Amps X 10 Bus81 (Nom. kV=23, Plot Ref.

kV=23)
,5 1 3 5 10 30 50 100 300 500 1K 3K 5K 10K
1K 1K
Relay BBA 1 - P - 51
OC1
500 Square D 500
Sepam Series 20
300 CT Ratio 100:1 300
Extremely Inverse Time Relay Cabecera Switchgear - P - 51
Pickup = 0,2 (0,1 - 2,4 xCT Sec) OC1
Time Dial = 0,39 Square D
3x = 4,83 s, 5x = 1,61 s, 8x = 0,613 s Sepam Series 40
100 CT Ratio 100:1 100
IEC - Extremely Inverse
Pickup = 1,8 (0,1 - 2,4 xCT Sec)
50 Time Dial = 0,13 50
3x = 1,61 s, 5x = 0,536 s, 8x = 0,204 s
30 Relay BBA 2 - P - 51 30

OC1
Square D
Sepam Series 20
CT Ratio 50:5
10 10
Extremely Inverse Time
Pickup = 0,4 (0,1 - 2,4 xCT Sec)
Time Dial = 0,39
5 5
3x = 4,83 s, 5x = 1,61 s, 8x = 0,613 s

Seconds
Seconds

Relay Molino 3 - P - 51
3 3
OC1
Square D
Sepam Series 80
CT Ratio 100:5
1 IAC - Extremely Inverse 1
Pickup = 1,6 (0,05 - 2,4 xCT Sec)
Time Dial = 1,15
Relay CCM - P - 51 3x = 7,57 s, 5x = 3,07 s, 8x = 1,55 s
,5 ,5
OC1
,3 Square D ,3
Sepam Series 20
CT Ratio 50:5
IAC - Extremely Inverse
Pickup = 0,2 (0,1 - 2,4 xCT Sec)
,1 Time Dial = 0,1 ,1
3x = 0,658 s, 5x = 0,267 s, 8x = 0,135 s

,05 ,05
Bus81 R Relay Cabecera Switchgear

,03 ,03

R R R
R

Relay BBA 1Relay BBA 2Relay CCM


Relay Molino 3

,01 ,01
,5 1 3 5 10 30 50 100 300 500 1K 3K 5K 10K

Amps X 10 Bus81 (Nom. kV=23, Plot Ref. kV=23) ETAP Star 20.0.0C

Project: Date: 30-07-2021


Location: SN:
Contract: Rev: Base
Engineer: Fault: Phase
Filename: D:\Documentos\PROYECTOS ICASEL\Pucobre\01 - Estudio coordinacion de protec