You are on page 1of 2

Risk Assessment/Management Form

Ref:
Section / Dept: civil Activity: Risk Assessment for Bin
Contractor :- building Erection

bility
Current control measure

Proba
bility
Sl Basic Job Potential Consequen Initi Ad

Proba
No. Steps Hazard ce Risk rating al diti Risk rating
Risk on
P E A R al P E A R
Steel structure will be transported at stacking co
zone by hydra ntr
Tripping Get Injury ol
Stacking zone should be in proper sequence 1 0 0 1 2 2 me
Transportation Only skilled riggers will be employed while asu
1
by Hydra/Crane unloading the materials re
Unloading & Get
Unloading will be done with proper certified
stacking Injury/Fatality
slings,D-Shackles & hydra/crane of required
capacity as per load of the structures

Tripping Get Injury 2 0 0 2 2 4


Material shall be stacked at designated place

Stacking of Height of stacked materials shall be


2 maintained as per safety norms & users
materials Unloading &
Get Injury convenience
stacking
Stacking shall be done as per the shape,size
& weight of the materials
Take hot work permit before starting the
cutting activity
Cutting sets must have proper gas pipes with
Get dial watch & Flash back arrestor
3 Cutting activity Burn & Fire
Injury/Fatality To provide fire extinguisher where the hot
work is being carried out 2 0 0 1 2 4
Cutting nozzles must be cleaned before
starting the activity on daily basis
Ascending & Descending shall be
donethrough the inbuilt ladder with anchoring
of double rope safety harness attached with
Ascending and
fall arrestor
Descending of
4 Fall of man Fatality
man at the top Person must be medically fit and he must be
of Col. experienced at specially on height job

Use of safety shoes,helmet,jacket & goggles 2 0 0 1 2 4

All slings and D-shackles used for erection


shall have third party inspection certificate
Capacity of Hydra/Crane must be in
accordance with the weight of the load
Get During erection the signal man must be
5 Erection Failure of slings wearing of reflective jacket
Injury/Fatality
After erection the structures will be anchor 2 0 0 1 2 4
bolted/grouted
Erection team employed in erection must be
skilled & identified
Take Wah permit before starting the activity
Use double rope full body harness for
ascending and descending
Always anchor the safety belt above the
Working at Get
6
height
Fall from height
Injury/Fatality
head height 2 0 0 1 2 4
The erection team employed in erection must
be skilled & identified
Welding activity to be done after taking hot
work permit
Only trained & Experienced Personnel shall
be allowed for welding
Get injury Welding holder should be heavily insulated
Electric shock Respiratory Welding m/c.should be connected with 1 0 0 1 2 2
problem separate earthing
Use of good quality leather hand gloves (Dry
condition)

7 Welding Looking at welders ARC should be avoided


while working with in the vicinity of welding
Use welding screen with helmet of correct
specification of glass
Damage of
Eye injury
both eyes Use of proper ppe 1 0 0 1 2 2

The welding work is done for fixing breching


at taibeam only on the proper temporary
platform and with safe anchoring point
Prepaired by Reviwed by
1of2
Contractor Contractor
Date Date Date

2of2

You might also like