Professional Documents
Culture Documents
→ (1)
→ (1)
2 4
• Step 3: Compute
→ (2)
→ (2)
EE16601-PSOC VENKATESAN C AP/EE/SVCE
→ (3)
→ (2)
d
d
d
d
→ (2)
Where,
• PL = Transmission Losses in p.u.
• PG = Plant loading in p.u.
• B = Loss coefficients in p.u
• indicate independent summation to include all sources
→ (1)
• Equality constraint is
• or decrease by , if
Find the optimal generations PG1 and PG2 for = 20. Also
compute the transmission loss and received power.
→ (1)
→ (2)
Iteration 3:
Iteration 4:
Since load demand is not given, need not to find P and check < 1
• Iteration 1:
>1
→ (1)
→ (2)
• Fig. shows the start-up cost Vs time during cooling and banking period.
• Upto point 'p', cost of banking < Cost of cooling
• When the shut down cost is incurred, the unit may be said to be in hot-
reserve.
• Finally, the capacity limits of thermal units may change frequently, so
we must consider the thermal constraints for solving unit
commitment.
EE16601-PSOC VENKATESAN C AP/EE/SVCE
Other Constraints
❑ Hydro Constraints:
• Unit commitment problem involves only thermal units.
• In hydro-thermal scheduling, to allocate maximum hydro units during
rainy seasons and to allocate thermal units during remaining periods.
• We are not considering hydro units for unit commitment because
start-up and shunt-down time, operating costs are negligible.
• So we couldn't get the optimal solution.
❑ Must Run Constrains:
• Some units like nuclear units are given a must-run status during certain
times of the year to maintain the voltage in the transmission system.
❑ Fuel Constraints:
• If thermal and hydro sources are available, a combined operation is
economic and advantageous. i.e., to minimize the fuel cost of thermal
unit over a commitment period.
Assumptions:
• No load costs are zero.
• Unit input - output characteristics are linear between
zero output and full load.
• Start-up costs are a fixed amount.
• Ignore minimum up time and minimum down time.
5. For the load curve, shown in Fig., each hour load is varying.
• Assume load is dropping or decreasing, determine whether
dropping the next unit will supply generation and spinning reserve.
• If not, continue as it is. If yes, go to next step.
• All the three units would be held on until the load reached 900 MW.
• Units 1 and 3 would be held on until the load reached 500 MW, then unit 1
dropped
• Total fuel cost for the case (i) is less than that of the case (ii)
of feasible solution
• So when the system load level is 800 MW, it is preferable to
keep units 1 and 3 running
Algorithm
• For a load cycle, at each load level, the algorithm is to run
either of the units or both units with a certain load sharing.
• Determine the most economical cost curve of a single
equivalent unit.
• Then add the third unit and repeat the steps.
• The process is repeated until all the units are added.
• Determine the possible number of combinations and
determine the economic dispatch and total cost.
• Where
Fcost (K, I) = Least total cost to arrive at state (K, I)
Pcost (K, I) = Production cost for state (K, I)
Scost (K-1, L: K, I) = Transition cost from state (K-1, L) to state (K, I)
State (K, I) is the Ith combination in hour K
L = “N” feasible states in interval K — 1.