You are on page 1of 8

PROJECT

AZITO PHASE IV PROJECT


COMBINED CYCLE POWER PLANT EXPANSION PROJECT
(CÔTE D’IVOIRE)

ANNEX

ESSAIS DES CELLULES MV

DOCUMENT NUMBER

AZ-0014-PRO-AEE-0004

REVISION 00
DOCUMENT ISSUED FOR: REVIEW
DATE 11/03/2021

VLT-AEE POWER YEB-AEE POWER JIV-AEE POWER

Issued by: Revised by: Approved by:

THIS DOCUMENT CONTAINS PROPRIETARY INFORMATION AND CAN NOT BE DUPLICATED, MODIFIED OR DISCLOSED TO
THIRD PARTIES FOR ANY USE OTHER THAN THIS PROJECT AND THE PURPOSE FOR WHICH IT IS INTENDED FOR, WITHOUT
THE WRITTEN CONSENT OF COBRA.
Document No.:
EGARC-EPMV
Document Title: Reference Documents:
Medium Voltage Primary Switchgear Site Test Procedure IEC: 62271-200
IEC: 62271-1
Issued By: Date of release: Language: Page:
Mohamed Ghonim 2016 – 02 – 01 En 1/7
Issuing Department: Revision index: Document Kind:
EPMV Service Operations 1 Manual

PURPOSE

This procedure describes the works to be executed at site including the Site
Acceptance Test to verify that the installed equipment is in accordance to the
requirement of the contract.

PRE-REQUISITES FOR EXECUTION OF WORKS


The site works for the Compact secondary substation shall start after the
following pre-requisites.

a. Equipment is delivered to site.


b. Ensure drawings and SAT sheets are available.
c. Equipment is tested as per SAT for replacement/refurbishment works,
Operational checks and signal checks are only to be done for retrofit works after
completion of the retrofits under shutdown.
d. Shutdown taken and work permit received.
e. Necessary safety procedures are followed.
f. Check the cables are voltage free.
Document No.:
EGARC-EPMV
Document Title: Reference Documents:
Medium Voltage Primary Switchgear Site Test Procedure IEC: 62271-200
IEC: 62271-1
Issued By: Date of release: Language: Page:
Mohamed Ghonim 2016 – 02 – 01 En 2/7
Issuing Department: Revision index: Document Kind:
EPMV Service Operations 1 Manual

CONTENTS:

1- MECHANICAL OPERATION TEST.


(IEC 62271-200 clause 7.102)

2- TESTS ON AUXILIARY AND CONTROL CIRCUITS.


(IEC 62271-1 clause 7.2)

a) Functional tests. (IEC 62271-1 clause 7.2.2)

b) Dielectric tests. (IEC 62271-1 clause 7.2.4)

3- POWER FREQUENCY VOLTAGE WITHSTAND TEST ON THE MAIN CIRCUIT.


(IEC 62271-200 clause 7.1)

4- TEST OF THE MEASURING AND PROTECTION CIRCUITS.


Document No.:
EGARC-EPMV
Document Title: Reference Documents:
Medium Voltage Primary Switchgear Site Test Procedure IEC: 62271-200
IEC: 62271-1
Issued By: Date of release: Language: Page:
Mohamed Ghonim 2016 – 02 – 01 En 3/7
Issuing Department: Revision index: Document Kind:
EPMV Service Operations 1 Manual

1. MECHANICAL OPERATION TEST

(acc. to IEC 62271-200 clause 7.102)

Purpose
This test shall be carried out to ensure the correct mechanical operation of the Switchgear
and that all-mechanical interlock operates correctly.

Preliminary Conditions
- Switchgear completely assembled.
- Auxiliary circuit supplies available.

Procedure

1.1 Check the correct closing of doors.

1.2 Check that the shutters are automatically and fully closed when the circuit
breaker/vacuum contactors is withdrawn out from the switchgear panel.

1.3 Check the impossibility of either inserting or isolating the circuit breaker when closed.

1.4 Check that the mechanical interlock prevents the circuit breaker contacts closing if the
truck is positioned between service and test position.

1.5 Check that the circuit breaker cannot be inserted into service position when the earthing
switch is closed.

1.6 Check that the earthing switch cannot be closed when the circuit breaker is in service
position

1.7 Check the signaling of the mechanical indicators.

1.8 Check that the circuit breaker cannot be inserted into service position when the
secondary contacts plug has not been fitted.

1.9 Check the impossibility disconnects the secondary contacts plug of the circuit breaker
when the circuit breaker is in service position.

1.10 Check the functionality of the key interlocks, if provided and the difference in code

1.11 Check the signaling of the mechanical indicators


Document No.:
EGARC-EPMV
Document Title: Reference Documents:
Medium Voltage Primary Switchgear Site Test Procedure IEC: 62271-200
IEC: 62271-1
Issued By: Date of release: Language: Page:
Mohamed Ghonim 2016 – 02 – 01 En 4/7
Issuing Department: Revision index: Document Kind:
EPMV Service Operations 1 Manual

2 TESTS ON AUXILIARY AND CONTROL CIRCUITS


(acc. to IEC 62271-1 clause 7.2.)

2.a FUNCTIONAL TEST


(acc. to IEC 62271-1 clause 7.2.2)
Purpose
This Procedure defines the correct functioning of the control circuit breakers and the
auxiliary devices and relays of the Switchgear, the tests for the protection relays.

Preliminary Conditions
- Switchgear completely assembled.
- Interconnection between panels finished.
- Auxiliary circuit supplies available.

Test Instrument List

Relay tester,
Digital multi meter
Auxiliary power supplies

Procedure

2a.1 Check the correct wiring interconnection according to the drawing.

2a.2 Check the correct function of the circuits to be connected to the D.C.S.
(if provided)

2a.3 Check the functionality of the circuit breaker limit switches (test / service)

2a.4 Check the functionality of the circuit breaker aux. contacts (open / closed).

2a.5 Check the functionality of the earthing switch aux. contacts (open / closed)

2a.6 Following the SWGR functional schemes and the protection relays,
verify the panels and switchgear functionality. Checking:
Electrical interlocks, electrical sequences, functional and control indicators.
Document No.:
EGARC-EPMV
Document Title: Reference Documents:
Medium Voltage Primary Switchgear Site Test Procedure IEC: 62271-200
IEC: 62271-1
Issued By: Date of release: Language: Page:
Mohamed Ghonim 2016 – 02 – 01 En 5/7
Issuing Department: Revision index: Document Kind:
EPMV Service Operations 1 Manual

2.b DIELECTRIC TEST ON CONTROL AND AUXILIARY CIRCUITS


(acc. to IEC 62271-1 clause 7.2.4)

Test Instrument List


High Voltage Test Kit 5 KV AC

Procedure
Carry out the power frequency voltage withstand test of auxiliary and control circuits applying
a voltage of AC 1kV / 1Sec between auxiliary and control circuit connected together as a whole
and the frame of the switchgear.

Acceptance Criteria

The test shall be considered as positive if neither flashover, nor puncture will occur.
Document No.:
EGARC-EPMV
Document Title: Reference Documents:
Medium Voltage Primary Switchgear Site Test Procedure IEC: 62271-200
IEC: 62271-1
Issued By: Date of release: Language: Page:
Mohamed Ghonim 2016 – 02 – 01 En 6/7
Issuing Department: Revision index: Document Kind:
EPMV Service Operations 1 Manual

3. POWER FREQUENCY VOLTAGE WITHSTAND TEST ON THE MAIN CIRCUIT


(acc. to IEC 62271-200clause 7.1)

Purpose
Dielectric test is performed to verify if the insulation of live parts is satisfactory and to
permit the Switchgear to be energized.

Preliminary conditions
- Equipment installed and connected.
- Switchgear is cleaned of dust, dirt, moisture, etc.
- Temporary disconnection of electronic devices.
- Voltage transformer fuses drawn out.

Test Instrument List

1- 60 KV / 100 KV , Voltage Test Kit.

Procedure

Carry out the main circuits power frequency voltage withstand test among each phase in
succession and the earthed one. The circuit breakers / LBS are closed.

Kv, AC per 60sec for each phase in succession

The test voltage will be as follows:

20 KV, AC per 60 sec. for rated insulation voltage 7.2 Kv.

28KV, AC per 60 sec. for rated insulation voltage 12 Kv.

38KV, AC per 60 sec. for rated insulation voltage 17.5 Kv.

50KV, AC per 60 sec. for rated insulation voltage 24 Kv.

70KV, AC per 60 sec. for rated insulation voltage 36 Kv.

For Second time the value should be 80%

Acceptance Criteria

The test is considered as successful if neither flashovers nor perforations occur during each
test
Document No.:
EGARC-EPMV
Document Title: Reference Documents:
Medium Voltage Primary Switchgear Site Test Procedure IEC: 62271-200
IEC: 62271-1
Issued By: Date of release: Language: Page:
Mohamed Ghonim 2016 – 02 – 01 En 7/7
Issuing Department: Revision index: Document Kind:
EPMV Service Operations 1 Manual

4. TEST OF THE MEASURING AND PROTECTION CIRCUITS

Test Instrument List

Primary Injection Current & Primary Injection Voltage

Current Circuits
Procedure
4.1 According to CTs ratio inject to primary side a suitable one / three phases current
and verify the correct ammeter reading, current transducers function etc.
According to Specifications of current protection functions carry out the
secondary injection to the protection relays to verify the correct operation of
protection circuits.

Voltage Circuits
Procedure
4.2 According to voltage transformers' ratio apply on primary side of transformers a
suitable voltage and verify correct voltmeter reading, voltage transducers
function etc.
According to Specifications of voltage protection functions carry out the
secondary injection to the protection relays to verify the correct operation of
protection circuits.