IRAQI DRILLING COMPANY DAILY REPORT

INTEGRATED MANGEMENT SYSTEM (IDCP08F4)

Daily Operation Report Date: 03-11-2019 Project: KEC Location: FIEHA FIELD Country : IRAQ
Rig: IDC45 Well No.: FH-5 ROW Conductor : RT - GL: 7.6 M Activity: WORKOVER Spud Date:
Obj:FISHING THE PERFORATING GUN Planned Depth: Planned Days: Report No.: 2 Start Of Moving Date : 28 /9 /2019 End Of Moving Date : 8 / 10 /2019
Days Of Acc : Day POB: 25
Depth MD (m) TVD (m) Bit current previous ID (in) OD (in) Lenght Total (m)
00:00 hrs Make (m)
18:00 hrs Serial #
24:00 hrs Run #
Meterage Diameter(in)
Lithology Top(m) Bottom(m) Model
Dibdibba
Nozzles (in)
L-faris
GHAR Mts Drilled
Dammam Oper. hrs
RUS IADC
UM RADHUMA
TAYARAT Depth in BHA
shiranish DULL Grading
SaDI Bit no.

24:00 PM situation WAITING ON DAYLIGHT


K.D

06:00 AM situation WAITING ON MAST LEG PAD INSPECTION T.D

Casing Depth (m) F.C (m) D.V (m) TVD (m) AngleClosure (m) Severity (deg/30m)
pre.
Current
Mud Type: Density In : g/cc Density Out: Temp. In : degC Formation Tests Material tons Stock
Sand : ECD : g/cm3 Ca= Temp. Out: degC EMW Test g/c Camp fuel(L)
Gel 0: Gel = API Cake: PP EMW g/cm3
600 / 300 = API Vol. Cm3 AV = Choride: mg/L FP EMW g/cm3
Viscosity = sec. PV YP = Water: Test Date
RIG FUEL : M³
pH = Fil Sand : Solids : oil :
Weight on Bit : ton. SPM1 = SPM2 = achievement ratio for workover OPS. : 100%
R.P.M =. Liner Size1:
Stand pipe Pressure = psi Liner Size2: Well Kill Drill Date: Time:
Torque: AMP Flow Rate: L/m Koomey: Manifold: psi Accumulator:psi Annular : psi
Wt. of string: Ton Annular Velocity: Rental Crane 30 TON Hrs
pump press. = psi
Rental Fork Lift 10 ton Hrs
Summary of Previous Day:
TIME H CODE Operations (03-11-2019)
00:00-06:00 6 WAITING ON DAYLIGHT
DUE TO ONGOING PROTESTING AND SENSITIVE NATURE OF ROAD CLOSURES ( RIG CREW , INSPECTION CREW , CRANE DRIVER) CANNOT REACH TO
06:00-16:00 10 23.1
FH#5
LOCATION SO THAT RIGGING UP OPERATION WAS SUSPENDED
16:00-24:00 8 WAITING ON DAYLIGHT

24
TIME H CODE Operations (04-11-2019) Components and Aux. Equipments

00:00-06:00 6 WAITING ON DAYLIGHT

Mud Engneeer BAHA YAQUB


Accumulate
Remaining M³ Item Received M³ Safety Coord. LOAY/
Quantity of M3
: INDS. WATER R.O water Medic MAHMOD
liquids in Mud
: BRINE industrial water 1st Crain Operator N/A
tanks
6 HI.VIS gas oil Forklift operator N/A
Day Summary : OPERATION SUSPENDE BECAUSE OF DEMONSTRATIONS
Forecast : MAST LEG PAD INSPECTION , CONT. RIGGING UP
Comments:
The Needed
PIPE FITTER ,Engineering Services Team TO COMPLETE CAMP RIG UP .
Supplies

Rig Manager : ABD ALHASSAN SWADI SITE ENGINEER : GHAZWAN NOMAS NIGHT PUSER : ALI SABEEH CHIEF EL: HABEB CHIEF Mech.: HAIDER HASHIM