PROJECT SPECIFICATION
DESCRIPTION
FOR
DISCIPLINE
ENGINEER
_______________ EPC13 UTILITIES DISTRIBUTION PACKAGE
DATE _________
JAZAN REFINERY AND
PROJECT
ENGINEER
_______________ ECONOMIC CITY PROJECT DEPARTMENT
DATE _________
CERTIFIED
_______________
DATE _________
DATE _________ 07H 06/26/14 IFC WITHOUT HOLD T.N. K.E. H.T.
00H 06/12/13 ISSUE FOR COMMENTS C.D. K.E. H.T.
EDSD VERIFICATION
------------------------------
CONTROL NUMBER
DATE: __________
BY: ____________
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
Table of Contents
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
1. SCOPE ............................................................................................... 4
1.1 General ................................................................................... 4
CERT
1.6 Quotation................................................................................ 9
1.7 Manufacturer Drawings and Data ........................................10
1.7.1 Protective Device Settings and Curves ..................10
1.7.2 Documentation Required .......................................10
JO/EWO
------------------------------
CONTROL NUMBER
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
2.18 Current Transformers ...........................................................29
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
2.19 Cable Termination ................................................................30
2.20 Gas Insulated Surge Arresters ............................................31
CERT
DISCIPLINE
ENGINEER
_______________
DATE _________
PROJECT
ENGINEER
_______________
DATE _________
CERTIFIED
_______________
DATE _________
CONSTRUCTION
AGENCY
_______________
DATE _________
OPERATIONS
_______________
DATE _________
EDSD VERIFICATION
------------------------------
CONTROL NUMBER
DATE: __________
BY: ____________
THIS INDICATES THAT REV. NO. ______
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
1. SCOPE
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
1.1 General
CERT
1.3 Environment
Generally, the equipment shall be installed indoors in environmentally
DISCIPLINE
ENGINEER
controlled rooms. Where the equipment will be installed outdoors, it
_______________ shall be rated for the environmental conditions specified in SAES-A-112.
DATE _________
Ambient conditions and specific plant site data are as indicated on the
PROJECT
ENGINEER
project design document J95-A-DOC-VE-514855.
_______________
DATE _________
1.4 Units
CERTIFIED
Unless otherwise stated, all units shall be in the metric International
System of Units (SI) in accordance with SAEP-103 (metric units of
_______________
weights and measures). All documentation and nameplates shall be in
DATE _________
the English language.
CONSTRUCTION
AGENCY Equipment warning labels and instructions shall be in English and
_______________
Arabic languages.
DATE _________
1.5 Codes, and Industry Standards
OPERATIONS
------------------------------
CONTROL NUMBER
DATE: __________
BY: ____________
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
Standards including but not limited to those listed below:
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
SEC Saudi Electricity Company
ANSI/IEEE C37.2 Standard Electric Power System.
CERT
Breakers
ANSI/IEEE C37.38 Gas-insulated, metal enclosed
disconnecting, interrupter and
grounding switches.
JO/EWO
DISCIPLINE
ANSI/IEEE C57.13 Standard requirements for Instrument
ENGINEER Transformers
_______________
CONSTRUCTION
IEEE 80-2000 Guide for Safety in AC Substation
AGENCY
_______________
Grounding
DATE _________
SAES-A-112 Meteorological and Seismic Data
OPERATIONS
SAES-P-100 Basic Power System Design Criteria
_______________
------------------------------
CONTROL NUMBER
DATE: __________
BY: ____________
SAES-P-111 Grounding
SAES-P-114 Power System and Equipment
Protection
THIS INDICATES THAT REV. NO. ______
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
SAES-P-126 Power System Automation
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
Indoor
DATE _________
IEC 60050 Chapter 441: Switchgear, Controlgear
and Fuses
EDSD VERIFICATION
------------------------------
CONTROL NUMBER
DATE: __________
BY: ____________
systems
FOR ALL APPROVAL / CERTIFICATION
OF THIS DOCUMENT IS COVERED,
REVISION CERTIFICATION
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
AGENCY
PROJECT
BY: ____________
ENGINEER
ENGINEER
CERTIFIED
DISCIPLINE
COMPLETION CERTIFICATE
OPERATIONS
DATE _________
DATE _________
DATE _________
DATE _________
DATE _________
CONSTRUCTION
_______________
_______________
_______________
_______________
_______________
(DCC) NO. ___________ DATE: __________
JAZAN
Project Specification
IEC 60137
SAUDI ARABIA
DWG. TYPE
J95
PLANT
P
INDEX
voltages above 1000V
JO EWO : BI-10-01055-0013
Insulated bushings for
SAUDI ARABIAN OIL COMPANY
DOC.
7 VE-780470
of
35
SHT.
alternating
REV.
10H
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
SAUDI ARABIAN OIL COMPANY
OPRNS
IEC 60185 Current Transformers
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
Identification
------------------------------
Controlgear.
CONTROL NUMBER
DATE: __________
BY: ____________
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
IEC 61554 Panels Mounted Equipment –Electrical
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
Measuring Instruments-Dimensions for
Panels Mounting
CERT
switches
DISCIPLINE
IEC 62271-203 High-voltage switchgear and
ENGINEER
_______________
controlgear - Part 203: Gas-insulated
metal-enclosed switchgear for rated
DATE _________
voltages above 52 kV
PROJECT
ENGINEER
_______________ 1.6 Quotation
DATE _________
In addition to quotation requirements the Bidder shall furnish three (3)
CERTIFIED copies of the following documents with the proposal:
_______________
- Descriptive bulletins (to aid in determining compliance with this
DATE _________ specification)
CONSTRUCTION
AGENCY
- Heat loss data for each typical unit and for the switchgear in
_______________ its entirety
DATE _________
- Preliminary one-line diagram
OPERATIONS
------------------------------
CONTROL NUMBER
DATE: __________
BY: ____________
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
- Specific types of relays and metering to be used. Provide
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
technical information for each type of relay and meter
proposed.
CERT
rates
- A list of spare parts required for installation and
commissioning of the switchgear, and a list of spare parts
DESCRIPTION
DISCIPLINE
- Relay type, range, and pick-up value
ENGINEER
_______________
- Relay settings including current, voltage, time settings,
DATE _________ instantaneous, power-factor, frequency, etc. Devices shall
PROJECT be cross-referenced to the appropriate time-current curve.
ENGINEER
_______________
- The Manufacturer shall provide a complete set of time-
DATE _________
current curves for the relays listed above.
CERTIFIED
_______________
1.7.2 Documentation Required
DATE _________ The Bidder is required to furnish and include the costs for the following
CONSTRUCTION
documents after placement of order:
AGENCY
_______________ - One-line diagram
DATE _________
- Schematic diagrams for all circuits
OPERATIONS
- Legend and symbol definitions for all drawings
_______________
------------------------------
CONTROL NUMBER
DATE: __________
BY: ____________
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
- Final assembly arrangement drawings showing main circuits,
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
main dimensions, foundation plan, shipping section and
cable termination arrangement details
CERT
DATE _________
- Fault finding/trouble shooting data shall be included
PROJECT - GIS insulation coordination
ENGINEER
_______________
DATE _________
1.7.3 Drawing Presentation
CERTIFIED
Graphic symbol for electrical diagrams shall be according to ANSI
Y32.2/IEEE STD.315. Device code numbers per ANSI/IEEE C37.2 shall
_______________
be indicated adjacent to device symbol.
DATE _________
CONSTRUCTION
1.8 Deviations
AGENCY
_______________ Any deviations from the requirements stated within this specification or
DATE _________ the drawings/data sheets which define the 132kV GIS gear shall be
submitted in writing to the Purchaser for approval.
OPERATIONS
_______________
DATE _________
2. TECHNICAL REQUIREMENTS
EDSD VERIFICATION
------------------------------
CONTROL NUMBER
DATE: __________
BY: ____________
2.1 General
The switchgear rating shall be as noted on data sheet and one-line
diagrams and shall comply with ANSI/IEEE C37.122, IEC 62271 and
IEC 60694. The switchgear shall be operated continuously at the
ambient conditions as specified on data sheets. All high voltage
THIS INDICATES THAT REV. NO. ______
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
components shall be enclosed and insulated in Sulfur Hexafluoride
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
(SF6) gas under positive pressure.
The supplied equipment shall be immune from the harmonic currents
CERT
and voltages on the electrical supply system which are at a level below
the limits that are defined in Table 1 of IEC 61000-3-6. Immunity shall
include the supplied equipment operating properly at the designed
ENG’G
ratings.
Switchgear shall be fixed-mounted, metal-clad, gas insulated type (GIS),
free standing, self ventilating, self supporting, having a double bus bar
DESCRIPTION
DATE _________
The equipment shall be capable of proper operation for voltage
deviations as defined in SAES-P-100. In addition, all components shall
PROJECT
ENGINEER be able to ride through voltage dips to 85% nominal, such as those
_______________ experienced during motor starting.
DATE _________
The switchgear components shall be provided as defined in IEC 60050
CERTIFIED Chapter (441).
_______________
Switchgear components shall be housed in individual gas
DATE _________
compartments. Manufacturer shall provide details on standard design
CONSTRUCTION for separation of components into individual gas compartments.
AGENCY
_______________ Components requiring periodic maintenance and all mechanical parts
DATE _________ which are outside of gas filled compartments shall be easily externally
accessible and serviceable without disconnecting the main bus bar or
OPERATIONS
feeder circuits. The GIS shall be provided with galleries, stairways,
_______________
movable platform or walkways with grounding provision for accessing
DATE _________
the equipment above two meters for maintenance and operation.
Combined disconnector and grounding switch, cable termination, VT
EDSD VERIFICATION
------------------------------
CONTROL NUMBER
DATE: __________
BY: ____________
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
All circuit breakers in the switchgear assembly shall be installed in
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
single tier (one high) formation.
The switchgear shall be extendable at either end without drilling or
CERT
Separate GIS bus link module shall be provided at both ends of the GIS
to avoid modification of the existing bus for future extension by GIS
manufacturers other than the original manufacturer.
DESCRIPTION
operating step.
The layout of the operational front and the location of the components
of the assembly shall be arranged in a logical and systematic sequence
DATE
DATE _________ Interlocking systems shall be provided for all devices as noted on the
one-line diagram(s). Electrical interlock scheme shall be fail-safe to
OPERATIONS
prevent loss of interlock function upon loss of control voltage.
_______________
DATE _________
Space heaters to prevent condensation shall be provided within the
switchgear assembly. Power for the space heater circuit shall be
supplied from a separate low voltage source (230V AC 60Hz
EDSD VERIFICATION
------------------------------
CONTROL NUMBER
DATE: __________
BY: ____________
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
Provision shall be made for condition monitoring, diagnostics and site
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
testing. Where these facilities are integral to the switchgear, they shall
not reduce the integrity of the prime function of the switchgear or that of
neighboring switchgear.
CERT
Circuit breaker shall comply with normal and fault current ratings as
shown on the one-line diagrams and data sheets.
REV NO.
------------------------------
CONTROL NUMBER
DATE: __________
BY: ____________
The circuit breaker shall be designed for simultaneous three (3) pole
operation. Circuit breakers requiring external devices to accomplish
their rated interrupting capabilities are not acceptable.
The total interrupting time at all currents shall be less than the rated
THIS INDICATES THAT REV. NO. ______
short circuit interrupting current and shall not exceed the rated
FOR ALL APPROVAL / CERTIFICATION
OF THIS DOCUMENT IS COVERED,
REVISION CERTIFICATION
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
maximum interrupting time. Re-strikes shall not occur during any type of
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
load switching and fault interruption.
The control power supply to all trip and closing coil circuits shall be
CERT
provided with isolating switch. One auxiliary contact of this switch shall
be wired to alarm when the switch is in open position. Both positive and
negative poles of the close coil shall be switched.
ENG’G
------------------------------
CONTROL NUMBER
DATE: __________
BY: ____________
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
In addition to the required number of auxiliary contacts needed for the
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
control and indication circuits, each breaker shall be provided with at
least four NO and NC contacts, double gap, voltage free and wired to
the auxiliary terminal block of the low voltage compartment for future
CERT
use.
2.3 Switchgear Control Power
ENG’G
system.
Each switchgear bay shall be provided with a dedicated feeder from the
DC distribution board of the DC system as shown on the one-line
diagram (i.e., each feeder shall normally feed one section of the
switchgear). DC controls supply failure and under voltage annunciation
JO/EWO
shall be provided.
For the protection of control, measuring and auxiliary low voltage
DATE
------------------------------
CONTROL NUMBER
DATE: __________
BY: ____________
The disconnect and grounding switch should be three (3) pole gang
operated, no-load break, single stroke type, fault make rated and
comply with the requirements of ANSI/IEEE C37.38 or IEC62271-102
and IEC-62271-203.
The disconnector shall be capable of interrupting rated capacitive
THIS INDICATES THAT REV. NO. ______
currents originating from switching bus bars, bus ducts and very short
FOR ALL APPROVAL / CERTIFICATION
OF THIS DOCUMENT IS COVERED,
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
An integrally mounted 3-position, three phase grounding/disconnecting
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
switch, capable of making and carrying the prospective short circuit
current shall be provided on all HV switching devices. The operation of
the grounding switch shall be mechanically interlocked allowing closure
CERT
of the grounding switch only when the HV switching device is not in the
closed position. Clear instructions, preferably pictorial, shall be installed
ENG’G
grounding switches shall have the same short time current rating as
that of the switchgear.
DISCIPLINE
ENGINEER In all grounding switches, the ground connection of each phase shall be
_______________ isolated from the ground connection of the other phases and from the
DATE _________ switchgear enclosure, and brought out through an insulated bushing,
PROJECT rated 10kV minimum. Direct connection to ground shall be via a
ENGINEER
_______________
removable grounding strap. The rating of the grounding strap shall be
DATE _________
equal to the rating of the grounding switch.
CERTIFIED
Interlocks shall be provided by means of key interlocking to prevent
_______________
grounding of an energized supply, which has not been isolated, and to
prevent energizing a supply, which is grounded.
DATE _________
------------------------------
CONTROL NUMBER
DATE: __________
BY: ____________
indicators for the main contact open and closed positions, directly
FOR ALL APPROVAL / CERTIFICATION
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
standing on the substation floor near the equipment. The markings shall
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
be in white letters as ‘Open’ or ‘O’ on a green background and ‘Closed’
or ‘C’ on a red background.
CERT
moveable contact.
Anti-condensation heaters shall be provided within the housing of each
motor driven operating mechanism, and shall be power by 230V AC
DESCRIPTION
device.
Main switching devices shall be provided with a minimum of four (4)
REV NO.
normally open and four (4) normally closed voltage free contacts for
future use by Purchaser. Additional contacts shall be provided for
DISCIPLINE
ENGINEER controls and indications as required by the control schemes and one-
_______________
line diagram(s). The contacts shall be wired to the terminal blocks in the
DATE _________ low voltage control compartment.
PROJECT
ENGINEER 2.6 Secondary Wiring and Terminals
_______________
DATE _________
The minimum conductor sizes shall be according to 16-SAMSS-514
10H
Section 8, with following additional restrictions:
CERTIFIED
_______________
- #2 AWG (35 sqmm) for current transformer circuits,
DATE _________ - #6 AWG (16 sqmm) for power circuits,
CONSTRUCTION
AGENCY
- #12 AWG (4 sqmm) for control circuits,
_______________
All conductors used for instrumentation signal wiring, not covered by
DATE _________
Electrical standard, can have minimum cross section #18AWG (1.5
OPERATIONS sqmm).
_______________
All conductors shall be XHHW type.
DATE _________
The control wiring shall be heat resistant stranded annealed copper
conductor with flame retardant, insulation type SIS as per ANSI/NFPA
EDSD VERIFICATION
------------------------------
CONTROL NUMBER
DATE: __________
BY: ____________
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
troubleshooting and maintenance. The terminal blocks shall be
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
mounted inside the switchgear and shall be accessible from the front of
the switchgear without exposure to energized power voltage
components. These terminals shall be barrier type with screw terminals
CERT
for use with spade or ring type lugs. Quick-disconnect type terminal
blocks shall not be used.
ENG’G
Test block(s) for injection testing of relays and measuring devices shall
be provided on each panel.
DATE
_______________
Control wiring within the switchgear assembly equipment and the
DATE _________
control cabinets shall be securely held in place (either loomed or run in
raceways or galvanized rigid steel conduits or flexible steel tubing with
CONSTRUCTION
AGENCY
PVC jacket. They shall not obstruct the maintenance access to
_______________ devices/operating mechanism). Where wiring enters or passes through
DATE _________ compartments containing high voltage apparatus, it shall be run in
OPERATIONS
grounded metallic conduit/trunking. The conduits shall be installed and
located so as to minimize accidental damage and to eliminate the need
_______________
to dismantle the conduits during maintenance and/or removal of
DATE _________
modules, other than the conduit associated with the maintenance item.
The conduit shall be terminated via metallic adapters to ensure
EDSD VERIFICATION
------------------------------
CONTROL NUMBER
DATE: __________
BY: ____________
grounding.
The principles of control wiring practice in GIS with continuity of the
shield from one element to the next shall be per ANSI/IEEE C37.122.1
in the 1-30MHz frequency range. When a shielded control cable enters
a control cabinet, the cable shield shall be terminated immediately on
THIS INDICATES THAT REV. NO. ______
preferable.
REVISION CERTIFICATION
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
Terminal blocks shall be mounted on grounded DIN rails at an easily
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
accessible position approximately 30 cm above the base and shall be
equipped with barriers and color-coded terminal strips. The AC, DC and
CT and PT circuits shall be physically segregated in groups. The
CERT
------------------------------
CONTROL NUMBER
DATE: __________
BY: ____________
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
- Purchase Order Number/Contract Number/Job Order
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
Number
- Rated SF6 gas pressure for operation at 20 degree C
CERT
------------------------------
CONTROL NUMBER
DATE: __________
BY: ____________
source
- Termination points for all wiring brought to the switchgear from an
external power source
2.8 Degree of Protection
The degree of protection for all terminal boxes and operating
THIS INDICATES THAT REV. NO. ______
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
protection for control cabinets, auxiliary equipment enclosures and all
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
accessories shall be per 01-TMSS-01.
For all parts under SF6 gas, the degree of protection shall be at least
CERT
IP64.
Switchgear enclosures shall comply with IEC 62271-200 Annex A with
ENG’G
regard to their mechanical strength in the event of internal arc. The test
performance shall be in conformity with type A and the maximum
allowable arc duration shall be equal to that specified for the short
circuit withstand current. An arcing fault in one compartment should not
DESCRIPTION
Bus bar and connections shall be fully rated, braced and supported to
withstand thermal expansions, dynamic and dielectric stresses over the
REV NO.
full length of the switchgear and carry rated normal current and
withstand short circuit currents as specified in data sheets. The bus
DISCIPLINE
ENGINEER support insulators shall be of adequate strength to withstand electrical
_______________
and mechanical stresses that may be encountered in service. The
DATE _________ busbar phase conductor shall be adequately supported by cast resin
PROJECT insulators or other approved material equally supported, at least at both
ENGINEER
_______________
ends of each section making provision for free axial movement of
DATE _________
conductor.
CERTIFIED
Non-barrier insulators shall permit the gas pressure to equalize
_______________
between the compartments. Conductive particle traps shall be placed at
the support insulators, whenever required. Insulators shall be non-
DATE _________
tracking type.
CONSTRUCTION
AGENCY Suitable bus elbows, tees, bellows shall be provided as per the
_______________
manufacturer’s standard and recommendations depending on the
DATE _________
mechanical stress and vibration expected. The bus duct shall be
OPERATIONS provided with shipping caps and pressurized with positive pressure by
_______________ dry air or nitrogen for shipment.
DATE _________
All bolted connections shall be made with high tensile strength bolts
effectively secured against loosening.
EDSD VERIFICATION
------------------------------
CONTROL NUMBER
DATE: __________
BY: ____________
Bus bar shall be the same cross sectional area throughout the length of
the switchgear.
The phases shall be designated as R (Red), Y (Yellow) and B (Blue)
throughout the substation when viewed from East to West, from North
to South, from Left to Right and from Top to Bottom.
THIS INDICATES THAT REV. NO. ______
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
A grounding bus bar shall be provided along the full length of the
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
switchgear structure with provisions for ground cable connections at
each end with the use of compression type cable lugs bolted to the
grounding bus. This bus bar shall have a minimum cross sectional area
CERT
of 240mm².
2.10 Gas Compartment Technology
ENG’G
any other section. The vendor shall guarantee that no further gas
processing is required during its expected operating life of 30 years.
The equipment shall be fully functional without any inspection / refilling
DATE
DATE: __________
BY: ____________
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
effects of internal arc faults as well as maximum pressure differential
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
that could exist between adjoining compartments, i.e. with full vacuum
drawn on one side of the barrier and 1.5 times the operating pressure
on the other side.
CERT
_______________
It shall be possible to test and replace each pressure gauge and the
density switch/relay with the GIS in service.
DATE _________
DATE _________
The SF6 gas pressure/density monitors shall be preferably directly
coupled to the gas compartment. Where necessary permanently fixed
gas pipe work for SF6 gas pressure/density monitoring shall be
EDSD VERIFICATION
------------------------------
CONTROL NUMBER
DATE: __________
BY: ____________
installed.
At each gas compartment, provisions shall be made for connecting
online moisture measurement instrumentation and the gas service cart.
Individual gas compartments shall be equipped with pressure relief
THIS INDICATES THAT REV. NO. ______
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
operator during the time of his normal duty per ANSI/IEEE C37.122 and
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
IEC 62271.
Filters shall be inserted in all the gas compartments in addition to circuit
CERT
------------------------------
CONTROL NUMBER
DATE: __________
BY: ____________
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
The local control and monitoring equipment shall be located adjacent to
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
the switchgear that it controls in a local control panel, mounted separate
to the switchgear. The panels and associated controls / indication shall
be clearly labelled to indicate the apparatus it contains and the
CERT
switchgear it controls.
The local control panels shall ensure full and independent local control
ENG’G
All IED relays in the 132kV GIS switchgear (BCU, protection and control
cabinets) shall be connected to PSA Level 1 redundant ethernet
switches, compliant with 23-SAMSS-701, that are part of GIS supply
REV NO.
DATE _________ Relays with multiple trip and alarm functions shall have separate
operating contacts for each function wired out to separate terminals,
and bus wired to a central point per assembly section.
EDSD VERIFICATION
------------------------------
CONTROL NUMBER
DATE: __________
BY: ____________
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
Bay Control cabinet shall house all equipments as indicated in the
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
Protection & Metering diagram, providing direct control to the bay, and
shall comply with 16-SAMSS-514 and IEC61439. Cable entry shall be
both from top & bottom side, and finish colour shall be the same of GIS
CERT
switchgear.
BCU shall house also secondary terminals of CT’s & VT’s, as
ENG’G
marshalling.
BCU shall also provide bay mimic diagram and annunciator, together
with bay local control, and relevant IED shall be IEC 61850 compliant
DESCRIPTION
Bay Control cabinet shall house also I/O module for bay
interlock/intertrip, to be connected via dedicated redundant F.O. with
upstream/downstream interlock/intertrip device.
DATE
------------------------------
CONTROL NUMBER
DATE: __________
BY: ____________
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
All digital relays and meters shall have communications capability to
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
send and receive signals to/from a remote intelligent monitoring and
control system. Redundant fiber optic connections are required in each
relay.
CERT
Interfaces with the IGCC, the Power System Automation and/or SCADA
shall be in accordance with SAES-P-126.
The switchgear manufacturer shall coordinate with IGCC and the
DESCRIPTION
CERTIFIED
2.17 Voltage Transformers
_______________ Voltage transformer provided per the one-line diagrams and/or data
DATE _________ sheets shall be in accordance with IEEE C57.13 or IEC60044-2.
CONSTRUCTION
Primary and secondary terminals and polarity shall be marked as per
AGENCY applicable standards. The rated output shall match the maximum load
_______________
of the equipment connected and should be selected from the range of
DATE _________
standard values.
OPERATIONS
Voltage transformers shall be inductive type, SF6 gas insulated and
_______________
shall be located inside individual or common enclosure. VTs shall have
DATE _________
disconnect link (to be operated from GIS exterior) or separate
disconnect switch. The VTs shall have core with dual accuracy class
EDSD VERIFICATION
------------------------------
CONTROL NUMBER
DATE: __________
BY: ____________
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
Secondary windings shall be terminated at the local control cabinet
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
through a terminal box. The secondary terminals shall be connected to
the terminal box via gas-tight bushings. Voltage transformers shall be
protected at the LV side by industrial cartridge fuses or miniature circuit
CERT
shall be provided with miniature knife switch on the VT side of the fuses
and fuse/supervised MCB. Separate terminals shall be provided for VT-
fuse supervision.
DESCRIPTION
VT shall be provided on all incoming and outgoing feeders and for each
bus. The metal housing of the VT shall be connected to the metal
enclosure of the GIS for proper grounding.
Voltage transformers for metering and protective devices shall have
accuracy class and voltage ratio as stated on the data sheets.
JO/EWO
Bus bar mounted voltage transformers shall have provision for safely
disconnecting the voltage transformer from the energized bus bar.
REV NO.
------------------------------
CONTROL NUMBER
DATE: __________
BY: ____________
current ratio and accuracy class as shown on data sheets and one-line
OF THIS DOCUMENT IS COVERED,
REVISION CERTIFICATION
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
diagrams. Current transformers characteristics shall comply with
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
required knee point voltage, magnetising current, CT winding
secondary winding resistance & other special requirements as per data
schedule
CERT
The instrument security factor (ISF) at all ratios shall be less than five
(5) for metering core. ISF shall be verified without use of any auxiliary
ENG’G
reactor.
Where differential protection is specified, the Manufacturer shall provide
the calculations together with current transformer magnetization curves
DESCRIPTION
------------------------------
CONTROL NUMBER
DATE: __________
BY: ____________
switchgear end) shall allow for power cable disconnection from the gas-
OF THIS DOCUMENT IS COVERED,
REVISION CERTIFICATION
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
insulated bus through a removable link and provide means to permit
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
field testing of the cable.
Effective and long life gas-tight seals shall be provided between the
CERT
to dissipate the energy under normal conditions and also that generated
in case one of the circuit breaker poles fails to close and the circuit is
DISCIPLINE
ENGINEER then opened by the poles discrepancy protection after a time delay.
_______________
DATE _________
SF6 surge arresters must be of either plug-in construction or the
disconnecting-link type to provide disconnecting means for system
PROJECT
ENGINEER
dielectric tests.
_______________
DATE _________
The surge arrestor ground connection must be insulated from the
enclosure in order to permit monitoring of the leakage current. The
CERTIFIED ground connection shall be sized for the fault level of the GIS.
_______________
The surge arresters shall be fitted with non-resettable surge counter
DATE _________
having five digit cyclometer dial capable of registering up to 5
CONSTRUCTION discharges per second, leakage current monitor having a scale range of
AGENCY
_______________ 0-50mA Peak/1.414 (nonlinear scale) and bypass shunt to establish
DATE _________ continuity to ground from the surge arrester ground terminal.
OPERATIONS 2.21 Painting
_______________
The GIS switchgear shall be painted in accordance with the IEEE
DATE _________
C57.12.28. Bidder shall provide details of metal fabrication and painting.
The paint colour shall be light gray number 61 in accordance with
EDSD VERIFICATION
------------------------------
CONTROL NUMBER
DATE: __________
BY: ____________
special tools and lifting bars/ equipment for maintenance and erection.
FOR ALL APPROVAL / CERTIFICATION
OF THIS DOCUMENT IS COVERED,
REVISION CERTIFICATION
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
If so required in Purchase Order or mentioned in data sheet, the
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
following shall be provided:
A mobile SF6 gas treatment plant which shall be suitable for draining,
CERT
SF6 gas maintenance cart fitted with a cylinder of SF6 gas, and
pressure gauge and all necessary valves, hoses, adaptors, and
couplings for re-filling the switchgear. Storage capacity of cylinder of
SF6 gas shall compensate the % leakage for the service life of GIS. A
pressure relief valve shall be fitted to filling pipe or enclosure to prevent
JO/EWO
the gas pressure from rising to more than 10% above the design
pressure during filling. After operation of a pressure relief valve, it shall
reclose before the pressure has fallen to 75% of the design pressure.
DATE
The SF6 gas maintenance cart shall be easily moved by hand, and
shall be provided with enclosed storage facilities for neat storage of
REV NO.
_______________
The Manufacturer shall provide with his bid a list of spare parts required
for installation and commissioning of the switchgear, and a list of spare
DATE _________
parts required for two (2) years of operation.
CONSTRUCTION
AGENCY
_______________
_______________
3.1 Type Tests
DATE _________ The switchgear and its components shall have been type tested in
accordance with IEC 62271 or ANSI/IEEE C37. All type tests shall be
EDSD VERIFICATION
------------------------------
CONTROL NUMBER
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
Manufacturer shall provide type test certificates or factory test reports
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
for type tests performed on switchgear
- Dielectric Tests
CERT
------------------------------
minimum.
CONTROL NUMBER
DATE: __________
BY: ____________
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
- CT secondary resistance
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
- Excitation Characteristics
CERT
per IEEE:
- Determination of knee point voltage (Vk) for class ‘C’ or ‘K’ CTs
manufactured per IEEE C57.13
DESCRIPTION
order.
Inspection shall be made to verify:
REV NO.
------------------------------
CONTROL NUMBER
DATE: __________
BY: ____________
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________
OPRNS
3.2.3 Routine Tests
THIS DOCUMENT AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN WHOLE OR PART SHALL BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF THE OWNER.
PMT
The routine testing of all the switchgear and control panels shall include,
but not limited to the following:
CERT
- Dielectric tests
- Power frequency voltage withstand on auxiliary equipment
ENG’G
DATE _________
OPERATIONS
_______________
DATE _________
EDSD VERIFICATION
------------------------------
CONTROL NUMBER
DATE: __________
BY: ____________
THIS INDICATES THAT REV. NO. ______
REQUIREMENTS, BY DOCUMENT
COMPLETION CERTIFICATE
(DCC) NO. ___________