Professional Documents
Culture Documents
Spun Pile
Main Span Pilecap Construction
by
P0-P11 : Spun Pile P24-P27 : P28-P43 : Steel Pile P145-P282 : Spun Pile
P12-P23 : Steel Pile Bored Pile P44-P144 : Spun Pile P283-P292 : Bored Pile
* 19 nos. replacement spun piles P107-07 A & B, P102-12 A & B, P061-13 A & B,
P120-04 A & B, P122-07A & B, 8A, P137-7A & 7B, P193-21A & B, P9-17
A&B, P280-R15 A&B
Pile Testing Locations
BHT8 BHT9
BHT10
BHT7 BHT4
BHT6
BHT3&5
BHT2
BHT11
BHT1
BHT12
Pile Testing On Spun Pile, Steel Pile & Bored Pile
Pile Test No. Chainage Location Pile Type Working Total Test Total Not
(near to) Load (kN) Done Passed Conclusive
O-Cell Test BHT 3 CH 9+700 P161 Ø1.2m Steel Pile 5,800 1 1 -
O-Cell Test BHT 7 CH 2+688 P33 Ø1.6m Steel Pile 8,100 1 - 1
O-Cell Test BHT 9 CH 1+981 P25 Ø2.3~2.0m 25,500 1 - 1
Bored Pile
MLT & PDA BHT 1 CH 15+900 P273 Ø1.0m Spun Pile 3,800 1 1 -
MLT & PDA BHT 2 CH 11+700 P197 Ø1.0m Spun Pile 3,800 1 1 -
MLT & PDA BHT 5 CH 9+700 P161 Ø1.0m Spun Pile 3,840 1 1 -
MLT BHT 4 CH 3+500 P48 Ø1.0m Spun Pile 3,800 1 - 1
MLT & PDA BHT 6 CH 3+530 P48 Ø1.2m Spun Pile 4,600 1 1 -
MLT & PDA BHT 3 CH 9+700 P161 Ø1.2m Steel Pile 5,800 1 1 -
MLT & PDA BHT 11 CH 9+818 P163 Ø1.0m Spun Pile 3,720 1 1 -
Statnamic - CH 11+028 P185-L08 Ø1.0m Spun Pile 3,100 1 1 -
Statnamic BHT 11 CH 9+818 P163 Ø1.0m Spun Pile 3,720 1 1 -
MLT & (Statnamic BHT 12 CH 16+913 P292 Ø1.5m Bored Pile 8,000 1 - 1
on Anchor Pile)
MLT & (Statnamic BHT 8 CH 1+368 P15 Ø1.6m Steel Pile 7,210 1 1 -
on Anchor Pile)
Statnamic - CH 3+548 P49-R15 Ø1.0m Spun Pile 3,410 1 1 -
Statnamic - CH 1+980 P25-09 Ø2.0m Bored Pile 27,200 1 1 -
SPUN PILE
Spun Pile Detail
DETAILS OF PILESHOE
Spun Pile Detail
Extension Joint
Spun Pile Detail
Extension Joint
Spun Pile Detail
L1 L2 L3 L4 L5
~ -55.00 SPT = 50
Spun Pile Length
PDA Test...
Spun Pile Test For BHT11 (P163)
Statnamic Test...
Spun Pile Test For BHT11 (P163)
MLT
Min. 15 days after MLT
Statnamic
Spun Pile Test For BHT11 (P163)
Table 2 : Comparison of 2nd Cycle Nett Static & Statnamic Load Test Displacement
• From Table 1, settlement recorded from Statnamic test for M2-1 at 2.0 WL is 5.14mm less than
Static test for S2
• From Table 2, settlement recorded from Statnamic test for M2-1 at 2.0 WL is 2.38mm less than
Static test for S2
Spun Pile Test For BHT11 (P163)
Test Pile Penetrated Set Ultimate Initial Restrike Restrike / MLT / PDA
Pile Length Length (mm) Capacity of PDA PDA Initial Initial
(m) (m) MLT(kN) (kN) (kN)
S2 64 54.68 5.9 > 11,160 5150 10,800 2.10 >2.17
2.5
Mobilization
2
Factor
1.5
0.5
0
40 45 50 55 60
LP (m)
Mobilization Factor of Spun Pile
2.5
Mobilization
1.5
Factor
0.5
0
0 1000 2000 3000 4000 5000
Blow Count
Mobilization Factor of Spun Pile
Mobilization vs Set
Relationship Diagram Between SET & Mobilization Factor
3
2.5
Mobilization
1.5
Factor
0.5
0
0 2 4 6 8 10 12 14
SET (mm)
Mobilization Factor of Spun Pile
Mobilization vs Period
Relationship Diagram Between Period & Mobilization Factor
3
2.5
Mobilization
1.5
Factor
0.5
0
0 5 10 15
Period (Day)
Mobilization Factor of Spun Pile
8
7 Pile Head
6 Damage Cases
5 Total cases = 55
4
3
2
1
0 MayJuneJulyAugSepOct NovDec JanFebMarAprMayJuneJulyAugSepOct NovDecJanFebMarAprMayJuneJulyAugSep
09 09 09 09 09 09 09 09 10 10 10 10 10 10 10 10 10 10 10 10 11 11 11 11 11 11 11 11 11
Month
Pile Head Damage Analysis
7%
% Pile Head Damage
6%
5%
4%
3%
2%
1%
0%
90
94
73
68
2
220
225
112
145
169
185
226
327
247
270
208
209
195
252
256
175
148
156
160
244
279
177
125
150
May June July Aug Sep Oct Nov Dec Jan Feb Mar Apr MayJune July Aug Sep Oct Nov Dec Jan Feb Mar Apr May June July Aug Sep
09 09 09 09 09 09 09 09 10 10 10 10 10 10 10 10 10 10 10 10 11 11 11 11 11 11 11 11 11
1.37%
% Pile Head Damage
1.14%
0.91%
0.68%
0.46%
0.23%
0.00%
220
310
535
629
741
814
959
1128
1313
1539
1866
2113
2383
2591
2800
2995
3247
3503
3571
3746
3894
4050
4210
4454
4733
4910
5035
5185
5187
May June July Aug Sep Oct Nov Dec Jan Feb Mar Apr MayJuneJuly Aug Sep Oct Nov Dec Jan Feb Mar Apr May June July Aug Sep
09 09 09 09 09 09 09 09 10 10 10 10 10 10 10 10 10 10 10 10 11 11 11 11 11 11 11 11 11
2 QC on standard operating procedure •To replace hammer cushion once worn out
(Piling Operation) •Provide sufficient cushion materials
•Ensure hammer hits pile evenly and axially
•Reduce pile driving stresses by controlling hammer drop
height during hard driving
3 Factory visit, inspection and QAQC
procedure auditing at ICP factory
Pile Head Damage Analysis
• 2 hours waiting time was set aside for pile which has undergone spinning
process. On top of that, 8 hours of steam curing time is above the usual practice
of 5 hours.
• The allowable gap between end plates is only 2mm, which is much more
stringent than 5mm tolerance stated in MS1314: Part4:2004.
• Monthly inspection from CHEC & MMSB to ensure all piles produced to the
highest standard as stipulated in the Technical Requirements for Spun Pile.
Pile Head Damage Analysis
Jack
Test Pile
Dial Gauges
Support Support
Carry out pile head strengthening work (with carbon fiber & ICP method)
PDA Test
Coring Test
Validation Process
Piling work done in accordance with :
Pile Certification Report
- Approved construction drawing
-PDA test report
- Set criteria Pile Driving Record
- PDAR if required
- HPDI revised pile length confirmation
- SOR / NCR closure if any
- Shop drawing (if any changes)
Pile Cutting
Validation of Spun Pile
Set Criteria
Validation of Spun Pile
Piling Record
H>2m
Validation of Spun Pile
PDA Result
> 80%
> 2.5 x WL
Validation of Spun Pile
P24
P25
P26
P27
Main Navigation Span
Span Length
p26
p25
p27
p24 117.5 m
240 m
117.5 m
150 m
Navigation
Navigation ChannelChannel
Main Navigation Span
Pylon Detail
30m
5m
Main Navigation Span
General Description
17.5m
48.1m
6m
Main Span Pilecap Construction
Steel
St eelCasing
case Steel
St eelCasing
case
Main Span Pilecap Construction
-3.32m
-5.12m
Concreting Of Pilecap
+3.48m
+2.68m
the
2nd Layer
ndsecond layer concrete
2 Layer the second layer concrete
of the pilecap(3.0m)
(2.0m)
of the pilecap(2.0m)
1sttheLayer
first layer concrete of
steel fender (2.0m)
the pilecap(2.0m)
-1.32m
st Layer
1the second layer concrete
of the pilecap(3.0m)
(3.0m) Mass
mass Concrete
concrete(1.2m)
-2.52m
(1.2m)
Mass Concrete
mass concrete(1.8m)
(1.8m)
Temperature Control
JKR Specification
• Additive like GGBS and silica fume are added to the design mix
to minimize the cement content
Water boat
Thermocoupler
Cooling pipe
Main Span Pilecap Construction
Peak Temperature
80
70
Temperature/ ℃
60
50
40
30
20
10
0
0 20 40 60 80 100 120 140 160 180
Time/h
Thank You