevelOfEffort 7 0 StartToStart
LevelOfEffort 27 0 StartToStart
LevelOfEffort 5 0 StartToStart
LevelOfEffort 2 0 StartToStart
LevelOfEffort 2 0 StartToStart
LevelOfEffort 32 0 StartToStart
LevelOfEffort 32 0 StartToStart
LevelOfEffort 14 0 StartToStart
LevelOfEffort 15 0 StartToStart
LevelOfEffort 15 0 StartToStart
LevelOfEffort 15 0 StartToStart
LevelOfEffort 2 0 StartToStart
LevelOfEffort 2 0 StartToStart
LevelOfEffort 2 0 StartToStart
LevelOfEffort 15 0 StartToStart
LevelOfEffort 15 0 StartToStart
LevelOfEffort 55 0 StartToStart
LevelOfEffort 55 0 StartToStart
LevelOfEffort 257 0 StartToStart
LevelOfEffort 257 0 StartToStart
LevelOfEffort 291 0 StartToStart
LevelOfEffort 211 0 StartToStart
LevelOfEffort 92 0 StartToStart
LevelOfEffort 92 0 StartToStart
LevelOfEffort 120 0 StartToStart
LevelOfEffort 170 0 StartToStart
LevelOfEffort 105 0 StartToStart
LevelOfEffort 92 0 StartToStart
LevelOfEffort 92 0 StartToStart
LevelOfEffort 176 0 StartToStart
LevelOfEffort 4 0 StartToStart
LevelOfEffort 2 0 StartToStart
LevelOfEffort 2 0 StartToStart
LevelOfEffort 2 0 StartToStart
LevelOfEffort 2 0 StartToStart
LevelOfEffort 31 0 StartToStart
LevelOfEffort 31 0 StartToStart
LevelOfEffort 61 0 StartToStart
LevelOfEffort 31 0 StartToStart
LevelOfEffort 32 0 StartToStart
LevelOfEffort 31 0 StartToStart
LevelOfEffort 32 0 StartToStart
LevelOfEffort 32 0 StartToStart
LevelOfEffort 265 0 StartToStart
LevelOfEffort 281 0 StartToStart
LevelOfEffort 107 0 StartToStart
LevelOfEffort 128 0 StartToStart
LevelOfEffort 99 0 StartToStart
LevelOfEffort 99 0 StartToStart
LevelOfEffort 107 0 StartToStart
LevelOfEffort 107 0 StartToStart
LevelOfEffort 52 0 StartToStart
LevelOfEffort 51 0 StartToStart
LevelOfEffort 51 0 StartToStart
LevelOfEffort 31 0 StartToStart
LevelOfEffort 43 0 StartToStart
LevelOfEffort 43 0 StartToStart
LevelOfEffort 32 0 StartToStart
LevelOfEffort 57 0 StartToStart
LevelOfEffort 57 0 StartToStart
LevelOfEffort 57 0 StartToStart
LevelOfEffort 57 0 StartToStart
LevelOfEffort 14 0 StartToStart
LevelOfEffort 14 0 StartToStart
LevelOfEffort 44 0 StartToStart
LevelOfEffort 52 0 StartToStart
LevelOfEffort 52 0 StartToStart
LevelOfEffort 7 0 StartToStart
LevelOfEffort 52 0 StartToStart
LevelOfEffort 7 0 StartToStart
LevelOfEffort 339 0 StartToStart
LevelOfEffort 179 0 StartToStart
LevelOfEffort 170 0 StartToStart
LevelOfEffort 162 0 StartToStart
LevelOfEffort 171 0 StartToStart
LevelOfEffort 162 0 StartToStart
LevelOfEffort 179 0 StartToStart
LevelOfEffort 171 0 StartToStart
LevelOfEffort 7 0 StartToStart
LevelOfEffort 170 0 StartToStart
LevelOfEffort 171 0 StartToStart
LevelOfEffort 70 0 StartToStart
LevelOfEffort 7 0 StartToStart
LevelOfEffort 53 0 StartToStart
LevelOfEffort 52 0 StartToStart
LevelOfEffort 52 0 StartToStart
LevelOfEffort 52 0 StartToStart
LevelOfEffort 56 0 StartToStart
LevelOfEffort 56 0 StartToStart
LevelOfEffort 21 0 StartToStart
LevelOfEffort 66 0 StartToStart
LevelOfEffort 66 0 StartToStart
LevelOfEffort 66 0 StartToStart
LevelOfEffort 66 0 StartToStart
LevelOfEffort 59 0 StartToStart
LevelOfEffort 59 0 StartToStart
LevelOfEffort 62 0 StartToStart
LevelOfEffort 62 0 StartToStart
LevelOfEffort 226 0 StartToStart
LevelOfEffort 148 0 StartToStart
LevelOfEffort 87 0 StartToStart
LevelOfEffort 59 0 StartToStart
LevelOfEffort 148 0 StartToStart
LevelOfEffort 154 0 StartToStart
LevelOfEffort 4 0 StartToStart
LevelOfEffort 4 0 StartToStart
Contractor's Response for using FF Relationship
Predecessor Id
C2BDS25220
C2BDS25320
C2BDS25420
C2BDS25520
C2BDS25620
C2BCN11420
C2BCN11430
C2BCN11530
C2BCN11520
C2BCN11720
C2BCN11730
C2BCN11830
C2BCN11820
C2BCN30860
C2BCN32910
C2BIN27310
C2BCN23220
C2BCN23320
C2BIN26910
C2BCN32730
C2BGN23590
C2BIN21810
C2BIN23210
C2BIN23210
C2BIN24010
C2BIN24810
C2BIN27570
C2BIN27590
C2BIN24710
C2BIN27560
C2BIN27580
C2BIN25410
C2BIN25810
C2BIN25810
C2BIN25910
C2BIN26410
C2BCN16410
C2BCN16420
C2BIN21910
C2BIN25910
C2BIN22510
C2BIN22510
C2BIN22520
C2BIN22520
C2BIN28350
C2BIN28350
C2BIN28350
C2BIN28410
C2BIN28410
C2BIN28410
C2BIN28410
C2BSM10190
C2BSM10200
C2BSM10230
C2BSM10240
C2BSM10250
C2BSM10260
C2BSM10170
C2BSM10330
C2BSM10340
C2BSM10420
C2BSM10420
C2BSM10370
C2BSM10370
C2BSM10280
C2BSM10130
C2BSM10120
C2BSM10160
C2BSM10160
C2BSM10290
C2BSM10360
C2BSM10360
C2BSM10140
C2BSM10480
C2BSM10500
C2BSM10510
C2BSM10510
C2BSM10490
C2BSM10490
C2BSM10560
C2BSM10560
C2BSM10410
C2BSM10110
C2BSM10300
C2BSM10300
C2BSM10450
C2BSM10450
C2BSM10150
C2BSM10180
C2BSM10210
C2BSM10220
C2BCN45300
C2BSM10410
C2BSM10400
C2BSM10400
C2BSM10460
C2BSM10460
C2BSM10440
C2BSM10440
C2BSM10470
C2BSM10520
C2BSM10000
C2BSM10020
C2BSM10010
C2BSM10580
C2BSM10030
C2BSM10050
C2BSM10070
C2BSM10590
C2BSM10600
C2BSM10610
C2BSM10620
C2BSM10630
C2BSM10770
C2BSM10660
C2BSM10640
C2BSM10810
C2BSM10830
C2BSM10800
C2BSM10820
C2BSM10710
C2BSM10720
C2BSM10910
C2BSM10920
C2BSM10930
C2BSM10940
C2BSM10740
C2BSM10750
C2BSM10860
C2BSM10860
C2BSM10950
C2BSM10950
C2BSM10950
C2BSM10760
C2BSM10960
C2BSM10970
C2BSM10870
C2BSM10880
C2BSM10890
C2BSM10900
C2BSM11080
C2BSM10990
C2BSM10980
C2BSM11010
C2BSM11090
C2BSM11120
C2BSM11110
C2BSM11290
C2BSM11140
C2BSM11270
C2BSM11130
C2BSM11280
C2BSM11030
C2BSM11040
C2BSM11200
C2BSM11210
C2BSM11220
C2BSM11230
C2BSM11050
C2BSM11060
C2BSM11300
C2BSM11150
C2BSM11150
C2BSM11240
C2BSM11240
C2BSM11070
C2BSM11250
C2BSM11260
C2BSM11160
C2BSM11170
C2BSM11180
C2BSM11190
C2BSM11340
C2BSM11420
C2BSM11430
C2BSM11360
C2BSM11630
C2BSM11570
C2BSM11590
C2BSM11650
C2BSM11650
C2BSM10590
C2BSM11660
C2BSM10080
C2BSM10090
C2BSM10100
C2BSM10350
C2BCN12130
C2BCN12330
C2BSM10570
C2BGN21160
C2BTC11190
C2BIN26410
C2BIN26510
C2BIN27830
C2BIN27820
C2BIN27920
C2BIN27910
C2BIN28410
C2BIN27700
C2BIN27690
C2BIN28190
C2BIN28160
C2BIN28330
C2BIN23620
C2BIN24410
C2BIN24120
C2BIN23120
C2BIN27710
C2BIN27720
C2BIN27750
C2BIN27770
C2BIN27870
C2BIN27860
C2BIN28530
C2BIN25010
C2BIN27790
C2BIN27800
C2BIN27810
C2BIN27890
C2BIN27900
C2BIN27880
C2BIN28350
C2BCN11440
C2BCN11740
C2BCN11540
C2BCN11840
C2BCN11640
C2BCN11940
C2BTC11000
Predecessor
[WNS01] Review, Resubmission & Acceptance : Operation & Maintenance Manuals
[WNS02] Review, Resubmission & Acceptance : Operation & Maintenance Manuals
[WNS03] Review, Resubmission & Acceptance : Operation & Maintenance Manuals
[WNS04] Review, Resubmission & Acceptance : Operation & Maintenance Manuals
[WNS05] Review, Resubmission & Acceptance : Operation & Maintenance Manuals
[WNS01] [Tank 1 | GL1/A] Construct Sump Pit
[WNS01] [Tank 1 | GL1/A] Construct Ground Slab
[WNS01] [Tank 3 | GL2/A] Construct Ground Slab
[WNS01] [Tank 3 | GL2/A] Construct Sump Pit
[WNS01] [Tank 2 | GL1/B] Construct Sump Pit
[WNS01] [Tank 2 | GL1/B] Construct Ground Slab
[WNS01] [Tank 4 | GL2/B] Construct Ground Slab
[WNS01] [Tank 4 | GL2/B] Construct Sump Pit
[WNS05] [Lime Bldg] Install Roofing
[WNS00 | C1A] Coordinated Access with C1A
[WNS00] Installation of Pipes and Valves
[WNS03] [GLA to GLD / GL1 to GL8] Install Roof Drainage System
[WNS03] [GLA to GLD / GL8 to GL14] Install Roof Drainage System
[WNS05] Installation of RIO & UPSDB Panels
[WNS00 | WNS02] Install Pipe Racks
Cube test (28 days)
[WNS03 | L1] Installation of EOT Cranes
[WNS03 | L2] Installation of RIO & UPSDB Panels
[WNS03 | L2] Installation of RIO & UPSDB Panels
[WNS03 | L4] Cable Raceway Installation (Electrical)
[WNS04] Installation of Sodium Hypochlorite Dosing System (Valves, Pumps, Instruments)
[WNS04] Installation of Ammonium Sulphate Dosing System (Valves, Pumps, Instruments)
[WNS04] Installation of Sodium Hydroxide Dosing System (Valves, Pumps, Instruments)
[WNS04] Installation of 2 Sodium Hypochlorite FRP Storage Tank
[WNS04] Installation of 2 Ammonium Sulphate Storage Tank
[WNS04] Installation of 6 Sodium Hydroxide FRP Storage Tank
[WNS04] Installation of RIO & UPSDB Panels
[WNS05] Installation of Lime Silos
[WNS05] Installation of Lime Silos
[WNS05] Installation of Lime Saturator
[WNS05] Installation of Transformer
[WNS02] [Tank 1 | GL1/A] Install Bored Piles (35 nos.)
[WNS02] [Tank 2 | GL2/A] Install Bored Piles (35 nos.)
[WNS03 | L1] Installation of Pumps
[WNS05] Installation of Lime Saturator
[WNS03 | L1] Installation of Lightning and Earthing Protection Equipment (Pump House) - Underground
[WNS03 | L1] Installation of Lightning and Earthing Protection Equipment (Pump House) - Underground
[WNS03 | L1] Installation of Lightning and Earthing Protection Equipment (Electrical Building) - Underground
[WNS03 | L1] Installation of Lightning and Earthing Protection Equipment (Electrical Building) - Underground
[WNS04] Cable Termination (Electrical)
[WNS04] Cable Termination (Electrical)
[WNS04] Cable Termination (Electrical)
[WNS05] Cable Termination (Electrical)
[WNS05] Cable Termination (Electrical)
[WNS05] Cable Termination (Electrical)
[WNS05] Cable Termination (Electrical)
[WNS01] Install, Testing & Report - TP03
[WNS01] Install, Testing & Report - TP06
[WNS01] Install, Testing & Report - TP02
[WNS01] Install, Testing & Report - TP05
[WNS01] Install, Testing & Report - TP01
[WNS01] Install, Testing & Report - TP04
[WNS01] Mobilisation for ULT
[WNS01] Piling at GL 1/A, 2/A & 3/A
[WNS01] Piling at GL 1/B, 2/B & 3/B
[WNS01] Ground Level Works
[WNS01] Ground Level Works
[WNS01] Working Load Test, PDA & PIT
[WNS01] Working Load Test, PDA & PIT
[WNS01] Active Tank Mixers
[WNS01] Electrical Manhole & Ductbank Works (Underground)
[WNS01] Lightning & Earthing Protection
[WNS01] DB, Cable & Cable Raceway Works
[WNS01] DB, Cable & Cable Raceway Works
[WNS01] Lighting Works
[WNS01] ICA Works
[WNS01] ICA Works
[WNS01] Site Enabling Works
[WNS02] Site Enabling Works
[WNS02] Install, Testing & Report - TP07
[WNS02] Install, Testing & Report - TP08
[WNS02] Install, Testing & Report - TP08
[WNS02] Mobilisation for ULT
[WNS02] Mobilisation for ULT
[WNS02] Ground Level Works
[WNS02] Ground Level Works
[WNS02] DB, Cable & Cable Raceway Works
[WNS02] Lightning & Earthing Protection
[WNS02] Lighting Works
[WNS02] Lighting Works
[WNS02] ICA Works
[WNS02] ICA Works
[WNS03] Site Enabling Works
[WNS03] Mobilisation for ULT
[WNS03] Install, Testing & Report - TP10
[WNS03] Install, Testing & Report - TP11
[WNS03] [UG Pipe Rack] Install Bored Piles (9 nos.)
[WNS02] DB, Cable & Cable Raceway Works
[WNS03] ERSS and Basement Works (Pump Station)
[WNS03] ERSS and Basement Works (Pump Station)
[WNS03] Ground Level & Superstructure Works (Pump Station)
[WNS03] Ground Level & Superstructure Works (Pump Station)
[WNS03] Ground Level & Superstructure Works (Electrical Building)
[WNS03] Ground Level & Superstructure Works (Electrical Building)
[WNS03] Partition Wall & Architectural Works (Electrical Building)
[WNS03] Partition Wall & Architectural Works (Pump Station)
[WNS03] EOT Cranes
[WNS03] NEWater, IW & Sump Pumps
[WNS03] Surge Vessels
[WNS03] Automatic Lubrication System
[WNS03] Transformer
[WNS03] EOT Crane Temporary Power Supply
[WNS03] Instruments
[WNS03] Switchgear, MCC & MDB
[WNS03] ACMV System
[WNS03] Fire Protection System
[WNS03] Plumbing & Sanitary System
[WNS03] ELV System
[WNS04] Site Enabling Works
[WNS04] Mobilisation for ULT
[WNS04] Install, Testing & Report - TP09
[WNS04] Ground Level & Superstructure Works (Sodium Hydroxide Building)
[WNS04] Partition Wall & Architectural Works (Sodium Hydroxide Building)
[WNS04] Ground Level & Superstructure Works (Ammonium Sulphate & Electrical Building)
[WNS04] Partition Wall & Architectural Works (Ammonium Sulphate & Electrical Building)
[WNS04] Sodium Hypochlorite FRP Storage Tank
[WNS04] Chemical Dosing System (Sodium Hypochlorite)
[WNS04] Ammonium Sulphate FRP Storage Tank
[WNS04] Chemical Dosing System (Ammonium Sulphate)
[WNS04] Sodium Hydroxide FRP Storage Tank
[WNS04] Chemical Dosing System (Sodium Hydroxide)
[WNS04] MCC & DB
[WNS04] Cable & Cable Raceway Works (Electrical)
[WNS04] Lightning & Earthing Protection
[WNS04] Lightning & Earthing Protection
[WNS04] Lighting Works
[WNS04] Lighting Works
[WNS04] Lighting Works
[WNS04] RIO & UPSDB Panels
[WNS04] Instruments
[WNS04] Cable & Cable Raceway Works (ICA)
[WNS04] ACMV System
[WNS04] Fire Protection System
[WNS04] Plumbing & Sanitary System
[WNS04] ELV System
[WNS05] Site Enabling Works
[WNS05] Mobilisation for ULT
[WNS05] Install, Testing & Report - TP12
[WNS05] Piling at Sprinkler Tank, Lime Tank, Electrical Building & Lime Silo
[WNS05] Piling at Lime Building
[WNS05] Ground Level Works (Sprinkler Tank)
[WNS05] Ground Level & Superstructure Works (Electrical Building)
[WNS05] Partition Wall & Architectural Works (Electrical Building)
[WNS05] Ground Level Works (Lime Tank)
[WNS05] Ground Level & Superstructure Works (Lime Building)
[WNS05] Partition Wall & Architectural Works (Lime Building)
[WNS05] Ground Level Works (Lime Silo)
[WNS05] Lime Silos
[WNS05] Lime Saturator
[WNS05] Lime Slurry, Saturated Lime & Lime Sludge Holding Tanks
[WNS05] Lime Slurry Transfer, Lime Sludge Transfer & Lime Dosing Pumps
[WNS05] Air Compressor Package
[WNS05] Piping & Valves
[WNS05] Transformer
[WNS05] MCC & MDB
[WNS05] Cable and Cable Raceway (Electrical)
[WNS05] Lightning & Earthing Protection
[WNS05] Lightning & Earthing Protection
[WNS05] Lighting Works
[WNS05] Lighting Works
[WNS05] RIO & UPSDB Panels
[WNS05] Instruments
[WNS05] Cable & Cable Raceway Works (ICA)
[WNS05] ACMV System
[WNS05] Fire Protection System
[WNS05] Plumbing & Sanitary System
[WNS05] ELV System
[WNS00 | WNS01] Piling & Foundation
[WNS00 | WNS02] Piling & Foundation
[WNS00] Install Pipe Rack
[WNS00] Piping & Valves
[WNS00] Cable and Cable Raceway (Electrical)
[WNS00] Bonding & Earthing Works
[WNS00] Cable & Cable Raceway Works (ICA)
[WNS03] Telemetry System
[WNS03] Telemetry System
[WNS03] Switchgear, MCC & MDB
[WNS03] High Voltage & Low Voltage VFD
[WNS01] NEWater Storage Tanks, Anciliaries and Hydrostatic Testing
[WNS01] Piping & Hydrostatic Test
[WNS02] Industrial Water Storage Tanks, Anciliaries and Hydrostatic Testing
[WNS02] Piping & Hydrostatic Test
[WNS01] [Tank 3 | GL2/A] Install Remaining Ancillary Archi Finishes
[WNS01] [Tank 4 | GL2/B] Install Remaining Ancillary Archi Finishes
[WNS03] Piping Works
IW Tank Hydrostatic Test Complete
[WNS02] Sterilization of Pipes
[WNS05] Installation of Transformer
[WNS05] Installation of MCC & DB
[WNS05] Installation of Lighting Works at Lime Building
[WNS05] Installation of Lighting Works at Electrical Building
[WNS05] Installation of Lightning and Earthing Protection Equipment (Electrical Building) - Aboveground
[WNS05] Installation of Lightning and Earthing Protection Equipment (Lime Building) - Aboveground
[WNS05] Cable Termination (Electrical)
[WNS02] Installation of Lighting Works at IW Tank No. 2
[WNS02] Installation of Lighting Works at IW Tank No. 1
[WNS02] Cable Termination to IW Tank No. 2 (Electrical)
[WNS02] Cable Termination to IW Tank No. 1 (Electrical)
[WNS03 | ROOF] Cable Termination (Electrical)
[WNS03 | L3] Installation of Lightning and Earthing Protection Equipment (For Electrical Building)
[WNS03 | ROOF] Installation of Lightning and Earthing Protection Equipment (For Electrical Building)
[WNS03 | L4] Installation of Lightning and Earthing Protection Equipment (For Electrical Building)
[WNS03 | L2] Installation of Lightning and Earthing Protection Equipment (For Electrical Building)
[WNS03 | L1] Installation of Lighting Works at Pump Station
[WNS03 | L1] Installation of Lighting Works at Electrical Building
[WNS03 | L2] Installation of Lighting Works at Electrical Building
[WNS03 | L4] Installation of Lighting Works at Electrical Building
[WNS03 | L1] Installation of Lightning and Earthing Protection Equipment (Electrical Building) - Aboveground
[WNS03 | L1] Installation of Lightning and Earthing Protection Equipment (Pump House) - Aboveground
[WNS03 | L4] Cable Termination (Electrical)
[WNS04] Installation of MCC & DB
[WNS04] Installation of Lighting Works at Electrical Building
[WNS04] Installation of Lighting Works at Sodium Hydroxide and Sodium Hypochlorite Building
[WNS04] Installation of Lighting Works at Ammonium Sulphate Building
[WNS04] Installation of Lightning and Earthing Protection Equipment (Ammonium Sulphate Building) - Abovegrou
[WNS04] Installation of Lightning and Earthing Protection Equipment (Electrical Building) - Aboveground
[WNS04] Installation of Lightning and Earthing Protection Equipment (Sodium Hydroxide Building) - Aboveground
[WNS04] Cable Termination (Electrical)
[WNS01] [Tank 1 | GL1/A] Embeds & Underground Pipes Works
[WNS01] [Tank 2 | GL1/B] Embeds & Underground Pipes Works
[WNS01] [Tank 3 | GL2/A] Embeds & Underground Pipes Works
[WNS01] [Tank 4 | GL2/B] Embeds & Underground Pipes Works
[WNS01] [Tank GL3/A] Embeds & Underground Pipes Works
[WNS01] [Tank GL3/B] Embeds & Underground Pipes Works
[WNS01] Single, Combined & Sub-system Testing on Electrical System
Pred Type Successor Id
Normal C2BDS25230
Normal C2BDS25330
Normal C2BDS25430
Normal C2BDS25530
Normal C2BDS25630
Normal C2BCN11510
Normal C2BCN11510
Normal C2BCN11610
Normal C2BCN11610
Normal C2BCN11810
Normal C2BCN11810
Normal C2BCN11910
Normal C2BCN11910
Normal C2BCN31510
LevelOfEffoC2BCN32920
Normal C2BTC10950
Normal C2BCN23410
Normal C2BCN23510
Normal C2BIN27010
Normal C2BCN32920
Normal C2BGN10750
Normal C2BIN27730
Normal C2BIN23410
Normal C2BIN23420
Normal C2BIN24120
Normal C2BIN24910
Normal C2BIN27600
Normal C2BIN27620
Normal C2BIN24810
Normal C2BIN27570
Normal C2BIN27590
Normal C2BIN25510
Normal C2BIN26010
Normal C2BIN26110
Normal C2BIN26210
Normal C2BIN26510
Normal C2BIN21510
Normal C2BIN21510
Normal C2BIN27850
Normal C2BIN26310
Normal C2BCN21530
Normal C2BCN21730
Normal C2BCN22210
Normal C2BCN22310
Normal C2BIN27880
Normal C2BIN27890
Normal C2BIN27900
Normal C2BIN27910
Normal C2BIN27920
Normal C2BIN27820
Normal C2BIN27830
LevelOfEffoC2BCN45070
LevelOfEffoC2BCN45080
LevelOfEffoC2BCN45100
LevelOfEffoC2BCN45090
LevelOfEffoC2BCN45110
LevelOfEffoC2BCN45120
LevelOfEffoC2BCN43370
LevelOfEffoC2BCN11230
LevelOfEffoC2BCN11330
LevelOfEffoC2BCN11950
LevelOfEffoC2BCN11650
LevelOfEffoC2BCN43710
LevelOfEffoC2BCN43700
LevelOfEffoC2BIN27630
LevelOfEffoC2BIN27640
LevelOfEffoC2BIN21320
LevelOfEffoC2BIN28020
LevelOfEffoC2BIN28050
LevelOfEffoC2BIN27680
LevelOfEffoC2BIN28110
LevelOfEffoC2BIN28130
LevelOfEffoC2BCN11020
LevelOfEffoC2BCN16120
LevelOfEffoC2BCN45130
LevelOfEffoC2BCN45210
LevelOfEffoC2BCN45140
LevelOfEffoC2BCN43900
LevelOfEffoC2BCN43890
LevelOfEffoC2BCN16550
LevelOfEffoC2BCN16750
LevelOfEffoC2BIN28190
LevelOfEffoC2BIN21510
LevelOfEffoC2BIN27700
LevelOfEffoC2BIN27690
LevelOfEffoC2BIN28210
LevelOfEffoC2BIN28230
LevelOfEffoC2BCN21120
LevelOfEffoC2BCN44050
LevelOfEffoC2BCN45220
LevelOfEffoC2BCN45230
Normal C2BCN45310
LevelOfEffoC2BIN28160
LevelOfEffoC2BCN21550
LevelOfEffoC2BCN21750
LevelOfEffoC2BCN23220
LevelOfEffoC2BCN23320
LevelOfEffoC2BCN23630
LevelOfEffoC2BCN23730
LevelOfEffoC2BCN44740
LevelOfEffoC2BCN44120
LevelOfEffoC2BIN21820
LevelOfEffoC2BIN21910
LevelOfEffoC2BIN22010
LevelOfEffoC2BIN27850
LevelOfEffoC2BIN22310
LevelOfEffoC2BIN27730
LevelOfEffoC2BIN22710
LevelOfEffoC2BIN22810
LevelOfEffoC2BIN24510
LevelOfEffoC2BIN24520
LevelOfEffoC2BIN24530
LevelOfEffoC2BIN24540
LevelOfEffoC2BCN25120
LevelOfEffoC2BCN44390
LevelOfEffoC2BCN45240
LevelOfEffoC2BCN25350
LevelOfEffoC2BCN25820
LevelOfEffoC2BCN26130
LevelOfEffoC2BCN44800
LevelOfEffoC2BIN24710
LevelOfEffoC2BIN24810
LevelOfEffoC2BIN27560
LevelOfEffoC2BIN27570
LevelOfEffoC2BIN27580
LevelOfEffoC2BIN27590
LevelOfEffoC2BIN25010
LevelOfEffoC2BIN28350
LevelOfEffoC2BIN27890
LevelOfEffoC2BIN27900
LevelOfEffoC2BIN27790
LevelOfEffoC2BIN27800
LevelOfEffoC2BIN27810
LevelOfEffoC2BIN25410
LevelOfEffoC2BIN25510
LevelOfEffoC2BIN28370
LevelOfEffoC2BIN25620
LevelOfEffoC2BIN25630
LevelOfEffoC2BIN25640
LevelOfEffoC2BIN25650
LevelOfEffoC2BCN30120
LevelOfEffoC2BCN44530
LevelOfEffoC2BCN45250
LevelOfEffoC2BCN30340
LevelOfEffoC2BCN30420
LevelOfEffoC2BCN30530
LevelOfEffoC2BCN31140
LevelOfEffoC2BCN44910
LevelOfEffoC2BCN30730
LevelOfEffoC2BCN30860
LevelOfEffoC2BCN44970
LevelOfEffoC2BCN30930
LevelOfEffoC2BIN25810
LevelOfEffoC2BIN25910
LevelOfEffoC2BIN26010
LevelOfEffoC2BIN26110
LevelOfEffoC2BIN26210
LevelOfEffoC2BTC11010
LevelOfEffoC2BIN26410
LevelOfEffoC2BIN26510
LevelOfEffoC2BIN28410
LevelOfEffoC2BIN27920
LevelOfEffoC2BIN27910
LevelOfEffoC2BIN27820
LevelOfEffoC2BIN27830
LevelOfEffoC2BIN26910
LevelOfEffoC2BIN27010
LevelOfEffoC2BIN28430
LevelOfEffoC2BIN27120
LevelOfEffoC2BIN27130
LevelOfEffoC2BIN27140
LevelOfEffoC2BIN27150
LevelOfEffoC2BCN32520
LevelOfEffoC2BCN32720
LevelOfEffoC2BCN32920
LevelOfEffoC2BTC10950
LevelOfEffoC2BIN28450
LevelOfEffoC2BIN27930
LevelOfEffoC2BIN28470
LevelOfEffoC2BIN23420
LevelOfEffoC2BIN23410
LevelOfEffoC2BIN23810
LevelOfEffoC2BIN23810
LevelOfEffoC2BTC11110
LevelOfEffoC2BTC11150
LevelOfEffoC2BTC11170
LevelOfEffoC2BTC11190
Normal C2BTC10770
Normal C2BTC10770
LevelOfEffoC2BTC11210
Milestone C2BTC11220
Normal C2BTC11220
Normal C2BTC11350
Normal C2BTC11350
Normal C2BTC11350
Normal C2BTC11350
Normal C2BTC11350
Normal C2BTC11350
Normal C2BTC11350
Normal C2BTC11230
Normal C2BTC11230
Normal C2BTC11230
Normal C2BTC11230
Normal C2BTC11270
Normal C2BTC11270
Normal C2BTC11270
Normal C2BTC11270
Normal C2BTC11270
Normal C2BTC11270
Normal C2BTC11270
Normal C2BTC11270
Normal C2BTC11270
Normal C2BTC11270
Normal C2BTC11270
Normal C2BTC11270
Normal C2BTC11310
Normal C2BTC11310
Normal C2BTC11310
Normal C2BTC11310
Normal C2BTC11310
Normal C2BTC11310
Normal C2BTC11310
Normal C2BTC11310
Normal C2BCN11430
Normal C2BCN11730
Normal C2BCN11530
Normal C2BCN11830
Normal C2BCN11630
Normal C2BCN11930
Normal C2BGN21260
Successor
[WNS01] Preparation & Submission : Training Manuals
[WNS02] Preparation & Submission : Training Manuals
[WNS03] Preparation & Submission : Training Manuals
[WNS04] Preparation & Submission : Training Manuals
[WNS05] Preparation & Submission : Training Manuals
[WNS01] [Tank 3 | GL2/A] Excavate to FEL
[WNS01] [Tank 3 | GL2/A] Excavate to FEL
[WNS01] [Tank GL3/A] Excavate to FEL
[WNS01] [Tank GL3/A] Excavate to FEL
[WNS01] [Tank 4 | GL2/B] Excavate to FEL
[WNS01] [Tank 4 | GL2/B] Excavate to FEL
[WNS01] [Tank GL3/B] Excavate to FEL
[WNS01] [Tank GL3/B] Excavate to FEL
[WNS05] [Lime Bldg] Install External Walls
[WNS00 | C1A] Install Pipe Racks
[WNS00] Hydrostatic Test of Pipes
[WNS03] [GLD to GLG / GL1 to GL7] Construct Beams & Slabs at SFL 18.40
[WNS03] [GLD to GLG / GL7 to GL13] Construct Beams & Slabs at SFL 18.40
[WNS05] Installation of Instruments
[WNS00 | C1A] Install Pipe Racks
Revise & Resubmit to SO : Concrete design mix
[WNS03 | L1] Installation of Temporary Power Supply
[WNS03 | L2] Installation of Telemetry System to WNS JISR
[WNS03 | L2] Installation of Telemetry System to WNS CME
[WNS03 | L4] Installation of Lightning and Earthing Protection Equipment (For Electrical Building)
[WNS04] Installation of Sodium Hypochlorite Dosing Pipes and Valves
[WNS04] Installation of Ammonium Sulphate Dosing Pipes and Valves
[WNS04] Installation of Sodium Hydroxide Dosing Pipes and Valves
[WNS04] Installation of Sodium Hypochlorite Dosing System (Valves, Pumps, Instruments)
[WNS04] Installation of Ammonium Sulphate Dosing System (Valves, Pumps, Instruments)
[WNS04] Installation of Sodium Hydroxide Dosing System (Valves, Pumps, Instruments)
[WNS04] Installation of Instruments
[WNS05] Installation of Lime Slurry, Saturated Lime and Lime Sludge Holding Tanks
[WNS05] Installation of Lime Slurry Transfer, Lime Sludge Transfer and Lime Dosing Pumps
[WNS05] Installation of Air Compressor Package
[WNS05] Installation of MCC & DB
[WNS02] Installation of Lightning and Earthing Protection Equipment (for IW Tank No. 1 & 2)
[WNS02] Installation of Lightning and Earthing Protection Equipment (for IW Tank No. 1 & 2)
[WNS03 | L1] Installation of Automatic Lubrication System
[WNS05] Installation of Lime Dosing Piping Works & Valves
[WNS03] [GLA to GLD / GL1 to GL8] Construct Basement Slab / Floor Drain Pit
[WNS03] [GLA to GLD / GL8 to GL14] Construct Basement Slab / Pump Valve Chamber
[WNS03] [GLD to GLG / GL1 to GL7] Construct Ground Beams & Slabs at SFL 5.30
[WNS03] [GLD to GLG / GL7 to GL13] Construct Ground Beams & Slabs at SFL 5.30
[WNS04] Installation of Lightning and Earthing Protection Equipment (Sodium Hydroxide Building) - Aboveground
[WNS04] Installation of Lightning and Earthing Protection Equipment (Ammonium Sulphate Building) - Aboveground
[WNS04] Installation of Lightning and Earthing Protection Equipment (Electrical Building) - Aboveground
[WNS05] Installation of Lightning and Earthing Protection Equipment (Lime Building) - Aboveground
[WNS05] Installation of Lightning and Earthing Protection Equipment (Electrical Building) - Aboveground
[WNS05] Installation of Lighting Works at Electrical Building
[WNS05] Installation of Lighting Works at Lime Building
[WNS01] [TP03] QP(D)/SO review on Ultimate Load Test
[WNS01] [TP06] QP(D)/SO review on Ultimate Load Test
[WNS01] [TP02] QP(D)/SO review on Ultimate Load Test
[WNS01] [TP05] QP(D)/SO review on Ultimate Load Test
[WNS01] [TP01] QP(D)/SO review on Ultimate Load Test
[WNS01] [TP04] QP(D)/SO review on Ultimate Load Test
[WNS01] Cage fabrication & Delivery
[WNS01] [Tank GL3/A] Install Bored Piles (36 nos.)
[WNS01] [Tank GL3/B] Install Bored Piles (36 nos.)
[WNS01] [Tank GL3/B] Backfill Where Necessary
[WNS01] [Tank GL3/A] Backfill Where Necessary
[WNS01] [Tank GL 3/B] Working Load Test / PDA / PIT
[WNS01] [Tank GL 3/A] Working Load Test / PDA / PIT
[WNS01] Installation of Active Tank Mixers for NEWater Tanks
[WNS01] Installation of Electrical Manhole and Duct Bank
[WNS01] Installation of Lightning and Earthing Protection Equipment (for NW Tank No. 3 & 4)
[WNS01] Cable Termination to NW Tank No. 3 (Electrical)
[WNS01] Cable Termination to NW Tank No. 4 (Electrical)
[WNS01] Installation of Lighting Works at NW Tank No. 4
[WNS01] Cable Termination to NW Tank No. 3 (ICA)
[WNS01] Cable Termination to NW Tank No. 4 (ICA)
[WNS01] Hoardings, ECM and Site Access
[WNS02] Hoardings, ECM and Site Access
[WNS02] [TP07] QP(D)/SO review on Ultimate Load Test
[WNS02] [TP08] Dismantle Kentledge
[WNS02] [TP08] QP(D)/SO review on Ultimate Load Test
[WNS02] Cage fabrication & Delivery
[WNS02] Set-up Silo & Pile Rig
[WNS02] [Tank 1 | GL1/A] Backfill Where Necessary
[WNS02] [Tank 2 | GL2/A] Backfill Where Necessary
[WNS02] Cable Termination to IW Tank No. 2 (Electrical)
[WNS02] Installation of Lightning and Earthing Protection Equipment (for IW Tank No. 1 & 2)
[WNS02] Installation of Lighting Works at IW Tank No. 2
[WNS02] Installation of Lighting Works at IW Tank No. 1
[WNS02] Cable Termination to IW Tank No. 1 (ICA)
[WNS02] Cable Termination to IW Tank No. 2 (ICA)
[WNS03] Hoardings, ECM and Site Access
[WNS03] Cage fabrication & Delivery
[WNS03] [TP10] Dismantle Kentledge
[WNS03] [TP11] Dismantle Kentledge
[WNS03] [UG Pipe Rack] Working Load Test / PDA / PIT
[WNS02] Cable Termination to IW Tank No. 1 (Electrical)
[WNS03] [GLA to GLD / GL1 to GL8] Backfill Where Necessary & Remove Temporary ERSS
[WNS03] [GLA to GLD / GL8 to GL14] Backfill Where Necessary & Remove Temporary ERSS
[WNS03] [GLA to GLD / GL1 to GL8] Install Roof Drainage System
[WNS03] [GLA to GLD / GL8 to GL14] Install Roof Drainage System
[WNS03] [GLD to GLG / GL1 to GL7] Install Roof Drainage System
[WNS03] [GLD to GLG / GL7 to GL13] Install Roof Drainage System
[WNS03 | Electrical Building | L4] Staircase Finishes
[WNS03 | Pump Station | L1] Doors & Other anciliaries installation
[WNS03 | L1] Commissioning of EOT Cranes and MOM Registration
[WNS03 | L1] Installation of Pumps
[WNS03 | L1] Installation of Surge Vessels
[WNS03 | L1] Installation of Automatic Lubrication System
[WNS03 | L1] Installation of Transformer
[WNS03 | L1] Installation of Temporary Power Supply
[WNS03 | L1] Installation of Instruments
[WNS03 | L2] Installation of Switchgear, MCC & MDB
[WNS03 | ROOF] Installation of ACMV System
[WNS03 | ROOF] Installation of Fire Protection System
[WNS03 | ROOF] Installation of Plumbing and Sanitary System
[WNS03 | ROOF] Installation of ELV System
[WNS04] Hoardings, ECM and Site Access
[WNS04] Cage fabrication & Delivery
[WNS04] [TP09] Dismantle Kentledge
[WNS04] [Sodium Hydr Bldg] Install Roofing
[WNS04] [Sodium Hydr Bldg] Install Internal Walls
[WNS04] [Elec Bldg] Construct Staircase Structure
[WNS04 | Electrical Building | L1] Doors, Ironmongeries & Other anciliaries installation
[WNS04] Installation of 2 Sodium Hypochlorite FRP Storage Tank
[WNS04] Installation of Sodium Hypochlorite Dosing System (Valves, Pumps, Instruments)
[WNS04] Installation of 2 Ammonium Sulphate Storage Tank
[WNS04] Installation of Ammonium Sulphate Dosing System (Valves, Pumps, Instruments)
[WNS04] Installation of 6 Sodium Hydroxide FRP Storage Tank
[WNS04] Installation of Sodium Hydroxide Dosing System (Valves, Pumps, Instruments)
[WNS04] Installation of MCC & DB
[WNS04] Cable Termination (Electrical)
[WNS04] Installation of Lightning and Earthing Protection Equipment (Ammonium Sulphate Building) - Aboveground
[WNS04] Installation of Lightning and Earthing Protection Equipment (Electrical Building) - Aboveground
[WNS04] Installation of Lighting Works at Electrical Building
[WNS04] Installation of Lighting Works at Sodium Hydroxide and Sodium Hypochlorite Building
[WNS04] Installation of Lighting Works at Ammonium Sulphate Building
[WNS04] Installation of RIO & UPSDB Panels
[WNS04] Installation of Instruments
[WNS04] Cable Termination (ICA)
[WNS04] Installation of ACMV System
[WNS04] Installation of Fire Protection System
[WNS04] Installation of Plumbing and Sanitary System
[WNS04] Installation of ELV System
[WNS05] Hoardings, ECM and Site Access
[WNS05] Cage fabrication & Delivery
[WNS05] [TP12] Dismantle Kentledge
[WNS05] [Lime Silo] Install Bored Piles (28 nos.)
[WNS05] [Lime Bldg | GLA to GLC / GL4 to GL6] Install Bored Piles (36 nos.)
[WNS05] [Sprinkler Tank] Construct Drainage / Utility Trench
[WNS05] [Elec Bldg] Install Roof Drainage System
[WNS05 | Electrical Building | L2] Staircase Finishes
[WNS05] [Lime Tank] Construct Drainage / Utility Trench
[WNS05] [Lime Bldg] Install Roofing
[WNS05 | Lime Bldg | L1] Staircase Finishes
[WNS05] [Lime Silo] Construct Drainage / Utility Trench
[WNS05] Installation of Lime Silos
[WNS05] Installation of Lime Saturator
[WNS05] Installation of Lime Slurry, Saturated Lime and Lime Sludge Holding Tanks
[WNS05] Installation of Lime Slurry Transfer, Lime Sludge Transfer and Lime Dosing Pumps
[WNS05] Installation of Air Compressor Package
[WNS05] Hydrostatic Test of Lime Dosing Pipes
[WNS05] Installation of Transformer
[WNS05] Installation of MCC & DB
[WNS05] Cable Termination (Electrical)
[WNS05] Installation of Lightning and Earthing Protection Equipment (Electrical Building) - Aboveground
[WNS05] Installation of Lightning and Earthing Protection Equipment (Lime Building) - Aboveground
[WNS05] Installation of Lighting Works at Electrical Building
[WNS05] Installation of Lighting Works at Lime Building
[WNS05] Installation of RIO & UPSDB Panels
[WNS05] Installation of Instruments
[WNS05] Cable Termination (ICA)
[WNS05] Installation of ACMV System
[WNS05] Installation of Fire Protection System
[WNS05] Installation of Plumbing and Sanitary System
[WNS05] Installation of ELV System
[WNS00 | WNS01] Construct Pipe Rack Foundation Works
[WNS00 | WNS02] Construct Pipe Rack Foundation Works
[WNS00 | C1A] Install Pipe Racks
[WNS00] Hydrostatic Test of Pipes
[WNS00] Cable Termination (Electrical)
[WNS00] Installation of Bonding & Earthing Protection - Aboveground
[WNS00] Cable Termination (ICA)
[WNS03 | L2] Installation of Telemetry System to WNS CME
[WNS03 | L2] Installation of Telemetry System to WNS JISR
[WNS03 | L4] Installation of Switchgear, MCC & MDB
[WNS03 | L4] Installation of Switchgear, MCC & MDB
[WNS01] Sterilization of New Water Storage Tanks
[WNS01] Sterilization of Pipes Aboveground
[WNS02] Sterilization of Industrial Water Storage Tanks
[WNS02] Sterilization of Pipes
[WNS01] Hydrostatic Test of New Water Storage Tanks
[WNS01] Hydrostatic Test of New Water Storage Tanks
[WNS03 | L1] Sterilization of Pipes
[WNS02] Single, Combined & Sub-system Testing on Mechanical System
[WNS02] Single, Combined & Sub-system Testing on Mechanical System
[WNS05] Single, Combined & Sub-system Testing on Electrical System
[WNS05] Single, Combined & Sub-system Testing on Electrical System
[WNS05] Single, Combined & Sub-system Testing on Electrical System
[WNS05] Single, Combined & Sub-system Testing on Electrical System
[WNS05] Single, Combined & Sub-system Testing on Electrical System
[WNS05] Single, Combined & Sub-system Testing on Electrical System
[WNS05] Single, Combined & Sub-system Testing on Electrical System
[WNS02] Single, Combined & Sub-system Testing on Electrical System
[WNS02] Single, Combined & Sub-system Testing on Electrical System
[WNS02] Single, Combined & Sub-system Testing on Electrical System
[WNS02] Single, Combined & Sub-system Testing on Electrical System
[WNS03] Single, Combined & Sub-system Testing on Electrical System
[WNS03] Single, Combined & Sub-system Testing on Electrical System
[WNS03] Single, Combined & Sub-system Testing on Electrical System
[WNS03] Single, Combined & Sub-system Testing on Electrical System
[WNS03] Single, Combined & Sub-system Testing on Electrical System
[WNS03] Single, Combined & Sub-system Testing on Electrical System
[WNS03] Single, Combined & Sub-system Testing on Electrical System
[WNS03] Single, Combined & Sub-system Testing on Electrical System
[WNS03] Single, Combined & Sub-system Testing on Electrical System
[WNS03] Single, Combined & Sub-system Testing on Electrical System
[WNS03] Single, Combined & Sub-system Testing on Electrical System
[WNS03] Single, Combined & Sub-system Testing on Electrical System
[WNS04] Single, Combined & Sub-system Testing on Electrical System
[WNS04] Single, Combined & Sub-system Testing on Electrical System
[WNS04] Single, Combined & Sub-system Testing on Electrical System
[WNS04] Single, Combined & Sub-system Testing on Electrical System
[WNS04] Single, Combined & Sub-system Testing on Electrical System
[WNS04] Single, Combined & Sub-system Testing on Electrical System
[WNS04] Single, Combined & Sub-system Testing on Electrical System
[WNS04] Single, Combined & Sub-system Testing on Electrical System
[WNS01] [Tank 1 | GL1/A] Construct Ground Slab
[WNS01] [Tank 2 | GL1/B] Construct Ground Slab
[WNS01] [Tank 3 | GL2/A] Construct Ground Slab
[WNS01] [Tank 4 | GL2/B] Construct Ground Slab
[WNS01] [Tank GL3/A] Construct Ground Slab
[WNS01] [Tank GL3/B] Construct Ground Slab
Power Turn On from C2B
Succ Type Total Finis Lag Type Contractor's Response for using FF Relationship
Normal 101 0 FinishToFinish
Normal 299 0 FinishToFinish
Normal 299 0 FinishToFinish
Normal 101 0 FinishToFinish
Normal 101 0 FinishToFinish
Normal 158 0 FinishToFinish
Normal 158 0 FinishToFinish
Normal 207 0 FinishToFinish
Normal 207 0 FinishToFinish
Normal 158 0 FinishToFinish
Normal 158 0 FinishToFinish
Normal 172 0 FinishToFinish
Normal 172 0 FinishToFinish
Normal 162 0 FinishToFinish
Normal 226 0 FinishToFinish
Normal 148 0 FinishToFinish
Normal 27 0 FinishToFinish
Normal 27 0 FinishToFinish
Normal 56 0 FinishToFinish
Normal 226 0 FinishToFinish
Normal 3 0 FinishToFinish
Normal 92 0 FinishToFinish
Normal 154 0 FinishToFinish
Normal 154 0 FinishToFinish
Normal 14 0 FinishToFinish
Normal 128 0 FinishToFinish
Normal 99 0 FinishToFinish
Normal 107 0 FinishToFinish
Normal 128 0 FinishToFinish
Normal 99 0 FinishToFinish
Normal 107 0 FinishToFinish
Normal 43 0 FinishToFinish
Normal 170 0 FinishToFinish
Normal 171 0 FinishToFinish
Normal 70 0 FinishToFinish
Normal 53 0 FinishToFinish
Normal 259 0 FinishToFinish
Normal 259 0 FinishToFinish
Normal 92 0 FinishToFinish
Normal 7 0 FinishToFinish
Normal 15 0 FinishToFinish
Normal 15 0 FinishToFinish
Normal 2 0 FinishToFinish
Normal 2 0 FinishToFinish
Normal 51 0 FinishToFinish
Normal 51 0 FinishToFinish
Normal 51 0 FinishToFinish
Normal 52 0 FinishToFinish
Normal 52 0 FinishToFinish
Normal 52 0 FinishToFinish
Normal 52 0 FinishToFinish
Normal 283 0 FinishToFinish
Normal 283 0 FinishToFinish
Normal 186 0 FinishToFinish
Normal 186 0 FinishToFinish
Normal 79 0 FinishToFinish
Normal 79 0 FinishToFinish
Normal 79 0 FinishToFinish
Normal 79 0 FinishToFinish
Normal 79 0 FinishToFinish
Normal 172 0 FinishToFinish
Normal 207 0 FinishToFinish
Normal 204 0 FinishToFinish
Normal 239 0 FinishToFinish
Normal 305 0 FinishToFinish
Normal 258 0 FinishToFinish
Normal 351 0 FinishToFinish
Normal 175 0 FinishToFinish
Normal 175 0 FinishToFinish
Normal 146 0 FinishToFinish
Normal 145 0 FinishToFinish
Normal 145 0 FinishToFinish
Normal 79 0 FinishToFinish
Normal 5 0 FinishToFinish
Normal 5 0 FinishToFinish
Normal 35 0 FinishToFinish
Normal 5 0 FinishToFinish
Normal 5 0 FinishToFinish
Normal 5 0 FinishToFinish
Normal 5 0 FinishToFinish
Normal 5 0 FinishToFinish
Normal 28 0 FinishToFinish
Normal 259 0 FinishToFinish
Normal 7 0 FinishToFinish
Normal 7 0 FinishToFinish
Normal 27 0 FinishToFinish
Normal 27 0 FinishToFinish
Normal 2 0 FinishToFinish
Normal 2 0 FinishToFinish
Normal 32 0 FinishToFinish
Normal 32 0 FinishToFinish
Normal 82 0 FinishToFinish
Normal 28 0 FinishToFinish
Normal 15 0 FinishToFinish
Normal 15 0 FinishToFinish
Normal 55 0 FinishToFinish
Normal 55 0 FinishToFinish
Normal 257 0 FinishToFinish
Normal 257 0 FinishToFinish
Normal 211 0 FinishToFinish
Normal 291 0 FinishToFinish
Normal 92 0 FinishToFinish
Normal 92 0 FinishToFinish
Normal 120 0 FinishToFinish
Normal 92 0 FinishToFinish
Normal 170 0 FinishToFinish
Normal 92 0 FinishToFinish
Normal 176 0 FinishToFinish
Normal 114 0 FinishToFinish
Normal 2 0 FinishToFinish
Normal 2 0 FinishToFinish
Normal 2 0 FinishToFinish
Normal 2 0 FinishToFinish
Normal 31 0 FinishToFinish
Normal 31 0 FinishToFinish
Normal 61 0 FinishToFinish
Normal 32 0 FinishToFinish
Normal 32 0 FinishToFinish
Normal 265 0 FinishToFinish
Normal 281 0 FinishToFinish
Normal 107 0 FinishToFinish
Normal 128 0 FinishToFinish
Normal 99 0 FinishToFinish
Normal 99 0 FinishToFinish
Normal 107 0 FinishToFinish
Normal 107 0 FinishToFinish
Normal 52 0 FinishToFinish
Normal 51 0 FinishToFinish
Normal 51 0 FinishToFinish
Normal 51 0 FinishToFinish
Normal 31 0 FinishToFinish
Normal 31 0 FinishToFinish
Normal 31 0 FinishToFinish
Normal 43 0 FinishToFinish
Normal 43 0 FinishToFinish
Normal 32 0 FinishToFinish
Normal 57 0 FinishToFinish
Normal 57 0 FinishToFinish
Normal 57 0 FinishToFinish
Normal 57 0 FinishToFinish
Normal 14 0 FinishToFinish
Normal 14 0 FinishToFinish
Normal 44 0 FinishToFinish
Normal 52 0 FinishToFinish
Normal 7 0 FinishToFinish
Normal 339 0 FinishToFinish
Normal 179 0 FinishToFinish
Normal 179 0 FinishToFinish
Normal 170 0 FinishToFinish
Normal 162 0 FinishToFinish
Normal 162 0 FinishToFinish
Normal 171 0 FinishToFinish
Normal 171 0 FinishToFinish
Normal 7 0 FinishToFinish
Normal 170 0 FinishToFinish
Normal 171 0 FinishToFinish
Normal 70 0 FinishToFinish
Normal 7 0 FinishToFinish
Normal 53 0 FinishToFinish
Normal 53 0 FinishToFinish
Normal 52 0 FinishToFinish
Normal 52 0 FinishToFinish
Normal 52 0 FinishToFinish
Normal 52 0 FinishToFinish
Normal 52 0 FinishToFinish
Normal 56 0 FinishToFinish
Normal 56 0 FinishToFinish
Normal 21 0 FinishToFinish
Normal 66 0 FinishToFinish
Normal 66 0 FinishToFinish
Normal 66 0 FinishToFinish
Normal 66 0 FinishToFinish
Normal 59 0 FinishToFinish
Normal 62 0 FinishToFinish
Normal 226 0 FinishToFinish
Normal 148 0 FinishToFinish
Normal 87 0 FinishToFinish
Normal 59 0 FinishToFinish
Normal 148 0 FinishToFinish
Normal 154 0 FinishToFinish
Normal 154 0 FinishToFinish
Normal 4 0 FinishToFinish
Normal 4 0 FinishToFinish
Normal 228 0 FinishToFinish
Normal 186 0 FinishToFinish
Normal 54 0 FinishToFinish
Normal 5 0 FinishToFinish
Normal 228 0 FinishToFinish
Normal 228 0 FinishToFinish
Normal 105 0 FinishToFinish
Normal 5 0 FinishToFinish
Normal 5 0 FinishToFinish
Normal 52 0 FinishToFinish
Normal 52 0 FinishToFinish
Normal 52 0 FinishToFinish
Normal 52 0 FinishToFinish
Normal 52 0 FinishToFinish
Normal 52 0 FinishToFinish
Normal 52 0 FinishToFinish
Normal 7 0 FinishToFinish
Normal 7 0 FinishToFinish
Normal 7 0 FinishToFinish
Normal 7 0 FinishToFinish
Normal 4 0 FinishToFinish
Normal 4 0 FinishToFinish
Normal 4 0 FinishToFinish
Normal 4 0 FinishToFinish
Normal 4 0 FinishToFinish
Normal 4 0 FinishToFinish
Normal 4 0 FinishToFinish
Normal 4 0 FinishToFinish
Normal 4 0 FinishToFinish
Normal 4 0 FinishToFinish
Normal 4 0 FinishToFinish
Normal 4 0 FinishToFinish
Normal 31 0 FinishToFinish
Normal 31 0 FinishToFinish
Normal 31 0 FinishToFinish
Normal 31 0 FinishToFinish
Normal 31 0 FinishToFinish
Normal 31 0 FinishToFinish
Normal 31 0 FinishToFinish
Normal 31 0 FinishToFinish
Normal 97 0 FinishToFinish
Normal 97 0 FinishToFinish
Normal 158 0 FinishToFinish
Normal 158 0 FinishToFinish
Normal 207 0 FinishToFinish
Normal 172 0 FinishToFinish
Milestone 0 0 FinishToFinish
Id
C2BMF23300
C2BMF23930
C2BGN24500
C2BGN24530
C2BGN24590
C2BGN24700
C2BGN24750
C2BGN24780
C2BGN24690
C2BMF21310
C2BMF23310
C2BMF23940
C2BGN24470
C2BGN24540
C2BGN24600
C2BGN24710
C2BGN24760
C2BGN24790
C2BMF21220
C2BMF42650
C2BMF22210
C2BMF30140
C2BMF30260
C2BMF23290
C2BMF42590
C2BMF44010
C2BMF44260
C2BMF45120
C2BMF27550
C2BMF29340
C2BMF30080
C2BGN24900
C2BMF29270
C2BMF29280
C2BMF29290
C2BMF29300
C2BMF30230
C2BMF44470
C2BMF30150
C2BMF42600
C2BGN24630
C2BGN24510
C2BMF29660
C2BMF30190
C2BMF30500
C2BDS45040
C2BMF21910
C2BMF27560
C2BMF30090
C2BMF30350
C2BMF30370
C2BMF30390
C2BMF30410
C2BMF44490
C2BGN24570
C2BDS45680
C2BDS45760
C2BMF44910
C2BMF30240
C2BMF21610
C2BMF28930
C2BMF29350
C2BMF42660
C2BMF44290
C2BMF44350
C2BCN21410
C2BCN21430
C2BMF30510
C2BMF29670
C2BMF30200
C2BCN11210
C2BCN11310
C2BCN45280
C2BMF30100
C2BMF30160
C2BMF42870
C2BMF29540
C2BMF30060
C2BMF30170
C2BMF30360
C2BMF30380
C2BMF30400
C2BMF30420
C2BMF30430
C2BMF31220
C2BMF31250
C2BMF31280
C2BMF31310
C2BMF32350
C2BMF44310
C2BMF44370
C2BMF44500
C2BMF44920
C2BMF45100
C2BDS41350
C2BMF32310
C2BDS41430
C2BMF29710
C2BMF30520
C2BDS31510
C2BMF21510
C2BDS41450
C2BMF29610
C2BMF30440
C2BMF31230
C2BMF31260
C2BMF31290
C2BMF31320
C2BMF43700
C2BMF44410
C2BCN45290
C2BMF32300
C2BDS23220
C2BMF30110
C2BMF44320
C2BMF44380
C2BMF29470
C2BMF29770
C2BMF29880
C2BDS42470
C2BMF30070
C2BMF30180
C2BMF31520
C2BMF31550
C2BMF43030
C2BDS41970
C2BDS41990
C2BDS42010
C2BDS42030
C2BMF29560
C2BMF29720
C2BMF31350
C2BMF31420
C2BMF42800
C2BDS45600
C2BCN11320
C2BCN11220
C2BDS44280
C2BMF44430
C2BDS45720
C2BDS23320
C2BDS23520
C2BCN21440
C2BMF29050
C2BMF29360
C2BMF43710
C2BDS45320
C2BMF29910
C2BMF29980
C2BMF30470
C2BMF32330
C2BMF29620
C2BMF29950
C2BMF30450
C2BDS42520
C2BMF31240
C2BMF31270
C2BMF31300
C2BMF31330
C2BMF29630
C2BMF29780
C2BMF31360
C2BMF31430
C2BMF31530
C2BMF31560
C2BMF43040
C2BMF43090
C2BMF32370
C2BDS23420
C2BDS23620
C2BMF29790
C2BMF42920
C2BIN27640
C2BCN21420
C2BIN22510
C2BCN45380
C2BCN11430
C2BCN11730
C2BMF29480
C2BMF29590
C2BMF30290
C2BMF42810
C2BMF32380
C2BCN11440
C2BCN11740
C2BDS41570
C2BMF29730
C2BMF30000
C2BDS45200
C2BDS45240
C2BDS45800
C2BMF30480
C2BMF31490
C2BMF43220
C2BMF43280
C2BMF32410
C2BMF44440
C2BMF44530
C2BMF22630
C2BDS41370
C2BMF29370
C2BMF29990
C2BMF42980
C2BMF43100
C2BMF43510
C2BDS41330
C2BMF29960
C2BMF23400
C2BDS44840
C2BMF32390
C2BMF32400
C2BMF29640
C2BMF29680
C2BMF31440
C2BMF42930
C2BCN21520
C2BCN21720
C2BDS42230
C2BMF29820
C2BDS42410
C2BDS42430
C2BDS43440
C2BDS43460
C2BDS43520
C2BDS43540
C2BMF31370
C2BDS43840
C2BDS43880
C2BMF43340
C2BMF44610
C2BMF44650
C2BCN11330
C2BCN11230
C2BIN21310
C2BMF30330
C2BMF43050
C2BMF44550
C2BMF32360
C2BMF32420
C2BMF29800
C2BMF30010
C2BMF30270
C2BMF30300
C2BMF31500
C2BMF43230
C2BMF43290
C2BMF43520
C2BDS44240
C2BMF43760
C2BMF43820
C2BMF44060
C2BMF44090
C2BMF44120
C2BDS42500
C2BMF31580
C2BMF42990
C2BMF43880
C2BMF43940
C2BIN22520
C2BCN21530
C2BCN21730
C2BMF32450
C2BMF32430
C2BMF43110
C2BMF44670
C2BCN30410
C2BDS42090
C2BDS42290
C2BMF32440
C2BMF43160
C2BMF43350
C2BMF43450
C2BMF44620
C2BCN11540
C2BCN11840
C2BDS31710
C2BDS42170
C2BDS42330
C2BMF29430
C2BDS43760
C2BDS44320
C2BDS45280
C2BMF44950
C2BMF29690
C2BMF29830
C2BMF30340
C2BMF32510
C2BMF43530
C2BMF44070
C2BMF44100
C2BMF44130
C2BMF44560
C2BMF44710
C2BCN11530
C2BCN11830
C2BCN21820
C2BCN21920
C2BMF29500
C2BMF30280
C2BDS43720
C2BDS43800
C2BMF31590
C2BMF43400
C2BMF43570
C2BMF43770
C2BMF43830
C2BMF43890
C2BMF43950
C2BDS44520
C2BDS44560
C2BMF24000
C2BDS41720
C2BDS42350
C2BMF43460
C2BMF43640
C2BDS44400
C2BCN21540
C2BCN21740
C2BCN45010
C2BCN45020
C2BMF32460
C2BDS42250
C2BMF32470
C2BMF32480
C2BMF32490
C2BDS44360
C2BMF32500
C2BCN30330
C2BMF27540
C2BMF29520
C2BMF43170
C2BMF44680
C2BMF44970
C2BMF32530
C2BMF32540
C2BDS44440
C2BDS44600
C2BMF44730
C2BMF44770
C2BDS45400
C2BIN21320
C2BMF32520
C2BMF30310
C2BMF43580
C2BCN22210
C2BCN22310
C2BMF32560
C2BDS41520
C2BDS42210
C2BDS42270
C2BMF29510
C2BMF43410
C2BMF43650
C2BDS45080
C2BDS45120
C2BCN30340
C2BIN26720
C2BMF32620
C2BDS44040
C2BMF32640
C2BDS44720
C2BDS44960
C2BDS45000
C2BDS45360
C2BCN30420
C2BCN22010
C2BCN22110
C2BCN11640
C2BCN11940
C2BDS41680
C2BMF43470
C2BDS44880
C2BDS44920
C2BMF44790
C2BDS42190
C2BCN22220
C2BCN22320
C2BCN22230
C2BCN22330
C2BCN24110
C2BMF29530
C2BMF32580
C2BMF30320
C2BMF32590
C2BMF32600
C2BMF32610
C2BMF44980
C2BCN45390
C2BCN45400
C2BDS42130
C2BDS44480
C2BMF44740
C2BMF44850
C2BMF32650
C2BMF32660
C2BMF32700
C2BMF32630
C2BDS45440
C2BCN11630
C2BCN11930
C2BMF32550
C2BMF32710
C2BMF43590
C2BDS42050
C2BMF32670
C2BMF32680
C2BMF32690
C2BDS44640
C2BDS44800
C2BIN21110
C2BCN22410
C2BCN22510
C2BMF32850
C2BMF44800
C2BDS44680
C2BMF32730
C2BMF44860
C2BCN23910
C2BCN22020
C2BCN22120
C2BCN22030
C2BCN22130
C2BCN45030
C2BCN45040
C2BIN22410
C2BCN32510
C2BMF32720
C2BMF32760
C2BMF32770
C2BCN30610
C2BMF32740
C2BMF32790
C2BMF32750
C2BMF32800
C2BIN27650
C2BIN27660
C2BMF32820
C2BDS42110
C2BMF32830
C2BMF32780
C2BIN27950
C2BIN27980
C2BIN26710
C2BMF32810
C2BCN24010
C2BCN32710
C2BMF32840
C2BDS45480
C2BCN30810
C2BMF33120
C2BMF32940
C2BCN22610
C2BCN22710
C2BMF32860
C2BMF32870
C2BDS45520
C2BCN22810
C2BCN22910
C2BMF32890
C2BTC10250
C2BMF32880
C2BMF32900
C2BDS44760
C2BDS45560
C2BCN16420
C2BCN16410
C2BCN25210
C2BCN32720
C2BCN45460
C2BMF32100
C2BMF32950
C2BMF32910
C2BMF32920
C2BMF32930
C2BCN45410
C2BCN45420
C2BCN32520
C2BIN27840
C2BMF33010
C2BCN24120
C2BIN22310
C2BCN23810
C2BCN22620
C2BCN22720
C2BIN22210
C2BMF42410
C2BMF32970
C2BMF32990
C2BMF32960
C2BMF33040
C2BMF32980
C2BMF33000
C2BMF33060
C2BTC10300
C2BTC10400
C2BTC10320
C2BTC10330
C2BTC10340
C2BMF33030
C2BCN24020
C2BCN22820
C2BCN22920
C2BCN30620
C2BCN30710
C2BCN25220
C2BIN25210
C2BMF33050
C2BTC10380
C2BMF33020
C2BTC10770
C2BIN21410
C2BIN21420
C2BMF33170
C2BMF33100
C2BCN25310
C2BIN21510
C2BMF30750
C2BIN27860
C2BIN27870
C2BIN28480
C2BIN28540
C2BCN23210
C2BCN23310
C2BMF33070
C2BMF33080
C2BMF33090
C2BIN27630
C2BIN27670
C2BIN27680
C2BCN23010
C2BCN23110
C2BCN31010
C2BCN30630
C2BIN22810
C2BIN23010
C2BIN23120
C2BIN23210
C2BIN23310
C2BIN23410
C2BIN23420
C2BCN23920
C2BMF31150
C2BMF32190
C2BIN21430
C2BIN21440
C2BIN28010
C2BIN28040
C2BMF32200
C2BCN24130
C2BIN25220
C2BIN25230
C2BMF33110
C2BMF30990
C2BMF42720
C2BMF42750
C2BMF42780
C2BIN25810
C2BIN26110
C2BCN30820
C2BMF32110
C2BMF33130
C2BMF33140
C2BTC11100
C2BCN23820
C2BIN21810
C2BCN25510
C2BCN32730
C2BCN24030
C2BCN31020
C2BCN32530
C2BIN27310
C2BIN27410
C2BIN27520
C2BIN27930
C2BMF32180
C2BCN30730
C2BMF33150
C2BTC10670
C2BCN25330
C2BCN25360
C2BIN22610
C2BIN22710
C2BIN28260
C2BCN16530
C2BCN16540
C2BCN16730
C2BCN16740
C2BMF33160
C2BIN21820
C2BIN23510
C2BIN23620
C2BIN23710
C2BCN31110
C2BMF33180
C2BIN28500
C2BIN26010
C2BMF31110
C2BMF33190
C2BTC11110
C2BCN25340
C2BCN24140
C2BCN24040
C2BCN25620
C2BCN23930
C2BIN23910
C2BMF33200
C2BTC11000
C2BIN21910
C2BIN22010
C2BIN27710
C2BIN27720
C2BIN28490
C2BCN30840
C2BIN25910
C2BIN26210
C2BIN26310
C2BIN26910
C2BIN27010
C2BIN27110
C2BMF31070
C2BCN25530
C2BIN28440
C2BIN28460
C2BCN23610
C2BCN23710
C2BCN23430
C2BCN23530
C2BMF30650
C2BCN31120
C2BIN27120
C2BIN27130
C2BIN27140
C2BIN27150
C2BIN27760
C2BIN28380
C2BIN28280
C2BMF44400
C2BCN24150
C2BIN23810
C2BIN24010
C2BIN24120
C2BIN24210
C2BIN24310
C2BIN24510
C2BIN24520
C2BIN24530
C2BIN24540
C2BIN27910
C2BIN27920
C2BCN30850
C2BIN27880
C2BIN27890
C2BIN27900
C2BCN25810
C2BIN24810
C2BIN24910
C2BIN27580
C2BIN22720
C2BCN44080
C2BIN27750
C2BIN28510
C2BCN23620
C2BCN23720
C2BCN24050
C2BCN45050
C2BCN45060
C2BCN31130
C2BTC10950
C2BTC11350
C2BIN27590
C2BIN27620
C2BIN28420
C2BIN25410
C2BIN25510
C2BIN27570
C2BIN27600
C2BIN28450
C2BIN28470
C2BCN25740
C2BIN25610
C2BIN27770
C2BIN28300
C2BIN28520
C2BIN28290
C2BCN31140
C2BIN24410
C2BIN26410
C2BIN26510
C2BIN26610
C2BCN24160
C2BIN28240
C2BIN25620
C2BIN25630
C2BIN25640
C2BIN25650
C2BIN27850
C2BDS25320
C2BDS25420
C2BCN32920
C2BIN27820
C2BIN27830
C2BTC11310
C2BCN26130
C2BIN28400
C2BTC11270
C2BIN25010
C2BIN27790
C2BIN27800
C2BIN27810
C2BCN30860
C2BIN28360
C2BTC11300
C2BTC11010
C2BIN28430
C2BCN23630
C2BCN23730
C2BTC11260
C2BIN21710
C2BIN21720
C2BIN27530
C2BCN31330
C2BIN27690
C2BIN27700
C2BTC11230
C2BTC11370
C2BTC11360
C2BDS25340
C2BDS25440
C2BTC11280
C2BTC11330
C2BTC11290
C2BCN31530
C2BTC11340
C2BTC11320
C2BCN43340
C2BCN14110
C2BCN17310
C2BCN24310
C2BCN26310
C2BCN32210
C2BTC11410
C2BDS25220
C2BDS25520
C2BDS25620
C2BDS24220
C2BDS24320
C2BDS24420
C2BDS24520
C2BDS24620
C2BDS24720
C2BTC11060
C2BCN43350
C2BDS25240
C2BDS25540
C2BDS25640
C2BTC11070
C2BCN40110
C2BCN45200
C2BCN40120
Description
[WNS01] Prepare tender documents for Shortlisted Suppliers for NEWater Tanks
[WNS02] Prepare tender documents for Shortlisted Suppliers for Industrial Water Storage Tanks
[Prelim] Noise Monitoring Meter (Installation)
[Prelim] General Site Clearance & Setup
[Prelim] Establishment of Washing Bays
[Prelim] Establish Temporary Sanitary & Waste Disposal facility
[Prelim] Temporary Electricity Supply (Erection)
[Prelim] Erect Project Signboard
[Prelim] Operation & Maintenance of Radio Sets
[WNS01] List of Tenderers & Tender Packages for DB, Cable & Cable Raceway Works (Electrical)
[WNS01] RFQ, Bid Evaluation & Issuance of PO for NEWater Storage Tanks
[WNS02] RFQ, Bid Evaluation & Issuance of PO for Industrial Water Storage Tanks
[Prelim] Setting out Survey & Surveys during construction
[Prelim] Operation & Maintenance of the Temporary Access Road
[Prelim] Operation & Maintenance of Washing Bays
[Prelim] Operation & Maintenance of Temporary Sanitary & Waste Disposal facility
[Prelim] Temporary Electricity Supply (Maintenance)
[Prelim] Maintenance of Project Signboard
[WNS01] Prepare Tender documents for Aboveground Pipes & Valves
[WNS02] Prepare Tender documents for Lightning and Earthing Protection
[WNS03 | L1] List of Tenderers & Tender Packages for Transformer
[WNS03 | L1] Prepare Tender documents for Pipes & Valves
[WNS03 | L1] RFQ, Bid Evaluation & Issuance of PO - Lightning & Earthing Protection
[WNS01] RFQ, Bid Evaluation & Issuance of PO for Embeds & Underground Pipes
[WNS01] Prepare Tender documents for Lightning and Earthing Protection
[WNS05] RFQ, Bid Evaluation & Issuance of PO - Lightning and Earthing Protection
[WNS01] RFQ, Bid Evaluation & Issuance of PO for Electrical Manhole and Duct Bank Works
[WNS00] RFQ, Bid Evaluation & Issuance of PO for Electrical Manhole and Duct Bank Works
[WNS01] Piping quantity take-off for Aboveground Pipes & Valves
[WNS01] Prepare Tender documents for DB, Cable & Cable Raceway Works (Electrical)
[WNS03 | L1] Prepare Tender documents for NEWater, IW & Sump Pumps
[Prelim] Contractor Site Office : Erection of Office, E&M, Plumbing & Sanitary and Finishing Works
[WNS03 | ROOF] List of Tenderers & Tender Packages for ACMV System
[WNS03 | ROOF] List of Tenderers & Tender Packages for Fire Protection System
[WNS03 | ROOF] List of Tenderers & Tender Packages for Plumbing and Sanitary System
[WNS03 | ROOF] List of Tenderers & Tender Packages for ELV System
[WNS03 | L1] Prepare Tender documents for Transformer
[WNS03 | L1] List of Tenderers & Tender Packages for EOT Crane Temporary Power Supply Works
[WNS03 | L1] Pipes & Valves quantity take-off
[WNS01] RFQ, Bid Evaluation & Issuance of PO for Lightning and Earthing Protection
[Prelim] Contractor Site Office maintenance
[Prelim] Noise Monitoring Meter (Maintenance)
[WNS04] Prepare Tender documents for MCC & DB
[WNS03 | L1] Prepare Tender documents for Cable & Cable Raceway Works (Electrical)
[WNS05] List of Tenderers & Tender Packages for Building Services
[WNS05] Prepare & Submit : Lightning and Earthing Protection Design
[WNS03 | L1] List of Tenderers & Tender Packages for Surge Vessels
[WNS01] RFQ, Bid Evaluation & Issuance of PO for Aboveground Pipes & Valves
[WNS03 | L1] RFQ, Bid Evaluation & Issuance of PO - NEWater, IW & Sump Pumps
[WNS03 | ROOF] Prepare Tender documents for ACMV System
[WNS03 | ROOF] Prepare Tender documents for Fire Protection System
[WNS03 | ROOF] Prepare Tender documents for Plumbing and Sanitary System
[WNS03 | ROOF] Prepare Tender documents for ELV System
[WNS03 | L1] Prepare Tender documents for EOT Crane Temporary Power Supply Works
[Prelim] Operation & Maintenance of ECM
[WNS01] Prepare & Submit : Water Hammer Analysis, Vibration Analysis, CFD & Hydraulic Calculation
[WNS02] Prepare & Submit : Water Hammer Analysis, Vibration Analysis, CFD & Hydraulic Calculation
[WNS00] Prepare Tender documents for Bonding & Earthing Works
[WNS03 | L1] RFQ, Bid Evaluation & Issuance of PO - Transformer
[WNS03 | L1] List of Tenderers & Tender Packages for EOT Cranes
[WNS03 | L2] List of Tenderers & Tender Packages for Switchgear, MCC & MDB
[WNS01] RFQ, Bid Evaluation & Issuance of PO for DB, Cable & Cable Raceway Works (Electrical)
[WNS02] RFQ, Bid Evaluation & Issuance of PO for Lightning and Earthing Protection
[WNS01] List of Tenderers & Tender Packages for Lighting Works
[WNS02] List of Tenderers & Tender Packages for Lighting Works
[WNS03] [GLA to GLD / GL1 to GL8] Install Bored Piles (57 nos.)
[WNS03] [GLA to GLD / GL8 to GL14] Install Bored Piles (43 nos.)
[WNS05] Prepare Tender documents for Building Services
[WNS04] RFQ, Bid Evaluation & Issuance of PO - MCC & DB
[WNS03 | L1] RFQ, Bid Evaluation & Issuance of PO - Cable & Cable Raceway Works (Electrical)
[WNS01] [Tank 1 | GL1/A] Install Bored Piles (36 nos.)
[WNS01] [Tank 2 | GL1/B] Install Bored Piles (36 nos.)
[WNS01] [UG Pipe Rack] Install Bored Piles - Part 1 (22 nos.)
[WNS03 | L1] Prepare Tender documents for Surge Vessels
[WNS03 | L1] RFQ, Bid Evaluation & Issuance of PO - Pipes & Valves
[WNS03 | L2] RFQ, Bid Evaluation & Issuance of PO - Lightning & Earthing Protection
[WNS04] List of Tenderers & Tender Packages for FRP Storage Tank (Sodium Hypochlorite)
[WNS03 | L1] Prepare Tender documents for EOT Cranes
[WNS03 | L2] Prepare Tender documents for Switchgear, MCC & MDB
[WNS03 | ROOF] RFQ, Bid Evaluation & Issuance of PO - ACMV System
[WNS03 | ROOF] RFQ, Bid Evaluation & Issuance of PO - Fire Protection System
[WNS03 | ROOF] RFQ, Bid Evaluation & Issuance of PO - Plumbing and Sanitary System
[WNS03 | ROOF] RFQ, Bid Evaluation & Issuance of PO - ELV System
[WNS04] List of Tenderers & Tender Packages for Chemical Dosing System (Sodium Hypochlorite)
[WNS04] List of Tenderers & Tender Packages for FRP Storage Tank (Ammonium Sulphate)
[WNS04] List of Tenderers & Tender Packages for Chemical Dosing System (Ammonium Sulphate)
[WNS04] List of Tenderers & Tender Packages for FRP Storage Tank (Sodium Hydroxide)
[WNS04] List of Tenderers & Tender Packages for Chemical Dosing System (Sodium Hydroxide)
[WNS01] Material Purchase and Fabrication for Electrical Manhole and Duct Bank
[WNS01] Prepare Tender documents for Lighting Works
[WNS02] Prepare Tender documents for Lighting Works
[WNS03 | L1] RFQ, Bid Evaluation & Issuance of PO for EOT Crane Temporary Power Supply Works
[WNS00] RFQ, Bid Evaluation & Issuance of PO for Bonding & Earthing Works
[WNS00] Material Purchase and Fabrication for Electrical Manhole and Duct Bank
[WNS03 | L1] Prepare & Submit : NEWater, IW and Sump Pumps Design
[WNS01] [Tank GL1/A | 1/B] Material Purchase and Fabrication for Embeds & Underground Pipes
[WNS03 | L1] Prepare & Submit : Transformer Design
[WNS05] List of Tenderers & Tender Packages for Lime Dosing Piping Works & Valves
[WNS05] RFQ, Bid Evaluation & Issuance of PO - Building Services
[WNS01] Prepare & Submit : DB, Cable & Cable Raceway Works (Electrical) Design
[WNS01] List of Tenderers & Tender Packages for ICA Works
[WNS03 | L1] Prepare & Submit : Cable & Cable Raceway Works (Electrical) Design
[WNS04] Prepare Tender documents for FRP Storage Tank (Sodium Hypochlorite)
[WNS04] Prepare Tender documents for Chemical Dosing System (Sodium Hypochlorite)
[WNS04] Prepare Tender documents for FRP Storage Tank (Ammonium Sulphate)
[WNS04] Prepare Tender documents for Chemical Dosing System (Ammonium Sulphate)
[WNS04] Prepare Tender documents for FRP Storage Tank (Sodium Hydroxide)
[WNS04] Prepare Tender documents for Chemical Dosing System (Sodium Hydroxide)
[WNS04] Prepare Tender documents for Lightning and Earthing Protection Works
[WNS03 | L1] List of Tenderers & Tender Packages for Lighting Works
[WNS01] [UG Pipe Rack] Install Bored Piles - Part 2 (16 nos.)
[WNS01] Material Purchase and Fabrication for NEWater Storage Tanks No. 1 & 2
[WNS01] Review, Resubmission & Acceptance : Shop Drawings for Architectural Works
[WNS03 | L1] RFQ, Bid Evaluation & Issuance of PO - Surge Vessels
[WNS01] RFQ, Bid Evaluation & Issuance of PO for Lighting Works
[WNS02] RFQ, Bid Evaluation & Issuance of PO for Lighting Works
[WNS02] Piping quantity take-off for Pipes & Valves
[WNS05] Prepare Tender documents for Lime Silos
[WNS00] Prepare Tender documents for Pipes & Valves
[WNS03 | L1] Prepare & Submit : Pipes & Valves Design
[WNS03 | L1] RFQ, Bid Evaluation & Issuance of PO - EOT Cranes
[WNS03 | L2] RFQ, Bid Evaluation & Issuance of PO - Switchgear, MCC & MDB
[WNS05] Prepare Tender documents for Lime Saturators
[WNS05] Prepare Tender documents for Lime Slurry Transfer, Lime Sludge Transfer and Lime Dosing Pumps
[WNS03 | L3] List of Tenderers & Tender Packages for Cable & Cable Raceway Works (Electrical)
[WNS03 | ROOF] Prepare & Submit : ACMV System Design
[WNS03 | ROOF] Prepare & Submit : Fire Protection System Design
[WNS03 | ROOF] Prepare & Submit : Plumbing and Sanitary System Design
[WNS03 | ROOF] Prepare & Submit : ELV System Design
[WNS04] Prepare Tender documents for Piping Works (Sodium Hypochlorite)
[WNS05] Prepare Tender documents for Lime Dosing Piping Works & Valves
[WNS04] Prepare Tender documents for Piping Works (Ammonium Sulphate)
[WNS04] Prepare Tender documents for Piping Works (Sodium Hydroxide)
[WNS03 | L2] Prepare Tender documents for Cable & Cable Raceway Works (Electrical)
[WNS00] Prepare & Submit : Bonding & Earthing Works Design
[WNS01] [Tank 4 | GL2/B] Install Bored Piles (36 nos.)
[WNS01] [Tank 3 | GL2/A] Install Bored Piles (36 nos.)
[WNS03 | L2] Prepare & Submit : Lightning and Earthing Protection Equipment
[WNS03 | L1] Prepare Tender documents for Lighting Works
[WNS01] Prepare & Submit : Electrical System Analysis
[WNS02] Review, Resubmission & Acceptance : Shop Drawings for Architectural Works
[WNS04] Review, Resubmission & Acceptance : Shop Drawings for Architectural Works
[WNS03] [GLD to GLG / GL7 to GL13] Install Bored Piles (37 nos.)
[WNS03 | L2] List of Tenderers & Tender Packages for Telemetry System
[WNS01] Prepare Tender documents for ICA Works
[WNS04] RFQ, Bid Evaluation & Issuance of PO - Lightning and Earthing Protection Works
[WNS03 | L1] Prepare & Submit : EOT Crane Temporary Power Supply Works Design
[WNS00] List of Tenderers & Tender Packages for Cable & Cable Raceway Works (ICA)
[WNS00] Prepare Tender documents for Cable & Cable Raceway Works (Electrical)
[WNS04] Prepare Tender documents for Building Services
[WNS01] [Tank GL2/A | 2/B] Material Purchase and Fabrication for Embeds & Underground Pipes
[WNS04] RFQ, Bid Evaluation & Issuance of PO - FRP Storage Tank (Sodium Hypochlorite)
[WNS00] Pipes & Valves quantity take-off
[WNS04] RFQ, Bid Evaluation & Issuance of PO - Chemical Dosing System (Sodium Hypochlorite)
[WNS05] Prepare & Submit : Building Services Design
[WNS04] RFQ, Bid Evaluation & Issuance of PO - FRP Storage Tank (Ammonium Sulphate)
[WNS04] RFQ, Bid Evaluation & Issuance of PO - Chemical Dosing System (Ammonium Sulphate)
[WNS04] RFQ, Bid Evaluation & Issuance of PO - FRP Storage Tank (Sodium Hydroxide)
[WNS04] RFQ, Bid Evaluation & Issuance of PO - Chemical Dosing System (Sodium Hydroxide)
[WNS04] Piping quantity take-off (Sodium Hypochlorite)
[WNS05] RFQ, Bid Evaluation & Issuance of PO - Lime Silos
[WNS04] Piping quantity take-off (Ammonium Sulphate)
[WNS04] Piping quantity take-off (Sodium Hydroxide)
[WNS05] RFQ, Bid Evaluation & Issuance of PO - Lime Saturators
[WNS05] RFQ, Bid Evaluation & Issuance of PO - Lime Slurry Transfer, Lime Sludge Transfer and Lime Dosing Pumps
[WNS03 | L3] Prepare Tender documents for Cable & Cable Raceway Works (Electrical)
[WNS03 | L3] List of Tenderers & Tender Packages for Lightning & Earthing Protection
[WNS05] Material Purchase and Fabrication for Lightning and Earthing Protection
[WNS03] Review, Resubmission & Acceptance : Shop Drawings for Architectural Works
[WNS05] Review, Resubmission & Acceptance : Shop Drawings for Architectural Works
[WNS05] Lime Dosing Piping Works & Valves quantity take-off
[WNS03 | L2] Prepare Tender documents for RIO & UPSDB Panel
[WNS01] Installation of Electrical Manhole and Duct Bank
[WNS03] [GLD to GLG / GL1 to GL7] Install Bored Piles (30 nos.)
[WNS03 | L1] Installation of Lightning and Earthing Protection Equipment (Pump House) - Underground
[WNS03] Ground Instrumentation by Instrumentation & Monitoring Contractor
[WNS01] [Tank 1 | GL1/A] Construct Ground Slab
[WNS01] [Tank 2 | GL1/B] Construct Ground Slab
[WNS02] RFQ, Bid Evaluation & Issuance of PO for Pipes & Valves
[WNS04] List of Tenderers & Tender Packages for RIO & UPSDB Panels
[WNS03 | L2] Prepare Tender documents for Telemetry System
[WNS03 | L2] RFQ, Bid Evaluation & Issuance of PO - Cable & Cable Raceway Works (Electrical)
[WNS01] Material Purchase and Fabrication for Aboveground Pipes & Valves
[WNS01] [Tank 1 | GL1/A] Embeds & Underground Pipes Works
[WNS01] [Tank 2 | GL1/B] Embeds & Underground Pipes Works
[WNS03 | L2] Prepare & Submit : Switchgear, MCC & MDB Design
[WNS05] List of Tenderers & Tender Packages for Transformer
[WNS00] Prepare Tender documents for Cable & Cable Raceway Works (ICA)
[WNS01] Prepare & Submit : Lighting Works Design
[WNS02] Prepare & Submit : Lighting Works Design
[WNS02] Prepare & Submit : Electrical System Analysis
[WNS04] RFQ, Bid Evaluation & Issuance of PO - Building Services
[WNS05] Prepare Tender documents for Lime Slurry, Saturated Lime & Lime Sludge Holding Tanks
[WNS03 | L4] Prepare Tender documents for Switchgear, MCC & MDB
[WNS03 | L4] Prepare Tender documents for High Voltage & Low Voltage VFD
[WNS01] Material Purchase and Fabrication for NEWater Storage Tanks No. 3 & 4
[WNS03 | L1] RFQ, Bid Evaluation & Issuance of PO for Lighting Works
[WNS03 | L2] List of Tenderers & Tender Packages for Lighting Works
[WNS03 | L1] List of Tenderers & Tender Packages for Cable & Cable Raceway Works (ICA)
[WNS03 | L1] Prepare & Submit : Surge Vessel Design
[WNS01] RFQ, Bid Evaluation & Issuance of PO for ICA Works
[WNS00] RFQ, Bid Evaluation & Issuance of PO - Cable & Cable Raceway Works (Electrical)
[WNS03 | L2] Prepare Tender documents for Cable & Cable Raceway Works (ICA)
[WNS03 | L3] Prepare Tender documents for Lightning & Earthing Protection
[WNS03 | L4] List of Tenderers & Tender Packages for Cable & Cable Raceway Works (ICA)
[WNS03 | L1] Prepare & Submit : EOT Cranes Design
[WNS00] RFQ, Bid Evaluation & Issuance of PO - Pipes & Valves
[WNS01] Delivery to Site for NEWater Storage Tanks No. 1 & 2
[WNS04] Prepare & Submit : Lightning and Earthing Protection Works Design
[WNS02] Material Purchase and Fabrication for Lightning and Earthing Protection
[WNS03 | L1] Material Purchase and Fabrication for NEWater, IW & Sump Pumps
[WNS04] RFQ, Bid Evaluation & Issuance of PO - Piping Works (Sodium Hypochlorite)
[WNS04] Prepare Tender documents for RIO & UPSDB Panels
[WNS04] RFQ, Bid Evaluation & Issuance of PO - Piping Works (Sodium Hydroxide)
[WNS03 | L2] RFQ, Bid Evaluation & Issuance of PO - RIO & UPSDB Panel
[WNS03] [GLA to GLD / GL1 to GL8] Strutted Excavate to FEL
[WNS03] [GLA to GLD / GL8 to GL14] Strutted Excavate to FEL
[WNS05] Prepare & Submit : Lime Silos Design
[WNS05] Prepare Tender documents for Transformer
[WNS04] Prepare & Submit : FRP Storage Tank Design (Sodium Hypochlorite)
[WNS04] Prepare & Submit : Chemical Dosing System Design (Sodium Hypochlorite)
[WNS04] Prepare & Submit : FRP Storage Tank Design (Ammonium Sulphate)
[WNS04] Prepare & Submit : Chemical Dosing System Design (Ammonium Sulphate)
[WNS04] Prepare & Submit : FRP Storage Tank Design (Sodium Hydroxide)
[WNS04] Prepare & Submit : Chemical Dosing System Design (Sodium Hydroxide)
[WNS04] RFQ, Bid Evaluation & Issuance of PO - Piping Works (Ammonium Sulphate)
[WNS05] Prepare & Submit : Lime Saturator Design
[WNS05] Prepare & Submit : Lime Slurry Transfer, Lime Sludge Transfer and Lime Dosing Pumps Design
[WNS03 | L4] Prepare Tender documents for Cable & Cable Raceway Works (Electrical)
[WNS03 | L3] Prepare Tender documents for Lighting Works
[WNS03 | L4] List of Tenderers & Tender Packages for Lighting Works
[WNS01] [Tank GL3/B] Install Bored Piles (36 nos.)
[WNS01] [Tank GL3/A] Install Bored Piles (36 nos.)
[WNS01] Installation of Lightning and Earthing Protection Equipment (for NW Tank No. 1 & 2)
[WNS03 | L1] Prepare Tender documents for Instruments
[WNS03 | L3] RFQ, Bid Evaluation & Issuance of PO - Cable & Cable Raceway Works (Electrical)
[WNS03 | L2] Prepare Tender documents for Lighting Works
[WNS01] [Tank GL3/A | 3/B] Material Purchase and Fabrication for Embeds & Underground Pipes
[WNS03 | L1] Material Purchase and Fabrication for Cable & Cable Raceway Works (Electrical)
[WNS05] RFQ, Bid Evaluation & Issuance of PO - Lime Dosing Piping Works & Valves
[WNS00] RFQ, Bid Evaluation & Issuance of PO - Cable & Cable Raceway Works (ICA)
[WNS03 | L1] Prepare Tender documents for Cable & Cable Raceway Works (ICA)
[WNS03 | L2] RFQ, Bid Evaluation & Issuance of PO - Telemetry System
[WNS05] RFQ, Bid Evaluation & Issuance of PO - Lime Slurry, Saturated Lime & Lime Sludge Holding Tanks
[WNS03 | L4] RFQ, Bid Evaluation & Issuance of PO - Switchgear, MCC & MDB
[WNS03 | L4] RFQ, Bid Evaluation & Issuance of PO - High Voltage & Low Voltage VFD
[WNS03 | L4] Prepare Tender documents for Cable & Cable Raceway Works (ICA)
[WNS03 | L2] Prepare & Submit : Cable & Cable Raceway Works (Electrical) Design
[WNS04] Prepare Tender documents for Cable & Cable Raceway Works (ICA)
[WNS04] Prepare Tender documents for Instruments
[WNS05] Prepare Tender documents for RIO & UPSDB Panels
[WNS05] Prepare Tender documents for Instruments
[WNS05] Prepare Tender documents for Cable & Cable Raceway Works (ICA)
[WNS04] Prepare & Submit : Building Services Design
[WNS05] Prepare Tender documents for Air Compressor Package
[WNS03 | L2] RFQ, Bid Evaluation & Issuance of PO - Cable & Cable Raceway Works (ICA)
[WNS05] Prepare Tender documents for MCC & DB
[WNS05] Prepare Tender documents for Cable & Cable Raceway Works (Electrical)
[WNS03 | L1] Installation of Lightning and Earthing Protection Equipment (Electrical Building) - Underground
[WNS03] [GLA to GLD / GL1 to GL8] Construct Basement Slab / Floor Drain Pit
[WNS03] [GLA to GLD / GL8 to GL14] Construct Basement Slab / Pump Valve Chamber
[WNS01] Material Purchase and Fabrication for DB, Cable & Cable Raceway Works (Electrical)
[WNS03 | L1] Material Purchase and Fabrication for Transformer
[WNS03 | L3] RFQ, Bid Evaluation & Issuance of PO - Lightning & Earthing Protection
[WNS03 | L4] Prepare Tender documents for Lighting Works
[WNS05] [Lime Bldg | GLA to GLC / GL1 to GL4] Install Bored Piles (36 nos.)
[WNS02] Prepare & Submit : Pipes & Valves Design
[WNS00] Prepare & Submit : Cable & Cable Raceway Works (Electrical) Design
[WNS03 | L1] Material Purchase and Fabrication for Pipes & Valves
[WNS03 | L3] Prepare Tender documents for Cable & Cable Raceway Works (ICA)
[WNS03 | L4] RFQ, Bid Evaluation & Issuance of PO - Cable & Cable Raceway Works (Electrical)
[WNS03 | L4] List of Tenderers & Tender Packages for RIO & UPSDB Panel
[WNS03 | L3] RFQ, Bid Evaluation & Issuance of PO for Lighting Works
[WNS01] [Tank 3 | GL2/A] Embeds & Underground Pipes Works
[WNS01] [Tank 4 | GL2/B] Embeds & Underground Pipes Works
[WNS01] Prepare & Submit : Instrumentation, Control & Automation works Design
[WNS04] Prepare & Submit : Pipes and Valves Design (Sodium Hypochlorite)
[WNS00] Prepare & Submit : Pipes & Valves Design
[WNS02] List of Tenderers & Tender Packages for ICA Works
[WNS04] Prepare & Submit : Pipes and Valves Design (Sodium Hydroxide)
[WNS03 | L2] Prepare & Submit : RIO & UPSDB Panels Design
[WNS03 | L1] Prepare & Submit : Lighting Works Design
[WNS03 | L1] List of Tenderers & Tender Packages for Automatic Lubrication System
[WNS04] RFQ, Bid Evaluation & Issuance of PO - RIO & UPSDB Panels
[WNS05] RFQ, Bid Evaluation & Issuance of PO - Transformer
[WNS03 | L1] RFQ, Bid Evaluation & Issuance of PO - Instruments
[WNS00] Material Purchase and Fabrication for Bonding & Earthing Works
[WNS03 | L4] RFQ, Bid Evaluation & Issuance of PO - Cable & Cable Raceway Works (ICA)
[WNS05] RFQ, Bid Evaluation & Issuance of PO - RIO & UPSDB Panels
[WNS05] RFQ, Bid Evaluation & Issuance of PO - Instruments
[WNS05] RFQ, Bid Evaluation & Issuance of PO - Cable & Cable Raceway Works (ICA)
[WNS03 | L2] RFQ, Bid Evaluation & Issuance of PO for Lighting Works
[WNS03 | ROOF] List of Tenderers & Tender Packages for Cable & Cable Raceway Works (Electrical)
[WNS01] [Tank 3 | GL2/A] Construct Ground Slab
[WNS01] [Tank 4 | GL2/B] Construct Ground Slab
[WNS03] [GLD to GLG / GL1 to GL7] Construct Pump Cable Trench
[WNS03] [GLD to GLG / GL7 to GL13] Construct Pump Cable Trench
[WNS02] Prepare Tender documents for DB, Cable & Cable Raceway Works (Electrical)
[WNS03 | L1] RFQ, Bid Evaluation & Issuance of PO - Cable & Cable Raceway Works (ICA)
[WNS04] Prepare & Submit : Pipes and Valves Design (Ammonium Sulphate)
[WNS05] Prepare & Submit : Lime Slurry, Saturated Lime & Lime Sludge Holding Tanks Design
[WNS05] RFQ, Bid Evaluation & Issuance of PO - Air Compressor Package
[WNS03 | L4] Prepare Tender documents for Lightning & Earthing Protection
[WNS03 | ROOF] List of Tenderers & Tender Packages for Lightning & Earthing Protection
[WNS04] RFQ, Bid Evaluation & Issuance of PO - Cable & Cable Raceway Works (ICA)
[WNS04] RFQ, Bid Evaluation & Issuance of PO - Instruments
[WNS05] RFQ, Bid Evaluation & Issuance of PO - MCC & DB
[WNS05] RFQ, Bid Evaluation & Issuance of PO - Cable & Cable Raceway Works (Electrical)
[WNS03 | L4] Prepare & Submit : Switchgear, MCC & MDB Design
[WNS03 | L4] Prepare & Submit : High Voltage & Low Voltage VFD Design
[WNS01] Delivery to Site for NEWater Storage Tanks No. 3 & 4
[WNS03 | L2] Prepare & Submit : Telemetry System Design
[WNS00] Prepare & Submit : Cable & Cable Raceway Works (ICA) Design
[WNS03 | L4] Prepare Tender documents for RIO & UPSDB Panel
[WNS04] Prepare Tender documents for Cable & Cable Raceway Works (Electrical)
[WNS03 | L3] Prepare & Submit : Cable & Cable Raceway Works (Electrical) Design
[WNS03] [GLA to GLD / GL1 to GL8] Construct Vertical Elements to SFL 5.30
[WNS03] [GLA to GLD / GL8 to GL14] Construct Vertical Elements to SFL 5.30
[WNS01] [Tank 1 | GL1/A] Wall Panels Installation for NW Tank 1
[WNS01] [Tank 2 | GL1/B] Wall Panels Installation for NW Tank 2
[WNS03 | ROOF] Material Purchase and Fabrication for ACMV System
[WNS05] Prepare & Submit : Lime Dosing Piping Works & Valves
[WNS03 | ROOF] Material Purchase and Fabrication for Fire Protection System
[WNS03 | ROOF] Material Purchase and Fabrication for Plumbing and Sanitary System
[WNS03 | ROOF] Material Purchase and Fabrication for ELV System
[WNS03 | L2] Prepare & Submit : Cable & Cable Raceway Works (ICA) Design
[WNS03 | L1] Material Purchase and Fabrication for EOT Crane Temporary Power Supply Works
[WNS05] [Elec Bldg] Install Bored Piles (15 nos.)
[WNS01] RFQ, Bid Evaluation & Issuance of PO for Active Tank Mixers for NEWater Tanks
[WNS02] Prepare Tender documents for ICA Works
[WNS03 | L3] RFQ, Bid Evaluation & Issuance of PO - Cable & Cable Raceway Works (ICA)
[WNS03 | L4] RFQ, Bid Evaluation & Issuance of PO for Lighting Works
[WNS03 | L1] Prepare Tender documents for Automatic Lubrication System
[WNS05] Material Purchase and Fabrication for Building Services
[WNS03 | L2] Material Purchase and Fabrication for Lightning & Earthing Protection
[WNS03 | L3] Prepare & Submit : Lightning and Earthing Protection Equipment
[WNS03 | L4] Prepare & Submit : Cable & Cable Raceway Works (Electrical) Design
[WNS03 | ROOF] Prepare Tender documents for Cable & Cable Raceway Works (Electrical)
[WNS04] List of Tenderers & Tender Packages for Lighting Works
[WNS03 | L3] Prepare & Submit : Lighting Works Design
[WNS01] Installation of Lightning and Earthing Protection Equipment (for NW Tank No. 3 & 4)
[WNS03 | L1] Material Purchase and Fabrication for Surge Vessels
[WNS03 | L1] Prepare Tender documents for RIO & UPSDB Panel
[WNS03 | ROOF] Prepare Tender documents for Lightning & Earthing Protection
[WNS03] [GLD to GLG / GL1 to GL7] Construct Ground Beams & Slabs at SFL 5.30
[WNS03] [GLD to GLG / GL7 to GL13] Construct Ground Beams & Slabs at SFL 5.30
[WNS03 | L1] Material Purchase and Fabrication for EOT Cranes
[WNS03 | L1] Prepare & Submit : Instruments Design
[WNS05] Prepare & Submit : Transformer Design
[WNS05] Prepare & Submit : RIO & UPSDB Panels Design
[WNS02] RFQ, Bid Evaluation & Issuance of PO for DB, Cable & Cable Raceway Works (Electrical)
[WNS03 | L4] RFQ, Bid Evaluation & Issuance of PO - Lightning & Earthing Protection
[WNS04] RFQ, Bid Evaluation & Issuance of PO - Cable & Cable Raceway Works (Electrical)
[WNS05] Prepare & Submit : Instruments Design
[WNS05] Prepare & Submit : Cable & Cable Raceway Works (ICA) Design
[WNS05] [Lime Silo] Install Bored Piles (28 nos.)
[WNS05] Installation of Lightning and Earthing Protection Equipment (Electrical Building) - Underground
[WNS03 | L2] Material Purchase and Fabrication for Switchgear, MCC & MDB
[WNS05] Prepare & Submit : Air Compressor Package Design
[WNS02] Material Purchase and Fabrication for Industrial Water Storage Tanks
[WNS03 | L4] Prepare & Submit : Cable & Cable Raceway Works (ICA) Design
[WNS05] Prepare & Submit : MCC & DB Design
[WNS05] Prepare & Submit : Cable & Cable Raceway Works (Electrical) Design
[WNS03 | L2] Prepare & Submit : Lighting Works Design
[WNS05] [Lime Bldg | GLA to GLC / GL4 to GL6] Install Bored Piles (36 nos.)
[WNS03] [GLA to GLD / GL1 to GL8] Construct Ground Beams & Slabs at SFL 5.30
[WNS03] [GLA to GLD / GL8 to GL14] Construct Ground Beams & Slabs at SFL 5.30
[WNS01] [Tank GL3/A] Embeds & Underground Pipes Works
[WNS01] [Tank GL3/B] Embeds & Underground Pipes Works
[WNS03 | L1] Prepare & Submit : Cable & Cable Raceway Works (ICA) Design
[WNS03 | L4] RFQ, Bid Evaluation & Issuance of PO - RIO & UPSDB Panel
[WNS04] Prepare & Submit : Instruments Design
[WNS04] Prepare & Submit : Cable & Cable Raceway Works (ICA) Design
[WNS04] Prepare Tender documents for Lighting Works
[WNS04] Prepare & Submit : RIO & UPSDB Panels Design
[WNS03] [GLD to GLG / GL1 to GL7] Construct Columns to SFL 9.80
[WNS03] [GLD to GLG / GL7 to GL13] Construct Columns to SFL 9.80
[WNS03] [GLD to GLG / GL1 to GL7] Construct Drainage / Utility Trench
[WNS03] [GLD to GLG / GL7 to GL13] Construct Drainage / Utility Trench
[WNS03 | Electrical Building] Install Internal Walls to SFL 5.30
[WNS02] RFQ, Bid Evaluation & Issuance of PO for ICA Works
[WNS05] Material Purchase and Fabrication for Lime Silos
[WNS03 | L1] RFQ, Bid Evaluation & Issuance of PO - RIO & UPSDB Panel
[WNS05] Material Purchase and Fabrication for Lime Saturators
[WNS05] Material Purchase and Fabrication for Lime Slurry Transfer, Lime Sludge Transfer and Lime Dosing Pumps
[WNS04] Material Purchase and Fabrication for Lightning and Earthing Protection Works
[WNS03 | L1] RFQ, Bid Evaluation & Issuance of PO - Automatic Lubrication System
[WNS01] [Tank 1 | GL1/A] Dome Roof Installation for NW Tank 1
[WNS01] [Tank 2 | GL1/B] Dome Roof Installation for NW Tank 2
[WNS04] Prepare & Submit : MCC & DB Design
[WNS03 | L3] Prepare & Submit : Cable & Cable Raceway Works (ICA) Design
[WNS03 | ROOF] RFQ, Bid Evaluation & Issuance of PO - Cable & Cable Raceway Works (Electrical)
[WNS05] Prepare Tender documents for Lighting Works
[WNS04] Material Purchase and Fabrication for FRP Storage Tank (Sodium Hypochlorite)
[WNS04] Material Purchase and Fabrication for Chemical Dosing System (Sodium Hypochlorite)
[WNS04] Material Purchase and Fabrication for Chemical Dosing System (Sodium Hydroxide)
[WNS03 | L2] Material Purchase and Fabrication for RIO & UPSDB Panel
[WNS03 | L4] Prepare & Submit : Lighting Works Design
[WNS01] [Tank GL3/A] Construct Ground Slab
[WNS01] [Tank GL3/B] Construct Ground Slab
[WNS02] Material Purchase and Fabrication for Pipes & Valves
[WNS03 | L2] Material Purchase and Fabrication for Cable & Cable Raceway Works (Electrical)
[WNS03 | ROOF] RFQ, Bid Evaluation & Issuance of PO - Lightning & Earthing Protection
[WNS02] Prepare & Submit : DB, Cable & Cable Raceway Works (Electrical) Design
[WNS04] Material Purchase and Fabrication for FRP Storage Tank (Ammonium Sulphate)
[WNS04] Material Purchase and Fabrication for Chemical Dosing System (Ammonium Sulphate)
[WNS04] Material Purchase and Fabrication for FRP Storage Tank (Sodium Hydroxide)
[WNS03 | L4] Prepare & Submit : Lightning and Earthing Protection Equipment
[WNS04] Prepare & Submit : Cable & Cable Raceway Works (Electrical) Design
[WNS01] Installation of Aboveground Pipes & Valves
[WNS03] [GLD to GLG / GL1 to GL7] Construct Beams & Slabs at SFL 9.80
[WNS03] [GLD to GLG / GL7 to GL13] Construct Beams & Slabs at SFL 9.80
[WNS01] Material Purchase and Fabrication for ICA Works
[WNS04] RFQ, Bid Evaluation & Issuance of PO for Lighting Works
[WNS03 | L4] Prepare & Submit : RIO & UPSDB Panels Design
[WNS03 | L1] Material Purchase and Fabrication for Lighting Works
[WNS05] RFQ, Bid Evaluation & Issuance of PO for Lighting Works
[WNS03 | Pump Station] Install Internal Walls to SFL 5.30
[WNS03] [GLA to GLD / GL1 to GL8] Construct Columns to SFL 12.20
[WNS03] [GLA to GLD / GL8 to GL14] Construct Columns to SFL 12.20
[WNS03] [GLA to GLD / GL1 to GL8] Construct Drainage / Utility Trench
[WNS03] [GLA to GLD / GL8 to GL14] Construct Drainage / Utility Trench
[WNS01] [Tank 3 | GL2/A] Wall Panels Installation for NW Tank 3
[WNS01] [Tank 4 | GL2/B] Wall Panels Installation for NW Tank 4
[WNS03 | L1] Cable Raceway Installation (Electrical)
[WNS00 | WNS01] Install Bored Piles (26 nos.)
[WNS04] Material Purchase and Fabrication for Building Services
[WNS03 | L4] Material Purchase and Fabrication for Switchgear, MCC & MDB
[WNS03 | L4] Material Purchase and Fabrication for High Voltage & Low Voltage VFD
[WNS05] [Elec Bldg] Construct Ground Beams & Slabs at SFL 5.30
[WNS03 | L2] Material Purchase and Fabrication for Telemetry System
[WNS04] Material Purchase and Fabrication for Piping Works (Sodium Hypochlorite)
[WNS00] Material Purchase and Fabrication for Pipes & Valves
[WNS04] Material Purchase and Fabrication for Piping Works (Sodium Hydroxide)
[WNS01] Installation of Lighting Works at NW Tank No. 1
[WNS01] Installation of Lighting Works at NW Tank No. 2
[WNS01] Material Purchase and Fabrication for Active Tank Mixers for NEWater Tanks
[WNS02] Prepare & Submit : Instrumentation, Control & Automation works Design
[WNS00] Material Purchase and Fabrication for Cable & Cable Raceway Works (Electrical)
[WNS05] Material Purchase and Fabrication for Lime Slurry, Saturated Lime & Lime Sludge Holding Tanks
[WNS01] Cable Laying to NW Tank No. 1 (Electrical)
[WNS01] Cable Laying to NW Tank No. 2 (Electrical)
[WNS05] Installation of Lightning and Earthing Protection Equipment (Lime Building) - Underground
[WNS03 | L2] Material Purchase and Fabrication for Cable & Cable Raceway Works (ICA)
[WNS03 | Electrical Building] Install External Walls to SFL 9.80
[WNS00 | WNS02] Install Bored Piles (14 nos.)
[WNS04] Material Purchase and Fabrication for Piping Works (Ammonium Sulphate)
[WNS03 | ROOF] Prepare & Submit : Cable & Cable Raceway Works (Electrical) Design
[WNS05] [Lime Bldg] Construct Ground Beams & Slabs at SFL 5.30
[WNS03 | L1] Material Purchase and Fabrication for Instruments
[WNS03 | L3] Material Purchase and Fabrication for Cable & Cable Raceway Works (Electrical)
[WNS03] [GLA to GLD / GL1 to GL8] Construct Beams & Slabs at SFL 12.20
[WNS03] [GLA to GLD / GL8 to GL14] Construct Beams & Slabs at SFL 12.20
[WNS05] Material Purchase and Fabrication for Lime Dosing Piping Works & Valves
[WNS00] Material Purchase and Fabrication for Cable & Cable Raceway Works (ICA)
[WNS04] Prepare & Submit : Lighting Works Design
[WNS03] [GLD to GLG / GL1 to GL7] Construct Beams & Slabs at SFL 12.20
[WNS03] [GLD to GLG / GL7 to GL13] Construct Beams & Slabs at SFL 12.20
[WNS05] Material Purchase and Fabrication for Transformer
[WNS03 | L1] FAT & Inspection for NEWater, IW & Sump Pumps
[WNS05] Material Purchase and Fabrication for Air Compressor Package
[WNS03 | L3] Material Purchase and Fabrication for Lightning & Earthing Protection
[WNS03 | ROOF] Prepare & Submit : Lightning and Earthing Protection Equipment
[WNS05] Prepare & Submit : Lighting Works Design
[WNS02] [Tank 2 | GL2/A] Install Bored Piles (35 nos.)
[WNS02] [Tank 1 | GL1/A] Install Bored Piles (35 nos.)
[WNS04] [Sodium Hydr Bldg] Install Bored Piles (15 nos.)
[WNS00 | WNS02] Construct Pipe Rack Foundation Works
[WNS00] Install RC Piles (2600 m)
[WNS05] Delivery to Site for Lime Slurry Transfer, Lime Sludge Transfer and Lime Dosing Pumps
[WNS05] Material Purchase and Fabrication for MCC & DB
[WNS05] Material Purchase and Fabrication for RIO & UPSDB Panels
[WNS05] Material Purchase and Fabrication for Instruments
[WNS03 | L3] Material Purchase and Fabrication for Lighting Works
[WNS01] [Tank 3 | GL2/A] Dome Roof Installation for NW Tank 3
[WNS01] [Tank 4 | GL2/B] Dome Roof Installation for NW Tank 4
[WNS00 | WNS01] Construct Pipe Rack Foundation Works
[WNS00] Installation of Bonding & Earthing Protection - Underground
[WNS03 | L4] Material Purchase and Fabrication for Cable & Cable Raceway Works (Electrical)
[WNS03 | Electrical Building] Install Internal Walls to SFL 9.80
[WNS03 | L1] Installation of Transformer
[WNS03 | Pump Station] Install External Walls to SFL 12.20
[WNS03] [GLA to GLD / GL1 to GL8] Construct Columns to SFL 18.80
[WNS03] [GLA to GLD / GL8 to GL14] Construct Columns to SFL 18.80
[WNS03 | L1] Installation of Pipes & Valves
[WNS05] Delivery to Site for Lime Silos
[WNS05] Material Purchase and Fabrication for Cable & Cable Raceway Works (ICA)
[WNS04] Material Purchase and Fabrication for MCC & DB
[WNS03 | L3] Material Purchase and Fabrication for Cable & Cable Raceway Works (ICA)
[WNS05] Material Purchase and Fabrication for Cable & Cable Raceway Works (Electrical)
[WNS03 | L2] Material Purchase and Fabrication for Lighting Works
[WNS03 | L1] Material Purchase and Fabrication for RIO & UPSDB Panel
[WNS03 | L1] Material Purchase and Fabrication for Cable & Cable Raceway Works (ICA)
[WNS03 | ROOF] FAT & Inspection for ACMV System
[WNS05] FAT & Inspection for Building Services
[WNS03 | ROOF] FAT & Inspection for Fire Protection System
[WNS03 | ROOF] FAT & Inspection for Plumbing and Sanitary System
[WNS03 | ROOF] FAT & Inspection for ELV System
[WNS04] Material Purchase and Fabrication for Instruments
[WNS03 | Electrical Building] Install External Walls to SFL 12.20
[WNS03] [GLD to GLG / GL1 to GL7] Construct Columns to SFL 14.90
[WNS03] [GLD to GLG / GL7 to GL13] Construct Columns to SFL 14.90
[WNS05] [Elec Bldg] Construct Columns to SFL 8.050
[WNS05] [Lime Tank] Construct Ground Beams & Slabs at SFL 5.30
[WNS04] [Amm & Elec Bldg] Install Bored Piles (19 nos.)
[WNS04] Installation of Lightning and Earthing Protection Equipment (Sodium Hydroxide Building) - Underground
[WNS04] Material Purchase and Fabrication for RIO & UPSDB Panels Design
[WNS05] FAT & Inspection for Lime Saturators
[WNS03 | L4] Material Purchase and Fabrication for Cable & Cable Raceway Works (ICA)
[WNS01] Hydrostatic Test of New Water Storage Tanks
[WNS01] Panels and Instruments Installation at NW Tank No. 1
[WNS01] Panels and Instruments Installation at NW Tank No. 2
[WNS02] Material Purchase and Fabrication for Lighting Works
[WNS04] Material Purchase and Fabrication for Cable and Cable Raceway (ICA)
[WNS04] [Sodium Hydr Bldg] Construct Ground Beams & Slabs at SFL 5.30
[WNS02] Installation of Lightning and Earthing Protection Equipment (for IW Tank No. 1 & 2)
[WNS03 | L1] Delivery to Site for Surge Vessels
[WNS03 | L1] Installation of Lightning and Earthing Protection Equipment (Pump House) - Aboveground
[WNS03 | L1] Installation of Lightning and Earthing Protection Equipment (Electrical Building) - Aboveground
[WNS03 | L1] Cable Laying (Electrical)
[WNS00] Installation of Electrical Manhole and Duct Bank
[WNS03] [GLA to GLD / GL1 to GL8] Construct Beams & Slabs at SFL 18.80
[WNS03] [GLA to GLD / GL8 to GL14] Construct Beams & Slabs at SFL 18.80
[WNS03 | L4] Material Purchase and Fabrication for Lightning & Earthing Protection
[WNS03 | L1] Material Purchase and Fabrication for Automatic Lubrication System
[WNS03 | L4] Material Purchase and Fabrication for Lighting Works
[WNS01] Installation of Active Tank Mixers for NEWater Tanks
[WNS01] Installation of Lighting Works at NW Tank No. 3
[WNS01] Installation of Lighting Works at NW Tank No. 4
[WNS03] [GLD to GLG / GL1 to GL7] Construct Beams & Slabs at SFL 14.90
[WNS03] [GLD to GLG / GL7 to GL13] Construct Beams & Slabs at SFL 14.90
[WNS05] [Elec Bldg] Construct Beams & Slabs at SFL 8.050
[WNS05] [Elec Bldg] Construct Drainage / Utility Trench
[WNS03 | L2] Installation of Switchgear, MCC & MDB
[WNS03 | L2] Cable Raceway Installation (Electrical)
[WNS03 | L2] Installation of Lightning and Earthing Protection Equipment (For Electrical Building)
[WNS03 | L2] Installation of RIO & UPSDB Panels
[WNS03 | L2] Cable Raceway Installation (ICA)
[WNS03 | L2] Installation of Telemetry System to WNS JISR
[WNS03 | L2] Installation of Telemetry System to WNS CME
[WNS03 | Pump Station] Install Internal Walls to SFL 12.20
[WNS05] Delivery to Site for Building Services
[WNS05] Delivery to Site for Lime Slurry, Saturated Lime & Lime Sludge Holding Tanks
[WNS01] Panels and Instruments Installation at NW Tank No. 3
[WNS01] Panels and Instruments Installation at NW Tank No. 4
[WNS01] Cable Laying to NW Tank No. 3 (Electrical)
[WNS01] Cable Laying to NW Tank No. 4 (Electrical)
[WNS02] Delivery to Site for Industrial Water Storage Tanks
[WNS03 | Electrical Building] Install Internal Walls to SFL 12.20
[WNS04] Installation of Lightning and Earthing Protection Equipment (Ammonium Sulphate Building) - Underground
[WNS04] Installation of Lightning and Earthing Protection Equipment (Electrical Building) - Underground
[WNS02] Material Purchase and Fabrication for DB, Cable & Cable Raceway Works (Electrical)
[WNS03 | ROOF] Delivery to Site for ACMV System
[WNS03 | ROOF] Delivery to Site for Fire Protection System
[WNS03 | ROOF] Delivery to Site for Plumbing and Sanitary System
[WNS03 | ROOF] Delivery to Site for ELV System
[WNS05] Installation of Lime Silos
[WNS05] Installation of Lime Slurry Transfer, Lime Sludge Transfer and Lime Dosing Pumps
[WNS05] [Lime Bldg] Construct Drainage / Utility Trench
[WNS05] Delivery to Site for Lime Saturators
[WNS03 | L4] Material Purchase and Fabrication for RIO & UPSDB Panel
[WNS04] Material Purchase and Fabrication for Cable & Cable Raceway Works (Electrical)
[WNS01] Flushing of New Water Storage Tanks
[WNS03 | Pump Station] Install External Walls to SFL 18.80
[WNS03 | L1] Installation of EOT Cranes
[WNS04] [Amm & Elec Bldg] Construct Ground Beams & Slabs at SFL 5.30
[WNS00 | WNS02] Install Pipe Racks
[WNS03 | Electrical Building] Install External Walls to SFL 14.90
[WNS05] [Elec Bldg] Construct Columns to SFL 13.850
[WNS00 | WNS01] Install Pipe Racks
[WNS00] Installation of Pipes and Valves
[WNS00] Cable Raceway Installation (Electrical)
[WNS00] Cable Raceway Installation (ICA)
[WNS00] Installation of Bonding & Earthing Protection - Aboveground
[WNS04] Delivery to Site for Chemical Dosing System (Sodium Hydroxide)
[WNS05] [Lime Tank] Construct Drainage / Utility Trench
[WNS02] Material Purchase and Fabrication for ICA Works
[WNS04] FAT & Inspection for Building Services
[WNS04] [Sodium Hydr Bldg] Install Steel Columns
[WNS04] [Sodium Hydr Bldg] Construct Drainage / Utility Trench
[WNS03 | L1] Installation of RIO & UPSDB Panels
[WNS03 | L1] Installation of Instruments
[WNS03 | L2] Cable Laying (ICA)
[WNS02] [Tank 1 | GL1/A] Construct Ground Slab
[WNS02] [Tank 1 | GL1/A] Drainage Works
[WNS02] [Tank 2 | GL2/A] Construct Ground Slab
[WNS02] [Tank 2 | GL2/A] Drainage Works
[WNS03 | ROOF] Material Purchase and Fabrication for Lightning & Earthing Protection
[WNS03 | L1] Commissioning of EOT Cranes and MOM Registration
[WNS03 | L3] Cable Raceway Installation (Electrical)
[WNS03 | L3] Installation of Lightning and Earthing Protection Equipment (For Electrical Building)
[WNS03 | L3] Cable Raceway Installation (ICA)
[WNS05] [Elec Bldg] Construct Beams & Slabs at SFL 13.850
[WNS03 | ROOF] Material Purchase and Fabrication for Cable & Cable Raceway Works (Electrical)
[WNS03 | L2] Cable Laying (Electrical)
[WNS05] Installation of Lime Slurry, Saturated Lime and Lime Sludge Holding Tanks
[WNS05] Delivery to Site for Transformer
[WNS04] Material Purchase and Fabrication for Lighting Works
[WNS01] Sterilization of New Water Storage Tanks
[WNS04] [Sodium Hydr Bldg] Install Roof Truss
[WNS03 | Electrical Building] Install Internal Walls to SFL 14.90
[WNS03 | Electrical Building] Install External Walls to SFL 18.40
[WNS04] [Amm Bldg] Install Steel Columns
[WNS03 | Pump Station] Install Internal Walls to SFL 18.80
[WNS03 | L4] Installation High Voltage & Low Voltage VFD
[WNS05] Material Purchase and Fabrication for Lighting Works
[WNS01] Single, Combined & Sub-system Testing on Electrical System
[WNS03 | L1] Installation of Pumps
[WNS03 | L1] Installation of Surge Vessels
[WNS03 | L1] Installation of Lighting Works at Pump Station
[WNS03 | L1] Installation of Lighting Works at Electrical Building
[WNS03 | L1] Cable Termination (Electrical)
[WNS05] [Lime Bldg] Install Steel Columns
[WNS05] Installation of Lime Saturator
[WNS05] Installation of Air Compressor Package
[WNS05] Installation of Lime Dosing Piping Works & Valves
[WNS05] Installation of RIO & UPSDB Panels
[WNS05] Installation of Instruments
[WNS05] Cable Raceway Installation (ICA)
[WNS04] Delivery to Site for Building Services
[WNS04] [Amm & Elec Bldg] Construct Drainage / Utility Trench
[WNS00] Cable Laying (Electrical)
[WNS00] Cable Laying (ICA)
[WNS03] [GLD to GLG / GL1 to GL7] Construct Beams & Slabs at SFL 23.80
[WNS03] [GLD to GLG / GL7 to GL13] Construct Beams & Slabs at SFL 23.80
[WNS03] [GLD to GLG / GL1 to GL7] Construct Intermediate Beams & Slabs Between SFL 18.40 to 23.80
[WNS03] [GLD to GLG / GL7 to GL13] Construct Intermediate Beams & Slabs Between SFL 18.40 to 23.80
[WNS02] Delivery to Site for Pipes & Valves
[WNS05] [Elec Bldg] Construct Intermediate Beams & Slabs Between SFL 8.050 to 13.850
[WNS05] Installation of ACMV System
[WNS05] Installation of Fire Protection System
[WNS05] Installation of Plumbing and Sanitary System
[WNS05] Installation of ELV System
[WNS03 | L3] Installation of Lighting Works at Electrical Building
[WNS03 | L3] Cable Laying (Electrical)
[WNS03 | L3] Cable Laying (ICA)
[WNS02] Delivery to Site for Lighting Works
[WNS03 | Electrical Building] Install Internal Walls to SFL 18.40
[WNS03 | L4] Installation of Switchgear, MCC & MDB
[WNS03 | L4] Cable Raceway Installation (Electrical)
[WNS03 | L4] Installation of Lightning and Earthing Protection Equipment (For Electrical Building)
[WNS03 | L4] Installation of RIO & UPSDB Panels
[WNS03 | L4] Cable Raceway Installation (ICA)
[WNS03 | ROOF] Installation of ACMV System
[WNS03 | ROOF] Installation of Fire Protection System
[WNS03 | ROOF] Installation of Plumbing and Sanitary System
[WNS03 | ROOF] Installation of ELV System
[WNS05] Installation of Lightning and Earthing Protection Equipment (Lime Building) - Aboveground
[WNS05] Installation of Lightning and Earthing Protection Equipment (Electrical Building) - Aboveground
[WNS05] [Lime Bldg] Install Roof Truss
[WNS04] Installation of Lightning and Earthing Protection Equipment (Sodium Hydroxide Building) - Aboveground
[WNS04] Installation of Lightning and Earthing Protection Equipment (Ammonium Sulphate Building) - Aboveground
[WNS04] Installation of Lightning and Earthing Protection Equipment (Electrical Building) - Aboveground
[WNS04] [Sodium Hydr Bldg] Install External Walls
[WNS04] Installation of Sodium Hypochlorite Dosing System (Valves, Pumps, Instruments)
[WNS04] Installation of Sodium Hypochlorite Dosing Pipes and Valves
[WNS04] Installation of 6 Sodium Hydroxide FRP Storage Tank
[WNS03 | L1] Cable Raceway Installation (ICA)
[WNS03 | Pump Station | L1] Ceiling Finishes
[WNS03 | L2] Installation of Lighting Works at Electrical Building
[WNS03 | L2] Cable Termination (Electrical)
[WNS03] [GLD to GLG / GL1 to GL7] Construct Upper Roof Structures
[WNS03] [GLD to GLG / GL7 to GL13] Construct Upper Roof Structures
[WNS03 | Electrical Building] Install External Walls to SFL 23.80
[WNS02] [Tank 1 | GL1/A] Wall Panels Installation for IW Tank 1
[WNS02] [Tank 2 | GL2/A] Wall Panels Installation for IW Tank 2
[WNS05] [Elec Bldg] Construct Upper Roof Structures
[WNS00] Hydrostatic Test of Pipes
[WNS05] Single, Combined & Sub-system Testing on Electrical System
[WNS04] Installation of Sodium Hydroxide Dosing System (Valves, Pumps, Instruments)
[WNS04] Installation of Sodium Hydroxide Dosing Pipes and Valves
[WNS05] Cable Laying (ICA)
[WNS04] Installation of RIO & UPSDB Panels
[WNS04] Installation of Instruments
[WNS04] Installation of Ammonium Sulphate Dosing System (Valves, Pumps, Instruments)
[WNS04] Installation of Ammonium Sulphate Dosing Pipes and Valves
[WNS00] Cable Termination (Electrical)
[WNS00] Cable Termination (ICA)
[WNS04] [Elec Bldg] Install Roof Drainage System
[WNS04] Cable Raceway Installation (ICA)
[WNS03 | L4] Installation of Lighting Works at Electrical Building
[WNS03 | L4] Cable Laying (ICA)
[WNS03 | L4] Cable Laying (Electrical)
[WNS03 | L3] Cable Termination (ICA)
[WNS05] [Elec Bldg] Install Roof Drainage System
[WNS03 | ROOF] Installation of Lightning and Earthing Protection Equipment (For Electrical Building)
[WNS05] Installation of Transformer
[WNS05] Installation of MCC & DB
[WNS05] Cable Raceway Installation (Electrical)
[WNS03 | Electrical Building] Install Internal Walls to SFL 23.80
[WNS03 | L1] Cable Laying (ICA)
[WNS04] Installation of ACMV System
[WNS04] Installation of Fire Protection System
[WNS04] Installation of Plumbing and Sanitary System
[WNS04] Installation of ELV System
[WNS03 | L1] Installation of Automatic Lubrication System
[WNS02] Review, Resubmission & Acceptance : Operation & Maintenance Manuals
[WNS03] Review, Resubmission & Acceptance : Operation & Maintenance Manuals
[WNS00 | C1A] Install Pipe Racks
[WNS05] Installation of Lighting Works at Electrical Building
[WNS05] Installation of Lighting Works at Lime Building
[WNS04] Single, Combined & Sub-system Testing on Electrical System
[WNS04] [Elec Bldg] Construct Staircase Structure
[WNS05] Cable Laying (Electrical)
[WNS03] Single, Combined & Sub-system Testing on Electrical System
[WNS04] Installation of MCC & DB
[WNS04] Installation of Lighting Works at Electrical Building
[WNS04] Installation of Lighting Works at Sodium Hydroxide and Sodium Hypochlorite Building
[WNS04] Installation of Lighting Works at Ammonium Sulphate Building
[WNS05] [Lime Bldg] Install Roofing
[WNS04] Cable Laying (ICA)
[WNS04] Single, Combined & Sub-system Testing on Mechanical System
[WNS05] Hydrostatic Test of Lime Dosing Pipes
[WNS05] Cable Termination (ICA)
[WNS03] [GLD to GLG / GL1 to GL7] Install Roof Drainage System
[WNS03] [GLD to GLG / GL7 to GL13] Install Roof Drainage System
[WNS03] Single, Combined & Sub-system Testing on Mechanical System
[WNS02] Panels and Instruments Installation at NW Tank No. 1
[WNS02] Panels and Instruments Installation at NW Tank No. 2
[WNS02] Installation of Pipes & Valves
[WNS05] [Elec Bldg] Construct Staircase Structure
[WNS02] Installation of Lighting Works at IW Tank No. 1
[WNS02] Installation of Lighting Works at IW Tank No. 2
[WNS02] Single, Combined & Sub-system Testing on Electrical System
[WNS05] Single, Combined & Sub-system Testing on Building Services System
[WNS05] Single, Combined & Sub-system Testing on ICA System
[WNS02] Review, Resubmission & Acceptance : Training Manuals
[WNS03] Review, Resubmission & Acceptance : Training Manuals
[WNS03] Single, Combined & Sub-system Testing on ICA System
[WNS04] Single, Combined & Sub-system Testing on Building Services System
[WNS03] Single, Combined & Sub-system Testing on Building Services System
[WNS05] [Lime Bldg] Construct Staircase Structure
[WNS05] Single, Combined & Sub-system Testing on Mechanical System
[WNS04] Single, Combined & Sub-system Testing
TFP, TOP Approval
[WNS01] Security Fences & Other Ancillary Systems
[WNS02] Security Fences & CCTV Systems
[WNS03] Security Fences & CCTV Systems
[WNS04] Security Fences & Other Ancillary Systems
[WNS05] Security Fences & CCTV Systems
[WNS00 to 05] Pre-Commissioning Testing (Dry)
[WNS01] Review, Resubmission & Acceptance : Operation & Maintenance Manuals
[WNS04] Review, Resubmission & Acceptance : Operation & Maintenance Manuals
[WNS05] Review, Resubmission & Acceptance : Operation & Maintenance Manuals
[WNS01] Review, Resubmission & Acceptance : As-Built Drawings
[WNS02] Review, Resubmission & Acceptance : As-Built Drawings
[WNS03] Review, Resubmission & Acceptance : As-Built Drawings
[WNS04] Review, Resubmission & Acceptance : As-Built Drawings
[WNS05] Review, Resubmission & Acceptance : As-Built Drawings
[WNS00] Review, Resubmission & Acceptance : As-Built Drawings
[WNS00 to 05] Pre-Commissioning Testing (Wet)
CSC Approval
[WNS01] Review, Resubmission & Acceptance : Training Manuals
[WNS04] Review, Resubmission & Acceptance : Training Manuals
[WNS05] Review, Resubmission & Acceptance : Training Manuals
Process Commissioning
Operation & Maintenance Period 2 (14 Months)
DLP (24 Months)
Operation & Maintenance Period 3 (12 Months)
Original Duration Start Finish Total FloatContractor's Response
56.00 4/29/2021 6/23/2021 40 40
56.00 4/29/2021 6/23/2021 327 327
150.00 4/29/2021 9/25/2021 6 6
60.00 4/29/2021 6/27/2021 6 6
60.00 4/29/2021 6/27/2021 6 6
60.00 4/29/2021 6/27/2021 6 6
60.00 4/29/2021 6/27/2021 6 6
60.00 4/29/2021 6/27/2021 6 6
1,323.00 5/27/2021 1/8/2025 6 6
56.00 6/24/2021 8/18/2021 54 54
105.00 6/24/2021 10/6/2021 89 89
105.00 6/24/2021 10/6/2021 327 327
1,267.00 6/24/2021 12/11/2024 34 34
1,284.00 6/28/2021 1/1/2025 6 6
1,284.00 6/28/2021 1/1/2025 6 6
1,284.00 6/28/2021 1/1/2025 6 6
1,284.00 6/28/2021 1/1/2025 6 6
1,284.00 6/28/2021 1/1/2025 6 6
42.00 7/8/2021 8/18/2021 40 40
105.00 7/15/2021 10/27/2021 42 42
42.00 7/22/2021 9/1/2021 87 87
56.00 7/22/2021 9/15/2021 160 160
42.00 7/22/2021 9/1/2021 58 58
42.00 7/29/2021 9/8/2021 133 133
42.00 8/5/2021 9/15/2021 385 385
56.00 8/5/2021 9/29/2021 119 119
35.00 8/12/2021 9/15/2021 245 245
35.00 8/12/2021 9/15/2021 588 588
49.00 8/19/2021 10/6/2021 40 40
70.00 8/19/2021 10/27/2021 54 54
49.00 8/19/2021 10/6/2021 180 180
35.00 8/19/2021 9/22/2021 6 6
35.00 9/2/2021 10/6/2021 68 68
35.00 9/2/2021 10/6/2021 68 68
35.00 9/2/2021 10/6/2021 68 68
35.00 9/2/2021 10/6/2021 68 68
49.00 9/2/2021 10/20/2021 252 252
35.00 9/2/2021 10/6/2021 180 180
63.00 9/16/2021 11/17/2021 160 160
56.00 9/16/2021 11/10/2021 385 385
1,190.00 9/23/2021 12/25/2024 6 6
1,194.00 9/26/2021 1/1/2025 6 6
42.00 9/30/2021 11/10/2021 364 364
42.00 9/30/2021 11/10/2021 87 87
35.00 9/30/2021 11/3/2021 119 119
84.00 9/30/2021 12/22/2021 329 329
42.00 10/7/2021 11/17/2021 187 187
63.00 10/7/2021 12/8/2021 40 40
63.00 10/7/2021 12/8/2021 180 180
56.00 10/7/2021 12/1/2021 68 68
56.00 10/7/2021 12/1/2021 68 68
56.00 10/7/2021 12/1/2021 68 68
56.00 10/7/2021 12/1/2021 68 68
56.00 10/7/2021 12/1/2021 180 180
1,182.00 10/7/2021 12/31/2024 7 7
56.00 10/7/2021 12/1/2021 119 119
105.00 10/7/2021 1/19/2022 334 334
49.00 10/14/2021 12/1/2021 245 245
70.00 10/21/2021 12/29/2021 252 252
35.00 10/28/2021 12/1/2021 111 111
35.00 10/28/2021 12/1/2021 42 42
70.00 10/28/2021 1/5/2022 54 54
70.00 10/28/2021 1/5/2022 84 84
35.00 10/28/2021 12/1/2021 84 84
35.00 10/28/2021 12/1/2021 273 273
143.00 10/29/2021 3/20/2022 2 2
108.00 10/29/2021 2/13/2022 14 14
56.00 11/4/2021 12/29/2021 119 119
63.00 11/11/2021 1/12/2022 364 364
56.00 11/11/2021 1/5/2022 87 87
90.00 11/12/2021 2/9/2022 79 79
90.00 11/12/2021 2/9/2022 79 79
55.00 11/12/2021 1/5/2022 100 100
63.00 11/18/2021 1/19/2022 187 187
70.00 11/18/2021 1/26/2022 160 160
84.00 11/18/2021 2/9/2022 101 101
35.00 12/2/2021 1/5/2022 187 187
56.00 12/2/2021 1/26/2022 180 180
56.00 12/2/2021 1/26/2022 42 42
63.00 12/2/2021 2/2/2022 68 68
63.00 12/2/2021 2/2/2022 68 68
63.00 12/2/2021 2/2/2022 68 68
63.00 12/2/2021 2/2/2022 68 68
35.00 12/2/2021 1/5/2022 208 208
35.00 12/2/2021 1/5/2022 187 187
35.00 12/2/2021 1/5/2022 187 187
35.00 12/2/2021 1/5/2022 111 111
35.00 12/2/2021 1/5/2022 194 194
42.00 12/2/2021 1/12/2022 293 293
49.00 12/2/2021 1/19/2022 84 84
49.00 12/2/2021 1/19/2022 273 273
77.00 12/2/2021 2/16/2022 180 180
63.00 12/2/2021 2/2/2022 245 245
42.00 12/2/2021 1/12/2022 588 588
63.00 12/9/2021 2/9/2022 180 180
56.00 12/9/2021 2/2/2022 133 133
84.00 12/30/2021 3/23/2022 252 252
35.00 12/30/2021 2/2/2022 40 40
63.00 12/30/2021 3/2/2022 124 124
84.00 1/6/2022 3/30/2022 240 240
42.00 1/6/2022 2/16/2022 54 54
56.00 1/6/2022 3/2/2022 168 168
56.00 1/6/2022 3/2/2022 187 187
56.00 1/6/2022 3/2/2022 208 208
56.00 1/6/2022 3/2/2022 187 187
56.00 1/6/2022 3/2/2022 187 187
56.00 1/6/2022 3/2/2022 166 166
56.00 1/6/2022 3/2/2022 194 194
42.00 1/6/2022 2/16/2022 203 203
35.00 1/6/2022 2/9/2022 87 87
40.00 1/6/2022 2/14/2022 100 100
84.00 1/13/2022 4/6/2022 89 89
63.00 1/15/2022 3/18/2022 549 549
84.00 1/20/2022 4/13/2022 187 187
70.00 1/20/2022 3/30/2022 84 84
70.00 1/20/2022 3/30/2022 273 273
56.00 1/27/2022 3/23/2022 82 82
42.00 1/27/2022 3/9/2022 201 201
35.00 1/27/2022 3/2/2022 180 180
63.00 1/27/2022 3/30/2022 160 160
84.00 1/27/2022 4/20/2022 180 180
63.00 1/27/2022 3/30/2022 176 176
42.00 1/27/2022 3/9/2022 40 40
42.00 1/27/2022 3/9/2022 110 110
42.00 1/27/2022 3/9/2022 42 42
98.00 2/3/2022 5/11/2022 68 68
98.00 2/3/2022 5/11/2022 68 68
98.00 2/3/2022 5/11/2022 68 68
98.00 2/3/2022 5/11/2022 68 68
35.00 2/3/2022 3/9/2022 215 215
42.00 2/3/2022 3/16/2022 40 40
35.00 2/3/2022 3/9/2022 187 187
35.00 2/3/2022 3/9/2022 111 111
49.00 2/3/2022 3/23/2022 84 84
70.00 2/3/2022 4/13/2022 245 245
90.00 2/10/2022 5/10/2022 79 79
90.00 2/10/2022 5/10/2022 79 79
105.00 2/10/2022 5/25/2022 101 101
56.00 2/10/2022 4/6/2022 87 87
56.00 2/10/2022 4/6/2022 119 119
63.00 2/12/2022 4/15/2022 668 668
63.00 2/12/2022 4/15/2022 530 530
93.00 2/14/2022 5/17/2022 19 19
35.00 2/17/2022 3/23/2022 54 54
56.00 2/17/2022 4/13/2022 61 61
63.00 2/17/2022 4/20/2022 203 203
84.00 2/17/2022 5/11/2022 180 180
35.00 2/24/2022 3/30/2022 180 180
49.00 2/24/2022 4/13/2022 119 119
42.00 2/24/2022 4/6/2022 124 124
56.00 2/24/2022 4/20/2022 223 223
63.00 3/3/2022 5/4/2022 187 187
49.00 3/3/2022 4/20/2022 180 180
63.00 3/3/2022 5/4/2022 208 208
84.00 3/3/2022 5/25/2022 124 124
63.00 3/3/2022 5/4/2022 187 187
63.00 3/3/2022 5/4/2022 187 187
63.00 3/3/2022 5/4/2022 166 166
63.00 3/3/2022 5/4/2022 194 194
49.00 3/10/2022 4/27/2022 215 215
56.00 3/10/2022 5/4/2022 201 201
56.00 3/10/2022 5/4/2022 187 187
49.00 3/10/2022 4/27/2022 111 111
56.00 3/10/2022 5/4/2022 40 40
56.00 3/10/2022 5/4/2022 110 110
63.00 3/10/2022 5/11/2022 63 63
35.00 3/10/2022 4/13/2022 45 45
91.00 3/10/2022 6/8/2022 329 329
63.00 3/12/2022 5/13/2022 297 297
63.00 3/12/2022 5/13/2022 733 733
63.00 3/17/2022 5/18/2022 40 40
42.00 3/17/2022 4/27/2022 201 201
133.00 3/17/2022 7/27/2022 258 258
75.00 3/21/2022 6/3/2022 2 2
119.00 3/21/2022 7/17/2022 19 19
35.00 3/21/2022 4/24/2022 22 22
92.00 3/24/2022 6/23/2022 97 97
92.00 3/24/2022 6/23/2022 97 97
84.00 3/24/2022 6/15/2022 82 82
35.00 3/24/2022 4/27/2022 54 54
56.00 3/24/2022 5/18/2022 96 96
56.00 3/24/2022 5/18/2022 84 84
140.00 3/26/2022 8/12/2022 227 227
84.00 3/29/2022 6/20/2022 100 100
84.00 3/29/2022 6/20/2022 100 100
84.00 3/31/2022 6/22/2022 176 176
35.00 3/31/2022 5/4/2022 84 84
49.00 3/31/2022 5/18/2022 180 180
84.00 3/31/2022 6/22/2022 133 133
84.00 3/31/2022 6/22/2022 273 273
105.00 3/31/2022 7/13/2022 334 334
56.00 4/7/2022 6/1/2022 124 124
42.00 4/7/2022 5/18/2022 201 201
42.00 4/7/2022 5/18/2022 42 42
42.00 4/7/2022 5/18/2022 112 112
84.00 4/7/2022 6/29/2022 89 89
77.00 4/7/2022 6/22/2022 182 182
35.00 4/7/2022 5/11/2022 182 182
35.00 4/14/2022 5/18/2022 61 61
56.00 4/14/2022 6/8/2022 187 187
70.00 4/14/2022 6/22/2022 104 104
63.00 4/14/2022 6/15/2022 119 119
49.00 4/14/2022 6/1/2022 194 194
56.00 4/14/2022 6/8/2022 45 45
35.00 4/14/2022 5/18/2022 60 60
56.00 4/21/2022 6/15/2022 180 180
63.00 4/21/2022 6/22/2022 180 180
56.00 4/21/2022 6/15/2022 133 133
84.00 4/21/2022 7/13/2022 203 203
182.00 4/23/2022 10/21/2022 348 348
266.00 4/28/2022 1/18/2023 180 180
56.00 4/28/2022 6/22/2022 215 215
63.00 4/28/2022 6/29/2022 103 103
56.00 4/28/2022 6/22/2022 111 111
56.00 4/28/2022 6/22/2022 201 201
35.00 5/2/2022 6/5/2022 15 15
35.00 5/2/2022 6/5/2022 15 15
70.00 5/5/2022 7/13/2022 201 201
56.00 5/5/2022 6/29/2022 126 126
84.00 5/5/2022 7/27/2022 187 187
84.00 5/5/2022 7/27/2022 208 208
105.00 5/5/2022 8/17/2022 187 187
105.00 5/5/2022 8/17/2022 187 187
105.00 5/5/2022 8/17/2022 166 166
84.00 5/5/2022 7/27/2022 194 194
70.00 5/5/2022 7/13/2022 187 187
70.00 5/5/2022 7/13/2022 40 40
70.00 5/5/2022 7/13/2022 215 215
42.00 5/5/2022 6/15/2022 52 52
42.00 5/5/2022 6/15/2022 91 91
35.00 5/5/2022 6/8/2022 87 87
90.00 5/11/2022 8/8/2022 79 79
90.00 5/11/2022 8/8/2022 79 79
105.00 5/11/2022 8/23/2022 351 351
49.00 5/12/2022 6/29/2022 229 229
70.00 5/12/2022 7/20/2022 63 63
56.00 5/12/2022 7/6/2022 182 182
56.00 5/12/2022 7/6/2022 266 266
42.00 5/19/2022 6/29/2022 168 168
70.00 5/19/2022 7/27/2022 40 40
63.00 5/19/2022 7/20/2022 180 180
56.00 5/19/2022 7/13/2022 61 61
63.00 5/19/2022 7/20/2022 187 187
56.00 5/19/2022 7/13/2022 201 201
56.00 5/19/2022 7/13/2022 42 42
56.00 5/19/2022 7/13/2022 112 112
49.00 5/19/2022 7/6/2022 60 60
84.00 5/19/2022 8/10/2022 84 84
49.00 5/26/2022 7/13/2022 102 102
49.00 5/26/2022 7/13/2022 110 110
42.00 5/26/2022 7/6/2022 96 96
42.00 5/26/2022 7/6/2022 96 96
42.00 5/26/2022 7/6/2022 54 54
98.00 6/2/2022 9/7/2022 124 124
42.00 6/2/2022 7/13/2022 110 110
56.00 6/2/2022 7/27/2022 194 194
42.00 6/2/2022 7/13/2022 119 119
42.00 6/2/2022 7/13/2022 84 84
112.00 6/4/2022 9/23/2022 5 5
46.00 6/6/2022 7/21/2022 15 15
46.00 6/6/2022 7/21/2022 15 15
56.00 6/9/2022 8/3/2022 240 240
105.00 6/9/2022 9/21/2022 252 252
63.00 6/9/2022 8/10/2022 45 45
56.00 6/9/2022 8/3/2022 87 87
90.00 6/14/2022 9/11/2022 7 7
56.00 6/16/2022 8/10/2022 82 82
98.00 6/16/2022 9/21/2022 119 119
140.00 6/16/2022 11/2/2022 160 160
49.00 6/16/2022 8/3/2022 109 109
56.00 6/16/2022 8/10/2022 65 65
35.00 6/16/2022 7/20/2022 96 96
63.00 6/16/2022 8/17/2022 91 91
84.00 6/21/2022 9/12/2022 183 183
84.00 6/21/2022 9/12/2022 183 183
70.00 6/23/2022 8/31/2022 188 188
84.00 6/23/2022 9/14/2022 215 215
84.00 6/23/2022 9/14/2022 180 180
42.00 6/23/2022 8/3/2022 104 104
84.00 6/23/2022 9/14/2022 166 166
42.00 6/23/2022 8/3/2022 201 201
70.00 6/23/2022 8/31/2022 182 182
42.00 6/23/2022 8/3/2022 138 138
84.00 6/30/2022 9/21/2022 103 103
63.00 6/30/2022 8/31/2022 126 126
63.00 6/30/2022 8/31/2022 229 229
70.00 6/30/2022 9/7/2022 245 245
63.00 7/7/2022 9/7/2022 74 74
56.00 7/7/2022 8/31/2022 96 96
56.00 7/7/2022 8/31/2022 96 96
56.00 7/7/2022 8/31/2022 54 54
63.00 7/7/2022 9/7/2022 182 182
35.00 7/7/2022 8/10/2022 60 60
92.00 7/8/2022 10/7/2022 158 158
92.00 7/8/2022 10/7/2022 158 158
35.00 7/9/2022 8/12/2022 2 2
35.00 7/9/2022 8/12/2022 2 2
49.00 7/14/2022 8/31/2022 84 84
63.00 7/14/2022 9/14/2022 61 61
84.00 7/14/2022 10/5/2022 187 187
70.00 7/14/2022 9/21/2022 201 201
56.00 7/14/2022 9/7/2022 110 110
49.00 7/14/2022 8/31/2022 52 52
42.00 7/14/2022 8/24/2022 59 59
63.00 7/14/2022 9/14/2022 102 102
63.00 7/14/2022 9/14/2022 110 110
56.00 7/14/2022 9/7/2022 119 119
56.00 7/14/2022 9/7/2022 84 84
56.00 7/14/2022 9/7/2022 42 42
56.00 7/14/2022 9/7/2022 112 112
56.00 7/14/2022 9/7/2022 89 89
56.00 7/21/2022 9/14/2022 187 187
98.00 7/21/2022 10/26/2022 180 180
56.00 7/21/2022 9/14/2022 96 96
42.00 7/21/2022 8/31/2022 111 111
84.00 7/21/2022 10/12/2022 63 63
32.00 7/22/2022 8/22/2022 15 15
32.00 7/22/2022 8/22/2022 15 15
70.00 7/22/2022 9/29/2022 97 97
70.00 7/22/2022 9/29/2022 97 97
210.00 7/28/2022 2/22/2023 68 68
84.00 7/28/2022 10/19/2022 40 40
210.00 7/28/2022 2/22/2023 68 68
210.00 7/28/2022 2/22/2023 68 68
210.00 7/28/2022 2/22/2023 68 68
63.00 7/28/2022 9/28/2022 194 194
140.00 7/28/2022 12/14/2022 180 180
38.00 7/29/2022 9/4/2022 52 52
35.00 8/4/2022 9/7/2022 341 341
56.00 8/4/2022 9/28/2022 104 104
63.00 8/4/2022 10/5/2022 109 109
77.00 8/4/2022 10/19/2022 87 87
56.00 8/4/2022 9/28/2022 138 138
196.00 8/11/2022 2/22/2023 124 124
105.00 8/11/2022 11/23/2022 101 101
84.00 8/11/2022 11/2/2022 45 45
98.00 8/11/2022 11/16/2022 65 65
56.00 8/11/2022 10/5/2022 60 60
35.00 8/11/2022 9/14/2022 84 84
84.00 8/18/2022 11/9/2022 91 91
105.00 8/24/2022 12/6/2022 351 351
175.00 8/25/2022 2/15/2023 187 187
35.00 8/25/2022 9/28/2022 152 152
63.00 8/25/2022 10/26/2022 59 59
31.00 8/27/2022 9/26/2022 2 2
31.00 8/27/2022 9/26/2022 2 2
98.00 9/1/2022 12/7/2022 180 180
42.00 9/1/2022 10/12/2022 229 229
63.00 9/1/2022 11/2/2022 126 126
70.00 9/1/2022 11/9/2022 96 96
63.00 9/1/2022 11/2/2022 84 84
63.00 9/1/2022 11/2/2022 52 52
63.00 9/1/2022 11/2/2022 111 111
70.00 9/1/2022 11/9/2022 96 96
84.00 9/1/2022 11/23/2022 54 54
70.00 9/5/2022 11/13/2022 52 52
119.00 9/5/2022 1/1/2023 283 283
90.00 9/8/2022 12/6/2022 176 176
56.00 9/8/2022 11/2/2022 110 110
189.00 9/8/2022 3/15/2023 89 89
98.00 9/8/2022 12/14/2022 74 74
63.00 9/8/2022 11/9/2022 119 119
84.00 9/8/2022 11/30/2022 132 132
84.00 9/8/2022 11/30/2022 182 182
90.00 9/12/2022 12/10/2022 7 7
66.00 9/13/2022 11/17/2022 15 15
66.00 9/13/2022 11/17/2022 15 15
84.00 9/13/2022 12/5/2022 254 254
84.00 9/13/2022 12/5/2022 219 219
84.00 9/15/2022 12/7/2022 61 61
63.00 9/15/2022 11/16/2022 96 96
84.00 9/15/2022 12/7/2022 110 110
98.00 9/15/2022 12/21/2022 102 102
56.00 9/15/2022 11/9/2022 84 84
84.00 9/22/2022 12/14/2022 103 103
42.00 9/27/2022 11/7/2022 2 2
42.00 9/27/2022 11/7/2022 2 2
42.00 9/27/2022 11/7/2022 44 44
42.00 9/27/2022 11/7/2022 44 44
56.00 9/27/2022 11/21/2022 79 79
70.00 9/29/2022 12/7/2022 104 104
105.00 9/29/2022 1/11/2023 201 201
42.00 9/29/2022 11/9/2022 152 152
154.00 9/29/2022 3/1/2023 40 40
91.00 9/29/2022 12/28/2022 215 215
70.00 9/29/2022 12/7/2022 203 203
70.00 9/29/2022 12/7/2022 138 138
35.00 9/30/2022 11/3/2022 97 97
35.00 9/30/2022 11/3/2022 97 97
56.00 10/6/2022 11/30/2022 98 98
56.00 10/6/2022 11/30/2022 109 109
77.00 10/6/2022 12/21/2022 60 60
42.00 10/6/2022 11/16/2022 84 84
182.00 10/13/2022 4/12/2023 187 187
182.00 10/13/2022 4/12/2023 208 208
182.00 10/13/2022 4/12/2023 194 194
70.00 10/20/2022 12/28/2022 201 201
84.00 10/20/2022 1/11/2023 87 87
92.00 10/22/2022 1/21/2023 207 207
92.00 10/22/2022 1/21/2023 172 172
245.00 10/27/2022 6/28/2023 82 82
70.00 10/27/2022 1/4/2023 84 84
84.00 10/27/2022 1/18/2023 59 59
91.00 11/3/2022 2/1/2023 84 84
182.00 11/3/2022 5/3/2023 187 187
182.00 11/3/2022 5/3/2023 187 187
182.00 11/3/2022 5/3/2023 166 166
63.00 11/3/2022 1/4/2023 52 52
98.00 11/3/2022 2/8/2023 111 111
266.00 11/4/2022 7/27/2023 186 186
42.00 11/8/2022 12/19/2022 2 2
42.00 11/8/2022 12/19/2022 2 2
35.00 11/10/2022 12/14/2022 188 188
63.00 11/10/2022 1/11/2023 84 84
84.00 11/17/2022 2/8/2023 96 96
91.00 11/17/2022 2/15/2023 182 182
63.00 11/17/2022 1/18/2023 84 84
63.00 11/18/2022 1/19/2023 109 109
42.00 11/18/2022 12/29/2022 15 15
42.00 11/18/2022 12/29/2022 15 15
42.00 11/18/2022 12/29/2022 55 55
42.00 11/18/2022 12/29/2022 55 55
70.00 11/18/2022 1/26/2023 145 145
70.00 11/18/2022 1/26/2023 145 145
115.00 11/22/2022 3/16/2023 79 79
65.00 11/24/2022 1/27/2023 59 59
175.00 11/24/2022 5/17/2023 124 124
175.00 11/24/2022 5/17/2023 42 42
105.00 11/24/2022 3/8/2023 112 112
89.00 11/28/2022 2/24/2023 52 52
49.00 12/1/2022 1/18/2023 187 187
126.00 12/1/2022 4/5/2023 215 215
84.00 12/1/2022 2/22/2023 180 180
175.00 12/1/2022 5/24/2023 166 166
91.00 12/2/2022 3/2/2023 97 97
91.00 12/2/2022 3/2/2023 97 97
49.00 12/8/2022 1/25/2023 341 341
84.00 12/8/2022 3/1/2023 104 104
63.00 12/8/2022 2/8/2023 119 119
91.00 12/8/2022 3/8/2023 201 201
36.00 12/10/2022 1/14/2023 204 204
36.00 12/10/2022 1/14/2023 204 204
119.00 12/11/2022 4/8/2023 186 186
42.00 12/15/2022 1/25/2023 194 194
49.00 12/20/2022 2/6/2023 12 12
35.00 12/21/2022 1/24/2023 62 62
133.00 12/22/2022 5/3/2023 187 187
98.00 12/22/2022 3/29/2023 60 60
121.00 12/25/2022 4/24/2023 7 7
42.00 12/29/2022 2/8/2023 229 229
63.00 12/29/2022 3/1/2023 63 63
40.00 12/30/2022 2/7/2023 15 15
40.00 12/30/2022 2/7/2023 15 15
98.00 1/5/2023 4/12/2023 40 40
42.00 1/12/2023 2/22/2023 180 180
84.00 1/12/2023 4/5/2023 84 84
36.00 1/19/2023 2/23/2023 2 2
36.00 1/19/2023 2/23/2023 2 2
126.00 1/19/2023 5/24/2023 126 126
56.00 1/19/2023 3/15/2023 180 180
91.00 1/19/2023 4/19/2023 110 110
63.00 1/19/2023 3/22/2023 45 45
56.00 1/19/2023 3/15/2023 59 59
84.00 1/19/2023 4/12/2023 84 84
88.00 1/22/2023 4/19/2023 5 5
88.00 1/22/2023 4/19/2023 5 5
38.00 1/22/2023 2/28/2023 31 31
100.00 1/25/2023 5/4/2023 62 62
52.00 1/25/2023 3/17/2023 187 187
42.00 1/26/2023 3/8/2023 215 215
140.00 1/26/2023 6/14/2023 119 119
70.00 1/26/2023 4/5/2023 96 96
70.00 1/26/2023 4/5/2023 96 96
63.00 1/26/2023 3/29/2023 91 91
35.00 1/27/2023 3/2/2023 145 145
35.00 1/27/2023 3/2/2023 145 145
100.00 1/28/2023 5/7/2023 59 59
140.00 1/28/2023 6/16/2023 229 229
91.00 2/2/2023 5/3/2023 65 65
56.00 2/7/2023 4/3/2023 12 12
119.00 2/7/2023 6/5/2023 170 170
56.00 2/8/2023 4/4/2023 34 34
42.00 2/8/2023 3/21/2023 15 15
42.00 2/8/2023 3/21/2023 15 15
196.00 2/8/2023 8/22/2023 105 105
42.00 2/9/2023 3/22/2023 201 201
63.00 2/9/2023 4/12/2023 54 54
175.00 2/16/2023 8/9/2023 98 98
42.00 2/16/2023 3/29/2023 109 109
105.00 2/16/2023 5/31/2023 132 132
63.00 2/16/2023 4/19/2023 182 182
35.00 2/23/2023 3/29/2023 152 152
84.00 2/23/2023 5/17/2023 61 61
56.00 2/23/2023 4/19/2023 68 68
42.00 2/23/2023 4/5/2023 124 124
56.00 2/23/2023 4/19/2023 68 68
56.00 2/23/2023 4/19/2023 68 68
56.00 2/23/2023 4/19/2023 68 68
91.00 2/23/2023 5/24/2023 110 110
49.00 2/24/2023 4/13/2023 9 9
36.00 2/24/2023 3/31/2023 2 2
36.00 2/24/2023 3/31/2023 2 2
36.00 2/25/2023 4/1/2023 52 52
36.00 2/25/2023 4/1/2023 212 212
48.00 3/1/2023 4/17/2023 31 31
119.00 3/1/2023 6/27/2023 162 162
91.00 3/2/2023 5/31/2023 103 103
56.00 3/2/2023 4/26/2023 40 40
91.00 3/2/2023 5/31/2023 74 74
56.00 3/3/2023 4/27/2023 228 228
35.00 3/3/2023 4/6/2023 145 145
35.00 3/3/2023 4/6/2023 145 145
133.00 3/3/2023 7/13/2023 97 97
84.00 3/9/2023 5/31/2023 102 102
67.00 3/15/2023 5/20/2023 32 32
35.00 3/16/2023 4/19/2023 259 259
49.00 3/16/2023 5/3/2023 187 187
266.00 3/17/2023 12/7/2023 83 83
266.00 3/17/2023 12/7/2023 83 83
115.00 3/17/2023 7/9/2023 79 79
133.00 3/18/2023 7/28/2023 187 187
40.00 3/22/2023 4/30/2023 15 15
40.00 3/22/2023 4/30/2023 15 15
70.00 3/23/2023 5/31/2023 52 52
119.00 3/23/2023 7/19/2023 138 138
63.00 3/30/2023 5/31/2023 87 87
63.00 3/31/2023 6/1/2023 305 305
91.00 3/31/2023 6/29/2023 181 181
91.00 3/31/2023 6/29/2023 146 146
36.00 4/1/2023 5/6/2023 2 2
36.00 4/1/2023 5/6/2023 2 2
36.00 4/2/2023 5/7/2023 52 52
42.00 4/2/2023 5/13/2023 170 170
119.00 4/4/2023 7/31/2023 114 114
73.00 4/4/2023 6/15/2023 51 51
259.00 4/4/2023 12/18/2023 12 12
119.00 4/4/2023 7/31/2023 154 154
56.00 4/4/2023 5/29/2023 154 154
140.00 4/4/2023 8/21/2023 154 154
140.00 4/4/2023 8/21/2023 154 154
63.00 4/5/2023 6/6/2023 34 34
56.00 4/6/2023 5/31/2023 124 124
42.00 4/6/2023 5/17/2023 201 201
35.00 4/7/2023 5/11/2023 145 145
35.00 4/7/2023 5/11/2023 145 145
36.00 4/8/2023 5/13/2023 175 175
36.00 4/8/2023 5/13/2023 175 175
56.00 4/13/2023 6/7/2023 89 89
56.00 4/14/2023 6/8/2023 9 9
119.00 4/18/2023 8/14/2023 114 114
119.00 4/18/2023 8/14/2023 114 114
119.00 4/20/2023 8/16/2023 84 84
56.00 4/20/2023 6/14/2023 68 68
56.00 4/20/2023 6/14/2023 68 68
56.00 4/20/2023 6/14/2023 68 68
56.00 4/20/2023 6/14/2023 68 68
119.00 4/22/2023 8/18/2023 171 171
119.00 4/22/2023 8/18/2023 171 171
77.00 4/25/2023 7/10/2023 7 7
42.00 4/27/2023 6/7/2023 40 40
42.00 4/27/2023 6/7/2023 96 96
91.00 4/27/2023 7/26/2023 111 111
56.00 4/28/2023 6/22/2023 228 228
56.00 5/1/2023 6/25/2023 15 15
35.00 5/1/2023 6/4/2023 92 92
55.00 5/2/2023 6/25/2023 31 31
182.00 5/5/2023 11/2/2023 348 348
49.00 5/7/2023 6/24/2023 2 2
36.00 5/8/2023 6/12/2023 52 52
182.00 5/8/2023 11/5/2023 226 226
182.00 5/8/2023 11/5/2023 148 148
73.00 5/8/2023 7/19/2023 87 87
73.00 5/8/2023 7/19/2023 148 148
210.00 5/8/2023 12/3/2023 59 59
42.00 5/11/2023 6/21/2023 194 194
35.00 5/14/2023 6/17/2023 170 170
84.00 5/18/2023 8/9/2023 104 104
56.00 5/18/2023 7/12/2023 124 124
35.00 5/21/2023 6/24/2023 32 32
35.00 5/21/2023 6/24/2023 32 32
119.00 5/29/2023 9/24/2023 120 120
63.00 5/29/2023 7/30/2023 176 176
56.00 5/30/2023 7/24/2023 154 154
63.00 6/1/2023 8/2/2023 5 5
63.00 6/1/2023 8/2/2023 5 5
63.00 6/1/2023 8/2/2023 5 5
63.00 6/1/2023 8/2/2023 5 5
56.00 6/1/2023 7/26/2023 59 59
35.00 6/5/2023 7/9/2023 92 92
56.00 6/9/2023 8/3/2023 20 20
196.00 6/9/2023 12/21/2023 9 9
62.00 6/9/2023 8/9/2023 73 73
46.00 6/13/2023 7/28/2023 52 52
42.00 6/15/2023 7/26/2023 60 60
73.00 6/16/2023 8/27/2023 51 51
63.00 6/18/2023 8/19/2023 170 170
42.00 6/22/2023 8/2/2023 126 126
56.00 6/22/2023 8/16/2023 84 84
56.00 6/23/2023 8/17/2023 228 228
42.00 6/25/2023 8/5/2023 32 32
56.00 6/25/2023 8/19/2023 2 2
49.00 6/26/2023 8/13/2023 27 27
35.00 6/26/2023 7/30/2023 31 31
63.00 6/26/2023 8/27/2023 15 15
91.00 6/26/2023 9/24/2023 59 59
56.00 6/29/2023 8/23/2023 84 84
98.00 6/30/2023 10/5/2023 146 146
147.00 7/10/2023 12/3/2023 92 92
119.00 7/10/2023 11/5/2023 120 120
140.00 7/10/2023 11/26/2023 94 94
140.00 7/10/2023 11/26/2023 94 94
57.00 7/10/2023 9/4/2023 79 79
42.00 7/11/2023 8/21/2023 162 162
140.00 7/11/2023 11/27/2023 7 7
140.00 7/11/2023 11/27/2023 70 70
140.00 7/11/2023 11/27/2023 7 7
119.00 7/11/2023 11/6/2023 56 56
140.00 7/11/2023 11/27/2023 56 56
70.00 7/11/2023 9/18/2023 21 21
42.00 7/13/2023 8/23/2023 124 124
42.00 7/18/2023 8/28/2023 58 58
73.00 7/20/2023 9/30/2023 87 87
73.00 7/20/2023 9/30/2023 148 148
36.00 7/26/2023 8/30/2023 211 211
36.00 7/26/2023 8/30/2023 211 211
48.00 7/26/2023 9/11/2023 315 315
48.00 7/26/2023 9/11/2023 315 315
56.00 7/27/2023 9/20/2023 82 82
36.00 7/29/2023 9/2/2023 52 52
154.00 7/29/2023 12/29/2023 66 66
154.00 7/29/2023 12/29/2023 66 66
154.00 7/29/2023 12/29/2023 66 66
154.00 7/29/2023 12/29/2023 66 66
91.00 8/4/2023 11/2/2023 20 20
56.00 8/4/2023 9/28/2023 27 27
62.00 8/10/2023 10/10/2023 73 73
42.00 8/11/2023 9/21/2023 97 97
56.00 8/20/2023 10/14/2023 21 21
91.00 8/20/2023 11/18/2023 4 4
48.00 8/20/2023 10/6/2023 13 13
119.00 8/20/2023 12/16/2023 14 14
91.00 8/20/2023 11/18/2023 65 65
48.00 8/20/2023 10/6/2023 36 36
154.00 8/20/2023 1/20/2024 2 2
154.00 8/20/2023 1/20/2024 2 2
154.00 8/20/2023 1/20/2024 2 2
154.00 8/20/2023 1/20/2024 2 2
140.00 8/21/2023 1/7/2024 52 52
140.00 8/21/2023 1/7/2024 52 52
91.00 8/22/2023 11/20/2023 162 162
140.00 8/22/2023 1/8/2024 51 51
140.00 8/22/2023 1/8/2024 51 51
140.00 8/22/2023 1/8/2024 51 51
35.00 8/27/2023 9/30/2023 32 32
42.00 8/27/2023 10/7/2023 128 128
42.00 8/27/2023 10/7/2023 128 128
63.00 8/27/2023 10/28/2023 107 107
53.00 8/28/2023 10/19/2023 15 15
37.00 8/28/2023 10/3/2023 291 291
91.00 8/28/2023 11/26/2023 94 94
36.00 8/28/2023 10/2/2023 51 51
91.00 8/31/2023 11/29/2023 257 257
91.00 8/31/2023 11/29/2023 257 257
49.00 8/31/2023 10/18/2023 211 211
70.00 8/31/2023 11/8/2023 5 5
70.00 8/31/2023 11/8/2023 5 5
42.00 9/3/2023 10/14/2023 52 52
63.00 9/4/2023 11/5/2023 148 148
119.00 9/11/2023 1/7/2024 52 52
42.00 9/17/2023 10/28/2023 107 107
42.00 9/17/2023 10/28/2023 107 107
70.00 9/19/2023 11/27/2023 21 21
98.00 9/25/2023 12/31/2023 43 43
119.00 9/25/2023 1/21/2024 43 43
42.00 9/25/2023 11/5/2023 99 99
42.00 9/25/2023 11/5/2023 99 99
36.00 10/1/2023 11/5/2023 87 87
36.00 10/1/2023 11/5/2023 148 148
35.00 10/5/2023 11/8/2023 265 265
48.00 10/5/2023 11/21/2023 32 32
70.00 10/7/2023 12/15/2023 15 15
48.00 10/7/2023 11/23/2023 36 36
48.00 10/7/2023 11/23/2023 13 13
31.00 10/11/2023 11/10/2023 73 73
35.00 10/15/2023 11/18/2023 179 179
56.00 10/15/2023 12/9/2023 21 21
84.00 10/15/2023 1/6/2024 53 53
84.00 10/15/2023 1/6/2024 53 53
34.00 10/15/2023 11/17/2023 52 52
56.00 10/19/2023 12/13/2023 211 211
53.00 10/20/2023 12/11/2023 15 15
70.00 10/30/2023 1/7/2024 57 57
70.00 10/30/2023 1/7/2024 57 57
70.00 10/30/2023 1/7/2024 57 57
70.00 10/30/2023 1/7/2024 57 57
35.00 10/30/2023 12/3/2023 92 92
63.00 11/3/2023 1/4/2024 299 299
63.00 11/3/2023 1/4/2024 299 299
119.00 11/6/2023 3/3/2024 226 226
63.00 11/6/2023 1/7/2024 52 52
63.00 11/6/2023 1/7/2024 52 52
84.00 11/6/2023 1/28/2024 31 31
35.00 11/9/2023 12/13/2023 265 265
34.00 11/18/2023 12/21/2023 52 52
98.00 11/19/2023 2/24/2024 4 4
49.00 11/20/2023 1/7/2024 52 52
70.00 11/20/2023 1/28/2024 31 31
70.00 11/20/2023 1/28/2024 31 31
70.00 11/20/2023 1/28/2024 31 31
63.00 11/21/2023 1/22/2024 162 162
48.00 11/22/2023 1/8/2024 32 32
56.00 11/27/2023 1/21/2024 99 99
63.00 11/28/2023 1/29/2024 7 7
35.00 11/28/2023 1/1/2024 21 21
49.00 11/30/2023 1/17/2024 257 257
49.00 11/30/2023 1/17/2024 257 257
56.00 12/4/2023 1/28/2024 92 92
35.00 12/7/2023 1/10/2024 27 27
35.00 12/7/2023 1/10/2024 27 27
77.00 12/7/2023 2/21/2024 5 5
35.00 12/10/2023 1/13/2024 179 179
63.00 12/21/2023 2/21/2024 7 7
63.00 12/21/2023 2/21/2024 7 7
56.00 12/28/2023 2/21/2024 7 7
56.00 12/30/2023 2/23/2024 66 66
98.00 1/2/2024 4/8/2024 21 21
63.00 1/5/2024 3/7/2024 299 299
63.00 1/5/2024 3/7/2024 299 299
98.00 1/8/2024 4/14/2024 15 15
56.00 1/8/2024 3/3/2024 57 57
98.00 1/21/2024 4/27/2024 2 2
35.00 1/23/2024 2/26/2024 183 183
84.00 1/30/2024 4/22/2024 7 7
56.00 2/2/2024 3/28/2024 32 32
63.00 4/23/2024 6/24/2024 162 162
56.00 4/28/2024 6/22/2024 157 157
35.00 4/28/2024 6/1/2024 185 185
42.00 4/28/2024 6/8/2024 164 164
35.00 4/28/2024 6/1/2024 185 185
42.00 4/28/2024 6/8/2024 178 178
56.00 4/28/2024 6/22/2024 2 2
63.00 5/19/2024 7/20/2024 101 101
63.00 5/19/2024 7/20/2024 101 101
63.00 5/19/2024 7/20/2024 101 101
63.00 5/26/2024 7/27/2024 171 171
63.00 5/26/2024 7/27/2024 171 171
63.00 5/26/2024 7/27/2024 171 171
63.00 5/26/2024 7/27/2024 171 171
63.00 5/26/2024 7/27/2024 171 171
63.00 5/26/2024 7/27/2024 171 171
56.00 6/23/2024 8/17/2024 2 2
42.00 6/25/2024 8/5/2024 162 162
63.00 7/21/2024 9/21/2024 101 101
63.00 7/21/2024 9/21/2024 101 101
63.00 7/21/2024 9/21/2024 101 101
42.00 8/18/2024 9/28/2024 2 2
424.00 1/15/2025 3/14/2026 1 1
730.00 1/15/2025 1/14/2027 60 60
365.00 3/15/2026 3/14/2027 1 1