Distribution : Controlled X Uncontrolled Available on computer X

Document status : TO :

F.I ( Information ) EBWPC

F.C ( Comments )

F.E ( Execution )

F.A X ( Application )

Title : INTERTRIPPING TEST


NARI - PCS 931

Type : FIELD TEST REPORT

Contract :

B U R G O S
Contract specific number Name

by
on
by
on
by
on
A by Budi Pranata Pasti Malau BORIS ORIGINAL ISSUE 6
on 10.06.2014 10.06.2014 10.06.2014
Ind Rev Prepared Checked Approved Modification Sheets

PT. ALSTOM GRID


FA - SECTION

J K T A T I 0 8 H F A B 0 0 2 6
Place of issue File number

This document is the property of PT. AG and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. ALSTOM GRID INTERTRIPPING TEST Ref.
FA SECTION NARI - PCS 931 Chapt.

Sheet : 2
A T : I . 08 . H.FAB.0026 Rev. A

SUMMARY SHEET REVISION

1 - LIST OF TEST EQUIPMENT USED 2 A

2 - INTERTRIPPING DTT TEST 3 A

3 - INTERTRIPPING TEST 4-5 A

1 - LIST OF TEST EQUIPMENT USED

Test corresponding to paragr.


Identification Designation
Number

Tested by : Witnessed by : Date :

This document is the property of PT. AG and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. ALSTOM GRID INTERTRIPPING TEST Ref.
FA - SECTION NARI - PCS 931 Chapt.

Sheet : 3
A T : I . 08 . H.FAB.0026 Rev. A

2 - INTERTRIPPING DTT TEST

115 KV BORGOS..............S/S

DIAMETER:

System 1

1. Signal send:

Protection ............................................................
Protection ............................................................
Protection ............................................................
Protection ............................................................

2. Signal received:

Protection ............................................................
Protection ............................................................
Protection ............................................................
Protection ............................................................

System 2

1. Signal send:

Protection ............................................................
Protection ............................................................
Protection ............................................................
Protection ............................................................

2. Signal received:

Protection ............................................................
Protection ............................................................
Protection ............................................................
Protection ............................................................

Tested by : Witnessed by : Date :

This document is the property of PT. AG and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. ALSTOM GRID INTERTRIPPING TEST Ref.
FA - SECTION NARI - PCS 931 Chapt.

Sheet : 4
A T : I . 08 . H.FAB.0026 Rev. A

S/S NAME : LINE : SYSTEM :

SCHEME :

115KV BURGOS.. S/S 115KV LAOAG... S/S


4 1 2 3
F1 F2

N° FAULT CB 115 KV 115 KV BURGOS..... S/S 115KV LAOAG……S/S


TYPE Trip Reclose INDICATION ALARM RESULT INDICATION
ALARM RESULT
RELAY HMI RELAY H M I

1 RN

2 SN

3 TN

4 RS

Tested by : Witnessed by : Date :

This document is the property of PT. AG and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. ALSTOM GRID INTERTRIPPING TEST Ref.
FA - SECTION NARI - PCS 931 Chapt.

Sheet : 5
A T : I . 08 . H.FAB.0026 Rev. A

S/S NAME : LINE : SYSTEM :

SCHEME :

115KV BURGOS.. S/S 115KV LAOAG... S/S


4 1 2 3
F1 F2

FAULT CB 115 KV 115 KV BURGOS..... S/S 115KV LAOAG……S/S


N° TYPE Trip Reclose INDICATION ALARM RESULT INDICATION
ALARM RESULT
RELAY HMI RELAY H M I

5 ST

6 RT

7 RST

Tested by : Witnessed by : Date :