AREAS FOR PARKINGS AND DRIVEWAYS

Item Location Description Qty Rate Amount


1 FUNERAL HOME parking (m2) 2,550 900 2,295,000.00
driveway (m2) 1,050 900 945,000.00
Kerbs (lm) 300 585 175,500.00

2 OLE MOIYOI parking (m2) 3,040 900 2,736,000.00


Kerbs (lm) 160 585 93,600.00

3 NEW ADMINISTRATION parking (m2) 1,770 900 1,593,000.00


driveway (m2) 210 900 189,000.00
Kerbs (lm) 130 585 76,050.00

4 TWIN TOWERS parking (m2) 2,760 900 2,484,000.00


Kerbs (lm) 160 585 93,600.00

5 BSSC & AMPHITHEATRE parking (m2) 2,940 900 2,646,000.00

6 SCH. OF ENGINEERING parking (m2) 2,005 900 1,804,500.00

7 NYAYO GATE - SCH. OF driveway (m2) 2,750 900 2,475,000.00


ECONOMICS ROAD
Kerbs (lm) 40 585 23,400.00

ESTIMATED MATERIAL COST 17,629,650.00


AREAS FOR PARKINGS AND DRIVEWAYS

Item Location Description Unit Qty Rate Amount


1 FUNERAL HOME Parking SM 2,550 900 2,295,000.00
Driveway SM 1,050 900 945,000.00
Kerbs LM 300 585 175,500.00
Quarry dust Ton 340 1100 374,000.00

2 OLE MOIYOI Parking SM 3,040 900 2,736,000.00


Kerbs LM 160 585 93,600.00
Quarry dust Ton 245 1100 269,500.00

3 ADMISSIONS BLOCK Parking SM 1,770 900 1,593,000.00


Driveway SM 210 900 189,000.00
Kerbs LM 130 585 76,050.00
Hardcore CM 790 1100 869,000.00
Quarry dust Ton 160 1100 176,000.00

4 TWIN TOWERS Parking SM 2,760 900 2,484,000.00


Kerbs LM 160 585 93,600.00
Quarry dust Ton 220 1100 242,000.00

5 BSSC & AMPHITHEATRE Parking SM 2,940 900 2,646,000.00


Quarry dust Ton 235 1100 258,500.00

6 SCH. OF ENGINEERING Parking SM 2,005 900 1,804,500.00


Quarry dust Ton 160 1100 176,000.00

7 NYAYO GATE - SCH. OF Driveway SM 2,750 900 2,475,000.00


ECONOMICS ROAD
Kerbs LM 40 585 23,400.00
Quarry dust Ton 220 1100 242,000.00

ESTIMATED MATERIAL COST 20,236,650.00

Add: 25% for Labour 5,059,162.50

TOTAL ESTIMATED COST FOR ROADWORKS 25,295,812.50


AREAS FOR PARKINGS AND DRIVEWAYS

Item Location Description Unit Qty Rate Amount


1 FUNERAL HOME Parking (cabro) SM 2,550 900 2,295,000.00
Driveway (cabro) SM 1,050 900 945,000.00
Kerbs LM 300 585 175,500.00
Quarry dust Ton 340 1100 374,000.00

2 OLE MOIYOI Parking (cabro) SM 3,040 900 2,736,000.00


Kerbs LM 160 585 93,600.00
Quarry dust Ton 245 1100 269,500.00

3 ADMISSIONS BLOCK Parking (cabro) SM 1,770 900 1,593,000.00


Driveway (cabro) SM 210 900 189,000.00
Kerbs LM 130 585 76,050.00
Hardcore CM 790 1100 869,000.00
Quarry dust Ton 160 1100 176,000.00

4 TWIN TOWERS (ARTS COMPLEX) Parking (cabro) SM 2,760 900 2,484,000.00


Kerbs LM 160 585 93,600.00
Quarry dust Ton 220 1100 242,000.00

5 BSSC & AMPHITHEATRE Parking (cabro) SM 2,940 900 2,646,000.00


Quarry dust Ton 235 1100 258,500.00

6 SCH. OF ENGINEERING Parking (cabro) SM 2,005 900 1,804,500.00


Quarry dust Ton 160 1100 176,000.00

ESTIMATED MATERIAL COST 17,496,250.00


AREAS FOR PARKINGS AND DRIVEWAYS

Item Location Description Unit Qty Rate Amount

1 ADMISSIONS BLOCK Parking (cabro) SM 1,770 900 1,593,000.00


Driveway (cabro) SM 210 900 189,000.00
Kerbs LM 130 585 76,050.00
Hardcore CM 790 1100 869,000.00
Quarry dust Ton 160 1100 176,000.00

2 TWIN TOWERS (ARTS COMPLEX) Parking (cabro) SM 2,760 900 2,484,000.00


Kerbs LM 160 585 93,600.00
Quarry dust Ton 220 1100 242,000.00

3 BSSC Parking (cabro) SM 1,200 900 1,080,000.00


Quarry dust Ton 96 1100 105,600.00

4 SCH. OF ENGINEERING Parking (cabro) SM 2,005 900 1,804,500.00


Quarry dust Ton 160 1100 176,000.00

5 SZ 39 Parking (cabro) SM 2,120 900 1,908,000.00


Kerbs LM 315 585 184,275.00
Hardcore CM 650 1100 715,000.00
Quarry dust Ton 170 1100 187,000.00

ESTIMATED MATERIAL COST 11,883,025.00


Roadworks

ITEM DESCRIPTION QTY. UNIT RATE AMOUNT

UPGRADING OF NYAYO GATE-KAMAE GATE ROAD

A Grade, scarify, water and compact existing


carriageway as directed by the Engineer 2,750 SM 150 412,500.00

B
Provide, place, water and compact 200mm natural
gravel to 95% MDD to form a new base layer and for
sub base repairs on carriageway as directed by the
Engineer 2,750 SM 150 412,500.00

C
Supply and spray bituminous binders (prime coat) to
the prepared road surface to receive 20mm thick
overlay, measured separately (spray rate at 1.2litres/
square metre) 2,750 SM 120 330,000.00

D Supply asphalt (premix) and lay to a compacted


thickness of 20mm base course to falls. Allow for
laying of asphalt concrete to standard specification of
the Ministry of Roads
2,750 SM 650 1,787,500.00

E
Supply and spray bituminous binders (tack coat) to
the prepared road surface to receive 20mm thick
overlay, measured separately (spray rate at 0.8litres/
square metre) 2,750 SM 80 220,000.00

F Supply asphalt (premix) and lay to a compacted


thickness of 15mm wearing course to falls. Allow for
laying of asphalt concrete to standard specification of
the Ministry of Roads
2,750 SM 500 1,375,000.00

G Excavate for, provide, lay and joint 250x125mm


precast concrete kerb haunched in 100mm thick
class 15/20 concrete base bedding and mortar
jointed in support to carriage way as directed by the
Engineer
50 LM 900 45,000.00

H Allow for traffic control and safety of road users


during the upgrading period ITEM 20,000.00

CARRIED TO COLLECTION 4,602,500.00

RW/5
Roadworks

ITEM DESCRIPTION QTY. UNIT RATE AMOUNT

RECARPETING OF ROADS IN MAIN CAMPUS

A Cut off the failed areas (pot holes) to a minimum


depth of 150mm and dispose to spoils as directed 27,115 SM 80 2,169,200.00

B Pitch the cut potholes with quarry waste hardcore


and compact to approval 27,115 SM 100 2,711,500.00

C Supply quarry dust and fill the roads in item B above


27,115 SM 80 2,169,200.00

D
Supply and spray bituminous binders (tack coat) to
the prepared road surface to receive 20mm thick
overlay, measured separately (spray rate at 1.2litres/
square metre) 27,115 SM 120 3,253,800.00

E Supply asphalt (premix) and lay to a compacted


thickness of 20mm wearing course to falls. Allow for
laying of asphalt concrete to standard specification of
the Ministry of Roads
27,115 SM 650 17,624,750.00

F Allow for traffic control and safety of road users


during the recarpeting period ITEM 20,000.00

G Allow for removal of debris and soil deposits to side


drains ITEM 20,000.00

CARRIED TO COLLECTION KSH. 27,968,450.00

RW/6
Roadworks

ITEM DESCRIPTION QTY. UNIT RATE AMOUNT

COLLECTION

1 Preliminaries

2 From page RW/1 KSH. 4,602,500.00

3 From page RW/2 KSH. 27,968,450.00

4 Allow a provisional sum of Ksh 1,000,000.00 for


contingencies KSH. 1,000,000.00

TOTAL FOR ROADWORKS (Inclusive of VAT) KSH. 33,570,950.00

Signature and stamp of Tenderer ……………………………………...………………

Address ………………………………………………………………………….

Date …………………………………..

RW/7
Parkings

ITEM DESCRIPTION QTY. UNIT RATE AMOUNT

UPGRADING OF PARKINGS WITHIN THE CAMPUS

FUNERAL HOME (ROAD AND PARKING)

A Grade, scarify, water and compact existing


carriageway as directed by the Engineer 3,600 SM

B
Provide, place, water and compact 200mm natural
gravel to 95% MDD to form a new base layer and for
sub base repairs on carriageway as directed by the
Engineer 3,600 SM

C
Supply and spray bituminous binders (prime coat) to
the prepared road surface to receive 20mm thick
overlay, measured separately (spray rate at 1.2litres/
square metre) 3,600 SM

D Supply asphalt (premix) and lay to a compacted


thickness of 20mm base course to falls. Allow for
laying of asphalt concrete to standard specification of
the Ministry of Roads
3,600 SM

E
Supply and spray bituminous binders (tack coat) to
the prepared road surface to receive 20mm thick
overlay, measured separately (spray rate at 0.8litres/
square metre) 3,600 SM

F Supply asphalt (premix) and lay to a compacted


thickness of 15mm wearing course to falls. Allow for
laying of asphalt concrete to standard specification of
the Ministry of Roads
3,600 SM

G Excavate for, provide, lay and joint 250x125mm


precast concrete kerb haunched in 100mm thick
class 15/20 concrete base bedding and mortar
jointed in support to carriage way as directed by the
Engineer
300 LM

H Allow for traffic control and safety of users during the


upgrading period ITEM

CARRIED TO COLLECTION KSH.

P/8
Parkings

ITEM DESCRIPTION QTY. UNIT RATE AMOUNT

OLE MOIYOI PARKING

A Grade, scarify, water and compact existing


carriageway as directed by the Engineer 3,040 SM

B
Provide, place, water and compact 200mm natural
gravel to 95% MDD to form a new base layer and for
sub base repairs on carriageway as directed by the
Engineer 3,040 SM

C
Supply and spray bituminous binders (prime coat) to
the prepared road surface to receive 20mm thick
overlay, measured separately (spray rate at 1.2litres/
square metre) 3,040 SM

D Supply asphalt (premix) and lay to a compacted


thickness of 20mm base course to falls. Allow for
laying of asphalt concrete to standard specification of
the Ministry of Roads
3,040 SM

E
Supply and spray bituminous binders (tack coat) to
the prepared road surface to receive 20mm thick
overlay, measured separately (spray rate at 0.8litres/
square metre) 3,040 SM

F Supply asphalt (premix) and lay to a compacted


thickness of 15mm wearing course to falls. Allow for
laying of asphalt concrete to standard specification of
the Ministry of Roads
3,040 SM

G Excavate for, provide, lay and joint 250x125mm


precast concrete kerb haunched in 100mm thick
class 15/20 concrete base bedding and mortar
jointed in support to carriage way as directed by the
Engineer
160 LM

H Allow for traffic control and safety of users during the


upgrading period ITEM

CARRIED TO COLLECTION KSH.

P/9
Parkings

ITEM DESCRIPTION QTY. UNIT RATE AMOUNT

AMPHITHEATRE PARKING

A Grade, scarify, water and compact existing


carriageway as directed by the Engineer 1,750 SM

B
Provide, place, water and compact 200mm natural
gravel to 95% MDD to form a new base layer and for
sub base repairs on carriageway as directed by the
Engineer 1,750 SM

C
Supply and spray bituminous binders (prime coat) to
the prepared road surface to receive 20mm thick
overlay, measured separately (spray rate at 1.2litres/
square metre) 1,750 SM

D Supply asphalt (premix) and lay to a compacted


thickness of 20mm base course to falls. Allow for
laying of asphalt concrete to standard specification of
the Ministry of Roads
1,750 SM

E
Supply and spray bituminous binders (tack coat) to
the prepared road surface to receive 20mm thick
overlay, measured separately (spray rate at 0.8litres/
square metre) 1,750 SM

F Supply asphalt (premix) and lay to a compacted


thickness of 15mm wearing course to falls. Allow for
laying of asphalt concrete to standard specification of
the Ministry of Roads
1,750 SM

G Allow for traffic control and safety of users during the


upgrading period ITEM

CARRIED TO COLLECTION KSH.

P/10
Parkings

ITEM DESCRIPTION QTY. UNIT RATE AMOUNT

COLLECTION

1 Preliminaries KSH.

2 From page P/1 KSH.

3 From page P/2 KSH.

4 From page P/3 KSH.

5 Allow a provisional sum of Ksh 500,000.00 for


contingencies KSH. 500,000.00

TOTAL FOR PARKINGS (Inclusive of VAT) KSH.

Signature and stamp of Tenderer ……………………………………...………………

Address ………………………………………………………………………….

Date …………………………………..

P/11
Ruiru Campus Gate

ITEM DESCRIPTION QTY. UNIT RATE AMOUNT

TARMACKING TO RUIRU CAMPUS GATE

The hardcore handpacking and compaction has


already been done on site

A 150mm Thick gravel or murrum base compacted to


98% MDD, compaction at optimum moisture content
in road areas including grading to falls 160 SM 200 32,000.00

B
Supply and spray bituminous binders (prime coat) to
the prepared road surface to receive 20mm thick
overlay, measured separately (spray rate at 1.2litres/
square metre) 160 SM 120 19,200.00

C Supply asphalt (premix) and lay to a compacted


thickness of 20mm base course to falls. Allow for
laying of asphalt concrete to standard specification of
the Ministry of Roads
160 SM 650 104,000.00

D
Supply and spray bituminous binders (tack coat) to
the prepared road surface to receive 20mm thick
overlay, measured separately (spray rate at 0.8litres/
square metre) 160 SM 80 12,800.00

E Supply asphalt (premix) and lay to a compacted


thickness of 20mm wearing course to falls. Allow for
laying of asphalt concrete to standard specification of
the Ministry of Roads
160 SM 650 104,000.00

F Preliminaries SUM 100,000.00

G Allow a provisional sum of Ksh 100,000.00 for


contingencies SUM 100,000.00

TOTAL FOR TARMACKING (Inclusive of VAT) KSH. 472,000.00

Signature and stamp of Tenderer ……………………………………...………………

Address ………………………………………………………………………….

Date …………………………………..