Daily Site diary & Progress Report

THE DESIGN, PROCUREMENT, FURNISHING AND EXECUTION OF ETHIOPIAN SKYLIGHT 5-STAR HOTEL PHASE -II PROJECT
Project No. & Title: Ref: 693

Employer Engineer: Contractor

ON SITE STAFF & LABOUR RECORD Day: Wednesday Date: 2021/9/1 ON SITE PLANT & EQUIPMENT RECORD

No. Trade No. Hrs No. Trade No. Hrs No. Category No. Hrs No. Category No.

1 Generl Manager 1 9 Weather Sunny Cloudy Rainy Windy Dusty 1 Loader 1 9

2 DGM 1 9 √ 2 Lorry 1 9

3 Contract manager 1 9 3 Mobile Crane 1 9

4 Engineering manager 1 9 Temperature Minimum 9C


8 C Maximum28C
2 C 4 Generator 2 9

5 Safety director 1 9 5 Bar bender machine 2 9

6 MEP iManager 1 9 DELIVERY OF MATERIALS 6 Bar cutter machine 2 9

7 Construction manager 1 9 No. Material Qty. Unit 7 Concrete Pump 2 9

8 Commercial manager 1 9 1 8 Concret boom placer 0 9

9 Civil Engineer 4 9 2 9 Tower Crane 2 9

10 Financial Manager 1 9 3 10 Truck Mixer 4 9

11 Construction Staff 9 9 4 11 Construction hoist 3 9

12 Office Staff 7 9 5

13 Site Works 299 7 6

14 7

15 8

VISITORS ON SITE DESCRIPTION OF WORKS DONE

No. Name Organization No. Qty.

1 1 Platering for the ground floor and first floor. Following

2 2 Electrical conduit installation for the CCTV 1F 5%

3 3 Electrica conduit installation for the E6,E8,H4,F2 firebroadcasting . 5%

4 Electrical cable installation for the the roof E,F,H block 5%

Guest room drainage branche pipe installation "E""F""H" block. Following


5
Drainage pipe hole drill H8,Water supply drainage horizontal pipe installation F6water supply main
5%
6 vertical pipe installation "F" block

REMARKS 7 Fan coil branch pipe installation for the "E""F""H" block Following

8 AC water supply main pipe installation E1,balance valve installation "E"9 5%


The confirmed cases of COVID-19 in Ethiopian have seriously affected
the project progress .And it has resulted the mobilization delay of chinese 9 Firefighting branch pipe installation for the financial room H1,firefighting hydrant installation for H9, 5%
1
technican and local labor based the site progress and the local workers
10 Firefighting spray branch pipe installation for E8,H4 5%
have decreased rapidly at site.
11 Ventilation damper and sound reducer installation for B1 5%
Working time of the local workers has to be decreased from 9 hours to 7 hours Fan coil installation and fresh air duct installation for guest room H8 5%
for one day due to transportation problem caused by COVID -19 and they also 12
2
need more payments such as special transportation fee for their work.
13 AC fresh air duct installation for the daily restaurant and leisure area 1F. 5%

3 Covid-19 case appears on the project camp , this seriously affect the project
14 Aluminium frame installation and glass installation for guest room "E,F,H" block 5%
progress.
15 Steel bracket installation and waterproof primer applicationfor the west elevation "E" block Following

16 ID MEP work for the guest room Following

17 Wire mesh installation for the toilet for the plastering. Following

18 light steel frame for the dry wall and rock rool fill Following

19 Screed level for the guest room Following

20 Gypsum and polywood board installation Following

21 Toilet partition wall frame and cement board installation . Following

22 Curtain cabinet and light cabinet installation. Following

Submission: Noted:

Signed by: Song Baoliang Signature Signed by: Signature: