Professional Documents
Culture Documents
ESTIMATES (Autosaved) Kevin
ESTIMATES (Autosaved) Kevin
I SITE PREPARATION
a. clearing and grubbing 0.32 69,015.00
b. Building Layout 0.03 5,945.06
c. Excavation 0.70 149,451.00
d. temporary facilities
e. fencing
II SITE DRAINAGE 1.13 241,980.30
III REINFORC ED CONCRETE
a. Forms and Scaffoldings 1.83 392,010.02
b. Concrete Works 9.52 2,039,170.44
c. Reinforcing Steel Bars 32.20 6,894,919.39
IV MASONRY WORKS 3.92 839,591.09
V PLASTERING WORKS 1.55 332,120.65
VI TILE WORKS 8.27 1,770,217.73
VII FENESTRATIONS
a. Doors 1.79 383,510.00
b. windows 17.27 3,698,270.00
c. Curtain walls
d. Glass and Glazing
e. Iron works
VIII THERMAL PROTECTION 3.70 792,300.00
IX CARPENTRY WORKS
4.08 874,687.69
X PLUMBING WORKS
a. Fixtures and sanitary lines 1.00 214,848.24
b. Tiles and Trims 7.23 1,548,474.62
XI ELECTRICAL WORKS
XII PAINTING WORKS 5.18 1,109,805.25
XIII MISCELLANEOUS ITEMS 0.27 58,860.00
REMARKS: TOTAL PERCENTAGE 100.00
U. COST AMOUNT
I. SITE PREPARATION
a. clearing and grubbing
25.00 x 21.00 2300.5 sq.m. 30.00 69,015.00
b. building lay-out
16 pcs 2" x 2" x 10' 53.33 bdft 41.00 2,186.53
32 pcs 2" x 2" x 8' 85.33 bdft 41.00 3,498.53
3 1/4 kls assorted wire nail 80.00 260
TOTAL 5,945.06
c. excavation
200 sq.m. 600.00 cbmt
16 sets footing 233.28 cbmt
142 lnmt tie beams 51.12 cbmt
22.5 lnmt wall footing 2.25 cbmt
4 set septic tank (large) 77.32 cbmt
2 set septic tank (small) 29.32 cbmt
14 set catch basin 3.05 cbmt
996.34 cbmt 150.00
TOTAL 149,451.00
d. temorary facilities
7 pcs 2"x2"x5' 11.60 bdft 41.00 475.60
4 pcs 2"x2"x7' 9.33 bdft 41.00 382.53
25 pcs 2"x2"x8' 66.70 bdft 41.00 2,734.70
12 pcs 2"x2"x10' 32.00 bdft 41.00 1,312.00
10 pcs 2"x2"x16' 53.30 bdft 41.00 2,185.30
4 pcs 2"x2"x24' 32.00 bdft 41.00 1,312.00
2 pcs 2"x3'x5' 5.00 bdft 41.00 205.00
2 pcs 2"x3'x7' 7.00 bdft 41.00 287.00
29 pcs 2"x3'x8' 166.00 bdft 41.00 6,806.00
4 pcs 2"x3'x16' 32.00 bdft 41.00 1,312.00
2 pcs 2"x3'x24' 24.00 bdft 41.00 984.00
16 pcs 3"x4"x10' 160.00 bdft 41.00 6,560.00
44 pcs G.I gauge 26 at 8' 48.00 2112.00
25 pcs 1/2 marine plywood 640.00 16000
6.55 kls umbrella nails 80.00 524.00
3.96 kls c.w.nails 80.00 316.80
1 pc concrete water closet 220.00 220.00
2 bgs portland cement 230.00 460.00
0.15 cbmt sand 360.00 54.00
0.30 cbmt gravel 360.00 108.00
TOTAL 44,350.93
e. fencing
63 pcs 2"x2"x1' 21.00 bdft 41.00 861.00
94 pcs 2"x2"x6' 188.00 bdft 41.00 7708.00
63 pcs 2"x2"x10' 210.00 bdft 41.00 8610.00
63 pcs 2"x3"x8' 168.00 bdft 41.00 6888.00
30 pcs 10'x6' sawali 600.00 18000.00
10 kls assorted wire nails 80.00 800.00
TOTAL 42,867.00
U. COST AMOUNT
II. SITE DRAINAGE
a. down spout
b. drainage
14 sets catch basin 500.00 7,000.00
78 lnmt storm drain 8" diameter concrete pipes 400.00 31,200.00
c. septic tank
3.50 wd x 5.00L x 3.50depth 192,505.30
( see CHB works)
U. COST AMOUNT
III. REINFORCED CONCRETE WORKS
a. forms and scaffoldings
TOTAL 392,010.02
b. concrete works
Breakdown of cement
72.90 bgs wall footing 8.10 cbmt
360.00 bgs column footing 40.00 cbmt
847.40 bgs column C-1 89.20 cbmt
345.80 bgs tie beams 36.40 cbmt
2,474.01 bgs slab on fill 274.89 cbmt
1,478.30 bgs beams 155.61 cbmt
114.00 bgs roof beam 12.00 cbmt
455.53 bgs auxillary beam 47.95 cbmt
273.89 bgs basement wall 28.83 cbmt
38.57 bgs canilever beam 4.06 cbmt
34.77 bgs stiffener beam 3.66 cbmt
152.10 bgs septic tank 16.01 cbmt
20.43 bgs stair and ramp 2.15 cbmt
U. COST AMOUNT
TOTAL 2,039,170.44
U. COST AMOUNT
c. Reinforcing steel bars
FOUNDATION WORKS
208 pcs 20mm x 6.0 mtrs matting for columns 553.00 115,024.00
674.56 pcs 25mm x 6.0 mtrs columns 860.00 580,121.60
226 pcs 10mm x 6.00 mtrs ties of column 125.00 28,260.00
608 pcs 20mm x 6.00 mtrs beam 1 553.00 336,224.00
704 pcs 20mm x 9.00 mtrs beam 2 830.00 584,320.00
3758.01 pcs 10mm x 6.0 mtrs tie beam stirrups 125.00 469,751.25
15.75 pcs 12mm x 6.0 mtrs beam 2 182.00 2,866.50
12 pcs 25mm x 6.0 mtrs cantilever beam 860.00 10,320.00
27 pcs 10mm x 6.00 mtrs cantilever stirrups 125.00 3,375.00
24 pcs 20mm x 6.00 mtrs stiffener beam 553.00 13,272.00
169.44 pcs 10mm x 6.00 mtrs stiffener stirrups 125.00 21,180.00
ROOF BEAM
306.96 pcs 10mm x 6.00 mtrs stirrups 125.00 38,370.00
51 pcs 20mm x 6.00 mtrs roof beam 1 553.00 28,203.00
48 pcs 20mm x 9.00 mtrs roof beam 2 830.00 39,840.00
U. COST AMOUNT
12,288 pcs 6" concrete hallow blocks 12.00 147,451.20
16,649 pcs 4" concrete hallow blocks 10.00 166,492.95
1,315 bgs portland cement 230.00 302,522.08
1,224 pcs 10mm x 6.00 mtrs def. Bars 125.00 153,031.66
150.32 cbmt pure river sand 450.00 67,644.69
30.61 kls #16 tie wire 80.00 2,448.51
U. COST AMOUNT
V. PLASTERING WORKS
1,237 bags portland cement 230.00 284,422.47
106.00 cbmt screened sand 450.00 47,698.18
U. COST AMOUNT
VI. TILE WORKS
FLOORS
944 pcs 40 x 40 matte floor tiles baesement 151.00 67.21 63,429.44
918 pcs 60 x 60 rustic floor tiles ground floor 330.50 207.00 190,038.42
653 pcs 50 x 50 rustic floor tiles mezzanine 163.20 32.25 21,052.80
2116 pcs 40 x 40 rustic floor tiles second floor 338.50 67.21 142,191.49
2013 pcs 41 x 40 rustic floor tiles third floor 322.00 64.75 130,309.38
1625 pcs 42 x 40 rustic floor tiles fourth floor 260.00 67.21 109,216.25
1394 pcs 43 x 40 matte floor tiles roof deck 223.00 67.21 93,673.94
17 sqmt granite tile kitchen 4600.00 80,316.00
3930 pcs 20 x 20 rustic floor tiles toilet 157.20 14.33 56,316.90
WALLS
6808 pcs 20 x 20 rustic wall tiles toilet 272.30 14.33 97,551.48
sqmt golden wheat ext. accent
14 sqmt granite tile toilet 4,600.00 66,240.00
3 sqmt granite tile laundry 4,600.00 13,800.00
ACCESSORIES
2253 bags tile adhesive 244.00 549,624.64
2235 kilos tile grout 70.00 156,457.00
U. COST AMOUNT
VII. FENESTRATIONS
a. Door panels (see schedule of doors)
TOTAL 976,400.00
b. curtain wall
TOTAL 383,510.00
U. COST AMOUNT
c. windows (see schedule of windows) AREA
Aluminum window
e. Ironworks
TOTAL 527,500.00
SUB TOTAL 3,698,270.00
U. COST AMOUNT
VIII. THERMAL PROTECTION
278 sqmt Rigid steel roof framing 1,750.00 486,500.00
flat 2" x 2" (ceiling joist & nailers) 9,922.16 bdft 41.00 406,808.56
recessed 2" x 2" (ceiling joist & nailers) 694.50 bdft 41.00 28,474.50
cove 2" x 2" (ceiling joist & nailers) 252.51 bdft 41.00 10,352.91
suspended 2" x 2" (ceiling joist & nailers) 274.99 bdft 41.00 11,274.59
915.53 pcs marine plywood 360.00 329,590.80
135.61 kls finishing nails 80.00 10,848.80
92.02 kls assorted common wire nail 80.00 7,361.60
60.88 kls concrete nail 80.00 4,870.40
83.00 lnmt wood moulding 613.40 50,912.20
TOTAL 860,494.36
d. scaffolding
TOTAL 14,193.33
sub total 874,687.69
U. COST AMOUNT
X. PLUMBING WORKS
a. Fixtures
TOTAL 537,566.00
b. Pipes and fittings
TOTAL 214,848.24
c. Tilings and trims
d. Accessories
TOTAL 796,060.38
Sub Total 1,548,474.62
COST BREAKDOWN
REMARKS