Professional Documents
Culture Documents
4-WQ1-239 - Idc144-8-12-2021
4-WQ1-239 - Idc144-8-12-2021
Depth MD (m) TVD (m) Bit current previous BHA Amount ID (in) OD (in) Length (m) Total (m)
00:00 hrs
18:00 hrs
24:00 hrs
Meterage
Lithology Top(m) Bottom(m)
Casing Diameter (in) Depth (m) Date F.C (m) D.V (m) AngleAzimuth Closure (m) Severity (deg/30m)
Conductor 20 49.5
Surface 13 3/8" 794
Intermediate 9 5/8 2094
Production 7 2526
Mud Type FWB FCL Density In : gm/cc Density Out: gm/cc Temp. In : degC Formation Tests Material tons Stock
Sand : % ECD : g/cm3 Ca= Temp. Out: degC EMW Test g/cm3 Camp fuel(L)
Gel 0: kPa Gel 0: Gel 10: kPa API Cake: PP EMW g/cm3
600 / 300 = API Vol. Cm3 AV = Choride: mg/L FP EMW g/cm3
Viscosity = PV= YP = Water: Test Date Rig Fuel 13.7 M³
pH = Fil : Sand : % Solids% : 3
Weight on Bit = ton TOTAL FLOW RATE (L/Min) PUMP NO.1 PUMP NO.2 Achievement ratio for Programed: 70%
R.P.M = Efficiency (%) 90 workover: Not programed: 0%
Stand pipe Pressure= psi Liner Size ( in ) 6 Well Kill Drill Date: 20-05-2021 Time: 17:00
Torque: AMP St. Length ( in ) 7 Koomey - Shenkai Manifold: 1500 PSI Accumulator :3000 psi Annular :1300 psi
Liter / Stroke 8.75 Rental Crane 30 Lateef
Wt. of string= ton
ton 24 HRS 2 Driver
S.P.M Ali
Days Without LTI : 436 days FLOW RATE (L/Min) Rental Fork lift 10 Alaa
ton 12 HRS 1 Driver
TOTAL FLOW RATE (L/Min) 0.00
Summary Previous Day POOH & L/D 5 7/8" BIT WITH 7" SCRAPER BHA AND 2 7/8" DP SINGLE BY SINGLE TO SURFACE & WL JOB SET BP AT DEPTH 2420 M &
DUMP 3 M3 OF CEMENT ABOVE BRIDGE PLUG .
Held PJSM,TBT with Baker Hughues crew, WQ-FOD CM & rig crew to discussed RIH ESP completion string and
08:30-09:00 0.5
review WC procedure while RIH ESP.
09:00-09:30 0.5
19:00-23:00 4 22.1
23:00-24:00 1 22.1
*KEEP FILLING UP THE WELL WITH 5 M3 OF INDUSTERIAL WATER EACH 1 HR ,WITHOUT RETURN .
M , POOH TO SURFACE .
DISCONNECTED WIRE LINE EQUIPMENT :- N/D HAL. FLANGE
02:30-04:00 1.5 22.1 13 5/8" * 5K FROM THE TOP OF ANNULAR PREVENTER AND Safety Coord. Karrar
WSS Muslim/Mohammed
Receiv
Item Accumulate M3
ed
Jar hrs industrial water in tank brine High Vis. R.O water 10 80
Day Summary WAITING ON CEMENT TO BE HARDEN & CHANGE PIPE RAM FROM 2 7/8" TO 3 1/2" & M/U 5 3/4" GAUGE CUTTER , JUNK BASKET , GR/CCL .
Forecast WOC & TAG THE TOP OF CEMENT THEN RIH ESP WITH 3 1/2" TBG
Comments: SEND 253 JTS 4" TBG , 13 JTS 4 1/2" TBG TO THE SEISMIC YARD .
Needed WE NEED FOR 1 TRUCK TO COLLECT THE NEW SPOOLER OF DRILLIN LINE .
TOOL PUSHER : Sattar Chasib SITE ENGINEER : Atheer F. Hameed NIGHT PUSER : Hashim Ihsan CHIEF EL: Maithem Salah CHIEF Mech.: Basim Salim
IRAQI DRILLING COMPANY DAILY REPORT
INTEGRATED MANGEMENT SYSTEM (IDCP08F4)
Daily Operation Report Date: 17/ 05 / 2021 Project : Exxon Mobil Location area : WQ1 - 053 ROW : 82 Country : Iraq
Rig:IDC-144 Well No.: WQ1 - 053 Conductor : 20 ' RT - GL: 5.8M Activity: work over Spud Date: XX/XX/XXXX@ XX:XX am
Obj: Isolate mB2 Planned Depth: 2259.58 M Planned Days: 14 Days GL Elev: 0.8M P.O.B: 51 Report No: 3 R/M.
Well Type : Oil Producer Start Of Moving Date :15 / 05 /2021 End Of Moving Date : 17 /05 /2021 Days Of Acc : 1
Lenght
Depth MD (m) TVD (m) Bit current previous ID (in) OD (in) Total (m)
(m)
BHA Amount
Lenght
00:00 hrs ID (in) OD (in) Total (m)
(m)
18:00 hrs
24:00 hrs
Meterage
Lithology Top(m) Bottom(m)
K.D
24 PM Situation
WORKING ON COMPLET THE CHECKLIST ITEMS
…… IN PROGRESS
Tagged at 0.00
06 AM Situation
WAITING ON REPAIR THE RELIEF VALVE & T.D 0.00
PROVIDE 4" RAMS
Casing Diameter (in) Depth (m) Date F.C (m) D.V (m) Angle Azimuth Closure (m) Severity (deg/30m)
7" 2807
Mud Type FWB FCL Density In : gm/cc Density Out: gm/cc Temp. In : degC Formation Tests Material tons Stock
Sand : % ECD : g/cm3 Ca= Temp. Out: degC EMW Test g/cm3 Camp fuel(L)
Gel 0: kPa Gel 0: Gel 10: kPa API Cake: PP EMW g/cm3
600 / 300 = API Vol. Cm3 AV = Choride: mg/L FP EMW g/cm3
Viscosity = PV= YP = Water: Test Date
Rig Fuel 27.5 M³
pH = Fil : Sand : % Solids% : 3
Weight on Bit = ton
TOTAL FLOW RATE (L/Min) PUMP NO.1 PUMP NO.2 Programed: 0%
Achievement ratio for workover:
R.P.M = Efficiency (%) Not programed: 0%
Stand pipe Pressure= psi Liner Size ( in ) Well Kill Drill Date: Time:
Torque: AMP St. Length ( in ) Koomey - Manifold: Accumulator Annular
Liter / Stroke
Wt. of string= ton
S.P.M
Rental Crane 30 ton 0 HRS 0 Driver
Days Without LTI: FLOW RATE (L/Min)
TOTAL FLOW RATE (L/Min) 0.00
Rental Fork lift 10 ton 0 HRS 0 Driver
06:00-24:00 18 HPJSM WITH RIG CREW AND TRANSPORTER CREW, DISCUSSED THE MAIN HAZARDS OF R/U OPERATIONS.
INSTALLED THE LINE OF THE WASTE TANK AND CONNECTED IT TO THE CHOCK MANIFOLD.
CONNECTED THE LOWER PART OF THE RIG FLOOR WITH THE UPPER PART AND TIGHT ALL BOLTS & RAISE
THE FLOOR.
RAISE THE LOWER AND UPPER SECTION OF RIG MAST THE CONNECTED THE TURNBUCKLE OF IT .
R/U THE LADDERS OF RIG FLOOR , FENCE OF THE FLOOR ,V-DOOR AND PIPE RACK .
R/U THE DRILLER STORE AND INSTALLED ALL THE STAIRS OF THE RIG FLOOR.
INSTALLED THE ACCUMULATOR AND CONNECTED IT HOSES WITH THE PANELS.
R/U 100 % PREPARING FOR RIG ACCEPTANCE
N/U 13 5/8" BOPS ON THE TEST STAMP , FILLING UP THE BOP WITH WATER THEN P/T 13 5/8" BLIND RAM BY
TEST UNIT WITH (500/2500) PSI FOR (5/10) MIN. … OK
WORKING ON COMPLET THE CHECKLIST ITEMS …… IN PROGRESS.
00:00-06:00 6 CONNECTED THE SECOND CATLINE WITH THE MANUAL TONGS …. OKAY. Mud Engineer Galib Salman
CONNECTED THE SURFACE LINES WITH THE CHOCK MANIFOLD & P/T
THE SURFACE LINES, CHOCK MANIFOLD & NRV WITH LOW & HIGH Safety Coord. Assad/Karrar
PRESSURE 500/3000 PSI FOR 5/10 MINUTES BY OUR CREW …. OKAY.
CHECKED THE POP-OFF (RELIEF VALVE) OF THE MAIN PUMP …. OKAY. Medic Ali
CHECKED THE POP-OFF (RELIEF VALVE) OF THE SECOND PUMP …. FAILED WSS Khalid/Ayad
(NEED MAINTENANCE)
WAITING:- WAITING TO PROVIDE 4" RAMS FOR THE 13 5/8" BOP & REPAIR THE
RELIEF VALVE.
industrial water in
Jar hrs brine High Vis. R.O water 10 10
tank
0 80 0 0 industrial water 80 80
TOTAL HRS 6 gas oil
Forecast COMPLETE THE CHECKLIST ITEMS, REVIEW IT & ACCEPT THE RIG.
Comments: IT TEAM CONNECTED THE INTERNET NETWORK SYSTEM & SERVICE TEAM CONNECTED THE PIPES OF WATER .
Supplies
Needed PROVIDE 4" RAMS FOR THE 13 5/8" BOP & REPAIR THE POP-OFF VALVE OF THE SECOND PUMP.
TOOL PUSHER : Ali Hussien Jolehim SITE ENGINEER : Ibrahim S.Hanon NIGHT PUSER : Raqeb asem CHIEF EL: Thafer Rasheed CHIEF Mech.: Basim Salim
IRAQI DRILLING COMPANY DAILY REPORT
INTEGRATED MANGEMENT SYSTEM (IDCP08F4)
Daily Operation Report Date: 18/ 05 / 2021 Project : Exxon Mobil Location area : WQ1 - 053 ROW : 82 Country : Iraq
Rig:IDC-144 Well No.: WQ1 - 053 Conductor : 20 ' RT - GL: 5.8M Activity: work over Spud Date: XX/XX/XXXX@ XX:XX am
Obj: Isolate mB2 Planned Depth: 2259.58 M Planned Days: 14 Days GL Elev: 0.8M P.O.B: 49 Report No: 4 R/M.
Well Type : Oil Producer Start Of Moving Date :15 / 05 /2021 End Of Moving Date : 17 /05 /2021 Days Of Acc : 1
Lenght
Depth MD (m) TVD (m) Bit current previous ID (in) OD (in) Total (m)
(m)
BHA Amount
Lenght
00:00 hrs ID (in) OD (in) Total (m)
(m)
18:00 hrs
24:00 hrs
Meterage
Lithology Top(m) Bottom(m)
K.D
24 PM Situation
PREPARATIONS TO P/T THE BLIND RAM OF 11"
BOP STACK.
Tagged at 0.00
Casing Diameter (in) Depth (m) Date F.C (m) D.V (m) Angle Azimuth Closure (m) Severity (deg/30m)
7" 2807
Mud Type FWB FCL Density In : gm/cc Density Out: gm/cc Temp. In : degC Formation Tests Material tons Stock
Sand : % ECD : g/cm3 Ca= Temp. Out: degC EMW Test g/cm3 Camp fuel(L)
Gel 0: kPa Gel 0: Gel 10: kPa API Cake: PP EMW g/cm3
600 / 300 = API Vol. Cm3 AV = Choride: mg/L FP EMW g/cm3
Viscosity = PV= YP = Water: Test Date
Rig Fuel 27 M³
pH = Fil : Sand : % Solids% : 3
Weight on Bit = ton
TOTAL FLOW RATE (L/Min) PUMP NO.1 PUMP NO.2 Programed: 0%
Achievement ratio for workover:
R.P.M = Efficiency (%) Not programed: 0%
Stand pipe Pressure= psi Liner Size ( in ) Well Kill Drill Date: Time:
Torque: AMP St. Length ( in ) Koomey - Manifold: Accumulator Annular
Liter / Stroke Latif
Wt. of string= ton Rental Crane 30 ton 24 HRS 2 Driver
S.P.M Ali
Days Without LTI: FLOW RATE (L/Min) Alaa Saad
Rental Fork lift 10 ton 12 HRS 1 Driver
TOTAL FLOW RATE (L/Min) 0.00
CONNECTED THE SURFACE LINES WITH THE CHOCK MANIFOLD & P/T THE SURFACE LINES, CHOCK
MANIFOLD & NRV WITH LOW & HIGH PRESSURE 500/3000 PSI FOR 5/10 MINUTES BY OUR CREW …. OKAY.
CHECKED THE POP-OFF (RELIEF VALVE) OF THE MAIN PUMP …. OKAY.
CHECKED THE POP-OFF (RELIEF VALVE) OF THE SECOND PUMP …. FAILED (NEED MAINTENANCE).
CHECKED THE RPM & SPM BY OUR CREW …. OKAY, WAITING ON PROVIDE THE 4" PIPE RAM & POP-OFF
VALVE.
FOUND THAT THE RIG CENTRALIZE NOT IN SHAPE, DECIDED TO R/D THE MAST & SHIFTING THE BASE OF
06:00-18:00 12
FLOOR, WAITING ON CRANE DURING THAT :
DISCONNECTED THE TURNBUCKLES, L/D THE LADDERS OF FLOOR, DRILLER STORE, LOWER THE FLOOR &
L/D THE RIG MAST.
REMOVED THE RIG CARRIER, CARRIER RAMP & COMPLETED WORKING ON SHIFTING THE FLOOR BASE
(CRANE ARRIVED AT 11:00 AM).
RE-INSTALLED THE CARRIER RAMP & RIG CARRIER, R/U THE MAST, INSTALLED THE LADDERS OF FLOOR &
DRILLER STORE.
INSTALLED THE LINES OF MUD PUMPS AND SURFACE LINES WITH THE CHOCK MANIFOLD & P/T IT …. OKAY.
N/U 11" BOPS ON THE TEST STAMP , FILLING UP THE BOP WITH WATER THEN & CONNECTED THE
HYDRAULIC HOSES.
WELDING & PREPARE THE V-DOOR.
CENTRALIZE THE RIG MAST, CONNECTED THE MANUAL TONG & INSATALLED THE PIPE RACK.
23:30-24:00 0.5 TEST UNIT ARRIVED TO LOCATION & PREPARATION TO P/T THE BLIND RAM.
P/T THE BLIND RAM FOR 11" BOP WITH LOW & HIGH PRESSURE 500/3500
00:00-06:00 6 Mud Engineer Galib Salman
PSI FOR 5/10 MINUTES …. OKAY.
REVIEW THE CHECKLIST WITH FOD REPRESENTATIVE AS FOLLOWING: Safety Coord. Assad/Karrar
CHECKED THE SPM, RPM, SAFETY CROWN O-MATIC ….. OK. Medic Ali
P/T THE CHOCK MANIFOLD, KILL MANIFOLD WITH 500/3500 PSI FOR 5/10 WSS Khalid/Saeed
MINUTES …… OKAY.
P/T THE POP-OFF VALVE WITH 2500 PSI FOR THE MUD PUMP ….. OKAY
industrial water in
Jar hrs brine High Vis. R.O water 10
tank
0 80 0 0 industrial water 80
TOTAL HRS 6 gas oil
R/D THE MAST, SHIFTING THE BASE OF FLOOR TO CENTRALIZE IT IN A SUTIABLE SHAPE, R/U THE MAST & WORKING ON COMPLETE R/U OPERATION….. IN
Day Summary :
PROGRESS.
Comments:
Supplies
Needed NEED THE SERVICE TEAM TO DO MAINTENANCE FOR THE PIPES OF WATER BELONG TO FOD CARAVANS.
TOOL PUSHER : Ali Hussien Jolehim SITE ENGINEER : Ibrahim S.Hanon NIGHT PUSER : Raqeb asem CHIEF EL: Thafer Rasheed CHIEF Mech.: Basim Salim
IRAQI DRILLING COMPANY DAILY REPORT
INTEGRATED MANGEMENT SYSTEM (IDCP08F4)
Daily Operation Report Date: 19/ 05 / 2021 Project : Exxon Mobil Location area : WQ1 - 053 ROW : 82 Country : Iraq
Rig:IDC-144 Well No.: WQ1 - 053 Conductor : 20 ' RT - GL: 5.8M Activity: work over Spud Date: 19-05-2021@ 20:00
Obj: Isolate mB2 Planned Depth: 2259.58 M Planned Days: 20 Days GL Elev: 0.8M P.O.B: 49 Report No: 4 R/M + 1 OPS.
Well Type : Oil Producer Start Of Moving Date :15 / 05 /2021 End Of Moving Date : 17 /05 /2021 Days Of Acc : 1
Lenght
Depth MD (m) TVD (m) Bit current previous ID (in) OD (in) Total (m)
(m)
BHA Amount
Lenght
00:00 hrs ID (in) OD (in) Total (m)
(m)
18:00 hrs
24:00 hrs
Meterage
Lithology Top(m) Bottom(m)
K.D
24 PM Situation OPEN THE WELL TO WAST TANK FLOW OIL & GAS Tagged at 0.00
Casing Diameter (in) Depth (m) Date F.C (m) D.V (m) Angle Azimuth Closure (m) Severity (deg/30m)
7" 2807
Mud Type FWB FCL Density In : gm/cc Density Out: gm/cc Temp. In : degC Formation Tests Material tons Stock
Sand : % ECD : g/cm3 Ca= Temp. Out: degC EMW Test g/cm3 Camp fuel(L)
Gel 0: kPa Gel 0: Gel 10: kPa API Cake: PP EMW g/cm3
600 / 300 = API Vol. Cm3 AV = Choride: mg/L FP EMW g/cm3
Viscosity = PV= YP = Water: Test Date
Rig Fuel 26 M³
pH = Fil : Sand : % Solids% : 3
Weight on Bit = ton
TOTAL FLOW RATE (L/Min) PUMP NO.1 PUMP NO.2 Programed: 2%
Achievement ratio for workover:
R.P.M = Efficiency (%) Not programed: 0%
Stand pipe Pressure= psi Liner Size ( in ) Well Kill Drill Date: Time:
Torque: AMP St. Length ( in ) Koomey - Manifold: Accumulator Annular
Liter / Stroke Latif
Wt. of string= ton Rental Crane 30 ton 24 HRS 2 Driver
S.P.M Ali
Days Without LTI: FLOW RATE (L/Min)
TOTAL FLOW RATE (L/Min) 0.00
Rental Fork lift 10 ton 0 HRS 0 Driver
SUCTION HOSE OF THE MUD PUMP #2 HAVE LEAK FROM THE BODY.
TORQUE GAUGE & MUD PUMP PRESSURE GAUGE DIDN'T WORK.
THE HOSE BELONG TO HOISTING LINE (CUTLINE) NEED TO CHANGE.
FIXED THE NRV FOUND THAT THE INSIDE SPRING BROKEN CHANGED IT WITH NEW ONE & TEST IT WITH
06:00-10:00 4.0
FOD SUPERVISOR…… TEST OKAY.
CLOSED THE ITEM OF ESCAPE LINE, CHANGED THE HOSE OF HOISTING LINE & FIXED THE TORQUE GAUGE
PROBLEM.
10:00-15:00 5.0 WAITING TO SUPPLY US WITH ( POP-OFF VALVE, PP GAUGE (TYPE CAMERON) + SUCTION HOSE).
(PP GAUGE, POP-OFF VALVE & SUCTION HOSE) ARRIVED TO LOCATION, CONNECTED PP GAUGE & SUCTION
15:00-20:00 5.0
HOSE & CHECK IT…… OKAY.
KILL THE WELL :- KILLED THE WELL BY BULLHEAD FROM TUBING 10M3
00:00-02:00 2 22.1 Mud Engineer Galib Salman
INDUSTRIAL WATER , 3M3 HI - VIS ,15 M3 INDUSTRIAL WATER
WOWH:- N/D 4 1/16 3K X-MASS -TREE WITH 7 1/16" 3K THA HARD TO OPEN NUTS
5:00 - 6 :00 1 22.1 WSS Khalid/Saeed
IN PROGRESS
industrial water in
Jar hrs brine High Vis. R.O water 10
tank
0 80 0 0 industrial water 80
TOTAL HRS 6 gas oil
WORKING ON RIG ACCEPTANCE & Rig WAS ACCEPTED AT 20:00 IN 19-May-2021 & SAFETY MEETING & CONNECTED SURFACE LINE & READ PRESSURE AND TEST
Day Summary :
PACKER SEAL .
Comments:
Supplies
Needed NEED THE SERVICE TEAM TO DO MAINTENANCE FOR THE PIPES OF WATER BELONG TO FOD CARAVANS.
TOOL PUSHER : Ali Hussien Jolehim SITE ENGINEER : Ipraheem Sabah NIGHT PUSER : Raqeb asem CHIEF EL: Thafer Rasheed CHIEF Mech.: Basim Salim
IRAQI DRILLING COMPANY DAILY REPORT
INTEGRATED MANGEMENT SYSTEM (IDCP08F4)
Daily Operation Report Date: 20/ 05 / 2021 Project : Exxon Mobil Location area : WQ1 - 053 ROW : 82 Country : Iraq
Rig:IDC-144 Well No.: WQ1 - 053 Conductor : 20 ' RT - GL: 5.8M Activity: work over Spud Date: 19-05-2021@ 20:00
Obj: Isolate mB2 Planned Depth: 2259.58 M Planned Days: 20 Days GL Elev: 0.8M P.O.B: 50 Report No: 4 R/M + 2 OPS.
Well Type : Oil Producer Start Of Moving Date :15 / 05 /2021 End Of Moving Date : 17 /05 /2021 Days Of Acc : 1
Lenght
Depth MD (m) TVD (m) Bit current previous ID (in) OD (in) Total (m)
(m)
BHA Amount
Lenght
00:00 hrs ID (in) OD (in) Total (m)
(m)
18:00 hrs
24:00 hrs
Meterage
Lithology Top(m) Bottom(m)
K.D
Casing Diameter (in) Depth (m) Date F.C (m) D.V (m) Angle Azimuth Closure (m) Severity (deg/30m)
7" 2807
Mud Type FWB FCL Density In : gm/cc Density Out: gm/cc Temp. In : degC Formation Tests Material tons Stock
Sand : % ECD : g/cm3 Ca= Temp. Out: degC EMW Test g/cm3 Camp fuel(L)
Gel 0: kPa Gel 0: Gel 10: kPa API Cake: PP EMW g/cm3
600 / 300 = API Vol. Cm3 AV = Choride: mg/L FP EMW g/cm3
Viscosity = PV= YP = Water: Test Date
Rig Fuel 25 M³
pH = Fil : Sand : % Solids% : 3
Weight on Bit = ton
TOTAL FLOW RATE (L/Min) PUMP NO.1 PUMP NO.2 Programed: 10%
Achievement ratio for workover:
R.P.M = Efficiency (%) Not programed: 0%
Stand pipe Pressure= psi Liner Size ( in ) Well Kill Drill Date: Time:
Torque: AMP St. Length ( in ) Koomey - Manifold: Accumulator Annular
Liter / Stroke Latif
Wt. of string= ton
S.P.M
Rental Crane 30 ton 24 HRS 2 Driver
Ali
Days Without LTI: FLOW RATE (L/Min) Alaa
TOTAL FLOW RATE (L/Min) 0.00
Rental Fork lift 10 ton 12 HRS 0 Driver
02:00-04:00 2 22.1 WELL MONITOR:- MONITOR WELL FOR FLOW CHECK ,NO RETURNS .
04:00- 05:00 1 22.1 INSTALL BPV :- REMOVED 4 1/16 , 3K TOP FLANGE THEN INSTALLED 4" BPV INTO T- HANGER
05:00-11:00 6 22.1 WOWH:- N/D 4 1/16 3K X-MASS -TREE WITH 7 1/16" 3K THA . OBSERVED THE STUDS AND NUTS WERE STUCK .
WOWH & KILL THE WELL:- N/U 11"*5K BOP (PIPE & BLIND RAM ) VERY CARFULLY , CLOSED BLIND RAM AND
13:00-17:00 4 22.1 BULHEADING THE WEEL BY 2 M3 HI-VIS CHASED BY 15 M3 OF INDUSTRIAL WATER , CHECK THE BPV THE
WELL WAS DEAD .
WOWH:- N/U 13 5/8" ANNULAR PRVENTER WITH DSA (11"*5K- 13 5/8" * 5K ) AND CONNECTED THE HYDRAULIC
17:00-23:00 6 22.1
HOSES .
P/T BOP :- P/U 4" TBG LANDING JOINT AND CONNECTED IT WITH TBG HANGER THEN WHEN TRIED TO TEST
23:00-24:00 1.0 22.1
ANNULUR PREVENTER AND PIPE RAM GOT HIGH DROP WITHOUT EXTERNAL LEAK .
P/T BOP :- CON. TRIED TO TEST ANNULUR PREVENTER AND PIPE RAM ,
GOT HIGH DROP WITHOUT EXTERNAL LEAK , APPLIED 1000 PSI PRESSURE
12:00-03:00 3 22.1 Mud Engineer Mohammed Gassan
IN ANNULUS AND TEST ANNULUR PREVENTER AND PIPE RAM WITH
(500/1000 ) PSI FOR (5/10) MIN. ….OK .
03:00-04:00 1 22.1 HOUSEKEEPING:- GENERAL HOUSEKEEPING FOR THE RIG FLOOR . Safety Coord. Idress/ Mohammed
P/U KELLY :-P/U , M/U 3 1/2" KELLY WITH XOS ( 2 7/8" IF - 3 1/2" N.V ) , XOS ( 3
04:00-06:00 2 22.1 1/2" N.V - 4" N.V ) AND CONNECTED ROTARY HOSE THEN CONNECTED IT Medic Ali
INTO TBG HANGER
WSS Mohammed/Saeed
industrial water in
Jar hrs brine High Vis. R.O water 20
tank
KILL THE WELL & WOWH N/D X-MASS TREE & N/U 11" BOP & P/U 4" TBG LANDING JOINT AND CONNECTED IT WITH TBG HANGER THEN WHEN TRIED TO TEST
Day Summary :
ANNULUR PREVENTER AND PIPE RAM GOT HIGH DROP WITHOUT EXTERNAL LEAK .
Comments:
Supplies
Needed
TOOL PUSHER : Ali Hussien Jolehim SITE ENGINEER : Atheer F. Hameed NIGHT PUSER : Raqeb asem CHIEF EL: Thafer Rasheed CHIEF Mech.: Basim Salim
IRAQI DRILLING COMPANY DAILY REPORT
INTEGRATED MANGEMENT SYSTEM (IDCP08F4)
Daily Operation Report Date: 21/ 05 / 2021 Project : Exxon Mobil Location area : WQ1 - 053 ROW : 82 Country : Iraq
Rig:IDC-144 Well No.: WQ1 - 053 Conductor : 20 ' RT - GL: 5.8M Activity: work over Spud Date: 19-05-2021@ 20:00
Obj: Isolate mB2 Planned Depth: 2259.58 M Planned Days: 20 Days GL Elev: 0.8M P.O.B: 50 Report No: 4 R/M + 3 OPS.
Well Type : Oil Producer Start Of Moving Date :15 / 05 /2021 End Of Moving Date : 17 /05 /2021 Days Of Acc : 1
Lenght
Depth MD (m) TVD (m) Bit current previous ID (in) OD (in) Total (m)
(m)
BHA Amount
Lenght
00:00 hrs ID (in) OD (in) Total (m)
(m)
18:00 hrs
24:00 hrs
Meterage
Lithology Top(m) Bottom(m)
K.D
06 AM Situation
POOH& L/D 4" N.V OLD COMPLETION STRING TO T.D 0.00
DEPTH 2259 M .
Casing Diameter (in) Depth (m) Date F.C (m) D.V (m) Angle Azimuth Closure (m) Severity (deg/30m)
7" 2807
Mud Type FWB FCL Density In : gm/cc Density Out: gm/cc Temp. In : degC Formation Tests Material tons Stock
Sand : % ECD : g/cm3 Ca= Temp. Out: degC EMW Test g/cm3 Camp fuel(L)
Gel 0: kPa Gel 0: Gel 10: kPa API Cake: PP EMW g/cm3
600 / 300 = API Vol. Cm3 AV = Choride: mg/L FP EMW g/cm3
Viscosity = PV= YP = Water: Test Date
Rig Fuel 24 M³
pH = Fil : Sand : % Solids% : 3
Weight on Bit = ton
TOTAL FLOW RATE (L/Min) PUMP NO.1 PUMP NO.2 Programed: 15%
Achievement ratio for workover:
R.P.M = Efficiency (%) Not programed: 0%
Stand pipe Pressure= psi Liner Size ( in ) Well Kill Drill Date: Time:
Torque: AMP St. Length ( in ) Koomey - Manifold: Accumulator Annular
Liter / Stroke Latif
Wt. of string= ton Rental Crane 30 ton 24 HRS 2 Driver
S.P.M Ali
Days Without LTI: FLOW RATE (L/Min)
TOTAL FLOW RATE (L/Min) 0.00
Rental Fork lift 10 ton 0 HRS 0 Driver
KILL THE WELL & WOWH N/D X-MASS TREE & N/U 11" BOP & P/U 4" TBG LANDING JOINT AND
Summary Previous Day CONNECTED IT WITH TBG HANGER THEN WHEN TRIED TO TEST ANNULUR PREVENTER AND PIPE
RAM GOT HIGH DROP WITHOUT EXTERNAL LEAK .
TIME H CODE Operations
P/T BOP :- CON. TRIED TO TEST ANNULUR PREVENTER AND PIPE RAM , GOT HIGH DROP WITHOUT EXTERNAL
12:00-03:00 3 22.1 LEAK , APPLIED 1000 PSI PRESSURE IN ANNULUS AND TEST ANNULUR PREVENTER AND PIPE RAM WITH
(500/1000 ) PSI FOR (5/10) MIN. ….OK .
03:00-04:00 1 22.1 HOUSEKEEPING:- GENERAL HOUSEKEEPING FOR THE RIG FLOOR .
P/U KELLY :-P/U , M/U 3 1/2" KELLY WITH XOS ( 2 7/8" IF - 3 1/2" N.V ) , XOS ( 3 1/2" N.V - 4" N.V ) AND CONNECTED
04:00-06:00 2 22.1
ROTARY HOSE THEN CONNECTED IT INTO TBG HANGER
TBG HANGER SCREWS :- BACK OUT LOCK DOWN SCREWS OF TBG HANGER AND ENSURED ALL WERE FULLY
06:00-07:00 1 22.1
OPEN .
RELEASE ANCHOR :- PULL OUT STRING WITH WEIGHT 33 TON ,APPLIED 2 TON OVERPULL ROTATED STRING
07:00-09:30 2.5 22.1 9 TURNS CLOCK WISE , ANCHOR GOT RELEASED , CLOSED ANNULUAR AND START PUMPIN 40 M3 OF
INDUSTERIAL WATER DOWN ANNULUS .
RE-LATCHE ANCHOR :- RE-LATCHE ANCHOR BACK TO PACKER , PUMPIN DOWN TBG 3 M3 HI-VIS AND 15 M3
09:30-10:30 1 22.1
OF INDUSTERIAL WATER .
L/D KELLY & P/U 3 1/2" LANDING JOINT :- L /D 3 1/2" KELLY WITH XOS ( 2 7/8" IF - 3 1/2" N.V ) , XOS ( 3 1/2" N.V -
10:30-12:00 1.5 22.1 4" N.V ) & P/U 3 1/2" TBG LANDING JOINT WITH XOS ( 3 1/2" N.V - 4" N.V ) AND CONNECTED IT INTO TBG
HANGER
12:00-12:30 0.5 22.1 SAFETY MEETING :-HPJSM HAL. SL CREW WITH RIG CREW
12:30-15:00 2.5 22.1 SLICK LINE OPERATION:- R/U HAL. SL EQUIPMENT AND P/T IT BY ( 500/1500 ) PSI for (5/15) MIN. …...OK.
SLICK LINE OPERATION :- RIH 2.75 " GAUGE CUTTER BY SL TO DEPTH (TAG F-NIPPLE @ 2329.5 M ) ,POOH TO
15:00-16:00 1.0 22.1
SURFACE .
SLICK LINE OPERATION :- RIH 2.75 " FWG PLUG BY SL TO DEPTH 2329.5 & SET IT AT F-NIPPLE ,POOH 10 M P/T
16:00-18:00 2.0 22.1
THE WELL AGAINST PLUG BY 500/1000 PSI FOR 5/10 MIN … OK THEN POOH SL TOOL TO SURFACE .
18:00-21:00 3.0 22.1 SLICK LINE OPERATION :- R/D HAL. SL EQUIPMENT .
L/D LANDING JOINT & P/U KELLY:- L /D 3 1/2" TBG LANDING JOINT WITH XOS ( 3 1/2" N.V - 4" N.V ) & P/U 3 1/2"
21:00-22:30 1.5 22.1
KELLY WITH XOS ( 2 7/8" IF - 3 1/2" N.V ) , XOS ( 3 1/2" N.V - 4" N.V ) AND CONNECTED IT INTO TBG HANGER
RELEASE ANCHOR & WELL CLEANING :- PULL OUT STRING WITH WEIGHT 33 TON ,APPLIED 2 TON OVERPULL
22:30-24:00 1.5 22.1 ROTATED STRING 3 TURNS CLOCK WISE , ANCHOR GOT RELEASED , CLOSED ANNULUAR AND START
NORMAL CIRCULATION WITH INDUSTERIAL WATER TO CLEAN THE WELL IN PROGRESS .
L/D KELLY :- L /D 3 1/2" KELLY WITH XOS ( 2 7/8" IF - 3 1/2" N.V ) , XOS ( 3 1/2"
04:00-05:00 1 22.1 Safety Coord. Idress/ Mohammed
N.V - 4" N.V ) .
POOH:-POOH& L/D 4" N.V OLD COMPLETION STRING FROM DEPTH 2307 M
05:00-06:00 1 22.1 Medic Ali
TO 2259 M .
WSS Mohammed/Saeed
industrial water in
Jar hrs brine High Vis. R.O water 10 30
tank
P/T BOP & RELEASE ANCHOR & PUMPIN 40 M3 OF IND. WATER DOWN ANNULUS , 3M HI-VIS WITH 15 M3 IND. WTER DOWN TBG & RE-LATCHE ANCHOR & HPJSM
Day Summary : HAL. SL & SLICK LINE OPERATION ( RIH 2.75" GC TO DEPTH 2329.5 M & RIH 2.75" FWG PLUG AND SET IT AT DEPTH 2329.5 M ) & R/D SL EQUIPMENNT & RELEASE
ANCHOR & TEST PLUG BY 1000 PSI ... OK & START NORMAL CIRCULATION WITH INDUSTERIAL TO CLEAN THE WELL IN PROGRESS .
Forecast POOH & L/D 4" OLD COMPLETION STRING TO SURFACE & N/D BOP , N/D 7 1/16" OLD THA & AND N/U 11" NEW THA .
Comments:
Supplies
Needed WE NEED FOR 6G WELDING TEAM TO WORK ON WELL HEAD ON MONDAY (23-05-2021 ) MORNING & DFA SPOOL (11"*5K-11"*5K ) .
TOOL PUSHER : Ali Hussien Jolehim SITE ENGINEER : Atheer F. Hameed NIGHT PUSER : Raqeb asem CHIEF EL: Thafer Rasheed CHIEF Mech.: Basim Salim
IRAQI DRILLING COMPANY DAILY REPORT
INTEGRATED MANGEMENT SYSTEM (IDCP08F4)
Daily Operation Report Date: 22/ 05 / 2021 Project : Exxon Mobil Location area : WQ1 - 053 ROW : 82 Country : Iraq
Rig:IDC-144 Well No.: WQ1 - 053 Conductor : 20 ' RT - GL: 5.8M Activity: work over Spud Date: 19-05-2021@ 20:00
Obj: Isolate mB2 Planned Depth: 2259.58 M Planned Days: 20 Days GL Elev: 0.8M P.O.B: 50 Report No: 4 R/M + 4 OPS.
Well Type : Oil Producer Start Of Moving Date :15 / 05 /2021 End Of Moving Date : 17 /05 /2021 Days Of Acc : 1
Lenght
Depth MD (m) TVD (m) Bit current previous ID (in) OD (in) Total (m)
(m)
BHA Amount
Lenght
00:00 hrs ID (in) OD (in) Total (m)
(m)
18:00 hrs
24:00 hrs
Meterage
Lithology Top(m) Bottom(m)
K.D
24 PM Situation
POOH& L/D 4" N.V OLD COMPLETION STRING TO DEPTH
963 M . Tagged at 0.00
06 AM Situation
POOH& L/D 4" N.V OLD COMPLETION STRING TO T.D 0.00
DEPTH 579 M .
Casing Diameter (in) Depth (m) Date F.C (m) D.V (m) Angle Azimuth Closure (m) Severity (deg/30m)
7" 2807
Mud Type FWB FCL Density In : gm/cc Density Out: gm/cc Temp. In : degC Formation Tests Material tons Stock
Sand : % ECD : g/cm3 Ca= Temp. Out: degC EMW Test g/cm3 Camp fuel(L)
Gel 0: kPa Gel 0: Gel 10: kPa API Cake: PP EMW g/cm3
600 / 300 = API Vol. Cm3 AV = Choride: mg/L FP EMW g/cm3
Viscosity = PV= YP = Water: Test Date
Rig Fuel 23.2 M³
pH = Fil : Sand : % Solids% : 3
Weight on Bit = ton
TOTAL FLOW RATE (L/Min) PUMP NO.1 PUMP NO.2 Programed: 20%
Achievement ratio for workover:
R.P.M = Efficiency (%) Not programed: 0%
Stand pipe Pressure= psi Liner Size ( in ) Well Kill Drill Date: Time:
Torque: AMP St. Length ( in ) Koomey - Manifold: Accumulator Annular
Liter / Stroke Latif
Wt. of string= ton
S.P.M
Rental Crane 30 ton 12 HRS 1 Driver
Days Without LTI: FLOW RATE (L/Min) Alaa
TOTAL FLOW RATE (L/Min) 0.00
Rental Fork lift 10 ton 12 HRS 1 Driver
P/T BOP & RELEASE ANCHOR & PUMPIN 40 M3 OF IND. WATER DOWN ANNULUS , 3M HI-VIS WITH 15 M3 IND. WTER DOWN TBG & RE-LATCHE
ANCHOR & HPJSM HAL. SL & SLICK LINE OPERATION ( RIH 2.75" GC TO DEPTH 2329.5 M & RIH 2.75" FWG PLUG AND SET IT AT DEPTH 2329.5
Summary Previous Day M ) & R/D SL EQUIPMENNT & RELEASE ANCHOR & TEST PLUG BY 1000 PSI ... OK & START NORMAL CIRCULATION WITH INDUSTERIAL TO
CLEAN THE WELL IN PROGRESS .
05:00-24:00 19 22.1 L/D OLD COMPLETION:-POOH& L/D 4" N.V OLD COMPLETION STRING FROM DEPTH 2307 M TO 963 M .
Medic Ali
WSS Mohammed/Saeed
industrial water in
Jar hrs brine High Vis. R.O water 0 30
tank
Day Summary : NORMAL CIRCULATION & PERFORMED KICK WITH H2S DRILL & POOH& L/D 4" N.V OLD COMPLETION STRING FROM DEPTH 2307 M TO 963 M .
Forecast POOH & L/D 4" OLD COMPLETION STRING TO SURFACE & N/D BOP , N/D 7 1/16" OLD THA & AND N/U 11" NEW THA .
Supplies
Needed WE NEED FOR 6G WELDING TEAM TO WORK ON WELL HEAD ON MONDAY (23-05-2021 ) MORNING & DFA SPOOL (11"*5K-11"*5K ) .
TOOL PUSHER : Ali Hussien Jolehim SITE ENGINEER : Atheer F. Hameed NIGHT PUSER : Raqeb asem CHIEF EL: Thafer Rasheed CHIEF Mech.: Basim Salim
IRAQI DRILLING COMPANY DAILY REPORT
INTEGRATED MANGEMENT SYSTEM (IDCP08F4)
Daily Operation Report Date: 23/ 05 / 2021 Project : Exxon Mobil Location area : WQ1 - 053 ROW : 82 Country : Iraq
Rig:IDC-144 Well No.: WQ1 - 053 Conductor : 20 ' RT - GL: 5.8M Activity: work over Spud Date: 19-05-2021@ 20:00
Obj: Isolate mB2 Planned Depth: 2259.58 M Planned Days: 20 Days GL Elev: 0.8M P.O.B: 50 Report No: 4 R/M + 5 OPS.
Well Type : Oil Producer Start Of Moving Date :15 / 05 /2021 End Of Moving Date : 17 /05 /2021 Days Of Acc : 1
Lenght
Depth MD (m) TVD (m) Bit current previous ID (in) OD (in) Total (m)
(m)
BHA Amount
Lenght
00:00 hrs ID (in) OD (in) Total (m)
(m)
18:00 hrs
24:00 hrs
Meterage
Lithology Top(m) Bottom(m)
K.D
24 PM Situation N/D 7 1/16"*3K TOP- 11"*3K BOTTOM THS IN PROGRESS Tagged at 0.00
06 AM Situation
EXTENDED THE OLD 7" CASING BY WELDED 5 CM T.D 0.00
INPROGRESS .
Casing Diameter (in) Depth (m) Date F.C (m) D.V (m) Angle Azimuth Closure (m) Severity (deg/30m)
7" 2807
Mud Type FWB FCL Density In : gm/cc Density Out: gm/cc Temp. In : degC Formation Tests Material tons Stock
Sand : % ECD : g/cm3 Ca= Temp. Out: degC EMW Test g/cm3 Camp fuel(L)
Gel 0: kPa Gel 0: Gel 10: kPa API Cake: PP EMW g/cm3
600 / 300 = API Vol. Cm3 AV = Choride: mg/L FP EMW g/cm3
Viscosity = PV= YP = Water: Test Date
Rig Fuel 22.2 M³
pH = Fil : Sand : % Solids% : 3
Weight on Bit = ton
TOTAL FLOW RATE (L/Min) PUMP NO.1 PUMP NO.2 Programed: 25%
Achievement ratio for workover:
R.P.M = Efficiency (%) Not programed: 0%
Stand pipe Pressure= psi Liner Size ( in ) Well Kill Drill Date: Time:
Torque: AMP St. Length ( in ) Koomey - Manifold: Accumulator Annular
Liter / Stroke Latif
Wt. of string= ton
S.P.M
Rental Crane 30 ton 12 HRS 1 Driver
Days Without LTI: FLOW RATE (L/Min) Alaa
TOTAL FLOW RATE (L/Min) 0.00
Rental Fork lift 10 ton 12 HRS 1 Driver
Summary Previous Day NORMAL CIRCULATION & PERFORMED KICK WITH H2S DRILL & POOH& L/D 4" N.V OLD COMPLETION STRING FROM DEPTH 2307 M TO 963 M .
16:30-17:00 0.5 22.1 PRESSURE TEST:- CLOSE BLIND RAM AND P/T THE WELL AGAINST THE PLUG BY 1000 PSI FOR 15 MIN. …OK .
WOWH:- DISCONNCETD THE HYDRAULIC HOSES & COMPLETED N/D 11" * 5K BOP STACK WITH 13 5/8"
18:00-23:00 5 22.1
ANNULAR PREVENTOR , 11"*5K- 7 1/16"*5K DSA & 7 1/16"*5K - 7 1/16" DFA.
23:00-24:00 1 22.1 WOWH:- N/D 7 1/16"*3K TOP- 11"*3K BOTTOM THS IN PROGRESS .
WOWH:- N/D 7 1/16"*3K TOP- 11"*3K BOTTOM THS (VERY HARD TO OPEN
STUDSDUE TO RUSTY & OLD). MEASURED THE LENGTH OF 7" CASING
00:00-03:00 3 22.1 Mud Engineer Mohammed Gassan
FOUND IT 7.5 CM ,UNSUITABLE WITH NEW THS NEEDED FOR EXTENDED 5
CM
MODIFIED THE CSG STUB:- EXTENDED THE OLD 7" CASING BY WELDED 5
04:00-06:00 2 22.1 Medic Ali
CM , TOTAL LENGTH 12.5 CM INPROGRESS .
WSS Mohammed/Saeed
industrial water in
Jar hrs brine High Vis. R.O water 20 50
tank
Day Summary :
NORMAL CIRCULATION ONE HOLE VOLUME 45 M3 INDUSTERIAL WATER TO CLEAN THE WELL & POOH& L/D 4" N.V OLD COMPLETION STRING FROM DEPTH 963 M
TO SURFACE & P/T THE PLUG … OK & N/D BOP .N/D 7 1/16"*3K TOP- 11"*3K BOTTOM THS IN PROGRESS .
Comments:
Supplies
Needed
TOOL PUSHER : Ali Hussien Jolehim SITE ENGINEER : Atheer F. Hameed NIGHT PUSER : Raqeb asem CHIEF EL: Thafer Rasheed CHIEF Mech.: Basim Salim
IRAQI DRILLING COMPANY DAILY REPORT
INTEGRATED MANGEMENT SYSTEM (IDCP08F4)
Daily Operation Report Date: 24/ 05 / 2021 Project : Exxon Mobil Location area : WQ1 - 053 ROW : 82 Country : Iraq
Rig:IDC-144 Well No.: WQ1 - 053 Conductor : 20 ' RT - GL: 5.8M Activity: work over Spud Date: 19-05-2021@ 20:00
Obj: Isolate mB2 Planned Depth: 2259.58 M Planned Days: 20 Days GL Elev: 0.8M P.O.B: 50 Report No: 4 R/M + 6 OPS.
Well Type : Oil Producer Start Of Moving Date :15 / 05 /2021 End Of Moving Date : 17 /05 /2021 Days Of Acc : 1
Lenght
Depth MD (m) TVD (m) Bit current previous ID (in) OD (in) Total (m)
(m)
BHA Amount
Lenght
00:00 hrs ID (in) OD (in) Total (m)
(m)
18:00 hrs
24:00 hrs
Meterage
Lithology Top(m) Bottom(m)
K.D
06 AM Situation
RIH 6" PACKER MILLING ASSEMBLY TO DEPTH 356 T.D 0.00
M.
Casing Diameter (in) Depth (m) Date F.C (m) D.V (m) Angle Azimuth Closure (m) Severity (deg/30m)
7" 2807
Mud Type FWB FCL Density In : gm/cc Density Out: gm/cc Temp. In : degC Formation Tests Material tons Stock
Sand : % ECD : g/cm3 Ca= Temp. Out: degC EMW Test g/cm3 Camp fuel(L)
Gel 0: kPa Gel 0: Gel 10: kPa API Cake: PP EMW g/cm3
600 / 300 = API Vol. Cm3 AV = Choride: mg/L FP EMW g/cm3
Viscosity = PV= YP = Water: Test Date
Rig Fuel 21.4 M³
pH = Fil : Sand : % Solids% : 3
Weight on Bit = ton
TOTAL FLOW RATE (L/Min) PUMP NO.1 PUMP NO.2 Programed: 30%
Achievement ratio for workover:
R.P.M = Efficiency (%) Not programed: 0%
Stand pipe Pressure= psi Liner Size ( in ) Well Kill Drill Date: Time:
Torque: AMP St. Length ( in ) Koomey - Manifold: Accumulator Annular
Liter / Stroke Latif
Wt. of string= ton Rental Crane 30 ton 24 HRS 1 Driver
S.P.M Ali
Days Without LTI: FLOW RATE (L/Min)
TOTAL FLOW RATE (L/Min) 0.00
Rental Fork lift 10 ton 12 HRS Driver
NORMAL CIRCULATION ONE HOLE VOLUME 45 M3 INDUSTERIAL WATER TO CLEAN THE WELL & POOH& L/D 4" N.V OLD COMPLETION STRING
Summary Previous Day FROM DEPTH 963 M TO SURFACE & P/T THE PLUG … OK & N/D BOP .N/D 7 1/16"*3K TOP- 11"*3K BOTTOM THS IN PROGRESS .
04:00-07:00 3 22.1 MODIFIED THE CSG STUB:- EXTENDED THE OLD 7" CASING BY WELDED 5 CM , TOTAL LENGTH 12.5 CM .
06:30-08:30 2 22.1 WOWH:- N/U 11"*3K BOTTOM- 11"*5K TOP NEW DELTA DOHA THS & TIGHT ALL BOLTS .
PRESSURE TEST:- P/T THE PRIMARY/ SECONDARY SEALS WITH LOW & HIGH PRESSURE 500/2000 PSI FOR 5/15
09:00-10:00 1 22.1
MIN. ... OK THEN DID P/T FOR THE CAVITY & FOR RING GASKET 500/2000 PSI FOR 5/15 MIN. ... OK .
WOWH:- N/U 11"*5K BOP WITH DSA ( 11"*5K-13 5/8" *5K) DSA AND 13 5/8"*5K ANNULAR PREVENTER THEN
10:00-15:00 5 22.1
TIGHT ALL BOLTS , CONNECTED THE HYDRAULIC HOSE .
15:00-17:00 2 22.1 WOWH:-CONNECTED BELL NIPPLE WITH FLOW LINE .
PRESSURE TEST:- P/U & M/U 7" CUP TESTER BHA ASSY. WITH 2 7/8" DP, CLOSED THE PIPE RAMP/T THE & P/T
IT WITH LOW & HIGH PRESSURE 500/2000 PSI FOR 5/15 MINUTES…OK, OPENED PIPE RAM, CLOSED ANNULAR &
18:00-21:30 3.5 22.1
P/T WITH 500/1500 FOR 5/15 MINUTES.....OK THEN , CLOSED BLIND RAM & P/T ITWITH 500/1000 PSI FOR 5/15
MINUTES.....OK, POOH 2 7/8" DP & L/D 7" CUP TESTER BHA ASSY.
21:30-22:00 0.5 21.1 SAFETY MEETING :-HPJSM WITH RIG CREW AND DISCUSS THE HAZARD OF MILLING OPERATION .
MILLING OPERATION :- P/U , M/U & RIH 6" PACKER MILLING ASSEMBLY ( QUICK PICK (6" FRONT MILL) ,JUNK
22:00-24:00 2.0 22.1
BASKET , 4 3/4" BIT SUB ,4 3/4" JAR , 3 JTS DC 4 3/4") TO DEPTH 35 M .
MILLING OPERATION :- CON. P/U , M/U & RIH 6" PACKER MILLING
ASSEMBLY ( QUICK PICK (6" FRONT MILL) ,JUNK BASKET , 4 3/4" BIT SUB ,
00:00-02:00 2 22.1 Mud Engineer Mohammed Gassan
4 3/4" JAR , 4 JTS DC 4 3/4" INTENSIFIEER & 2 JTS 4 3/4" DC ) FROM DEPTH 35
M TO 68 M
Medic Ali
WSS Mohammed/Saeed
industrial water in
Jar hrs brine High Vis. R.O water 50
tank
Day Summary : N/D OLD THS & MODIFIED THE CSG STUB & N/U NEW THS & P/T IT OK & N/U BOP & P/T IT …OK & SAFETY MEETING & RIH PACKER MILLING BHA TO DEPTH 35 M
Comments:
Supplies
Needed
TOOL PUSHER : Ali Hussien Jolehim SITE ENGINEER : Atheer F. Hameed NIGHT PUSER : Raqeb asem CHIEF EL: Thafer Rasheed CHIEF Mech.: Basim Salim
IRAQI DRILLING COMPANY DAILY REPORT
INTEGRATED MANGEMENT SYSTEM (IDCP08F4)
Daily Operation Report Date: 25/ 05 / 2021 Project : Exxon Mobil Location area : WQ1 - 053 ROW : 82 Country : Iraq
Rig:IDC-144 Well No.: WQ1 - 053 Conductor : 20 ' RT - GL: 5.8M Activity: work over Spud Date: 19-05-2021@ 20:00
Obj: Isolate mB2 Planned Depth: 2259.58 M Planned Days: 20 Days GL Elev: 0.8M P.O.B: 50 Report No: 4 R/M + 7 OPS.
Well Type : Oil Producer Start Of Moving Date :15 / 05 /2021 End Of Moving Date : 17 /05 /2021 Days Of Acc : 1
Lenght
Depth MD (m) TVD (m) Bit current previous ID (in) OD (in) Total (m)
(m)
BHA Amount
Lenght
00:00 hrs ID (in) OD (in) Total (m)
(m)
K.D
24 PM Situation RIH 6" PACKER MILLING ASSEMBLY TO DEPTH 1657 M Tagged at 0.00
06 AM Situation
RIH 6" PACKER MILLING ASSEMBLY TO DEPTH T.D 1657.95
2091 M
Casing Diameter (in) Depth (m) Date F.C (m) D.V (m) Angle Azimuth Closure (m) Severity (deg/30m)
7" 2807
Mud Type FWB FCL Density In : gm/cc Density Out: gm/cc Temp. In : degC Formation Tests Material tons Stock
Sand : % ECD : g/cm3 Ca= Temp. Out: degC EMW Test g/cm3 Camp fuel(L)
Gel 0: kPa Gel 0: Gel 10: kPa API Cake: PP EMW g/cm3
600 / 300 = API Vol. Cm3 AV = Choride: mg/L FP EMW g/cm3
Viscosity = PV= YP = Water: Test Date
Rig Fuel 20.6 M³
pH = Fil : Sand : % Solids% : 3
Weight on Bit = ton
TOTAL FLOW RATE (L/Min) PUMP NO.1 PUMP NO.2 Programed: 35%
Achievement ratio for workover:
R.P.M = Efficiency (%) Not programed: 0%
Stand pipe Pressure= psi Liner Size ( in ) Well Kill Drill Date: Time:
Torque: AMP St. Length ( in ) Koomey - Manifold: Accumulator Annular
Liter / Stroke Latif
Wt. of string= ton
S.P.M
Rental Crane 30 ton 12 HRS 1 Driver
Days Without LTI: FLOW RATE (L/Min) Alaa
TOTAL FLOW RATE (L/Min) 0.00
Rental Fork lift 10 ton 12 HRS 1 Driver
N/D OLD THS & MODIFIED THE CSG STUB & N/U NEW THS & P/T IT OK & N/U BOP & P/T IT …OK & SAFETY MEETING & RIH PACKER MILLING
Summary Previous Day BHA TO DEPTH 35 M .
Medic Ali
WSS Mohammed/Saeed
industrial water in
Jar hrs brine High Vis. R.O water 50
tank
Day Summary : RIH 6" PACKER MILLING ASSEMBLY WITH 2 7/8" DP SINGLE BY SINGLE TO DEPTH 1657 M
Supplies
Needed
TOOL PUSHER : Ali Hussien Jolehim SITE ENGINEER : Atheer F. Hameed NIGHT PUSER : Raqeb asem CHIEF EL: Thafer Rasheed CHIEF Mech.: Basim Salim
IRAQI DRILLING COMPANY DAILY REPORT
INTEGRATED MANGEMENT SYSTEM (IDCP08F4)
Daily Operation Report Date: 26/ 05 / 2021 Project : Exxon Mobil Location area : WQ1 - 053 ROW : 82 Country : Iraq
Rig:IDC-144 Well No.: WQ1 - 053 Conductor : 20 ' RT - GL: 5.8M Activity: work over Spud Date: 19-05-2021@ 20:00
Obj: Isolate mB2 Planned Depth: 2259.58 M Planned Days: 20 Days GL Elev: 0.8M P.O.B: 50 Report No: 4 R/M + 8 OPS.
Well Type : Oil Producer Start Of Moving Date :15 / 05 /2021 End Of Moving Date : 17 /05 /2021 Days Of Acc : 1
Lenght
Depth MD (m) TVD (m) Bit current previous ID (in) OD (in) Total (m)
(m)
BHA Amount
Lenght
00:00 hrs ID (in) OD (in) Total (m)
(m)
24:00 hrs
JUNK BASKET 1 2.80 5 1.32 2.53
BIT SUB 1 2.25 4 3/4 0.92 3.44
Meterage
Jar 1 2.25 4 3/4 3.56 7.00
Lithology Top(m) Bottom(m)
DC 4 2.25 4 3/4 37.89 44.89
Jar Intensifier 1 2 4 3/4 4.57 49.45
DC 2 2.25 4 3/4 18.48 67.93
XOS 1 4 2 0.20 68.13
DP 234 2 8/53 2 7/8 2255.05 2323.18
K.D 2.45
24 PM Situation
WAITING ON FOD TO GET DECISION TO SAFE DRILL
STRING AND WELL Tagged at 0.00
Casing Diameter (in) Depth (m) Date F.C (m) D.V (m) Angle Azimuth Closure (m) Severity (deg/30m)
7" 2807
Mud Type FWB FCL Density In : gm/cc Density Out: gm/cc Temp. In : degC Formation Tests Material tons Stock
Sand : % ECD : g/cm3 Ca= Temp. Out: degC EMW Test g/cm3 Camp fuel(L)
Gel 0: kPa Gel 0: Gel 10: kPa API Cake: PP EMW g/cm3
600 / 300 = API Vol. Cm3 AV = Choride: mg/L FP EMW g/cm3
Viscosity = PV= YP = Water: Test Date
Rig Fuel 19.6 M³
pH = Fil : Sand : % Solids% : 3
Weight on Bit = ton
TOTAL FLOW RATE (L/Min) PUMP NO.1 PUMP NO.2 Programed: 35%
Achievement ratio for workover:
R.P.M = Efficiency (%) Not programed: 0%
Stand pipe Pressure= psi Liner Size ( in ) Well Kill Drill Date: Time:
Torque: AMP St. Length ( in ) Koomey - Manifold: Accumulator Annular
Liter / Stroke Latif
Wt. of string= ton
S.P.M
Rental Crane 30 ton 24 HRS 2 Driver
Ali
Days Without LTI: FLOW RATE (L/Min)
Summary Previous Day RIH 6" PACKER MILLING ASSEMBLY WITH 2 7/8" DP SINGLE BY SINGLE TO DEPTH 1657 M
10:30-12:00 1.5 22.1 RIG UP KELLY :- L/D ONE JOINT 2 7/8" DP ,P/U 3 1/2" KELLY & LUBRICATED THE SWIVEL .
MILLING OPERATION :- START MILLING PACKER FROM DEPTH 2325.63 TO 23226 .15 M ( TOATAL MIILING 52
12:00-21:00 9 22.1 CM ) WITH SURFACE PARAMETERS : WOB = 1-3 TON , RPM = 60-80 , SPM= 70 , P= 400-500 PSI , TQ= 50-60 AMP . THE
WEIGHT OF DRILL STRING WITH KELLY 39 TON .
*AT DEPTH 2326.15 OBSERVED THE TORQUE INCREASE FROM 50-200 AMP , THE DRILLER REDUCE THE RPM TO
ZERO TO PREVENT THE STRING BACK REVERSE FASTLY THEN PULL UP THE STRING 1.25 M AND BACK TO
ORGINAL WEIGHT (39 TON ) , CALL BAKER HUGHESS & FOD REPRESENTATIVEAND WHEN BACK TO
ORIGINAL DEPTH OBSERVED OBSTRUCTION , THE PACKER GO UP WITH DRILL STRING , WHEN MILLING
WITH SAME PARAMETER WOB =3 TON , RPM = 60-80 , SPM= 70 , P= 400-500 PSI ) OBSERVED HIGH TORQUE UP TO
200 AMP. AND WE CAN'T BACK TO ORGINAL WEIGHT DUE TO THE KELLY BUSHING WILL GO OUT FROM THE
ROTARY TABLE , FOD COMPANY MAN DECIDED TO STAY IN THE SAME POINT BECAUSE OF IF PULL THE
KELLY BUSHING OUT THE ROTARY TABLE WE CAN'T RELEASE THE BASKET GRAPPLE FROM PACKER
BECAUSE OF WE CAN'T ROTATE THE DRILL STRING WITHOUT KELLY .
DISCUSS THE NEXT STEP :- FOD & BAKER HUGHES DECIDED TO PUMPING HI-VIS WITH 100 C.P VISCOSITY
21:00-22:00 1 24.0
CHASED BY INDUSTERIAL WATER TO CLEAN THE TOP MILLING PACKER TO RESUME MILLING OPERATIONS .
22::00-22:30 0.5 8.3 FIXING :-FIXING THE WEIGHT INDICATOR AND CHECKED MUD PUMP .
WELL CLEANING:-PUMPING 3 M3 HI-VIS CHASED BY INDUSTERIAL WATER TO CLEAN THE WELL TOP OF
22:30-23:300 1 22.2
PACKER , STOP CIRCULATION WHEN HI-VIS ARRIVED TO MUD SYSTEM .
22:30-24:00 0.5 22.2 MILLING OPERATION :-WHEN RESUME MILLING OBSERVED THE TORQUE INCREASE FROM 50 - 200 AMP
* STOP THE OPERATION DUE TO AVOID FROM BACKOFF THE DRILL STRING BACKOFF THEN LOST THE
DRILL STRING .
*WAITING ON FOD TO GET DECISION TO SAFE DRILL STRING AND WELL
00:00-06:00 6 24.0 WAITING :-WAITING ON FOD ORDER . Mud Engineer Mohammed Gassan
Medic Ali
WSS Mohammed/Saeed
industrial water in
Jar hrs brine High Vis. R.O water 50
tank
RIH 6" PACKER MILLING ASSEMBLY WITH 2 7/8" DP SINGLE BY SINGLE TO DEPTH 2325.62 & MILLING PACKE TO DEPTH 23226 .15 M & PUMPING 3 M3 HI-VIS
Day Summary : CHASED BY INDUSTERIAL WATER TO CLEAN THE WELL TOP OF PACKER & * STOP THE OPERATION DUE TO AVOID FROM BACKOFF THE DRILL STRING AND STAY
IN THE WELL & WAITING ON FOD TO GET RIGHT DECISION TO SAFE THE WELL
Comments:
Supplies
Needed
TOOL PUSHER : Ali Hussien Jolehim SITE ENGINEER : Atheer F. Hameed NIGHT PUSER : Raqeb asem CHIEF EL: Thafer Rasheed CHIEF Mech.: Basim Salim
IRAQI DRILLING COMPANY DAILY REPORT
INTEGRATED MANGEMENT SYSTEM (IDCP08F4)
Daily Operation Report Date: 27/ 05 / 2021 Project : Exxon Mobil Location area : WQ1 - 053 ROW : 82 Country : Iraq
Rig:IDC-144 Well No.: WQ1 - 053 Conductor : 20 ' RT - GL: 5.8M Activity: work over Spud Date: 19-05-2021@ 20:00
Obj: Isolate mB2 Planned Depth: 2259.58 M Planned Days: 20 Days GL Elev: 0.8M P.O.B: 50 Report No: 4 R/M + 9 OPS.
Well Type : Oil Producer Start Of Moving Date :15 / 05 /2021 End Of Moving Date : 17 /05 /2021 Days Of Acc : 1
Lenght
Depth MD (m) TVD (m) Bit current previous ID (in) OD (in) Total (m)
(m)
BHA Amount
Lenght
00:00 hrs ID (in) OD (in) Total (m)
(m)
24:00 hrs
JUNK BASKET 1 2.80 5 1.32 2.53
BIT SUB 1 2.25 4 3/4 0.92 3.44
Meterage
Jar 1 2.25 4 3/4 3.56 7.00
Lithology Top(m) Bottom(m)
DC 4 2.25 4 3/4 37.89 44.89
Jar Intensifier 1 2 4 3/4 4.57 49.45
DC 2 2.25 4 3/4 18.48 67.93
XOS 1 4 2 0.20 68.13
DP 139 2 8/53 2 7/8 1339.05 1407.19
K.D 2.45
06 AM Situation
WAITING ON MAINTENANCE THE GEAR BOX OF T.D
CARRIER TRUCK (ELECTRICAL PART ) .
Casing Diameter (in) Depth (m) Date F.C (m) D.V (m) Angle Azimuth Closure (m) Severity (deg/30m)
7" 2807
Mud Type FWB FCL Density In : gm/cc Density Out: gm/cc Temp. In : degC Formation Tests Material tons Stock
Sand : % ECD : g/cm3 Ca= Temp. Out: degC EMW Test g/cm3 Camp fuel(L)
Gel 0: kPa Gel 0: Gel 10: kPa API Cake: PP EMW g/cm3
600 / 300 = API Vol. Cm3 AV = Choride: mg/L FP EMW g/cm3
Viscosity = PV= YP = Water: Test Date
Rig Fuel 18.4 M³
pH = Fil : Sand : % Solids% : 3
Weight on Bit = ton
TOTAL FLOW RATE (L/Min) PUMP NO.1 PUMP NO.2 Programed: 45%
Achievement ratio for workover:
R.P.M = Efficiency (%) Not programed: 0%
Stand pipe Pressure= psi Liner Size ( in ) Well Kill Drill Date: Time:
Torque: AMP St. Length ( in ) Koomey - Manifold: Accumulator Annular
Liter / Stroke Latif
Wt. of string= ton
S.P.M
Rental Crane 30 ton 24 HRS 2 Driver
Ali
Days Without LTI: FLOW RATE (L/Min)
RIH 6" PACKER MILLING ASSEMBLY WITH 2 7/8" DP SINGLE BY SINGLE TO DEPTH 2325.62 & MILLING PACKE TO DEPTH 23226 .15 M &
Summary Previous Day PUMPING 3 M3 HI-VIS CHASED BY INDUSTERIAL WATER TO CLEAN THE WELL TOP OF PACKER & * STOP THE OPERATION DUE TO AVOID
FROM BACKOFF THE DRILL STRING AND STAY IN THE WELL & WAITING ON FOD TO GET RIGHT DECISION TO SAFE THE WELL
*FOD DECIDED TO RESUME MILLING THE PACKER BY ATTEND IDC FISHER MAN .
MILLING OPERATION :-
- IDC FISHER MAN PULL UP THE DRILL STRING 1 TON THEN RIH FASTLY SEVERAL TIMES .
-IDC FISHER MAN ROTATE THE DRILL STRING WITH (3,5&10) TURNS TO CHECK HOW MANY THE DRILL
STRING BACK REVERSE , STRING BACK SLOWLY .
-WHEN START MILLING THE TORQUE GO UP TO 220 AFTER THAT BACK 50-100 AMP .
09:30-15:30 6 21.1 - START MILLING PACKER FROM DEPTH 2324.9 M TO 2326.9 M WITH SURFACE PARAMETERS : WOB = 1-3 TON ,
RPM = 50-80 , SPM= 60 , P= 400-600 PSI , TQ= 50-100 AMP . PACKER ELEMNT GOT SHEAR AND COMPLETE LOSSES
AT DEPTH 2326 M . COMPLETE MILL THE PACKER .
- POOH KELLY UP & DOWN OBSERVED ( 20 TON OVER PULL & 10 TON SLACKOFF WEIGHT ) THEN WORKING
ON JARRING UP SEVRAL TIMES STRING GOT FREE UP , GOOD INDICTION TO FISH THE PACKER
- FOD & IDC FISHER MAN DECIDED TO L/D KELLY & START POOH .
16:30-24:00 7.5 22.1 POOH :- POOH 6" PACKER MILLING ASSEMBLY FROM DEPTH 2323 M TO 1407 M
*DURING POOH FROM DEPTH 2323 M TO 2168 M OBSERVED OVER PULL UP TO 20 TON WORKING ON JARRING
UP SEVRAL TIMES , L/D 3 JTS 2 7/8" DP DUE TO FACED HIGH OVER PULL WHEN POOH DPL.
Medic Ihab
WSS Muslim/Mohammed
industrial water in
Jar hrs brine High Vis. R.O water 10 60
tank
Day Summary : WAITING ON FOD ORDER & MILLING OPERATION & POOH 6" PACKER MILLING ASSEMBLY FROM DEPTH 2323 M TO 1407 M
Comments:
Supplies
Needed
TOOL PUSHER : Sattar Chasib SITE ENGINEER : Atheer F. Hameed NIGHT PUSER : Raqeb asem CHIEF EL: Maithem Salah CHIEF Mech.: Basim Salim
IRAQI DRILLING COMPANY DAILY REPORT
INTEGRATED MANGEMENT SYSTEM (IDCP08F4)
Daily Operation Report Date: 28/ 05 / 2021 Project : Exxon Mobil Location area : WQ1 - 053 ROW : 82 Country : Iraq
Rig:IDC-144 Well No.: WQ1 - 053 Conductor : 20 ' RT - GL: 5.8M Activity: work over Spud Date: 19-05-2021@ 20:00
Obj: Isolate mB2 Planned Depth: 2259.58 M Planned Days: 20 Days GL Elev: 0.8M P.O.B: 50 Report No: 4 R/M + 10 OPS.
Well Type : Oil Producer Start Of Moving Date :15 / 05 /2021 End Of Moving Date : 17 /05 /2021 Days Of Acc : 1
Lenght
Depth MD (m) TVD (m) Bit current previous ID (in) OD (in) Total (m)
(m)
BHA Amount
Lenght
00:00 hrs ID (in) OD (in) Total (m)
(m)
18:00 hrs
24:00 hrs
Meterage
Lithology Top(m) Bottom(m)
K.D
06 AM Situation
RIH 5 7/8" BIT WITH 7" SCRAPER BHA BY 2 7/8" DP T.D
TO DEPTH 810 M
Casing Diameter (in) Depth (m) Date F.C (m) D.V (m) Angle Azimuth Closure (m) Severity (deg/30m)
7" 2807
Mud Type FWB FCL Density In : gm/cc Density Out: gm/cc Temp. In : degC Formation Tests Material tons Stock
Sand : % ECD : g/cm3 Ca= Temp. Out: degC EMW Test g/cm3 Camp fuel(L)
Gel 0: kPa Gel 0: Gel 10: kPa API Cake: PP EMW g/cm3
600 / 300 = API Vol. Cm3 AV = Choride: mg/L FP EMW g/cm3
Viscosity = PV= YP = Water: Test Date
Rig Fuel 17.4 M³
pH = Fil : Sand : % Solids% : 3
Weight on Bit = ton
TOTAL FLOW RATE (L/Min) PUMP NO.1 PUMP NO.2 Programed: 50%
Achievement ratio for workover:
R.P.M = Efficiency (%) Not programed: 0%
Stand pipe Pressure= psi Liner Size ( in ) Well Kill Drill Date: Time:
Torque: AMP St. Length ( in ) Koomey - Manifold: Accumulator Annular
Liter / Stroke Latif
Wt. of string= ton
S.P.M
Rental Crane 30 ton 24 HRS 2 Driver
Ali
Days Without LTI: FLOW RATE (L/Min)
TOTAL FLOW RATE (L/Min) 0.00
Rental Fork lift 10 ton 12 HRS Driver
Summary Previous Day WAITING ON FOD ORDER & MILLING OPERATION & POOH 6" PACKER MILLING ASSEMBLY FROM DEPTH 2323 M TO 1407 M
00:00-12:45 12.75 8.3 MAINTENANCE :- WORKING ON MAINTENANCE THE GEAR BOX OF CARRIER TRUCK (ELECTRICAL PART ) .
*SPECIAL TEAM FROM NORTH RUMILA WORKSHOP WORKING ON FIXING THE GEAR BOX .
POOH :- RESUMED POOH 6" PACKER MILLING ASSEMBLY WITH 2 7/8" DP FROM DEPTH 1407 M TO SURFACE &
12:45-24:00 11.25 22.1
L/D MILLING TOOLS WITH PACKER ASSEMBLY .
* HARD TO OPEN THE DRILL PIPE DUE TO HIGH TORQUE THAT GET FROM MILLING OPERATIONS .
RIH SCRAPER:- P/U , M/U 5 7/8" BIT WITH 7" SCRAPER BHA ( 4 3/4" B.S , 4 3/4"
00:00-06:00 6 22.1 Mud Engineer Galib Salman
XOS & 2 JOINT 4 3/4" DC ) AND RIH BY 2 7/8" DP TO DEPTH 810 M .
Medic Ihab
*KEEP FILLING UP THE WELL WITH 5 M3 OF INDUSTERIAL WATER EACH 1 WSS Muslim/Mohammed
HR .
industrial water in
Jar hrs brine High Vis. R.O water 0 60
tank
WAITING ON MAINTENANCE THE GEAR BOX OF CARRIER TRUCK (ELECTRICAL PART ) & RESUMED POOH 6" PACKER MILLING ASSEMBLY WITH 2 7/8" DP FROM
Day Summary :
DEPTH 1407 M TO SURFACE .
Forecast RIH SCARPER & POOH & L/D 7" SCRAPER WITH 2 7/8" DP TO SURFACE .
Comments:
Supplies
Needed
TOOL PUSHER : Sattar Chasib SITE ENGINEER : Atheer F. Hameed NIGHT PUSER : Raqeb asem CHIEF EL: Maithem Salah CHIEF Mech.: Basim Salim
IRAQI DRILLING COMPANY DAILY REPORT
INTEGRATED MANGEMENT SYSTEM (IDCP08F4)
Daily Operation Report Date: 29/ 05 / 2021 Project : Exxon Mobil Location area : WQ1 - 053 ROW : 82 Country : Iraq
Rig:IDC-144 Well No.: WQ1 - 053 Conductor : 20 ' RT - GL: 5.8M Activity: work over Spud Date: 19-05-2021@ 20:00
Obj: Isolate mB2 Planned Depth: 2259.58 M Planned Days: 20 Days GL Elev: 0.8M P.O.B: 50 Report No: 4 R/M + 11 OPS.
Well Type : Oil Producer Start Of Moving Date :15 / 05 /2021 End Of Moving Date : 17 /05 /2021 Days Of Acc : 1
Lenght
Depth MD (m) TVD (m) Bit current previous ID (in) OD (in) Total (m)
(m)
BHA Amount
Lenght
00:00 hrs ID (in) OD (in) Total (m)
(m)
18:00 hrs
24:00 hrs
Meterage
Lithology Top(m) Bottom(m)
K.D
24 PM Situation
POOH & L/D 5 7/8" BIT WITH 7" SCRAPER BHA AND 2 7/8"
DP TO DEPTH 2208 M Tagged at
06 AM Situation
POOH & L/D 5 7/8" BIT WITH 7" SCRAPER BHA AND T.D
2 7/8" DP TO DEPTH 1823 M
Casing Diameter (in) Depth (m) Date F.C (m) D.V (m) Angle Azimuth Closure (m) Severity (deg/30m)
7" 2807
Mud Type FWB FCL Density In : gm/cc Density Out: gm/cc Temp. In : degC Formation Tests Material tons Stock
Sand : % ECD : g/cm3 Ca= Temp. Out: degC EMW Test g/cm3 Camp fuel(L)
Gel 0: kPa Gel 0: Gel 10: kPa API Cake: PP EMW g/cm3
600 / 300 = API Vol. Cm3 AV = Choride: mg/L FP EMW g/cm3
Viscosity = PV= YP = Water: Test Date
Rig Fuel 16.5 M³
pH = Fil : Sand : % Solids% : 3
Weight on Bit = ton
TOTAL FLOW RATE (L/Min) PUMP NO.1 PUMP NO.2 Programed: 55%
Achievement ratio for workover:
R.P.M = Efficiency (%) Not programed: 0%
Stand pipe Pressure= psi Liner Size ( in ) Well Kill Drill Date: Time:
Torque: AMP St. Length ( in ) Koomey - Manifold: Accumulator Annular
Liter / Stroke
Wt. of string= ton
S.P.M
Rental Crane 30 ton 12 HRS 1 Driver
Ali
Days Without LTI: FLOW RATE (L/Min)
TOTAL FLOW RATE (L/Min) 0.00
Rental Fork lift 10 ton 12 HRS Driver
WAITING ON MAINTENANCE THE GEAR BOX OF CARRIER TRUCK (ELECTRICAL PART ) & RESUMED POOH 6" PACKER MILLING ASSEMBLY WITH
Summary Previous Day 2 7/8" DP FROM DEPTH 1407 M TO SURFACE .
RIH SCRAPER:- CON. RIH 5 7/8" BIT WITH 7" SCRAPER BHA AND 2 7/8" DP SINGLE BY SINGLE FROM DEPTH
15:00-18:00 3 22.1
2237 M TO 2495 M . TAG TD AT DEPTH 2495 M . , L/D 1 JOINT DP .
WELL CLEANING :- L/U SURFACE LINE AND START NORMAL CIRCULATION WITH 5 M3 HI-VIS CHASED BY 60
18:00-21:00 3 22.1
M3 OF INDUSTERIAL WATER ,WITHOUT RETURN . (P=350 PSI , SP=40 ) AT DEPTH 2488 M .
POOH SCRAPER:- POOH & L/D 5 7/8" BIT WITH 7" SCRAPER BHA AND 2 7/8" DP SINGLE BY SINGLE FROM
21:00-24:00 3 22.1
DEPTH 2488 M TO 2208 M .
POOH SCRAPER:- POOH & L/D 5 7/8" BIT WITH 7" SCRAPER BHA AND 2 7/8"
00:00-06:00 6 22.1 Mud Engineer Galib Salman
DP SINGLE BY SINGLE FROM DEPTH 2208 M TO 1823 M .
Medic Ihab
*KEEP FILLING UP THE WELL WITH 5 M3 OF INDUSTERIAL WATER EACH 1 WSS Muslim/Mohammed
HR .
industrial water in
Jar hrs brine High Vis. R.O water 10 70
tank
RIH 5 7/8" BIT WITH 7" SCRAPER BHA BY 2 7/8" DP TO DEPTH 2495 M & L/U SURFACE LINE AND START NORMAL CIRCULATION WITH 5 M3 HI-VIS CHASED BY 60
Day Summary : M3 OF INDUSTERIAL WATER ,WITHOUT RETURN & POOH & L/D 5 7/8" BIT WITH 7" SCRAPER BHA AND 2 7/8" DP SINGLE BY SINGLE FROM DEPTH 2488 M TO
2208 M
Forecast POOH & L/D 7" SCRAPER WITH 2 7/8" DP TO SURFACE & RIH BP , SET IT AT 2420 M AND DUMP 3 M3 OF CEMENT ABOVE BP .
Comments:
Supplies
Needed
TOOL PUSHER : Sattar Chasib SITE ENGINEER : Atheer F. Hameed NIGHT PUSER : Raqeb asem CHIEF EL: Maithem Salah CHIEF Mech.: Basim Salim
IRAQI DRILLING COMPANY DAILY REPORT
INTEGRATED MANGEMENT SYSTEM (IDCP08F4)
Daily Operation Report Date: 30/ 05 / 2021 Project : Exxon Mobil Location area : WQ1 - 053 ROW : 82 Country : Iraq
Rig:IDC-144 Well No.: WQ1 - 053 Conductor : 20 ' RT - GL: 5.8M Activity: work over Spud Date: 19-05-2021@ 20:00
Obj: Isolate MB2 Planned Depth: 2259.58 M Planned Days: 20 Days GL Elev: 0.8M P.O.B: 50 Report No: 4 R/M + 12 OPS. Well Type :
Oil Producer Start Of Moving Date :15 / 05 /2021 End Of Moving Date : 17 /05 /2021 Days Of Acc : 1
Depth MD (m) TVD (m) Bit current previous BHA Amount ID (in) OD (in) Length (m) Total (m)
00:00 hrs
18:00 hrs
24:00 hrs
Meterage
Lithology Top(m) Bottom(m)
24 PM Situation POOH & L/D 5 7/8" BIT WITH 7" SCRAPER BHA TO DEPTH 348 M well T.D 2 526 m
06 AM Situation POOH & L/D 5 7/8" BIT WITH 7" SCRAPER BHA TO SURFACE Planned Packer Setting 2250.26 m
Depth
Casing Diameter (in) Depth (m) Date F.C (m) D.V (m) AngleAzimuth Closure (m) Severity (deg/30m)
Conductor 20 49.5
Surface 13 3/8" 794
Intermediate 9 5/8 2094
Production 7 2526
Mud Type FWB FCL Density In : gm/cc Density Out: gm/cc Temp. In : degC Formation Tests Material tons Stock
Sand : % ECD : g/cm3 Ca= Temp. Out: degC EMW Test g/cm3 Camp fuel(L)
Gel 0: kPa Gel 0: Gel 10: kPa API Cake: PP EMW g/cm3
600 / 300 = API Vol. Cm3 AV = Choride: mg/L FP EMW g/cm3
Viscosity = PV= YP = Water: Test Date Rig Fuel 15.5 M³
pH = Fil : Sand : % Solids% : 3
Weight on Bit = ton TOTAL FLOW RATE (L/Min) PUMP NO.1 PUMP NO.2 Achievement ratio for Programed: 60%
R.P.M = Efficiency (%) 90 workover: Not programed: 0%
Stand pipe Pressure= psi Liner Size ( in ) 6 Well Kill Drill Date: 20-05-2021 Time: 17:00
Torque: AMP St. Length ( in ) 7 Koomey - Shenkai Manifold: 1500 PSI Accumulator :3000 psi Annular :1300 psi
Liter / Stroke 8.75 Rental Crane 30 Lateef
Wt. of string= ton ton 12 HRS 1 Driver
S.P.M
Days Without LTI : 434 days FLOW RATE (L/Min) Rental Fork lift 10 Alaa
ton 12 HRS 1 Driver
TOTAL FLOW RATE (L/Min) 0.00
RIH 5 7/8" BIT WITH 7" SCRAPER BHA BY 2 7/8" DP TO DEPTH 2495 M & L/U SURFACE LINE AND START NORMAL CIRCULATION WITH 5
Summary Previous Day M3 HI-VIS CHASED BY 60 M3 OF INDUSTERIAL WATER ,WITHOUT RETURN & POOH & L/D 5 7/8" BIT WITH 7" SCRAPER BHA AND 2 7/8"
DP SINGLE BY SINGLE FROM DEPTH 2488 M TO 2208 M
00:00-24:00 24 22.1 POOH SCRAPER :- POOH & L/D 5 7/8" BIT WITH 7" SCRAPER BHA AND 2 7/8" DP SINGLE BY SINGLE FROM DEPTH 2208
M TO 348 M .
00:00-06:00 6 22.1 POOH SCRAPER :- POOH & L/D 5 7/8" BIT WITH 7" SCRAPER BHA AND 2 7/8" Mud Engineer Galib Salman
DP SINGLE BY SINGLE TO SURFACE .
Safety Coord. Assad Hamza
Medic Ihab
*KEEP FILLING UP THE WELL WITH 5 M3 OF INDUSTERIAL WATER EACH 1 HR . WSS Muslim/Mohammed
Receiv
Item Accumulate M3
ed
Jar hrs industrial water in tank brine High Vis. R.O water 0 70
Day Summary POOH & L/D 5 7/8" BIT WITH 7" SCRAPER BHA AND 2 7/8" DP SINGLE BY SINGLE FROM DEPTH 2208 M TO 348 M .
Comments: ???????????
Supplies ???????????
Needed ???????????
TOOL PUSHER : Sattar Chasib SITE ENGINEER : Atheer F. Hameed NIGHT PUSER : Raqeb asem CHIEF EL: Maithem Salah CHIEF Mech.: Basim Salim
IRAQI DRILLING COMPANY DAILY REPORT
INTEGRATED MANGEMENT SYSTEM (IDCP08F4)
Daily Operation Report Date: 31/ 05 / 2021 Project : Exxon Mobil Location area : WQ1 - 053 ROW : 82 Country : Iraq
Rig:IDC-144 Well No.: WQ1 - 053 Conductor : 20 ' RT - GL: 5.8M Activity: work over Spud Date: 19-05-2021@ 20:00
Obj: Isolate MB2 Planned Depth: 2259.58 M Planned Days: 20 Days GL Elev: 0.8M P.O.B: 50 Report No: 4 R/M + 13 OPS. Well Type :
Oil Producer Start Of Moving Date :15 / 05 /2021 End Of Moving Date : 17 /05 /2021 Days Of Acc : 1
Depth MD (m) TVD (m) Bit current previous BHA Amount ID (in) OD (in) Length (m) Total (m)
00:00 hrs
18:00 hrs
24:00 hrs
Meterage
Lithology Top(m) Bottom(m)
Casing Diameter (in) Depth (m) Date F.C (m) D.V (m) AngleAzimuth Closure (m) Severity (deg/30m)
Conductor 20 49.5
Surface 13 3/8" 794
Intermediate 9 5/8 2094
Production 7 2526
Mud Type FWB FCL Density In : gm/cc Density Out: gm/cc Temp. In : degC Formation Tests Material tons Stock
Sand : % ECD : g/cm3 Ca= Temp. Out: degC EMW Test g/cm3 Camp fuel(L)
Gel 0: kPa Gel 0: Gel 10: kPa API Cake: PP EMW g/cm3
600 / 300 = API Vol. Cm3 AV = Choride: mg/L FP EMW g/cm3
Viscosity = PV= YP = Water: Test Date Rig Fuel 14.7 M³
pH = Fil : Sand : % Solids% : 3
Weight on Bit = ton TOTAL FLOW RATE (L/Min) PUMP NO.1 PUMP NO.2 Achievement ratio for Programed: 60%
R.P.M = Efficiency (%) 90 workover: Not programed: 0%
Stand pipe Pressure= psi Liner Size ( in ) 6 Well Kill Drill Date: 20-05-2021 Time: 17:00
Torque: AMP St. Length ( in ) 7 Koomey - Shenkai Manifold: 1500 PSI Accumulator :3000 psi Annular :1300 psi
Liter / Stroke 8.75 Rental Crane 30 Lateef
Wt. of string= ton ton 12 HRS 1 Driver
S.P.M
Days Without LTI : 435 days FLOW RATE (L/Min) Rental Fork lift 10 Alaa
ton 12 HRS 1 Driver
TOTAL FLOW RATE (L/Min) 0.00
Summary Previous Day POOH & L/D 5 7/8" BIT WITH 7" SCRAPER BHA AND 2 7/8" DP SINGLE BY SINGLE FROM DEPTH 2208 M TO 348 M .
00:00-06:00 6 22.1
POOH SCRAPER :- POOH & L/D 5 7/8" BIT WITH 7" SCRAPER BHA AND 2 7/8" DP SINGLE BY
SINGLE TO SURFACE .
06:00-08:00 2 22.1 WOWH:- N/D BELL NIPPLE WITH FLOW LINE .
08:00-12:00 4 22.1
CONNECTED WIRE LINE EQUIPMENT :- CONNECTED 13 5/8" ON THE TOP OF ANNULAR
PREVENTER AND R/U WIRE LINE EQUIPMENT .
P/T WL EQUIPMENT :-P/T WIRE LINE EQUIPMENT BY 500 PSI .. FAILURE ,OBSERVED LEAK
12:00-14:30 2.5 22.2 FROM WL LUBRICATOR , CHANGE THE LUBRICATOR AND RE- TEST WL EQUIOMENT BY
250/500 PSI FOR 5 MIN… OK
14:30-17:00 2.5 22.1
WIRE LINE OPERATION :- M/U 5 3/4" GAUGE CUTTER , JUNK BASKET , GR/CCL AND RIH BY WL
TAG T.D AT DEPTH 2487.5 M , POOH TO SURFACE .
00:00-06:00 6 22.1 WOC:- WAITING ON CEMENT TO BE HARDEN . Mud Engineer Galib Salman
Medic Ihab
*KEEP FILLING UP THE WELL WITH 5 M3 OF INDUSTERIAL WATER EACH 1 HR . WSS Muslim/Mohammed
Receiv
Item Accumulate M3
ed
Jar hrs industrial water in tank brine High Vis. R.O water 10 80
Forecast WOC & TAG THE TOP OF CEMENT THEN RIH ESP WITH 3 1/2" TBG
Supplies RECEIVED 80 M3 OF INDUSTERIAL WATER AND 10 M3 WATER RO & 3 1/2" PIPE RAM FROM NORTH RUMILA WORKSHOP
Needed WE NEEDED FOR FOUR TRUCK TO TRANSOPRTATION 253 JTS OLD 4" TBG TO SEISMIC YARD ROW-96
TOOL PUSHER : Sattar Chasib SITE ENGINEER : Atheer F. Hameed NIGHT PUSER : Hashim Ihsan CHIEF EL: Maithem Salah CHIEF Mech.: Basim Salim
IRAQI DRILLING COMPANY DAILY REPORT
Daily Operation Report Date: 8/12 /2021 Project : Exxon Mobil Location area : WQ1 - 239 ROW : 96 Country : Iraq
Rig:IDC-144 Well No.: WQ1 - 239 Conductor : 20 ' RT - GL: 5.8M Activity: workover Spud Date:
Obj: Tubing change . Planned Depth: 2306.76 M Planned Days: 10 Days GL Elev: 0.8M P.O.B: 41 Report No: 4 ( OPs)
Well Type : Production well Start Of Moving Date : 1 / 12 /2021 End Of Moving Date : 3/12/2021 Days Of Acc : 1 day
Depth MD (m) TVD (m) Bit current previous BHA Amount ID (in) OD (in) Length (m) Total (m)
00:00 hrs
18:00 hrs
24:00 hrs
Meterage
24 PM Situation N/D 7 1/16'' 3K * 11'' 3K top flang 11'' 3K bottom flang old THS well T.D
06 AM Situation
pressure test between primery and secoundary seals and ring gasket with Planned Packer Setting
low/high pressure 300/2000 psi .. OK Depth
Casing Diameter (in) Depth (m) Date F.C (m) D.V (m) Angle Azimuth Closure (m) Severity (deg/30m)
Conductor 20 48
Surface 13 3/8" 848
Intermediate 9 5/8 2078
Production 7 2526
Mud Type braine Density In : gm/cc Density Out: gm/cc Temp. In : degC Formation Tests Material tons Stock
Sand : % ECD : g/cm3 Ca= Temp. Out: degC EMW Test g/cm3 Camp fuel(L)
Gel 0: kPa Gel 0: Gel 10: kPa API Cake: PP EMW g/cm3 Rig Fuel
600 / 300 = API Vol. Cm3 AV = Choride: mg/L FP EMW g/cm3
12.2 m3
Viscosity = PV= YP = Water: Test Date
pH = Fil : Sand : % Solids% : 3
Consumed 0.9 m3
Weight on Bit = ton TOTAL FLOW RATE (L/Min) PUMP NO.1 PUMP NO.2 Programed: 0%
Achievement ratio for workover:
R.P.M = Efficiency (%) 90 Not programed: 0%
Stand pipe Pressure= psi Liner Size ( in ) 5.5 Well Kick Drill Date:1-09-2021 Time: 10:00 am
Torque: AMP Koomey - Shenkai Manifold: 1500 PSI Accumulator :3000 psi Annular :1500 psi
St. Length ( in ) 7
Summary Previous Day many Tried to relreased The anchor from PKR after that the anchor was released , Re-install BOP stack,N.cir 2 cycle to displaced the crude oil from annulas, Started POOH & L/D old
completion string 3 1/2" VAGT to depth 1389 mKB .
TIME H CODE Daily Operations
00:00-06:00 6.00 22.1 Continued POOH and L/D 3 1/2" VAGT, L-80,9.2# TBG old completion string from depth 1389 mKB to depth 945 mKB.
06:00-06:30 0.5 21.1 Shift changded, held PJSM, TBT with day shift discuused the Ops & hazards for next 12 hrs.
06:30-10:00 3.5 22.1 Continued POOH and L/D 3 1/2" VAGT, L-80,9.2# TBG old completion string from depth 945 mKB to depth 543 mKB.
10:00-11:00 1.0 22.1 Performed Slip drilling line wire 18 m ,and set crown-o-matic … OK.
11:00-18:00 1.0 22.1 Continued POOH anckor by L/D 3 1/2" VAGT, L-80,9.2# TBG old completion string from depth 543 mKB to the surface on pipe rack
18:00-22:00 4.0 22.1 N/D 7 1/16'' 3K * 11'' 5K DSA and 11'' * 5K BOPs stack .
22:00-24:00 2.0 22.1 N/D 7 1/16'' 3K * 11'' 3K top flang 11'' 3K bottom flang old THS
WSS Ahamad/Ali
Jar hrs industrial water in tank brine High Vis. R.O water 30
industrial
0 30 80 120
water
Day Summary Started POOH & L/D old completion string 3 1/2" VAGT to surface . , N/D 11" * 5K BOPs stack . N/D 7 1/16'' 3K * 11'' 3K top flang 11'' 3K bottom flang old THS
Comments: Conducted Safety Meeting for the day and night shift .
Supplies NA
Needed NA
Rig Manager : Sattar Chasib SITE ENGINEER : Marwan Adnan NIGHT PUSER : Ahmed Abdulzhra CHIEF EL : Maitham Salah CHIEF Mech.: Ali Hameed