5 Check for All the Frame work materials used as per specs
12 Check the provision for fixing of A/C grills & electrical fittings.
Observations if any :
Page 1 of 2
REQUEST DATE:
QUALITY CONTROL - WORKS INSPECTION ITEMS: Metal Ceiling
REF. NO.:
TITLE OF THE PROJECT Sandvik Pvt Ltd G Block
PACKAGE C&I packages
CONTRACTOR Architects Evolution
DESCRIPTION OF WORKS INSPECTION OF INSTALLATION OF MATERIALS FOR QUALITY COMPLIANCE
CONTRACT CLAUSE DATE
INSPECTION
SAND-BOQ-INT-01 - I - BY
BOQ REF. NO. TIME
65
ITEM DETAILS: Modular Metal Ceiling
WING NO. G-Block
LOCATION FOR
INSPECTION Toilet
FLOOR NO. 3rd floor AREA Coromet, Projects
5 Check for All the Frame work materials used as per specs
12 Check the provision for fixing of A/C grills & electrical fittings.
Observations if any :
Page 2 of 2