You are on page 1of 37

Marine Risks during Installation of

Deepwater Projects

Marine Risks Workshop


OGP Forum London
Presentation March 19,2003
Request to HMC

Perception
Inventory of risks related to deepwater risk-likely
hood are
projects quite
different
based on current best practice and
identification of key risks
Risk to contractor
and Risk to operator
the gaps in codes/tools/practices

RISK March 2003


Contents of this presentation

„ Heerema Group & HMC‘s Deepwater Experience


„ Best Practice Installation procedures
„ Risks during installation
„ Risks induced prior to installation
„ Risk mitigation

RISK March 2003


This presentation

„ Heerema Group & HMC‘s Deepwater Experience


„ Best Practice Installation procedures
„ Risks during installation
„ Risks induced prior to installation
„ Risk mitigation

RISK March 2003


Heerema Group Divisions

FIELD DEVELOPMENT ONSHORE & OFFSHORE OFFSHORE


CONCEPTUAL & OFFSHORE HEAVY TRANSPORT
DETAILED ENGINEERING STEEL TRANSPORT & INSTALLATION
CONSTRUCTION
Typical Deepwater Field Dev’t
Floating Facility
Export pipe lines

Jumper PLET moorings

Flowlines
In line sled
assemblies

SCR’s

manifolds

RISK March 2003


Deepwater Experience area’s

Mobile
U.S.A. 20

New Orleans
Houston

80
Fourchon
40

20 VK
Horn Mountain
Matterhorn
Nakika / Okeanos
40 0
50 00
10 Thunder Hors e
Prince MC

Corpus Christi 50 0 0
15 0

00
20
Gunnis on Hols tein Marco Polo
10 0
0 Atlantis
EB GB Mad Dog GC AV
0
15 0
0
25 0

20 00
AC KC WR LU
20

30 0
0

35
80

00
RISK March 2003
The presentation

„ Heerema Group & HMC‘s Deepwater Experience


„ Best Practice Installation procedures
„ Risks during installation
„ Risks induced prior to installation
„ Risk mitigation

RISK March 2003


Typical Deepwater Installation
scope & Installation procedures
Fly-jib
1. Moorings
2. Facilities
3. Pipelines, in- J-lay + A&R
line sled system
assemblies &
SCR’s
MLD winch

RISK March 2003


Typical Deepwater Installation
scope & Installation procedures

1. Moorings
2. Facilities
3. Pipelines, in-line sled assemblies & SCR’s

RISK March 2003


Mooring installation

BP VASTAR Stud less Chain:


HORN SSW: 800-930 ft
3500 ft 5 ¾”
MOUNTAIN
SSW: 5”
3500 ft
5”

Stud less Chain:


250 ft
5 ¾”

Suction pile:
18 ft OD
90-95 ft long
200 sht

Risk of rotation of Risk of damaging


pile /Risk of sheathing of wire
damage to
connections
RISK March 2003
Best Practice BP Vastar
Horn Mountain

•Damage free handling


•Safe working environment

17 days No LTI’s No Damage


RISK March 2003
SUCTION PILE UPENDING

Risk drivers

Very high
installation
forces

Handling of
many
components
RISK March 2003
Overboarding the connection
between Upper and Lower SSWs
Risk drivers

Damage to
sheathing of
wire

Manual
Handling

RISK March 2003


Typical Deepwater Installation
scope & Installation procedures

1. Moorings
2. Facilities
3. Pipelines, in-line sled assemblies & SCR’s

RISK March 2003


Experience
Topsides Installation – Dual crane capacity

RISK March 2003


Lifting Topsides on Floaters

RISK March 2003


Relative Motions Two Floaters

Risk drivers

Very high
installation
forces
Coupling of
two main
bodies
effects DP
stability

RISK March 2003


Deepwater Installation
Risky business?
Typical Deepwater Installation
scope & Installation procedures

1. Moorings
2. Facilities
3. Pipelines, in-line sled assemblies & SCR’s

RISK March 2003


Deepwater Pipeline
installation
Risk drivers
• Heavy walled pipe
Very high
• Ability to hold flooded pipe installation
• Pipe-in-pipe flowlines forces

• Export lines
Fatigue
• SCR’s > 20” damage
• In line sled assemblies On-bottom
• No free spans on bottom configuration
RISK March 2003
Tensioning system

High pipe tensions:


don’t rely on friction!
J-lay collar /
buckle
arrestors
provide
“locking” of
pipeline

RISK March 2003


Handling sled assemblies

RISK March 2003


Installing in-line sled
assemblies
Risk drivers

Very high
installation
forces

Handling of
many
components
by many
RISK March 2003
cranes
Controlled Lowering using
buoys
WSA Installation, OD Transition
Risk
drivers
BALDER BALDER
BALDER

U/W weight
Buoy
changes
WSA

Handling
capabilities

Two
vessels
Bring WSA into tower using PS Install WSA in tower and
Install 21 hex joints (28").
working
crane jib. prepare for buoy installation.

RISK March 2003


together
Pipeline connections

Risk
drivers

Mis -
alignment

Handling
capabilities

Pre-installed
RISK March 2003
This presentation

„ Heerema Group & HMC‘s Deepwater Experience


„ Best Practice Installation procedures
„ Risks during installation
„ Risks induced prior to installation
„ Risk mitigation

RISK March 2003


Environmental Risk

„ Liability to third parties for bodily injury or property


damage
„ Liability to governments (eg. Clean-up of spills or
removal of pollutants

RISK March 2003


Early involvement installation
Risks during installation
contractor to match design with
capacities&methods
Risks Mitigation
„ High loads and high installation „ Equipment preparation/JSA/Trials
forces => handling of large Design to consider installation
structures and components
HAZOP/HAZID/JSA => toolbox
„ Damage to pipelines, piles and
talks ; eqm’t & provisions
structures due to hydrostatic
pressure „ J-Lay method + collars; no plastic
„ Schedule risk , duration of deformations
installation „ Multi Role vessels , works
„ Orientation and geometry of preparation
pipelines , anchor piles and „ J-lay and crane capacities
structures on seabed
„ Early weather data collection
„ Weather risk in new areas
„ Integration of subsea components
„ Connection and testing of sbsea
components
RISK March 2003
This presentation

„ Heerema Group & HMC‘s Deepwater Experience


„ Best practice Installation procedures
„ Risks during installation
„ Risks induced prior to installation
„ Risk mitigation

RISK March 2003


Risks induced prior to
installation
“Perceived” Cost Reductions
Field development scenario
Design

Procurement

(Pre-) Fabrication

Transport

Installation

RISK March 2003


Risks of Perceived Cost
reductions
Design driven to minimise
a) Capital-efficient developments cost => less material =>
RISK OF COLLAPSE for eg
pipeline or piles

Operators drive cost to the


b) Competing solutions boneÎ Contractors incur
LARGE losses => RIP

Delay of delivery goods,


c) Improvement of cash-out equipment and services till
just NOT in time
schedules
=>Operators buy problems

Major loss of expertise ; not


d) Personnel reductions ; HR issues attracting younger
engineers

RISK March 2003


Competing solutions

„ Operators seem to consider deepwater installation


contracting as a “commodity” market whereby the
lowest bidder stands a fair chance of getting the job
„ Deepwater is still in the experimental & development
stage requiring a large up-front effort in engineering
and works preparation AND equipment
Operators drive cost to
the boneÎ Contractors
incur LARGE losses =>
RIP

„ Mitigation by co-operation models whereby each is


responsible for the risk they can manage

RISK March 2003


This presentation

„ Heerema Group & HMC‘s Deepwater Experience


„ Best practice Installation procedures
„ Risks induced prior to installation
„ Risks during installation
„ Risk mitigation

RISK March 2003


Deepwater arena
Risk Mitigation
•Retain personnel
•Lessons learned program
Pocketsize booklet

•Job Safety Analysis


for on deck use
Project Job Safety
Procedures Analysis Toolbox
(HAZID’s) (JSA’s) Talks
Stop the Work •Stop the work culture
Heerema Safety Management System

•Capability breakthroughs
•Versatile and stable base
•Optimized for deep water fields
RISK March 2003
Management System

Pocketsize booklet
for on deck use

Project Job Safety


Toolbox
Procedures Analysis
Talks
(HAZID’s) (JSA’s)

Stop the Work

Heerema Safety Management System


Safety awareness and
management
RISK March 2003
involvement
END OF PRESENTATION

START DISCUSSION

RISK March 2003

You might also like