FOR CONSTRUCTION
Issue for
0 11 July 2021 J.M Baek J.M Baek J.M Baek J.M Oh
Construction
B 22 May 2021 Issue for Approval J.M Baek J.M Baek J.M Baek J.M Oh
A 27 APR 2021 Issue for Approval J.M Baek J.M Baek J.M Baek J.M Oh
Rev.
Issue Date Revision Text Prepared Checked Reviewed Approved
No.
The contents of this document are the sole property of POSCO E&C. Any rights not expressly
granted herein are reserved. Reproduction, transfer or distribution of part or all of the contents in
any form without the prior written permission of POSCO E&C is prohibited.
Title Construction Inspection and Test Plan Procedure
Document No. ELT-01-CQ-PC-0001
Revision No. 0
Page No. 2 of 13
TABLE OF CONTENTS
1 ...........................................3
Purpose .............................................................................. Error! Bookmark not defined.
2 Scope............................................................................................................................. 3
4 Definitions ................................................................................................................... 3
5 Responsibilities .......................................................................................................... 5
6 General ........................................................................................................................ 6
7 Procedure .................................................................................................................... 6
8 Records ....................................................................................................................... 9
9 Attachment ................................................................................................................ 12
Title Construction Inspection and Test Plan Procedure
Document No. ELT-01-CQ-PC-0001
Revision No. 0
Page No. 3 of 13
1. Purpose
This procedure has been developed to ensure that shall be performed in accordance
with the contract, applicable codes and management methods to be established.
Should conflict exist between Code and this procedure, Subcontractor shall notify
Construction Engineer and Project Quality Manager for clarification by written
agreement prior to proceed with the work.
2. Scope
This Procedure shall be applied to assign responsibilities, describe the methods and
provide procedures for site inspection and testing of field construction work, including
documentation interface with the Owner, Contractor and their subcontractors.
3. Reference documents
4. Definitions
Inspection:
Inspection means, examinations, tests or measurements to determine whether items
such as equipment, material, components, parts, assemblies, systems and structures
resulting from manufacturing or construction processes conform to specified
requirements.
Receiving Inspection:
Receiving Inspection will perform in accordance with [ELT-01-CQ-PC-0008] Receiving
Inspection Procedure
In-process Inspection:
Final Inspection:
to specified requirements.
Inspector:
Inspector means, a qualified person who performs inspection activities to verify
conformance to specific requirements.
The hold point which can’t be waived. If the inspection is rejected, the following process
can’t be proceeded and it must be issued as high grade of NCR in accordance with
[ELT-01-MQ-PC-0004] Nonconformance Procedure.
5. Responsibilities
5.1. Project Quality Manager (PQM) is responsible for the coordination and verification of
activities on the site of all items related to quality, such as inspection, test & witnessing,
monitoring, preparation & issue of ITPs, procedures and relative documents.
5.2. Construction Engineer (CE) is responsible for the preparation of activities on the site of
all items related to quality, such as preparation & issue of ITPs, procedures and relative
documents.
5.3.2 Plan and establish general and individual procedures for the field Inspection for
each work category.
5.3.3 Hold pre-inspection and inspection meetings as required with all the parties
concerned. The Owner will be invited to attend.
5.3.4 Submit to the Owner an application of notification for inspection for Witness or
Hold points in accordance with ITP’s.
5.3.5 Prepare written reports detailing the results of specific tests and inspections.
5.4.1 Review details of the field Inspection requirements or activities in accordance with
the specifications, Owner standard, other applicable codes and standard of the
Contract.
5.4.3 Maintain regular contact with the Owner including reporting all field Inspection
activities.
5.4.4 attending and performing test at the specific witness/hold inspection points which will
be indicated on the approved ITP
Title Construction Inspection and Test Plan Procedure
Document No. ELT-01-CQ-PC-0001
Revision No. 0
Page No. 6 of 13
(1) Summit inspection and test plan (ITP) to the Construction Engineer
(4) Maintain and provide to the Contractor the inspection/test status and
schedule
(5) Submit to the Contractor the inspection/test records showing that all
required inspection/test activities are completed.
6. General
6.1 Contractor shall control the quality of all stages of construction by meeting the
requirements of Inspection and Test Plan (ITP) and inspection procedures.
6.2 Construction Engineer shall prepare the QC dossier (Handover documents) cooperated
with QC personnel after completion of site fabrication/installation and shall submit it to
the Client according to the Contract for turnover. The QC dossier shall form part of the
turnover documents.
7. Procedure
7.1.2 ITP (Attachment #2) shall include the receiving inspection item (material verification
process) / construction discipline.
7.1.3 Hold point, witness point, review point for subcontractor/Contractor, shall be
reviewed and approved by Project Quality manager (PQM) or a designee (Home
Office or Site), as the case may be prior to implementation.
7.1.4 Applicable discipline engineer establish witness and hold point in concurrent with
the QA/QC Engineer or QC Inspector.
7.2.2 If it becomes necessary for the Contractor to change the schedule (date, time,
etc.), he shall promptly notify the Company for the proposed change in the same
manner.
7.3.1 Inspection and tests shall cover all phases of manufacturing and construction
to as certain that all works comply with the project specification and with the
Applicable codes and standard, that materials and workmanship are of good
quality and that all parts of the works are appreciate for the purpose which
they were intended to fulfill. In particular, inspection and testing shall include
all test and inspection as called For in the applicable codes and standard as
well as those specifically requested in the project specifications
(2) If Owner has designated a witness or hold point in ITP, inspector shall notify
the Owner of inspection schedule to witness inspection.
(3) Notification to the Owner shall be issued after successful completion of the
activity to be witnessed. The activity shall be inspected and approved by
the Contractor Inspector prior to issuing the notification. All site inspection
notifications to the Company shall be issued to the Contractor Quality Team.
(5) After completion of subcontracted work, PQM shall verify completion of all
the activities including inspections specified in the ITP, corrections for
nonconformance and completion of construction have been satisfactorily
completed, and shall review applicable records.
Title Construction Inspection and Test Plan Procedure
Document No. ELT-01-CQ-PC-0001
Revision No. 0
Page No. 9 of 13
(1) The PQM shall perform final inspection when all of construction works has
been completed.
(2) The PQM shall verify whether all of inspections/tests specified in contract
quality requirements have been implemented completely and all non-
conformances issued have been closed.
(3) Owner's witness/hold points for final inspection are designated in ITP, the
Company shall be notified in order to be able to witness.
The Contractor shall ensure that all materials and equipment are used at site after
acceptance inspection. In case any nonconforming items are discovered, they shall
be clearly identified, recorded and traced in accordance with [ELT-01-MQ-PC-0004
Nonconformance Control Procedure].
8 Records
9 Attachment
Inspection Notification
Project
Name
Subcontract
Project No.
or
Notification
System
No./Date
Inspection
Discipline
Date/Time
ITP No. Activities
Reference
DWG.
Inspection
Items
Detail Description (If Required)