REPAIR WORKS
(BY USING BELZONA SUPERWRAP II)
3. Monitoring (M): The activity shall be observe/monitor by dedicated inspection personnel and formal request is not required.
4. Actual Inspection (A): The standard inspection shall be carried out by dedicated personnel through out activity and formal
request is not required.
5. Surveillance (S): During execution of activity at any stage the Contractor/Company representative can visit and verify/inspect
and formal request is not required.
6. Review (R): This is a binding request to review and accept documents, certificates, procedures for specific activities and test and
required document will submit by the sub contractor.
Page 2 of 4
20" Oil Pipeline
Project Number:
Item: INSPECTION AND TEST PLAN FOR PIPELINE REPAIR WORKS Rev. A
(By USING BELZONA SUPERWRAP II)
Phase Activity Acceptance Criteria Verifying Document Contractor TPI Company Remarks
A- Preliminary Activity
A A.1 Procedure Qualification Trial Project Specification, Approved Construction -Company Approval A H
Procedure -Hydrostatic Test report
B-Material Inspection
A B.1 Material Receiving/Identification/MTC Review EN10204 3.1, Project Specification & AFC Material Test Certificates & Material A R
Drawings receiving Inspection Report
A C.1 Surface Preparation Inspection ISO 8501-1, Sa2 1/2 Visual Inspection Report A S
C.2 Surface cleaning (Cleaner Degreaser 9111) Contractor's approved procedure Visual Inspection Report A W
A C.3 Application of Steel patch and sealing with Belzona 1111 Contractor's approved procedure, Defect size Visual Inspection Report A W
C.4 Surface cleaning (Cleaner Degreaser 9111) Contractor's approved procedure Visual Inspection Report A W
A C.5 Apply resin grade Belzona 1982 Contractor's approved procedure, Patch size Visual Inspection Report A W
A C.6 Apply reinforcement sheet (Belzona 9381 Project Specification, Approved Construction Visual Inspection Report A W
Procedure
3 of 4
20" Oil Pipeline
Project Number:
Item: INSPECTION AND TEST PLAN FOR PIPELINE REPAIR WORKS Rev. A
(By USING BELZONA SUPERWRAP II)
Phase Activity Acceptance Criteria Verifying Document Contractor TPI Company Remarks
Name
Date