Notification Planned Dates

Task ID Task Weightage Start End


Boiler 1 Annual Shutdown June 2021 6/13/2021 8/16/2021
Unit Shutdown Activity 6/13/2021 6/20/2021
Boiler Hot box-up 6/13/2021 6/14/2021
Start ID Fan for boiler cooling 6/14/2021 6/14/2021

Force air cooling and bed material draining


6/14/2021 6/17/2021
from combustor, all FBHE EC BC, Seal pot & BAC

Electrical isolation (Only Fans excluding


6/17/2021 6/17/2021
blowers ) for Manhole door opening.

Manhole door opening - LHS & RHS cyclone


6/17/2021 6/18/2021
inlet duct. Combustor and COD if required.

COD & CID Inside Cleaning from Outside


(with ID fan Running) 6/18/2021 6/20/2021

HSD Line blinding 6/17/2021 6/17/2021


Manhole door opening - Balance doors 6/18/2021 6/18/2021
Non Pressure Part Leakage Checking 6/18/2021 7/3/2021

SA & PA APH inlet duct and SCAPH cleaning 6/28/2021 6/30/2021

FBHE APH tube air leak test 6/18/2021 6/19/2021


SA & PA SCAPH tube hydro test 6/30/2021 7/3/2021
Electrical isolation after leak test (All Blower 6/19/2021 6/19/2021
Isolation)
Boiler Cleaning Activities 6/18/2021 7/12/2021

LHS & RHS Cyclone Inlet Duct Inside Cleaning 6/20/2021 6/21/2021

LHS & RHS Cyclone Outlet Duct Inside


6/21/2021 6/23/2021
Cleaning
Both Seal pot inside cleaning 6/18/2021 6/19/2021
Combustor inside cleaning 6/19/2021 6/21/2021
FBHE-1 & 4 EC & BC inside cleaning 6/20/2021 6/22/2021
FBHE-2 & 3 EC & BC inside cleaning 6/21/2021 6/24/2021
Windbox inspection and cleaning 6/24/2021 6/25/2021
Second Pass Complete Cleaning 6/22/2021 6/30/2021
Bed Ash Cooler 1 &2 Cleaning 6/25/2021 6/26/2021

Eco to APH Inside Cleaning (O2 Analyser) 6/25/2021 6/30/2021

Boiler outside cleaning 6/22/2021 7/2/2021

Boiler zero meter- ground floor cleaning 7/2/2021 7/12/2021

SPRING SUPPORT OF STEAM HEADERS &


RETURN LEGS (BORL list-18) (Maintenance 6/30/2021 7/5/2021
defect rectify if any identified)
Drum floor and first pass pent house roof
7/5/2021 7/7/2021
top cleaning
Second pass pent house inside cleaning 7/7/2021 7/9/2021
First pass pent house inside cleaning 7/9/2021 7/11/2021
Mechanical 6/17/2021 8/9/2021
ESP Activities 6/22/2021 7/31/2021
ESP isolation and kesal key removal and
7/8/2021 7/9/2021
field earthing
Improvement - Air Tapping Provision for 7/9/2021 7/10/2021
ESP Cleaning Task
ESP roof top manhole door opening 7/9/2021 7/9/2021
ESP roof top cleaning- both pass 7/10/2021 7/12/2021
ESP air cleaning- both Pass from pent
house 7/12/2021 7/14/2021

Stop ash conveying and hopper bellow


removal 6/22/2021 6/23/2021

Air Cleaning 7/19/2021 7/23/2021


Inspection of ESP 7/23/2021 7/24/2021

Rectification by Mechanical & Electrical 7/24/2021 7/28/2021

After rectification IR valve checked and


clerance given to box up. 7/30/2021 7/31/2021

Manhole door box up and hopper bellow


7/31/2021 7/31/2021
box up work
IBR Inspection & Hydro Test 7/2/2021 8/3/2021
Internal Hydro 1 7/2/2021 7/3/2021
Defect rectification (if any leakage
7/3/2021 7/6/2021
identified)

Internal hydrotest after defect rectification 7/6/2021 7/6/2021

External Hydro Test (In Presence of IBR


7/13/2021 7/13/2021
Inspector)
Hydro After Joint Repair 7/30/2021 7/31/2021
Defect Rectification 7/31/2021 8/3/2021
Final Hydro 8/3/2021 8/3/2021
Combustor ( Scallop Plate) 6/21/2021 8/2/2021
Permit issuing and site readiness 6/21/2021 6/22/2021
Pressure Part Tube Thickness Mapping
7/5/2021 7/15/2021
(Including S Bend)

Inspection & Rectification of Scallop Plate 7/12/2021 7/16/2021

Pressure parts rectification. (if identified) 7/15/2021 7/18/2021

Inspection of Refractory 7/22/2021 7/23/2021


Refractory Breaking (Combustor & Return
7/18/2021 7/19/2021
Leg)

Anchor Welding For refractory Application 7/19/2021 7/20/2021

Refractory Application ( Return Leg & loop


7/21/2021 7/25/2021
Seal) - LiZ
Refractory 90 XR. 7/20/2021 7/24/2021
Nozzle cleaning, pinning and damaged 7/28/2021 8/2/2021
nozzle replacement work

RHS Cyclone (Vortex Finder Re-installation) 6/24/2021 8/9/2021

RHS Cyclone Roof Cutting for Vortex Finder


Lifting 6/24/2021 6/26/2021

Pocket Cutting at Cyclone Roof for Vortex


6/26/2021 6/28/2021
Finder Lifting Arrangement
Vortex Lifting 6/26/2021 6/30/2021
Vortex Fitment at Position 7/11/2021 7/15/2021
Refractory Breaking / Brick Removal
7/15/2021 7/20/2021
(Conical & Cylidrical Portion)
Refractory Applications (LiZ + LC 80) -
Conical & Cylindrical Portion 7/20/2021 7/27/2021

Vortex Plate / Clamp welding & Inspection 7/15/2021 7/17/2021

Cyclone Roof Refractory & Leakage 7/17/2021 7/19/2021


Rectification
Cyclone Inlet Duct NMEJ wool Stuffing 7/15/2021 7/16/2021
Plate Welding an Cyclone Outlet after
7/15/2021 7/16/2021
Vortex Fitment
Improvement - Process Tapping
7/17/2021 7/18/2021
Modification
Standpipe & Seal Pot area Cleaning ,Nozzle
8/4/2021 8/7/2021
Inspection
Dechocking of Drain Pipe 8/7/2021 8/8/2021
Nozzle Replacement 8/8/2021 8/9/2021
LHS Cyclone 7/13/2021 8/7/2021
Refractory Breaking / Brick Removal
7/13/2021 7/18/2021
(Conical & Cylidrical Portion)
Refractory Applications (LiZ + LC 80) -
7/18/2021 7/24/2021
Conical & Cylindrical Portion
Cyclone Roof Refractory & Leakage
7/24/2021 7/26/2021
Rectification
Cyclone Inlet Duct MEJ wool Stuffing 7/24/2021 7/25/2021
Improvement - Process Tapping
7/30/2021 7/31/2021
Modification
Standpipe & Seal Pot area Cleaning ,Nozzle
8/3/2021 8/5/2021
Inspection
Dechocking of Drain Pipe 8/5/2021 8/6/2021
Nozzle Replacement 8/6/2021 8/7/2021
FBHE 1 (Partition Wall ) 6/22/2021 7/16/2021
Inspection of FBHE EC & BC 6/22/2021 6/22/2021
Parttion Wall Refractory Breaking 6/22/2021 6/25/2021
Damaged/burn-out plate cutting and 6/25/2021 6/28/2021
removing. (if required)
1st stage New plate fitment and full
6/28/2021 6/30/2021
welding and anchor welding.
1st stage Refractory application as per
standard procedures. 6/30/2021 7/1/2021

2nd stage New plate fitment and full


7/1/2021 7/2/2021
welding and anchor welding.
2nd stage Refractory application as per
7/2/2021 7/3/2021
standard procedures.
Tube thickness mapping 7/4/2021 7/6/2021
3rd stage New plate fitment and full
7/4/2021 7/5/2021
welding and anchor welding.
3rd stage Refractory application as per
standard procedures. 7/5/2021 7/6/2021

4th stage New plate fitment and full


7/6/2021 7/8/2021
welding and anchor welding.
4th stage Refractory application as per 7/8/2021 7/9/2021
standard procedures.
5th stage New plate fitment and full
7/9/2021 7/11/2021
welding and anchor welding.
5th stage Refractory application as per
7/11/2021 7/12/2021
standard procedures.
BC Side refractory Work 7/12/2021 7/14/2021
Nozzle cleaning, pinning and damaged
7/15/2021 7/16/2021
nozzle replacement work
Final Inspection & Box up 7/16/2021 7/16/2021
FBHE-1 roof top leakage rectification (roof
7/9/2021 7/11/2021
air cleaning required)
Coil Insertion Area Ceramic Wool Stuffing
7/8/2021 7/10/2021
& Refractory Application
Improvement - Partition Wall Cooling Air
Provision 7/5/2021 7/6/2021

Improvement - Windbox Inspection


Manhole Door Opening 7/5/2021 7/6/2021

FBHE 4 6/24/2021 7/23/2021


Inspection of FBHE EC & BC 6/24/2021 6/24/2021
Parttion Wall Refractory Breaking 6/24/2021 6/27/2021
Damaged/burn-out plate cutting and
6/27/2021 6/30/2021
removing. (if required)
1st stage New plate fitment and full 6/30/2021 7/2/2021
welding and anchor welding.
1st stage Refractory application as per
7/2/2021 7/3/2021
standard procedures.
2nd stage New plate fitment and full
7/3/2021 7/4/2021
welding and anchor welding.
2nd stage Refractory application as per 7/4/2021 7/5/2021
standard procedures.
Tube thickness mapping 7/5/2021 7/7/2021
3rd stage New plate fitment and full
welding and anchor welding. 7/6/2021 7/7/2021

3rd stage Refractory application as per


7/7/2021 7/8/2021
standard procedures.
4th stage New plate fitment and full
7/8/2021 7/10/2021
welding and anchor welding.
4th stage Refractory application as per
7/10/2021 7/11/2021
standard procedures.
5th stage New plate fitment and full
welding and anchor welding. 7/11/2021 7/13/2021

5th stage Refractory application as per


7/13/2021 7/14/2021
standard procedures.
BC Side refractory Work 7/14/2021 7/16/2021
Nozzle cleaning, pinning and damaged 7/16/2021 7/17/2021
nozzle replacement work
Final Inspection & Box up 7/17/2021 7/18/2021
FBHE-1 roof top leakage rectification (roof
7/18/2021 7/19/2021
air cleaning required)
Coil Insertion Area Ceramic Wool Stuffing 7/19/2021 7/21/2021
& Refractory Application
Improvement - Partition Wall Cooling Air
7/21/2021 7/22/2021
Provision
Improvement - Windbox Inspection
7/22/2021 7/23/2021
Manhole Door Opening
FBHE 2 6/24/2021 7/25/2021
Inspection of FBHE EC & BC 6/24/2021 6/24/2021
Parttion Wall Refractory Breaking 6/27/2021 6/30/2021
Damaged/burn-out plate cutting and
removing. (if required) 6/30/2021 7/3/2021

1st stage New plate fitment and full


welding and anchor welding. 7/3/2021 7/5/2021

1st stage Refractory application as per


7/5/2021 7/6/2021
standard procedures.
2nd stage New plate fitment and full
7/6/2021 7/7/2021
welding and anchor welding.
2nd stage Refractory application as per 7/7/2021 7/8/2021
standard procedures.
Tube thickness mapping 7/7/2021 7/9/2021
3rd stage New plate fitment and full
7/8/2021 7/9/2021
welding and anchor welding.
3rd stage Refractory application as per 7/9/2021 7/10/2021
standard procedures.
4th stage New plate fitment and full
7/10/2021 7/12/2021
welding and anchor welding.
4th stage Refractory application as per
standard procedures. 7/12/2021 7/13/2021

5th stage New plate fitment and full


7/13/2021 7/15/2021
welding and anchor welding.
5th stage Refractory application as per
7/15/2021 7/16/2021
standard procedures.
BC Side refractory Work 7/16/2021 7/18/2021
Nozzle cleaning, pinning and damaged
7/18/2021 7/19/2021
nozzle replacement work
Final Inspection & Box up 7/20/2021 7/20/2021
FBHE-1 roof top leakage rectification (roof
7/18/2021 7/20/2021
air cleaning required)
Coil Insertion Area Ceramic Wool Stuffing 7/18/2021 7/20/2021
& Refractory Application
Improvement - Partition Wall Cooling Air 7/23/2021 7/24/2021
Provision
Improvement - Windbox Inspection
7/24/2021 7/25/2021
Manhole Door Opening
FBHE 3 6/27/2021 7/23/2021
Inspection of FBHE EC & BC 6/27/2021 6/27/2021
Parttion Wall Refractory Breaking 6/27/2021 6/30/2021
Damaged/burn-out plate cutting and
removing. (if required) 6/30/2021 7/3/2021

Tube thickness mapping 7/3/2021 7/5/2021


BC Side refractory Work 7/5/2021 7/7/2021
Nozzle cleaning, pinning and damaged
7/7/2021 7/8/2021
nozzle replacement work
Final Inspection & Box up 7/8/2021 7/9/2021
FBHE-1 roof top leakage rectification (roof
7/9/2021 7/10/2021
air cleaning required)
Coil Insertion Area Ceramic Wool Stuffing
7/5/2021 7/7/2021
& Refractory Application
Improvement - Partition Wall Cooling Air
7/7/2021 7/8/2021
Provision
Improvement - Windbox Inspection
7/22/2021 7/23/2021
Manhole Door Opening
Bed Ash Cooler 1 6/18/2021 7/19/2021
Manhole Door Opening 6/18/2021 6/18/2021

Inspection of Refractory & Partition Wall 6/26/2021 6/27/2021

Partition Wall Refractory Breaking 6/29/2021 7/3/2021

Partition Wall Plate Cutting & Removal 7/3/2021 7/7/2021

1st Stage - Partition Wall Fitment ,Welding


7/7/2021 7/8/2021
with Anchors
1st Stage - Partition Wall Refractory
Application 7/8/2021 7/9/2021

2nd Stage - Partition Wall Fitment ,Welding


7/9/2021 7/9/2021
with Anchors
2nd Stage - Partition Wall Refractory
7/9/2021 7/10/2021
Application
3rd Stage - Partition Wall Fitment ,Welding
7/11/2021 7/12/2021
with Anchors
3rd Stage - Partition Wall Refractory
Application 7/12/2021 7/13/2021

Roof Cleaning,Inspection Pocket Cutting &


7/13/2021 7/17/2021
Refractory Pouring
Nozzle Cleaning,Pinning,Inspection & 7/17/2021 7/19/2021
Replacement

Discharge Duct , MEJ Inspection & Repair 7/13/2021 7/14/2021

Old NMEJ Removal by Cutting 6/19/2021 6/21/2021


Cooling Water Line Cutting for New NMEJ
6/21/2021 6/22/2021
Fitment
New NMEJ Fitment 6/22/2021 6/24/2021
New NMEJ Flange Welding at Both Ends &
6/24/2021 6/27/2021
Bolting
Cooling Water line Restoration after NMEJ
6/27/2021 6/29/2021
Fitment
BAC 1 &2 Cooler Common Vent NMEJ &
7/14/2021 7/17/2021
Pipe Replacement/Repair
Bed Ash Cooler 2 6/18/2021 7/19/2021
Manhole Door Opening 6/18/2021 6/18/2021

Inspection of Refractory & Partition Wall 6/26/2021 6/27/2021

Partition Wall Refractory Breaking 6/30/2021 7/4/2021

Partition Wall Plate Cutting & Removal 7/4/2021 7/8/2021


1st Stage - Partition Wall Fitment ,Welding
7/8/2021 7/9/2021
with Anchors
1st Stage - Partition Wall Refractory 7/9/2021 7/10/2021
Application
2nd Stage - Partition Wall Fitment ,Welding
7/10/2021 7/10/2021
with Anchors
2nd Stage - Partition Wall Refractory
7/10/2021 7/11/2021
Application
3rd Stage - Partition Wall Fitment ,Welding 7/12/2021 7/13/2021
with Anchors
3rd Stage - Partition Wall Refractory
7/13/2021 7/14/2021
Application
Roof Cleaning,Inspection Pocket Cutting &
Refractory Pouring 7/14/2021 7/18/2021

Nozzle Cleaning,Pinning,Inspection &


Replacement 7/13/2021 7/15/2021

Discharge Duct , MEJ Inspection & Repair 7/18/2021 7/19/2021

Old NMEJ Removal by Cutting 6/21/2021 6/23/2021


Cooling Water Line Cutting for New NMEJ
Fitment 6/23/2021 6/24/2021

New NMEJ Fitment 6/24/2021 6/26/2021


New NMEJ Flange Welding at Both Ends &
6/26/2021 6/29/2021
Bolting
Cooling Water line Restoration after NMEJ 6/29/2021 7/1/2021
Fitment
Spiess Valve Overhauling ( All 07 Nos.) 6/25/2021 7/13/2021
BAC 1 - Valve Dismantling Work 6/25/2021 6/26/2021

Pipe & Nozzle Stone Area De-chocking 6/26/2021 6/28/2021

Nozzle Stone, Bricks,Lance Tube & Tip


6/28/2021 7/2/2021
Inspection & Gap Measurement
Spiess Valve HydroTest 7/2/2021 7/3/2021
Purging Air line De-chocking & Reapir /
7/3/2021 7/3/2021
Replacement
Stroke Checking & Stopper Provsion 7/3/2021 7/4/2021
BAC-2 - Valve Dismantling Work 6/26/2021 6/27/2021

Pipe & Nozzle Stone Area De-chocking 6/27/2021 6/29/2021

Nozzle Stone, Bricks,Lance Tube & Tip


6/29/2021 7/3/2021
Inspection & Gap Measurement
Spiess Valve HydroTest 7/3/2021 7/4/2021
Purging Air line De-chocking & Reapir /
7/4/2021 7/4/2021
Replacement
Stroke Checking & Stopper Provision 7/4/2021 7/5/2021
FBHE 4 to BAC 1 Spiess Valve Dismantling 6/24/2021 6/24/2021

Pipe & Nozzle Stone Area De-chocking 6/24/2021 6/26/2021

Nozzle Stone, Bricks,Lance Tube & Tip


6/26/2021 6/30/2021
Inspection & Gap Measurement
Spiess Valve HydroTest 6/30/2021 7/1/2021
Purging Air line De-chocking & Reapir / 7/1/2021 7/2/2021
Replacement
Stroke Checking & Stopper Provision 7/2/2021 7/3/2021

FBHE 1 - Spiess Valve Dismantling Work 6/28/2021 6/29/2021

Pipe & Nozzle Stone Area De-chocking 6/29/2021 6/30/2021

Nozzle Stone, Bricks,Lance Tube & Tip


Inspection & Gap Measurement 6/30/2021 7/4/2021

Spiess Valve HydroTest 7/4/2021 7/5/2021


Purging Air line De-chocking & Repair /
7/5/2021 7/5/2021
Replacement
Stroke Checking & Mechanical Stopper
Provision 7/5/2021 7/6/2021

FBHE 4 - Spiess Valve Dismantling Work 6/27/2021 6/28/2021

Pipe & Nozzle Stone Area De-chocking 7/1/2021 7/2/2021

Nozzle Stone, Bricks,Lance Tube & Tip 7/2/2021 7/4/2021


Inspection & Gap Measurement
Spiess Valve HydroTest 7/4/2021 7/5/2021
Purging Air line De-chocking & Repair /
7/5/2021 7/7/2021
Replacement
Stroke Checking & Mechanical Stopper
7/7/2021 7/7/2021
Provision

FBHE 2 - Spiess Valve Dismantling Work 6/25/2021 6/26/2021

Pipe & Nozzle Stone Area De-chocking 6/26/2021 6/26/2021

Nozzle Stone, Bricks,Lance Tube & Tip


6/26/2021 6/28/2021
Inspection & Gap Measurement
Spiess Valve HydroTest 6/28/2021 6/29/2021
Purging Air line De-chocking & Repair /
6/29/2021 7/1/2021
Replacement
Stroke Checking & Mechanical Stopper
7/1/2021 7/2/2021
Provision

FBHE 3 - Spiess Valve Dismantling Work 7/5/2021 7/6/2021


Pipe & Nozzle Stone Area De-chocking 7/6/2021 7/7/2021

Nozzle Stone, Bricks,Lance Tube & Tip 7/7/2021 7/9/2021


Inspection & Gap Measurement
Spiess Valve HydroTest 7/9/2021 7/10/2021
Purging Air line De-chocking & Repair /
7/10/2021 7/12/2021
Replacement
Stroke Checking & Mechanical Stopper 7/12/2021 7/12/2021
Provision
DCLF A 6/17/2021 7/1/2021
Removal of Top Covers 6/17/2021 6/18/2021
Old Chain Removal Work 6/18/2021 6/21/2021
New Chain Installtion Work 6/21/2021 6/25/2021
DE & NDE Side Bearing Inspection /
6/25/2021 6/26/2021
Replacement
Gearbox Oil Replacement 6/26/2021 6/27/2021
Coupling Inspection / Relacement &
6/27/2021 6/28/2021
Alignment
Fitment of Top Covers 6/28/2021 6/29/2021
Maintenance /Freeness of Plate Valve /
Gear & Lubrication 6/29/2021 7/1/2021

DCLF NMEJ Repair 7/1/2021 7/1/2021


DCLF B 7/1/2021 7/11/2021
Removal of Top Covers 7/1/2021 7/2/2021
Chain & Sprocket Inspection 7/2/2021 7/5/2021
DE & NDE Side Bearing Inspection / 7/5/2021 7/6/2021
Replacement
Gearbox Oil Replacement 7/6/2021 7/7/2021
Coupling Inspection / Relacement &
7/7/2021 7/8/2021
Alignment
Fitment of Top Covers 7/8/2021 7/9/2021
Maintenance /Freeness of Plate Valve /
7/9/2021 7/11/2021
Gear & Lubrication
DCLF NMEJ Repair 7/11/2021 7/11/2021
RAV Maintenance 7/3/2021 7/7/2021
Lime RAV 1 7/3/2021 7/4/2021
Lime RAV 2 7/4/2021 7/4/2021
Lime RAV 3 7/4/2021 7/5/2021
Lime RAV 4 7/5/2021 7/6/2021
Bed Ash Cooler 1 RAV 7/6/2021 7/7/2021
Bed Ash Cooler 2 RAV 7/7/2021 7/7/2021
Improvement - Bed Ash Cooler RAV
7/5/2021 7/6/2021
Purging & Seal Air Line Provision
Pet-coke RAV A 7/9/2021 7/15/2021
RAV Dismantling 7/9/2021 7/10/2021
Replacement of drive and driven gear 7/10/2021 7/11/2021

DE / NDE Side Sleeve & Gland Replacement 7/11/2021 7/12/2021

RAV Rotor Blade Clearance Adjustment 7/12/2021 7/13/2021

Bearing replacement and box-up activity 7/13/2021 7/13/2021

MFT Inspection for Jamming & 7/13/2021 7/14/2021


Rectification
Purging Air & Seal Air Line De-chocking
7/14/2021 7/15/2021
Correction/replacement
Coal RAV B 7/14/2021 7/21/2021
RAV Dismantling 7/14/2021 7/16/2021

Replacement of drive and driven gear NR 7/16/2021 7/17/2021

DE / NDE Side Sleeve & Gland Replacement 7/17/2021 7/17/2021

RAV Rotor Blade Clearance Adjustment 7/17/2021 7/18/2021

Bearing replacement and box-up activity 7/18/2021 7/19/2021

MFT Inspection for Jamming &


7/19/2021 7/20/2021
Rectification
Purging Air & Seal Air Line De-chocking 7/20/2021 7/21/2021
Correction/replacement
Blower House Valve Shifting Inside Blower 7/26/2021 8/2/2021
House
All 32 Soot Blower Maintenance 7/29/2021 8/6/2021
Bed Material Feed Pipe Replacement 6/18/2021 6/25/2021
Old Line Cutting 6/18/2021 6/19/2021
Original Seal Box Cutting 6/19/2021 6/20/2021
New Line Shifting to Location 6/18/2021 6/19/2021
Fitment & Welding of New Line 6/19/2021 6/21/2021
Purging Air Line Connection 6/21/2021 6/21/2021
Seal Box Restoration 6/21/2021 6/23/2021
Refractory Pouring in Sealbox 6/24/2021 6/24/2021
Seal Box Restoration 7/1/2021 7/31/2021
LHS cyclone top roof (CID top roof, cyclone
7/1/2021 7/4/2021
top roof) - 02 Nos.
FBHE-1 inlet duct - 03 Nos. 7/4/2021 7/7/2021
LHS U-bend syphon top(near 1A petcoke
RAV chute) 7/7/2021 7/8/2021

FBHE-4 top roof 7/9/2021 7/11/2021


FBHE-1 BC door top 7/11/2021 7/12/2021
LHS Seal pot return leg 7/12/2021 7/14/2021
BAC common vent line, near combustor
7/14/2021 7/16/2021
mating point

LHS Wall panel sealbox,near FBHE-1 return


7/16/2021 7/18/2021
leg and combustor mating pont area

FBHE-3 EC, Bc chambers ESP facing (near


7/18/2021 7/19/2021
inlet water HDR area)
FBHE-3 EC side plate near inlet duct 7/19/2021 7/21/2021
BAC-1 EC inlet duct after NMEJ 7/21/2021 7/23/2021

LHS cyclone stand pipe below purging line 7/23/2021 7/25/2021

Cyclone inlet duct bottom side near


bullnose area 7/25/2021 7/27/2021

BAC 1 EC side plate near inlet duct 7/27/2021 7/29/2021

Bed material feed line near combuster 7/29/2021 7/31/2021

Silensor (MSL ) 7/22/2021 8/4/2021


Removal of Silensor Assembly from Top to
7/22/2021 7/23/2021
Ground Floor
Internal Cleaning of Silensor 7/23/2021 7/24/2021
Inspection & Repair Work 7/24/2021 7/28/2021
Water Fill Test 7/28/2021 7/29/2021
Painting 7/29/2021 8/1/2021
Silensor Installation at Position 8/1/2021 8/2/2021
Removal of Silensor Assembly from Top to 7/24/2021 7/25/2021
Ground Floor
Internal Cleaning of Silensor 7/25/2021 7/26/2021
Inspection & Repair Work 7/26/2021 7/30/2021
Water Fill Test 7/30/2021 7/31/2021
Painting 7/31/2021 8/3/2021
Silensor Installation at Position 8/3/2021 8/4/2021
ID Fan Maintenance 6/22/2021 7/1/2021
Fan Casing Manhole Door Opening 6/22/2021 6/22/2021
Inside Inspection of Cone ,Casing and Duct
6/22/2021 6/25/2021
( Thickness Checking)
Repair of Duct,Casing etc. 6/25/2021 6/29/2021
Lube Oil Cooler Cleaning 6/29/2021 7/1/2021
PM - Fan (Bearing Inspection,Alignment) &
6/22/2021 6/28/2021
Voith Coupling
Damper Inspection 6/22/2021 6/26/2021
Manhole Door Box Up 7/1/2021 7/1/2021
SA Fan Maintenance 7/8/2021 7/15/2021
Fan Casing Manhole Door Opening 7/8/2021 7/8/2021
Inside Inspection of Cone ,Casing and Duct
7/8/2021 7/11/2021
( Thickness Checking)
Repair of Duct,Casing etc. 7/11/2021 7/15/2021
PM - Lube Oil Pump 7/15/2021 7/15/2021

PM - Fan (Bearing Inspection,Alignment) 7/11/2021 7/15/2021

Damper Inspection 7/11/2021 7/12/2021


Manhole Door Box Up 7/15/2021 7/15/2021
PA Fan Maintenance 7/12/2021 7/23/2021
PA fan casing manhole door opening. 7/12/2021 7/13/2021
Inside inspection of cone, casing, impeller , 7/13/2021 7/15/2021
bearings, LOP and IGV.
Defect rectification (if any identified) 7/15/2021 7/19/2021
Schedule PM of Lube oil pumps and fan
alignment etc. 7/19/2021 7/23/2021

manhole door box up. 7/15/2021 7/15/2021


BLR-1 PA fan discharge duct damaged, air
leakage found 7/13/2021 7/16/2021

PA fan cooling water DE & NDE side wheel


7/13/2021 7/13/2021
N/A,v/v jamming condition.
SA APH and SA Duct Inspection 6/29/2021 8/6/2021
SA & PA APH Cleaning 7/2/2021 7/5/2021

Duct Cutting for APH Duct Replacement 6/29/2021 7/2/2021

SA APH Duct Support Cutting (Inside) 7/2/2021 7/3/2021


SA APH Inlet Duct MEJ Repair Work 7/3/2021 7/5/2021
SA APH Tube Replacement (BORL- 7/15/2021 8/1/2021
Subcontract)
Duct Support Welding 7/30/2021 7/31/2021
Duct Welding 8/1/2021 8/4/2021
Insulation Application 8/4/2021 8/6/2021
Sleeve installation / Ferruling 7/30/2021 8/2/2021
SA Duct Inspection ,thickness mapping &
7/5/2021 7/9/2021
repair
PA APH 7/8/2021 7/18/2021

PA APH MEJ Leakage Rectification Work 7/8/2021 7/13/2021

PA APH Tube Ferruling Work (Cold Side) 7/13/2021 7/18/2021

ECO Inlet & Outlet Header 6/20/2021 7/31/2021


Insulation Removal from ECO Inlet &
Outlet Header (Radiography Work) 6/20/2021 6/22/2021

Tube Surface Cleaning & Buffing Work 6/22/2021 6/27/2021


Radiography of Economiser Joints (Inlet
6/27/2021 7/27/2021
&Outlet Header) - 15 / Day
Economoiser Inside Tube Cleaning for
6/27/2021 7/2/2021
Thickness Mapping
Tube Thickness Mapping (Outside & Inside) 7/13/2021 7/18/2021

Pressure Part Rectification 7/18/2021 7/22/2021


Repair of Economiser I/L & O/L Header 6/29/2021 7/29/2021
Joints - 15 / Day
Insulation of Economiser Inlet & Outlet
7/29/2021 7/31/2021
Header
Blower Maintenance 6/25/2021 7/17/2021
EC Blower 1 6/25/2021 6/26/2021
EC Blower 2 6/26/2021 6/28/2021
FBHE BC Blower 1 6/28/2021 6/29/2021
FBHE BC Blower 2 6/29/2021 7/1/2021
FBHE BC Blower 3 7/1/2021 7/2/2021
FBHE BC Blower 4 7/2/2021 7/4/2021
FBHE BC Blower 1-3 7/4/2021 7/5/2021
FBHE BC Blower 2-4 7/5/2021 7/7/2021
Ash Cooler Blower 1 7/7/2021 7/8/2021
Ash Cooler Blower 2 7/8/2021 7/10/2021
Purge & Seal Blower 1 7/10/2021 7/11/2021
Purge & Seal Blower 2 7/11/2021 7/13/2021
Seal Pot Blower 1 7/13/2021 7/14/2021
Seal Pot Blower 2 7/14/2021 7/16/2021
Seal Pot Blower 1-2 7/16/2021 7/17/2021
All 14 Headers Inspection 6/30/2021 7/19/2021
Insulation Removal at Headers 6/30/2021 7/4/2021
Tube Surface Cleaning ,Buffing & 7/4/2021 7/9/2021
Inspection
Repair as per Observation 7/9/2021 7/14/2021
Insulation Application 7/14/2021 7/19/2021
Boiler Drum 7/18/2021 7/31/2021
Boiler drum de-pressurization 7/18/2021 7/19/2021
Manhole Door Opening 7/19/2021 7/19/2021
Drum Sample Collection 7/19/2021 7/20/2021

Dismounting of Separator For Inspection 7/20/2021 7/21/2021

Water Cleaning and buffing of drum for UT.


7/21/2021 7/22/2021
(buffing as per inspection recommendation.)

Installtion of Removed Internal eg.


Separators 7/22/2021 7/23/2021

Drum Manhole Box Up (LHS & RHS )- Drum


Gasket Replacement 7/23/2021 7/24/2021

HP Dosing Pum A & B Preventive


7/24/2021 7/31/2021
Maintenance
Drum LHS PSV Overhauling 7/23/2021 7/27/2021
Drum RHS PSV Overhauling 7/23/2021 7/27/2021
Hot PA Duct to Combustor NMEJ 7/24/2021 7/28/2021
Hot PA Duct to Combustor NMEJ 7/24/2021 7/25/2021
Dismantling
Hot PA Duct to Combustor new NMEJ
7/25/2021 7/26/2021
Installation
Hot PA Duct to Combustor new NMEJ
7/26/2021 7/28/2021
Bolting
Windbox & Hot PA Duct 6/18/2021 7/30/2021
Hot PA duct manhole 6/18/2021 6/18/2021
Hot PA duct inside inspection including
7/19/2021 7/20/2021
wind box.
Rectification as per inspection
recommandation.(Emergency drain pipe, 7/20/2021 7/23/2021
nozzles and leakage)
Combustor DP drain line leakage at sliding
7/23/2021 7/24/2021
gate top side.
PA APH I/L MEJ air leakage 7/24/2021 7/29/2021
SCAPH common drain line at 0 mtr welding
7/29/2021 7/30/2021
leakage near drain pit.
APH to ESP inlet duct inspection. 7/5/2021 7/9/2021
APH to ESP inlet duct inspection. 7/5/2021 7/6/2021
Rectification as per inspection
7/6/2021 7/9/2021
recommandation.
ESP to ID up to stack Inspection 7/6/2021 7/13/2021
Cleaning inside ESP to ID fan & ID fan to 7/6/2021 7/8/2021
stack.
Duct inside inspection. 7/9/2021 7/10/2021
Rectification as per inspection
7/10/2021 7/13/2021
recommandation.

COD - SCWW ,Scallop & Refractory work 6/25/2021 7/21/2021

SCWW tube cutting for repair / spool


replacement work 6/25/2021 6/28/2021

Hanger tube shielding work 6/28/2021 6/30/2021


Scallop Plate repair work 6/28/2021 7/2/2021
SCWW tube fitment & weldign work 6/28/2021 6/30/2021
SCWW tube fins welding work 6/30/2021 7/2/2021
RHS & LHS COD - Refractory Breaking 7/2/2021 7/5/2021

RHS & LHS COD - Refractory Application 7/5/2021 7/8/2021

RHS & LHS COD - NMEJ wool stuffing 7/8/2021 7/10/2021


Second Pass pressure part thickness
7/9/2021 7/21/2021
Mapping (FSH,LTSH,ECO,Penthouse)
Electrical Maintenance 6/22/2021 8/4/2021
ESP -1 A-pass Rapper MCC (EERM ,CERM-
7/14/2021 7/15/2021
Feeders & Motors)
ESP -1 B-pass Rapper MCC (EERM ,CERM- 7/15/2021 7/17/2021
Feeders & Motors)
ESP MCC # 1 Control Circuit 7/17/2021 7/18/2021
ESP-03 Field A1-A5 & B1-B5 TRCC set 7/18/2021 7/20/2021
FBHE EC Blower 1 7/2/2021 7/3/2021
FBHE EC Blower 2 7/3/2021 7/4/2021
Purge & Seal Blower-01 7/4/2021 7/5/2021
Purge & Seal Blower-02 7/5/2021 7/6/2021
FBHE BC Blower Motor# 1 7/6/2021 7/6/2021
FBHE BC Blower Motor# 3 7/6/2021 7/7/2021
FBHE BC Blower Motor # 1/3 (standby) 7/7/2021 7/7/2021
FBHE BC Blower Motor# 2 7/7/2021 7/8/2021
FBHE BC Blower Motor# 4 7/8/2021 7/8/2021
FBHE BC Blower Motor # 2/4 (standby) 7/8/2021 7/9/2021
Ash Cooler Blower Motor # 1 7/9/2021 7/9/2021
Ash Cooler Blower Motor # 2 7/9/2021 7/10/2021
Seal Pot Blower#1 7/10/2021 7/10/2021
Seal Pot Blower#2 7/10/2021 7/11/2021
Seal Pot Blower stand by 7/11/2021 7/11/2021
PA Motor 7/11/2021 7/12/2021
SA Motor 7/12/2021 7/12/2021
ID Motor 6/22/2021 6/22/2021
Bin Vent Fan Motor # 1A 7/12/2021 7/13/2021
Bin Vent Fan Motor # 1B 7/13/2021 7/13/2021
Rotary Air LockFeeder (RAV) Motor # 1A 7/13/2021 7/14/2021
Rotary Air LockFeeder (RAV) Motor # 1B 7/14/2021 7/16/2021
DCLF Motor # 1A 7/16/2021 7/16/2021
DCLF Motor # 1B 7/16/2021 7/17/2021
Root Blower Motor # 1A 7/17/2021 7/17/2021
Root Blower Motor # 1B 7/17/2021 7/18/2021
Transformer-51 7/18/2021 7/18/2021
Transformer-52 7/18/2021 7/19/2021
Transformer-21 7/19/2021 7/19/2021
Transformer-22 7/19/2021 7/20/2021
Lime stone Bunker 1A RAV -1 7/20/2021 7/20/2021
Lime stone Bunker 1A RAV -2 7/20/2021 7/21/2021
Lime stone Bunker 1B RAV -1 7/21/2021 7/21/2021
Lime stone Bunker 1B RAV -2 7/21/2021 7/22/2021
Bed Ash Cooler RAV-1 7/22/2021 7/22/2021
Bed Ash Cooler RAV-2 7/22/2021 7/23/2021
Soot blower Motor (1 to 32) 7/23/2021 7/28/2021
MOV & Damper Checking Job 7/2/2021 7/16/2021
ESP Air Load test 8/3/2021 8/4/2021
CBD/IBD - Main & Inching MOV Platform 7/20/2021 7/24/2021

Normal Cooling Water MOV Platform 7/22/2021 7/24/2021


DESH 1 Main & Bypass MOV Platform 7/24/2021 7/26/2021
Start up Vent Inching MOV 7/28/2021 7/29/2021
MSSV 7/15/2021 7/16/2021
Control & Instrumentation 6/27/2021 7/31/2021
Upper DP Transmitter relocation and 7/10/2021 7/14/2021
Impulse line modification.(Not. 70007308)
DESH-1 Flow transmitter relocation &
7/16/2021 7/18/2021
Impulse line Modification work.
DESH-2 Flow transmitter relocation &
Impulse line Modification work. 7/20/2021 7/22/2021

Seal Pot LHS & RHS Side Process Tapping &


7/25/2021 7/27/2021
Impulse line modification job.
SA, & PA Fan Discharge duct Temperature
gauge taping not available tapping required. 7/29/2021 7/31/2021
(70007127)
BAC-1 &2 RAV inlet temperature thermo-
6/27/2021 6/29/2021
well relocation job.
LTSH Inlet Pressure Gauge Tapping
Replacement 6/28/2021 7/1/2021

FBHE-2 BC thermowell relocation job. 7/1/2021 7/4/2021


Bed Ash Hopper-1 & 2 DP Transmitter 7/4/2021 7/5/2021
impulse Line Modification Job.
Field Instruments & JBs Canopy fabrication 7/5/2021 7/19/2021
and Mounting.
Boiler-1 instuments JBs maintenance job.
7/19/2021 7/20/2021
(69JBs)
SA, PA & ID Fans IGV & Dampers Checking 7/20/2021 7/22/2021
job
Boiler-1, 12 nos control valve checking &
7/1/2021 7/5/2021
Calibration job.
SA, PA & ID Fan Instruments Preventive
7/5/2021 7/6/2021
maintenance.
Cyclone & Combustor Thermocouple &
7/5/2021 7/9/2021
thermowell Inspection & Rectification.

FBHE-1,2,3 & 4 thermocouple Inspection &


thermowell Inspection & Rectification. 7/9/2021 7/11/2021

Seal Pot-1 &2 Thermocouple inspection and


7/9/2021 7/11/2021
thermowell Inspection & Rectification.

Soot blower drain valve checking job. 7/11/2021 7/12/2021


Blower House Blowers ZSS & SRV healthiness
7/11/2021 7/12/2021
checking job.
Blower House Gate valve healthiness 7/11/2021 7/14/2021
checking job.
SA,PA, fans lube oil system Preventive
6/28/2021 7/2/2021
maintenance.
SUB-1, SUB2 shutoff Valve Sov & stroke
7/2/2021 7/4/2021
Checking Job
BMS system PM and healthiness checking 7/4/2021 7/6/2021
Job.
High energy spark igniter checking job. 7/6/2021 7/8/2021
Emergency bed drain valve healthiness 7/8/2021 7/10/2021
BLR#1 APH HOPPER TG N/A. TG REQUIRED.
(70007128) 7/10/2021 7/12/2021

Scaffolding 6/17/2021 8/9/2021


LHS & RHS Cyclone Inlet Duct ( Hard
6/21/2021 6/22/2021
Barrication)
Scaffodling erection for cleaning. ( Hard
barricading at ESP I/L , ESP O/L and PA & SA 7/14/2021 7/19/2021
inside duct cleaning activity .)

ESP Inside Scaffolding Material Removal 7/28/2021 7/30/2021

Combustor - Return Leg & Seal Pot


6/22/2021 6/27/2021
Scaffolding ( 04 Nos.)
Combustor - Scaffolding up to roof 6/27/2021 7/11/2021
Combustor - Scaffolding Removal including 7/18/2021 7/26/2021
Return Leg & Seal Pot

RHS Cyclone - Cantilever Scaffolding ( Target


6/28/2021 7/1/2021
Wall for Vortex Lifting & Refractory Inspection)

RHS Cyclone - Scaffolding from Stand Pipe to


7/1/2021 7/11/2021
Conical & Cylindrical Portion Roof
RHS Cyclone Roof - Scaffolding Approach for
Vortex Finder Lifting 6/23/2021 6/24/2021

RHS Cyclone - Complete Scaffolding Removal 7/27/2021 8/2/2021

RHS Cyclone (DCLF Floor) - Scaffolding for


7/15/2021 7/17/2021
Pressure Tapping Provision
RHS Cyclone (DCLF Floor) - Scaffolding
Removal After Process Tappign Work 7/17/2021 7/18/2021

LHS Cyclone - Cantilever Scaffolding ( Target


6/30/2021 7/3/2021
Wall for Vortex Lifting & Refractory Inspection)

LHS Cyclone - Scaffolding from Stand Pipe to


7/3/2021 7/13/2021
Conical & Cylindrical Portion Roof
LHS Cyclone - Complete Scaffolding Removal 7/28/2021 8/3/2021

LHS Cyclone (DCLF Floor) - Scaffolding for 7/28/2021 7/30/2021


Pressure Tapping Provision
LHS Cyclone (DCLF Floor) - Scaffolding
8/5/2021 8/6/2021
Removal After Process Tappign Work
FBHE 1 - Approach for BC 6/22/2021 6/22/2021
FBHE 1 Scaffolding - for height work. 7/3/2021 7/4/2021
FBHE 1 - Inside Scaffolding Complete 7/14/2021 7/15/2021
Removal
FBHE 1 - Approach Windbox Manhole
7/4/2021 7/5/2021
Provision
FBHE 4 - Approach for BC 6/27/2021 6/27/2021
FBHE 4 - Scaffolding - for height work. 7/5/2021 7/6/2021
FBHE 4 - Inside Scaffolding Complete
Removal 7/18/2021 7/19/2021

FBHE 4 - Approach Windbox Manhole


7/5/2021 7/6/2021
Provision
FBHE 2 - Approach for BC 6/24/2021 6/24/2021
FBHE 2 - Scaffolding - for height work. 7/7/2021 7/8/2021
FBHE 2 - Inside Scaffolding Complete
Removal 7/20/2021 7/21/2021

FBHE 2 - Approach Windbox Manhole


7/20/2021 7/21/2021
Provision
FBHE 3 - Approach for BC 6/27/2021 6/27/2021
FBHE 3 - Inside Scaffolding Complete 7/7/2021 7/8/2021
Removal
FBHE 3 - Approach Windbox Manhole
7/21/2021 7/22/2021
Provision
BAC 1 - Partition Wall Scaffolding 7/10/2021 7/11/2021
BAC 1 - Inside Cleaning & Scaffolding
7/17/2021 7/17/2021
Removal

BAC 1 & 2 - Scaffolding for BAC Inlet NMEJ 6/18/2021 6/19/2021

BAC 1 &2 - Inlet NMEJ Scaffolding Removal 6/29/2021 6/30/2021

BAC 2 - Partition Wall Scaffolding 7/11/2021 7/12/2021


BAC 2 - Inside Cleaning & Scaffolding
7/13/2021 7/13/2021
Removal
BAC Common Vent - Scaffolding for NMEJ &
7/13/2021 7/14/2021
Pipe Inspection
BAC Common Vent - Scaffolding Removal
7/19/2021 7/20/2021
from Vent Line
Spiess Valve - FBHE - Scaffolding for
6/24/2021 6/25/2021
Maintenance
Bed Material Feed Line - Scaffolding 6/18/2021 6/18/2021

Bed Material Feed Line - Scaffolding Removal 6/24/2021 6/25/2021

Silensor - Scaffolding Erection for Silensor 7/12/2021 7/22/2021


Removal

Silensor - Scaffolding Removal from Silensor 8/6/2021 8/9/2021

SA APH Duct - Scaffolding for Insulation 6/24/2021 6/26/2021


Removal & Duct Cutting Work
APH Hopper - Scaffolding for Tube Removal
7/2/2021 7/6/2021
& Cleaning
Scaffolding For APH tube ferruling 7/29/2021 8/1/2021
Scaffolding Removal from APH tube after
ferruling 8/2/2021 8/3/2021

PA APH Scaffolding for MEJ Leakage


Rectification 7/6/2021 7/8/2021

PA APH Scaffolding Removal 7/18/2021 7/19/2021


ECO Inlet & Outlet Header - Scaffolding
6/17/2021 6/20/2021
(Radiography Work)
ECO Inlet & Outlet Header - Scaffolding
Removal 7/31/2021 8/4/2021

All 14 Headers - Scaffolding for Tube


6/20/2021 6/30/2021
Inspection During Hydro
All 14 Headers - Scaffolding Removal after 7/19/2021 7/24/2021
Tube Inspection During Hydro
Hot PA Duct to Combustor - NMEJ 7/21/2021 7/24/2021
Replacement Scaffolding
Hot PA Duct to Combustor - NMEJ
7/28/2021 7/29/2021
Replacement Scaffolding Removal
Windbox - Scaffolding 7/15/2021 7/19/2021
ID Duct to stack Scaffoling 7/8/2021 7/9/2021
ID Duct to stack Scaffoling Removal 7/13/2021 7/14/2021
RHS COD - Scaffolding for SCWW tube repair
& scallop plate repair 6/20/2021 6/25/2021

RHS COD - Scaffolding for Refractory Work 6/25/2021 6/27/2021

LHS COD - Scaffolding for Refractory Work 6/27/2021 6/28/2021

Scaffolding Erection for Upper DP


Transmitter Relocation 7/6/2021 7/10/2021

Scaffolding Removal from Upper DP


Transmitter Relocation 7/14/2021 7/15/2021

Scaffolding for DESH 1 Flow Transmitter


7/15/2021 7/16/2021
Relocation
Scaffolding Removal from DESH 1 Flow
7/18/2021 7/19/2021
Transmitter
Scaffolding For DESH 2 Flow Transmitter 7/19/2021 7/20/2021
Relocation
Scaffolding Removal from DESH 2 Flow
7/22/2021 7/23/2021
Transmitter
Scaffolding Erection for LHS/RHS Seal Pot
7/23/2021 7/25/2021
Process Tapping

Scaffolding Removal From Seal Pot Location 7/27/2021 7/28/2021

Scaffolding for SA & PA Fan Discharge Duct 7/28/2021 7/29/2021

Scaffolding Removal from SA & PA Fan


Discharge Duct 7/14/2021 7/16/2021

SCWW - Scaffolding Removal 7/8/2021 7/12/2021


RHS & LHS COD - Scaffolding Removal 7/12/2021 7/17/2021
All Insulation Work 7/15/2021 7/30/2021
All Notification Closure 7/8/2021 7/20/2021
Refractory Dry Out & Re-Commissioning 7/30/2021 8/16/2021

Pre RDO activity .(Manhole door box up,


7/31/2021 8/1/2021
blower shifting ,trial, leakage testing etc.)

Burner trial & RDO. 8/9/2021 8/12/2021


Cooling. 8/12/2021 8/13/2021
Post inspection 8/13/2021 8/14/2021
Rectification and remaining manhole door 8/14/2021 8/16/2021
box. ( PTW closure)
All Drive enrgization and ESP Air load test
checking.(Drives need to energization and ID fan 8/14/2021 8/15/2021
required in running condition)
interlock checking. 8/14/2021 8/15/2021
PSSR of Boiler-1 (By team - with respective
7/30/2021 7/31/2021
dept. team member)
PSSR points rectification. 7/31/2021 8/5/2021
All drive trial run, bed material charging.
8/15/2021 8/16/2021
(HSD Line De-blinding activity)
Boiler Mock light up. 8/16/2021 8/16/2021
Actual Dates Days Req. % progress of today Cumulative %
Start End Plan Actual Plan Actual Days comp. Status Variance
Percentage of Tasks Complete
Complete 27.27%

Overdue 9.09%

In progress 18.18%

Not Started 45.45%

Pending Items
Decisions 5
Actions 2

Change Requests 4
Daily Planned Daily Actual Accumulative Planned Accumulative Actual
13-Jun
14-Jun
15-Jun
16-Jun
17-Jun
18-Jun
19-Jun
20-Jun
21-Jun
22-Jun
23-Jun
24-Jun
25-Jun
26-Jun
27-Jun
28-Jun
29-Jun
30-Jun
1-Jul
2-Jul
3-Jul
4-Jul
5-Jul
6-Jul
7-Jul
8-Jul
9-Jul
10-Jul
11-Jul
12-Jul
13-Jul
14-Jul
15-Jul
16-Jul
17-Jul
18-Jul
19-Jul
20-Jul
21-Jul
22-Jul
23-Jul
24-Jul
25-Jul
26-Jul
27-Jul
28-Jul
29-Jul
30-Jul
31-Jul
1-Aug
2-Aug
3-Aug
4-Aug
5-Aug
6-Aug
7-Aug
8-Aug
9-Aug
10-Aug
11-Aug
12-Aug
13-Aug
14-Aug
15-Aug
16-Aug