Alfil Millers Limited December 2019 Monthly Operations & Maintenance Report
Alfil Millers Limited December 2019 Monthly Operations & Maintenance Report
DECEMBER 2019
MONTHLY OPERATIONS &
MAINTENANCE REPORT
Monthly Report of Operations and Maintenance
For Alfil millers for both mill A and B For the Month of
December 2019
GENERAL MANAGER
Dear Sir:
The maintenance team is pleased to present the attached Monthly report. Included is a detailed
report of operation and maintenance of both Mill A, Mill B and motor vehicle for the month of
December 2019. The maintenance team welcomes any comments or questions on this report.
Sincerely,
Maintenance team
Executive Summary
During last month (December), we experienced minor break downs on dampening machine,
bucket elevators and one Air-locker for B1 /B2 which were all rectified. We installed rubber
hummers on two bran finishers & micro dozer and scourer sieves on their respective frames.
The rest of the maintenance work has been preventive, corrective and daily mill routine work.
On motor vehicle side, we have carried out breakdown maintenance on several trucks majority
of which had brake systems faults. The maintenance team members also engage in daily
production activities during day and night production shifts respectively including daily and
weekly maintenance programs.
Initiating the construction of wooden tool box for storing company tools
Note
The maintenance team includes one motor vehicle & one maintenance mechanic, one welder
and two technical helpers. One technical helpers also work in production shift changeovers as
well. The team work hand in hand to deliver precise results. The team also works hand in hand
with productions team to ensure proper mill maintenance