You are on page 1of 34

Qatar Rail

/- Document Review Sheet (Engineer)


Company Management System

roo• t"""' .. , ... ,.. ~ , ,..,.. ,., _,. , ..,..., ...,,_..., uo~ 11 uo- -~.,, , ,.. .,..._,.. , """ , ,.. , .,....,, v o ,.., ,..,"""
BOR General
2017, the review will be done on the next submission
I ii INoted I Closed

I MOOS-GDB-ENG-CER- 1
DVE Design and Verification Cer1ificate (MOOS.GDB-ENG-
__ ..___ ·--REV 1) includes EIGHT cond~ions.
Therefore cannot be considered as Design Verification Certification.
I ' Discussions have been held between ORIPMC, JV, DVE, Areadis and
I
2 I IMC
00125 REV 1
1
1
ii Atkins on 27th March 2017. caveats will be removed as far as possible , Closed
- · · - · ·- certificate with t he submission without conditions CK but some will be rema ining on MSI and until the MEP design is issued..

None of the assumptions are required to be submrtted through the RFI


process as [Tunnel ventilation, Emergency power, Traction power.
same assumptions u the DD1 report (MOOS·GDB·ARC.RPT-
Vehicles, Emergency Management, Public address and CCTV] are all by
vvv913 Rev 1) are listed here. State which assumptions have now been
3 I IMC I
Page 12 of28
Section 1.6 I 1
1
confirmed through RFis or Workshops.
-·· · --, (Deta iled Design) submission and should not include
i
other contractors and largely a repetition of the ERs and NFPA; a single I
fire event is an industry norm and repeated in the ERs; protection against
terrorist acts is outside the ERs. Repeat of DD1 response.
Closed

or rely on future workshops.


The term "assumption" has been relaced by " basis of design''

All design is being be sed on a SIL-2 system and thus compliant w~ th e


_v'" " "' the Fire Detection System within the Switch Box Technical ER.
4 I IMC I
Page 21 of213
Section 5.1.1 I 1
1
Rooms will be designed and installed to SIL-2 as per the Employers
Requirements.
ii
Any discussion for an a ~em ativ e system will be conducted by the JV
I Closed

outside the design.

Include all life safety and cr~ica l systems (e.g. Signalling systems,
'Communication systems, Fare collections gates, Emergency lighting We note that the majority of items listed by the reviewer are already
5 I IMC I
Page 24 of28
Section 6 .4.2 I 1 system, Fire command centre, Em ergency mechanical ventilation
system, Fire fighting pumps, Fire fighting lifts, etc.), shall be connected
ii included. The switchbox does not contain fare collection gates. We do
not sea that the signalling system is relevant to this FLS report..
I Closed

the Emergency Power System. Comply with ER Vo16. 13.3.2 5.b.iv

lEADING EXCEllENCE j1M 203-FQ3 Rev. 50 .11/10/1&


Page 1 of 3
Qatar Rail
Document Review Sheet (Engineer)
"" ~J-J ~I Company Management System

lire extinguishers shall ba provided in such numbers, sizes and


Page 22 of 28 at such locations as determined by the authority having
6 IMC Confirmed in FLS report revision 2 section 5.6.2 Closed
Section 5.6.1 liurisciction in accordance w~h NFPA 130: 5.4.6 . Specify the proposal
the switch box to allow QCDD to approve.

the reference to "anomoly" and clearly state the design loading


trucks on the access road end on the herd standing to allow carrying capacity figures quoted in the report come st raight from
Page 23 of28
7 I IMC I Section 5.9.4
to approve. QCDD standards so must be assummed to be to their sat isfaction. The Closed
a DD2 (Detailed Design) submission and should not include reference to an anomoly has been removed.
!assumptions or rely on future workshops.

th at "Concrete is proposed for the sw~chbox walking


Page 15 of 28 Section has been updated. Refer to updated report and drawings now
8 I IMC I Section 3.1.2
1 M006-GDB-STR-DWG-YWSB010.1L- 53100 details
showing Steel.
Closed
t t LWUKI\ W ALKWAY PLAN for the Sw ~chbox.

9 SPO Section 1.5.3 and 1.54 2015 and QCS 2014 edition shall be mentioned here

reference standards mentioned hera shall be the latest e~ions


10 SPO Sect1on 1.5.5
k and update

letter reference "MOOB-GDB-ENG-LTR-00516" is not found 1n


11 SPO Sect1on 6 4.3

par OR Low Voltage (LV) Power Distribution System Gu1dehnes, the


>le-4 shall be modified:
12 SPO Sect1on 6 4.3 Emergency light1ng facilities shall be supplied from the Central
System
BACS shall be fed from UPS.

LEADING EXCELLENCE 11M 20H03 Rev 50. 11/10/16


Page2 of 3
~
Qatar Rail
Document Review Sheet (Engineer)
Company Management System

Report has been given a condit1onnal NOWC status with regards


Building (architecture and structure) only
13 BOR General
of MEP design are to be dealt wrth dunng MEP 002 and
DC2 submiSsions.

14 BOR General

C. SONO E. FaiVNot approved

SA 1·1 Manager N81lle:

FLS Engineer Position:

c Chevallller I MEP Manager

ft;l~
Eric

Saleek Poovakundll I E&M Elec. Engr


-
Signature: f;l'{m/) Signature: Signature:

Mourad Zouyene I SA 1·1 Manager


lain McLean I E&M Eng. Elec Date: Z4 AUG 2017 loate: I loate: I Z4 AUG 2017

LEADING EXCELLENCE l l M·W3·HJ.l Rev '> O. 31/10/!C. Page3 of3


ALYSJ
j o i n t vent u re

QATAR INTEGRATED RAIL PROJECT


Doha Metro: Gold Line
Bin Mahmoud Switchbox
Fire And Life Safety Report {002)
M006-GDB-ARC-RPT-00188

PREPARATION BY CONTRACTOR:
Action Name Signature Role Company Date

Originator Paul Curran $£,.. Discipline


Engineer
ATKINS 24-Apr-2017
Technical
Checker lan Johnson
-·- ~L-· Director
ATKINS 24-Apr-2017

~ 6Z./;7~ v
Reviewer Dionysios PP ( Engineering
ALYSJ-JV
Panagiotopoulos · - · Man"!g_er
Approval Carlo Germani Ji;~/ Project Director ALYSJ-JV ax-b-~ ~
/I"' f
ENGINEER'S ASSISTANT /
l\
,. \~~
Engineer's
Samuel Adair McChesney ~ Qatar Rail 4 AUG Z017
Assistant
STATUS ~
A B c \ D) E F
Approved "'---/
Fail/Not No Review
Approved w ith SONO NOWC
Approved Required
Comments

I Document Number: MOOG-GDB-ARC-RPT-00188 Rev 2 Page 1 of 29 24-Apr-2017


Uncontrolled if printed, refer to EDMS for current version
Right First Time, Every Time – Zero Defect

Revision History:
Rev. Date Description Originator Checked Reviewed Approved

1 13-Dec-2016 Issued for approval PCU IJO DPN CGE

2 24-Apr-2017 Issued for approval PCU IJO DPN CGE

Controlled Copy Issue Log: (Applicable only for hard copy as may be required outside of EDMS)

This hard copy document has been assigned as below and will be reissued automatically upon any future
revision.

Copy Company Name Representative

Document Number: M006-GDB-ARC-RPT-00188 Rev 2 Page 2 of 29 24-Apr-2017


Uncontrolled if printed, refer to EDMS for current version
Right First Time, Every Time – Zero Defect

CONTENTS

EXECUTIVE SUMMARY ...............................................................................................................................8


1 INTRODUCTION ...................................................................................................................................9
1.1 General Description 9
1.2 Scope 10
1.3 Authority Having Jurisdiction 11
1.4 Status of the JV contract documents 11
1.5 Applicable Codes and References 11
1.6 Basis for this fire and life safety report 12
2 OCCUPANCY CLASSIFICATION AND HAZARD OF CONTENTS ..................................................14
2.1 Occupancy classification 14
2.2 Hazard evaluation 14
3 FEATURES OF FIRE PROTECTION..................................................................................................15
3.1 Construction Materials 15
3.2 Compartmentation 16
3.3 External fire spread 17
3.4 Roof finish classification 17
3.5 Interior finish for floors, walls and ceilings 17
3.6 Fire Doors 17
4 MEANS OF EGRESS ..........................................................................................................................18
4.1 Evacuation scenarios: 18
4.2 Level of Exit Discharge (LED) 18
4.3 Means of escape underground 18
4.4 Means of escape components 19
4.5 Illumination of means of egress and emergency lighting 20
5 FIRE PROTECTION SYSTEMS ..........................................................................................................21
5.1 Fire detection and alarm system 21
5.2 Fire sprinkler system 21
5.3 Clean agent fire extinguishing systems 21
5.4 Standpipes 21
5.5 External hydrants (by others) 22
5.6 Portable fire extinguishers 22
5.7 Emergency ventilation system 22
5.8 Pressurization 22
5.9 Fire service access 22
6 BUILDING SERVICES ........................................................................................................................24
6.1 General: 24
6.2 Heating, ventilation and air-conditioning equipment 24
6.3 Wiring requirements 24
6.4 Emergency power 24
6.5 Fire command centre 25
6.6 Lifts 25
7 APPENDIX A - DRAWINGS ................................................................................................................27
CONCLUSION .............................................................................................................................................28

Document Number: M006-GDB-ARC-RPT-00188 Rev 2 Page 3 of 29 24-Apr-2017


Uncontrolled if printed, refer to EDMS for current version
Right First Time, Every Time – Zero Defect

TABLES
Table 1: Components Fire Rating ............................................................................................................. 15
Table 2: Fire ratings for specific rooms/areas .......................................................................................... 16
Table 3: Minimum NFPA dimensional criteria for exit stairwell ................................................................ 20
Table 4: Power supply .............................................................................................................................. 25
Table 5: Relevant drawings ...................................................................................................................... 27

FIGURES:
Figure 1: Location Plan ............................................................................................................................... 9
Figure 2: 3D massing................................................................................................................................ 10
Figure 3: Switchbox walkways .................................................................................................................. 18
Figure 4: Fire appliance highway turning radii [QCDFSS 4.1 Annex D] ................................................... 23

Document Number: M006-GDB-ARC-RPT-00188 Rev 2 Page 4 of 29 24-Apr-2017


Uncontrolled if printed, refer to EDMS for current version
Right First Time, Every Time – Zero Defect

ABBREVIATIONS

AHJ Authority Having Jurisdiction


CFD Computational Fluid Dynamics
ER Employer’s Requirements
ER 5-3.5 Qatar Integrated Railways Project, Volume 5 Employer’s Requirements –
Particular – Section 3.5 “Station Sizing” - (Stamped documents)
ER 6-10 Requirements, namely Qatar Integrated Railways Project, Volume 6
Employer’s Requirements – Design and Specifications - Section 10 “Fire
Protection and Life Safety Requirements” (Stamped documents)
ER 6-11 Requirements, namely Qatar Integrated Railways Project, Volume 6
Employer’s Requirements – Design and Specifications - Section 11
“Architectural design of stations and buildings” (Stamped documents)
ER 6-13 Requirements, namely Qatar Integrated Railways Project, Volume 6
Employer’s Requirements – Design and Specifications - Section 13
“Mechanical, Electrical, Plumbing (MEP) Specifications” (Stamped
documents)
FLS Fire and Life Safety
GL Gold Line
ICC Integrated Control Centre (Referred to as the Operational Control Centre by
NFPA 130)
JV Joint venture comprising Aktor S.A.-Larsen & Tourbo Limited-Yapi Merkezi
Insaat V.E.-Sezai Turkes Feyzi Akkaya Marine Construction-Al Jaber
Engineering LLC
LED Level of exit discharge
NFPA National Fire Protection Association
OCC Operational Control Centre
OTE Over Track Exhaust
TSEVS Tunnel and station emergency ventilation systems
TVS Tunnel ventilation system
TPS Traction Power Sub-Station (when within stations)
QCD Qatar Civil Defence
QCDFSS Qatar Civil Defence Fire Safety Standard

Document Number: M006-GDB-ARC-RPT-00188 Rev 2 Page 5 of 29 24-Apr-2017


Uncontrolled if printed, refer to EDMS for current version
Right First Time, Every Time – Zero Defect

DEFINITIONS

Term Definition
Point of safety A point of safety is one of the following: (1) an enclosed exit that leads to a
public way or safe location outside the station, trainway, or vehicle; (2) an at-
grade point beyond the vehicle, enclosing station, or trainway; (3) any other
approved location. [NFPA 130:3.3.35]
Point of safety A location that (a) is exterior to and away from a building; or (b) is within a
building of any construction type protected throughout by an approved
automatic sprinkler system and that is either (1) within an exit enclosure
meeting the requirements of this Code, or (2) within another portion of the
building that is separated by smoke barriers in accordance with Section 8.5
having a minimum 1 / 2 -hour fire resistance rating, and that portion of the
building has access to a means of escape or exit that conforms to the
requirements of this Code and does not necessitate return to the area of fire
involvement; or (c) is within a building of Type I, Type II(222), Type II(111),
Type III(211), Type IV, or Type V(111) construction (see 8.2.1.2) and is either
(1) within an exit enclosure meeting the requirements of this Code, or (2) within
another portion of the building that is separated by smoke barriers in
accordance with Section 8.5 having a minimum 1/ 2 -hour fire resistance rating,
and that portion of the building has access to a means of escape or exit that
conforms to the requirements of this Code and does not necessitate return to
the area of fire involvement. [NFPA 101:3.3.213 & Glossary of terms]
Place of A place where people are protected from the effects of fire and smoke [CIBSE
relative safety Guide E “Fire Safety Engineering”]
Exit That portion of a means of egress that is separated from all other spaces of a
building or structure by construction or equipment as required to provide a
protected way of travel to the exit discharge.
[NFPA 101:3.3.83 & Glossary of terms]

Exits include exterior exit doors, exit passageways, horizontal exits, exit stairs,
and exit ramps. In the case of a stairway, the exit includes the following:

(1) Stair enclosure


(2) Door to the stair enclosure
(3) Stairs and landings inside the enclosure
(4) Door from the stair enclosure to the outside or to the level of exit discharge
(5) Any exit passageway and its associated doors, if such are provided, so as to
discharge the stair directly to the outside. In the case of a door leading directly
from the street floor to the street or open air, the exit comprises only the door.
Exit Hallways, corridors, passages, or tunnels used as exit components and
passageway separated from other parts of the building in accordance with NFPA 101, Life
Safety Code. [NFPA 101:7.2.6 & Glossary of terms].
Exit access That portion of a means of egress that leads to an exit
[NFPA 101:3.3.84 & Glossary of terms]
Exit discharge That portion of a means of egress between the termination of an exit and a
public way. [NFPA 101:3.3.85 & Glossary of terms]

Document Number: M006-GDB-ARC-RPT-00188 Rev 2 Page 6 of 29 24-Apr-2017


Uncontrolled if printed, refer to EDMS for current version
Right First Time, Every Time – Zero Defect

Term Definition
Smoke barrier A continuous membrane, or a membrane with discontinuities created by
protected openings, where such membrane is designed and constructed to
restrict the movement of smoke. [NFPA 101:3.3.31.2 & Glossary of terms]
Smoke A continuous membrane that is designed to form a barrier to limit the transfer
partition of smoke [NFPA 101:3.3.256 & Glossary of terms]
Draft Stop A continuous membrane used to subdivide a concealed space to resist the
passage of smoke and heat [NFPA 5000:3.3.173 & Glossary of terms]
(Draft stopping materials shall be not less than 13 mm gypsum board, or other
approved materials adequately supported)

NOTE:
Images within this document are indicative for the purposes of fire safety and may not be an
accurate representation of the final layout.

Document Number: M006-GDB-ARC-RPT-00188 Rev 2 Page 7 of 29 24-Apr-2017


Uncontrolled if printed, refer to EDMS for current version
Right First Time, Every Time – Zero Defect

EXECUTIVE SUMMARY
The purpose of this report is to provide description of the Fire Protection and Life Safety
features to be adopted for the Gold Line Bin Mahmoud Switchbox.

The Gold Line comprises 13 stations, three switchboxes and a stabling yard. Fire and Life
Safety reports have been produced for each individual station, switchbox and the stabling
yard to support the architectural, structural, mechanical, electrical and public health
submissions; which this report should be read in conjunction with.

This submission addresses Fire Protection provisions and Means of Escape, together with
measures such as fire compartmentation, mode of protection (extinguishment),
standpipes, risers, call points etc.

All the Fire Safety protection provisions are designed to comply with NFPA 130:2014 and
the QCDD regulations prevailing at the date of this report, as well as all the latest editions
of the standards, codes and regulations in relation to the fire regulations in Qatar. No
waivers to the above requirements are needed for this switchbox and the design is
compliant with these fire and life safety standards.

This report is the DD2 stage continuation of the DD1 stage FLS report M006-GDB-ARC-
RPT-00098.

Document Number: M006-GDB-ARC-RPT-00188 Rev 2 Page 8 of 29 24-Apr-2017


Uncontrolled if printed, refer to EDMS for current version
Right First Time, Every Time – Zero Defect

1 INTRODUCTION
1.1 General Description

1.1.1 This report outlines the principles of the Fire and Life Safety design for the Bin
Mahmoud switchbox as part of the larger Gold Line Doha Metro contract.

1.1.2 The Bin Mahmoud switchbox shall be constructed using a cut and cover technique,
overall measures circa 197m long x 18-31m wide with the track circa 22m below
ground.

Bin Mahmoud Switchbox

Figure 1: Location Plan

1.1.3 The switchbox is located immediately to the east end of the Bin Mahmoud station box
and is a section of tunnel where a portion of the wall separating two trainways is omitted
so that trains can move from one track to the other. The switchbox is not normally
occupied except for planned maintenance. There is an emergency evacuation shaft
located centrally at the east end of the switchbox and access to the station platform
emergency egress system at the west end.

1.1.4 The grade level buildings have been addressed in the production of this report.

1.1.5 This report addresses the Bin Mahmoud switchbox only. Fire and life safety provisions
for separate switchboxes, tunnels, stations or other facilities are addressed by other
individual line or system wide reports.

1.1.6 Separate documents and reports have been prepared by the JV, or are the
responsibility of other parties, to address specific elements, such as:

i. Fire and life safety strategy (M006-GDB-ARC-RPT-00020)


ii. MEP Basis of design report: Electrical Services (M006-GDB-ELE-RPT-00001)
Document Number: M006-GDB-ARC-RPT-00188 Rev 2 Page 9 of 29 24-Apr-2017
Uncontrolled if printed, refer to EDMS for current version
Right First Time, Every Time – Zero Defect

iii. MEP Basis of design report: Mechanical Services (M006-GDB-MEP-RPT-


00002)
iv. Tunnel ventilation and smoke control systems (by Systems Contractor)
v. Public address and mass notification (by Systems Contractor)
vi. Communications and monitoring (by Systems Contractor)
vii. External road network and fire hydrant system (by others)

Figure 2: 3D massing

1.2 Scope

1.2.1 Included in this report

i. construction classification;

Document Number: M006-GDB-ARC-RPT-00188 Rev 2 Page 10 of 29 24-Apr-2017


Uncontrolled if printed, refer to EDMS for current version
Right First Time, Every Time – Zero Defect

ii. accessibility to fire apparatus;


iii. means of egress;
iv. compartmentalization;
v. exterior walls;
vi. roof covering;
vii. fire zoning;
viii. fire rating of building material and building structural elements;
ix. evacuation strategy;
x. occupancy types and density, and
xi. travel distances.

1.3 Authority Having Jurisdiction

1.3.1 The Authority Having Jurisdiction (AHJ) for this project is Qatar Civil Defence.

1.4 Status of the JV contract documents

1.4.1 Drawings listed in Volume 8 of the Employer’s Requirements are provided for
information only.

1.5 Applicable Codes and References

1.5.1 The principal codes and documents upon which the tunnels, switchboxes and stations
have been designed are listed below. Where the Employer’s Requirements do not
specify a particular edition of a code or standard then the most current is adopted.

1.5.2 The ER subsume the standards on which they are based, in the following order of
priority:

i. NFPA 130
ii. Qatar Civil Defence Fire Safety Standards (QCDFSS)
iii. Qatar Construction Standards (QCS)

1.5.3 Project specific documents:

i. Qatar Integrated Railways Project, Volume 5 Employer’s Requirements –


Particular – Section 3.5 “Station Sizing” - (Stamped document);
ii. Blue Line patronage figures as issued via M006-GDB-ARC-RFI-00008
iii. Qatar Integrated Railways Project, Volume 6 Employer’s Requirements –
Design and Specifications - Section 10 “Fire Protection and Life Safety
Requirements” – (Stamped document);
iv. NFPA 130 Standard for fixed Guideway Transit and Passenger Rail Systems,
2014 edition;
v. NFPA 101 Life Safety Code, 2015 edition;
vi. QCDFSH Qatar Civil Defence Fire Safety Handbook;
vii. QCDFSS Qatar Civil Defence Fire Safety Standards, 2008 edition; and
viii. Qatar Construction Specifications 2010 edition.

1.5.4 Qatar Civil Defence fire safety reference standards include:

i. QCDFSS 1.1 Basic Requirements, 23 September 2007 edition;

Document Number: M006-GDB-ARC-RPT-00188 Rev 2 Page 11 of 29 24-Apr-2017


Uncontrolled if printed, refer to EDMS for current version
Right First Time, Every Time – Zero Defect

ii. QCDFSS 2.10: Fire protection water supplies, 27 March 2008 edition;
iii. QCDFSS 6.2: Rising main for fire-fighting, 18 February 2008 edition;
iv. QCDFSS 4.1: External access to site and building, 18 February 2008; and
v. QCDFSS 8.2.3: Fire command centre, 17 September 2007.

1.5.5 NFPA reference standards include:

i. NFPA 10 Standards for Portable Fire Extinguishers 2013 edition;


ii. NFPA 13 Standard for the Installation of Sprinkler Systems 2013 edition;
iii. NFPA 14 Standard for the Installation of Standpipe and Hose Systems 2013
edition;
iv. NFPA 24 Standard for the Installation of Private Fire Service Mains and Their
Appurtenances 2013 edition;
v. NFPA 70 National Electrical Code 2014 edition;
vi. NFPA 72 National Fire Alarm Code 2013 edition;
vii. NFPA 80 Standard for Fire Doors and Other Opening Protectives 2013 edition;
viii. NFPA 90A Standard for the Installation of Air Conditioning and Ventilating
Systems 2015 edition;
ix. NFPA 105 Standard for the Installation of Smoke Door Assemblies and Other
Opening Protectives 2013 edition;
x. NFPA 110 Standard for Emergency and Standby Power Systems, 2013
edition;
xi. NFPA 170 Standard for Fire Safety and Emergency Symbols 2015 edition;
xii. NFPA 220 Standard on Types of Building Construction 2015 edition;
xiii. NFPA 251, Standard Methods of Tests of Fire Resistance of Building
Construction and Materials 2006 edition; and
xiv. NFPA 5000 Building Construction and Safety Code 2015 edition.

1.5.6 The lists above are not exhaustive. Standards such as the British Standards (BS),
European Standards (EN) and other internationally approved standards may be used
in specifying, detailing of structure, fire safety systems, materials and devices subject
to the approval of QCD.

1.6 Basis for this fire and life safety report


The following items form the basis for this fire and life safety report and they are based
upon the Employers Requirements:

1.6.1 The fire protection methods of ER 6:10.3.2.9, NFPA 130, NFPA 101, QCDFSS and the
design approach outlined in this report are based on the premise that there will be a
single fire event from a single fire source and that multiple simultaneous fire incidents
will not occur.

1.6.2 The fire safety strategy for the Bin Mahmoud switchbox, Bin Mahmoud station and
associated ancillary facilities is based on the prescriptive-based methods of the code
and includes client specific requirements noted within the documents listed in Section
1.5 above.

1.6.3 The rolling stock and traction units are not part of the JV’s contract, but the fire strategy
has been based on the premise that they will be constructed to meet the requirements
of EN 45545.

Document Number: M006-GDB-ARC-RPT-00188 Rev 2 Page 12 of 29 24-Apr-2017


Uncontrolled if printed, refer to EDMS for current version
Right First Time, Every Time – Zero Defect

1.6.4 Protection against certain terrorist acts will generally require protection methods
beyond those required by NFPA 130, NFPA 101 and are outside the scope of this fire
and life safety report.

1.6.5 Emergency management and operation procedures:

The authority that is responsible for the safe and efficient operation of the passenger
rail system shall anticipate and plan for emergencies that could involve the system.
This shall comply with NFPA 130 Chapter 9 and involve, as a minimum –

i. Developing operational procedures for the management of emergency


situations
ii. Actively involving participating agencies such as Civil Defence, Police,
Medical, and Utility Companies.
iii. Maintaining a operations control centre for the operation and supervision of
the system
iv. Maintaining a list of all participating agencies and personnel
v. Establishing a command post to supervise and co-ordinate during an
emergency
vi. Insuring that personnel from the authority and participating agencies have the
necessary training to function during an emergency.
vii. Maintaining written records and recordings.
viii. Insuring that traction power is removed and restored in a controlled and safe
manner.

The authority shall operate an Integrated Control Centre (ICC) for the operation and
supervision of the system in accordance with the requirements of NFPA 130: 9.6. It is
noted that the provision of the ICC falls outside the scope of the Gold Line JV.

1.6.6 Emergency communications [by others]

Blue light stations are required at locations dictated by NFPA 130: 6.4.2 to allow
emergency service and authorised personnel to communicate with the ICC and
disconnect traction power.

1.6.7 Closed circuit television (CCTV) [by others]

A closed circuit television system shall be installed to permit remote operators to


monitor activity during both normal and emergency events. The system shall be
controllable from both the ICC and the adjacent station control room. The system
circuits shall be protected from fire damage for a period of not less than 1 hour in
accordance with NFPA 130: chapter 12. It is noted that ER 6-10.4.7.5b-iii stipulates that
fire resistive halogen free cables be used rather than the alternative arrangements
permitted by NFPA such as encasement or diversity in routing. The CCTV coverage
shall include as a minimum:

i. Platform and concourse public areas,


ii. Escape routes including exits,
iii. In corridors adjoining technical rooms.
iv. In tunnel sections

Document Number: M006-GDB-ARC-RPT-00188 Rev 2 Page 13 of 29 24-Apr-2017


Uncontrolled if printed, refer to EDMS for current version
Right First Time, Every Time – Zero Defect

2 OCCUPANCY CLASSIFICATION AND HAZARD OF CONTENTS


2.1 Occupancy classification

2.1.1 Per the definition given by NFPA 130: 3.3.52.1 the switchbox is part of a “Automated
Fixed Guideway Transit System”. Namely an electrified transportation system, utilizing
a fixed guideway, operating on right-of-way for the mass movement of passengers
within a metropolitan area, and consisting of its fixed guideways, fully automated
driverless transit vehicles, and other rolling stock; power system; buildings;
maintenance facilities; stations; transit vehicle yard; and other stationary and movable
apparatus, equipment, appurtenances, and structures

2.2 Hazard evaluation

2.2.1 The switchbox presents the conditions found in most buildings and will be classified as
Ordinary Hazard with regard to life safety hazard evaluation, per NFPA 101: 6.2 and
ER 6-10.4.1.2. i.e. contents likely to burn with moderate rapidity or to give off a
considerable volume of smoke. This classification does not apply to the sprinkler
protection classification, NFPA 13, Standard for the installation of sprinkler systems.

Document Number: M006-GDB-ARC-RPT-00188 Rev 2 Page 14 of 29 24-Apr-2017


Uncontrolled if printed, refer to EDMS for current version
Right First Time, Every Time – Zero Defect

3 FEATURES OF FIRE PROTECTION


3.1 Construction Materials

3.1.1 The switchbox has been designed to be constructed in reinforced concrete using a cut
and cover method. The minimum type of construction stipulated by NFPA 130 for
perimeter walls and related construction is Type II non-combustible construction. The
Employer’s Requirements further stipulates this as Type II (222). The switchbox vertical
exit shaft and ventilation structure are required to achieve at least Type I (332) non-
combustible construction [NFPA 130: 6.2.2.5]. Reinforced concrete is proposed and
meets the Type I criteria.

3.1.2 Steelwork is proposed for the switchbox walking surfaces intended for evacuation of
passengers and meets the non-combustible criteria.

3.1.3 Within the switchbox, ancillary areas are separated from the trainway sections by a
minimum of 2 hour fire resistive construction.

3.1.4 Type I and Type II construction are those types in which the fire walls, structural
elements, walls, floors and roofs are of approved non-combustible or limited
combustible materials. The switchbox structural elements have been designed to be
constructed in reinforced concrete and this meets the Type I and Type II criteria. Table
2 below is extracted from NFPA 220 Table 4.1.1 and indicates the fire resistance rating
that components of Type I (332) and Type II (222) construction must achieve.

Table 1: Components Fire Rating


Fire resistance rating (hours)
Type of Construction Type I Type II
(332)1 (222)1
Components
Exterior bearing walls
Supporting more than one floor, columns or other bearing walls 3 2
Supporting one floor only 3 2
Supporting a roof only 3 1
Interior bearing walls
Supporting more than one floor, columns or other bearing walls 3 2
Supporting one floor only 2 2
Supporting a roof only 2 1
Columns
Supporting more than one floor, columns or other bearing walls 3 2
Supporting one floor only 2 2
Supporting a roof only 2 1
Beams, girders, trusses and arches
Supporting more than one floor, columns or other bearing walls 3 2

Document Number: M006-GDB-ARC-RPT-00188 Rev 2 Page 15 of 29 24-Apr-2017


Uncontrolled if printed, refer to EDMS for current version
Right First Time, Every Time – Zero Defect

Fire resistance rating (hours)


Type of Construction Type I Type II
(332)1 (222)1
Supporting one floor only 2 2
Supporting a roof only 2 1
Other
Floor – Ceiling assemblies 2 2
Roof – Ceiling assemblies 1.5 1

Note 1:  First Arabic numeral Exterior bearing walls

 Second Arabic numeral Columns, beams, girders, trusses and


arches, supporting bearing walls,
columns, or loads from more than one
floor

 Third Arabic numeral Floor construction

3.1.5 Fire windows in fire resistance-rated assemblies are restricted to those locations
permitted by NFPA 101: Table 8.3.4.2.

3.2 Compartmentation

3.2.1 Refer to the Fire and Life Safety Strategy [Fire Policy] drawings listed in Appendix A for
the location of fire resistance rated barriers and fire doors.

3.2.2 Compartmentation for the switchbox is summarized in Table 3 below and based upon
the Employer’s Requirements ER 6-10.5.2., NFPA 130 and NFPA 101.

3.2.3 Where one element supports another, the more onerous fire rating requirement has
been applied to the supporting structure.

Table 2: Fire ratings for specific rooms/areas

Element Fire resistance Fire door


rating (hours) assembly (hours)
Ventilation or exit shaft structure 3 N/A
Exit enclosure 2 1.5
Fireman’s lift enclosures 2 1.5
Fire-fighting lobbies 2 1.5

3.2.4 Underground structures (stations, egress shafts, vent shafts, etc,) are protected from
the accidental ingress of flammable and combustible liquids. This includes the
prohibition on any vent or fan shaft used for the ventilation of the underground station

Document Number: M006-GDB-ARC-RPT-00188 Rev 2 Page 16 of 29 24-Apr-2017


Uncontrolled if printed, refer to EDMS for current version
Right First Time, Every Time – Zero Defect

terminating at grade on any vehicle roadway and if terminating on a median or sidewalk


then complying with NFPA 130:5.2.3.

3.3 External fire spread

3.3.1 The grade level emergency shafts, ventilation shafts and other structures are presently
more than 6m from other buildings such that there is no requirement for non-load
bearing external walls to be fire rated.

3.3.2 The requirement that external finishes comply with QCD FSS 3.2 and NFPA 5000
Chapter 37 “Exterior Wall Construction” has been communicated to and co-ordinated
with the Branding Architect.

3.4 Roof finish classification

3.4.1 For construction Type I (332) & Type II (222) the required minimum roof-covering
classification is Class B [NFPA 5000: Table 38.2.2]. This has been communicated to
and co-ordinated with the Branding Architect for incorporation. The roof covering shall
be tested and is required to comply with one of the following:

i. NFPA 256, or other approved test methods;


ii. FM 4470, Approval for Class 1 Roof Covers;
iii. UL 790, Standard Test Methods for Fire Tests of Roof Covering; or
iv. ASTM E 108, Standard Test Methods for Fire Tests of Roof Coverings.

3.5 Interior finish for floors, walls and ceilings

3.5.1 Interior finish for walls, floor and ceilings comply with NFPA 101 Chapter 10 “Interior
Finish, contents and furnishings” and are non-combustible.

3.6 Fire Doors

3.6.1 Fire doors serving as opening protectives have a minimum fire protection rating as
specified in NFPA 101: Table 8.3.4.2 and part repeated in Table 3 herein.

3.6.2 Fire door assemblies shall be installed in accordance with NFPA 80 and shall be self
closing or automatic closing in accordance with NFPA 101: 7.2.1.8.

3.6.3 Fire windows in fire resistance-rated assemblies are restricted to those locations
permitted by NFPA 101: Table 8.3.4.2 and shall be required to comply with NFPA 251.

Document Number: M006-GDB-ARC-RPT-00188 Rev 2 Page 17 of 29 24-Apr-2017


Uncontrolled if printed, refer to EDMS for current version
Right First Time, Every Time – Zero Defect

4 MEANS OF EGRESS
4.1 Evacuation scenarios:

4.1.1 In the event of a fire within the tunnel or switchbox the intent is for the train to continue
to the next station where passengers may evacuate via the exit system within the
station.

4.1.2 If a train is halted within the switchbox or tunnel due to a fire it is understood that the
emergency smoke control system shall operate so that occupants may evacuate in the
direction of the fresh air along the walkway and then evacuate via either the exit system
within the station or the exit system in the switchbox or tunnel.

4.2 Level of Exit Discharge (LED)

4.2.1 The level of exit discharge for the switchbox is external ground level.

4.3 Means of escape underground

4.3.1 The switchbox incorporates a walkway on one side of each trainway so that occupants
may evacuate to the nearest exit system. The walkway provides an unobstructed clear
space of at least 800mm width at the walking surface and corresponds with the NFPA
130: 6.3.2.1 requirements above that plane per ER 6-10.5.1.1 i), i.e. 610mm at the
walking surface, graduating to 760mm wide at 1575mm above the walking surface to
430mm wide at 2025mm above the walking surface.

Figure 3: Switchbox walkways

4.3.2 If a train is halted within the Bin Mahmoud station, switchbox or adjacent tunnel due to
a fire it is understood that the emergency smoke control system shall operate so that
occupants may evacuate in the direction of the fresh air along the walkway and then
evacuate using an emergency exit shaft.

4.3.3 The location of the train when it stops, the nature of the incident (e.g. whether it is a
derailment or fire and where it originates) will in part influence the ICC directed tunnel
ventilation response and hence whether passengers evacuate to the switchbox escape
shaft, Bin Mahmoud station escape shaft or cross passages east of the switchbox and
hence Al Sadd Station

Document Number: M006-GDB-ARC-RPT-00188 Rev 2 Page 18 of 29 24-Apr-2017


Uncontrolled if printed, refer to EDMS for current version
Right First Time, Every Time – Zero Defect

4.3.4 Evacuation of a train is based on the premise that occupants of a 60m long 3 car section
may move up or down within it and access to the walkway is controlled by the ICC to a
single door. Qatar Rail have confirmed that occupants cannot move between two 60m
long trains.

4.3.5 Raised walkways are provided with a continuous handrail on the side opposite the
trainway. The handrail does not project more than 114mm into the clear zone stipulated
by the Employer’s Requirement ER 6-10:5.1.1 i).

4.3.6 While the trainway is more than 760mm below the walkway a guarding is not required
along the open edge as the bottom of the trainway is closed with a deck (NFPA 130:
6.3.3.6).

4.3.7 In the switchbox the raised walkways connect with the track level crosswalk with steps.
The crosswalks are provided at track level to ensure walkway continuity and provide a
uniform walking surface at the top of the rail.

4.3.8 The switchbox fire-fighting stair and fire-fighting lift shaft are separated from the
trainway by a fire-fighting lobby.

4.3.9 The fire-fighting stairwell, fire-fighting lift and lift lobby are all pressurized.

4.3.10 The fire-fighting lobby at track level measures 9m2 in area with a minimum dimension
of 2.7m and so is compliant with the minimum dimensions set out by QCDFSS 2.2.13
of not less than 6m2 in area and 2m in either dimension. Thus the lobby is large enough
to accommodate a wheelchair refuge, fire-fighting equipment and passengers escaping

4.3.11 The exit stair shaft from track level to transfer level, linking exit passage way at transfer
level and exit stair shaft from transfer level to grade is protected as required for exits.
This includes but is not limited to –

i. minimum 2 hour fire rated enclosure with 90 minute self-closing fire doors;
ii. only contain equipment necessary for life safety within the exit; and
iii. do not open directly into any normally unoccupied space, i.e. are lobbied from
lift shafts, technical shafts and technical rooms.

4.3.12 Employer’s Requirements stipulate that the fire-fighting stairwell be provided with air
conditioning during evacuation. This requirement is achieved without compromising
NFPA requirements for the protection of exit enclosures [NFPA 101: 7.1.3.2.1].

4.3.13 The utility chase (Level -5) below the transfer corridor (level -4) is normally unoccupied,
secured from unauthorized access and used exclusively for the routing of electrical,
mechanical, or plumbing equipment. Hence the space is not subject to the provisions
of chapter 7 (Means of Egress) of NFPA 101.

4.4 Means of escape components

4.4.1 A exit door clear width of 820mm is provided between the tunnel walkway and fire-
fighting lobby, fire-fighting lobby and exit stairwell, and this exceeds both NFPA 130
and ER requirements of 810mm The doors open in the direction of escape, i.e. into the
lobby and into the stairwell at tunnel level and in the opposite direction at street level

Document Number: M006-GDB-ARC-RPT-00188 Rev 2 Page 19 of 29 24-Apr-2017


Uncontrolled if printed, refer to EDMS for current version
Right First Time, Every Time – Zero Defect

4.4.2 While noting that NFPA 130 does not require the fire-fighting stair to be any wider than
1120mm, a width of circa 1175mm is proposed, excluding a 114mm allowance for
handrails on each side.

4.4.3 Minimum dimensional criteria for the switchbox exit stairs are as follows:

Table 3: Minimum NFPA dimensional criteria for exit stairwell


Stair Component Dimensional Criteria
Stair width 1120mm (1175mm egress width proposed)
Maximum height of risers 180mm maximum
Minimum tread depth 280mm
Minimum headroom 2285mm minimum
Maximum height between landings 3660 mm

4.5 Illumination of means of egress and emergency lighting

4.5.1 As a minimum the lighting and emergency lighting systems comply with the
requirements of NFPA 101 sections 7.8 and 7.9, except as modified by NFPA 130 and
the Employer’s Requirements -

i. Exit lights, essential signs and emergency lights are included in the emergency
lighting system in accordance with NFPA 70;
ii. emergency fixtures, exit lights, and signs are wired separately from emergency
distribution panel;
iii. lighting system is designed so that, during a period of evacuation, illumination
levels of trainway walkways and walking surfaces shall not be less than 2.7 lx
measured along the path of egress at the walking surface;
iv. the emergency lighting system in the trainway produce illumination on the
walkway that does not exceed a uniformity ratio of 10:1 for the maximum
maintained horizontal illuminance to the minimum maintained horizontal
illuminance;
v. point illumination of means of egress elements are permitted to exceed the
10:1 uniformity ratio; and
vi. dynamic signs indicating the direction and distance to the nearest safe
emergency exit are provided at 25m centres along the walkway.

Document Number: M006-GDB-ARC-RPT-00188 Rev 2 Page 20 of 29 24-Apr-2017


Uncontrolled if printed, refer to EDMS for current version
Right First Time, Every Time – Zero Defect

5 FIRE PROTECTION SYSTEMS


5.1 Fire detection and alarm system

5.1.1 Whilst not required by NFPA 130 the tunnel trainway and technical rooms located within
the switchbox are provided with automatic fire detection as mandated by the
Employer’s Requirements.

The tunnel trainway and the switchbox fire detection system is provided and designed
by others (Railway Systems Contractor) except in the switchbox technical rooms where
the fire detection system is provided and designed by the JV contractor.

The fire detection and alarm system will interface with ICC/Rail SCADA via BACS

5.2 Fire sprinkler system

5.2.1 As per NFPA 130 and the Employer’s requirements an automatic sprinkler protection
system is not provided in the tunnel trainway.

5.3 Clean agent fire extinguishing systems

5.3.1 Electrical rooms within the switchbox and at grade, where the presence of water is not
desirable, are protected with clean agent fire extinguishing systems designed, installed
and maintained in compliance with NFPA 2001 [per ER 6-10:4.7.3-bi]. The fire
suppression system is operated automatically by a QCD approved fire detection
system. It is noted that QCDFSS 6.8 does not permit the use of Carbon Dioxide for fire
suppression or the storage of the clean agent within the protected enclosure.

5.3.2 The TPS room between Bin Mahmoud station and switchbox and the electrical rooms
at grade are protected with a clean agent fire extinguishing system.

5.4 Standpipes

5.4.1 A Class I standpipe system, wet pipe, is provided within the switchbox as required by
NFPA 130 and ER 6-10.5.5.2.c. The system shall be installed in accordance with NFPA
14 [per ER 6-10.5.5.2.c.ii] and ER 6-13.2.14.6.

5.4.2 Water breaching inlets to the system to permit QCD to supply additional water are
provided at fire service access points at grade per QCD standards including QCDFSS
6.2:5.0 and within 18m of the adjacent fire appliance access road.

5.4.3 The initial supply of water for the sprinkler and standpipe system is from storage tanks
located in the adjoining stations and be of adequate supply for at least one hour,
including supply to the adjacent tunnel system. The tanks comply with QCDFSS 2.10.

5.4.4 Within the tunnel the standpipe system is not enclosed in fire-rated construction as the
system is fed from two locations and isolation valves are installed not more than 244m
apart.

5.4.5 The fire standpipe system complies with and be approved by QCD (QCDFSS 1.1, 6.1,
6.2).

Document Number: M006-GDB-ARC-RPT-00188 Rev 2 Page 21 of 29 24-Apr-2017


Uncontrolled if printed, refer to EDMS for current version
Right First Time, Every Time – Zero Defect

5.5 External hydrants (by others)

5.5.1 NFPA 14 requires that a hydrant be provided within 30.5m (100ft) of the fire department
breeching inlet such that it is readily accessible by emergency services and can be
used to supply water to the underground standpipe systems. The provision of fire
hydrants falls under the landscaping and roadside improvements being undertaken by
Ashghal. The provision of fire hydrants will be raised as part of the interface with the
Ashghal works. It is noted that NFPA 14 permits the distance between breeching inlet
and hydrant to exceed 30.5m with the approval of the AHJ.

5.6 Portable fire extinguishers

5.6.1 Portable fire extinguishers shall be provided in such numbers, sizes and types and at
such locations as determined by the authority having jurisdiction in accordance with
NFPA 130: 6.4.5. At this time it is not proposed to provide portable fire extinguishers
within the operational trainways.

5.6.2 Both CO2 and ABC type portable fire extinguishers shall be provided for the sub-surface
and at grade technical areas such that they are within 15m of all areas, or as otherwise
required by the authority having jurisdiction in accordance with NFPA 130: 6.4.5.

5.7 Emergency ventilation system

5.7.1 The tunnel emergency ventilation system [by others] does not form part of this report
and shall be developed and submitted in due course by the Systems Contractor. This
submission should include fire scenarios involving a train on fire stopping in the tunnel
and a train stopping in the tunnel due to another emergency in the tunnel.

5.8 Pressurization

5.8.1 The switchbox stairwell, lift shaft and lobbies and are protected from the ingress of
smoke as follows [ER 6-10.4.6.3d-v & ER 6-13.2.6.6 b)]:

 Stair case & lift shaft are pressurized with relief @ 50 Pa pressure difference.
 Fire lobbies and pressurized corridors are pressurized with relief @ 25 Pa
pressure difference.

5.9 Fire service access

5.9.1 Access to the switchbox for the fire and rescue service is available via both the station
and switchbox escape shafts. Each escape shaft incorporates a fire-fighting lift and
pressurized stairwell. Access at street level incorporates a separate entrance for fire
service personnel to access the fire-fighting lift without being hindered by exiting
patrons. Vehicular access routes for Civil Defence appliances is by either public road
or service road and extends to within 10m of the access points to the emergency shaft
entrances.

5.9.2 Fire service vehicle access routes are a minimum of 6m wide, have an unobstructed
vertical clearance of 4.5m, accommodate two way traffic and be capable of
accommodating the stationary load from a 24 tonne fire appliance.

Document Number: M006-GDB-ARC-RPT-00188 Rev 2 Page 22 of 29 24-Apr-2017


Uncontrolled if printed, refer to EDMS for current version
Right First Time, Every Time – Zero Defect

5.9.3 Access routes for the emergency services are such that dead end roads occur; hence
turning areas are provided.

5.9.4 The fire appliance hard standing are within 10m of the building entry points, measure
at least 6m x 15m and are capable of accommodating the stationary load from a 45
tonne fire appliance. In addition, the hard standing is within 45m of every point on the
projected plan area of each building at ground level and within 50m of a fire hydrant.

5.9.5 Vehicle access route turning radii, internal and external, comply with QCDFSS 4.1,
refer to extract from Annex D below.

Figure 4: Fire appliance highway turning radii [QCDFSS 4.1 Annex D]


(Figure relates to turning radii not road widths)

5.9.6 At the time of writing the structures above grade are predominantly single storey. As
the design evolves these structures shall be evaluated in terms of compliance with
QCDFSS in terms of providing access panels along the perimeter.

5.9.7 The area between the switchbox emergency exit at grade and the public road has been
designed as a open and unrestrained space. A 400m2 area has been safeguarded for
the emergency services to use and may be used as a muster area to facilitate
passengers being bussed away but it is not intended that passengers be restricted or
prevented from dispersing themselves.

5.9.8 Interface meetings shall be held with Ashghal to discuss and agree responsibility for
roads and lay-bys.

Document Number: M006-GDB-ARC-RPT-00188 Rev 2 Page 23 of 29 24-Apr-2017


Uncontrolled if printed, refer to EDMS for current version
Right First Time, Every Time – Zero Defect

6 BUILDING SERVICES
6.1 General:

6.1.1 Specifications for general building services and utilities are included in other
documents. Specific and/or additional requirements for building services and utilities
resulting from fire and life safety provisions are included in the sections below.

6.2 Heating, ventilation and air-conditioning equipment

6.2.1 Heating ventilation ductwork and related equipment is in accordance with NFPA 90A.

6.3 Wiring requirements

6.3.1 All wiring materials and installations within the station other than those for traction
power conform to the requirements of NFPA 70 and in addition satisfy the requirements
of NFPA 130: chapter 12.

6.3.2 Fire resistive cables are listed and have a minimum 1 hour fire resistive rating in
accordance with ANSI/UL 2196 and be installed per the listing requirements. It is
understood that the ER 6- 10.3.2.14 statement that cables be non-combustible is a
typing mistake and that ER 6-10.4.4.4. takes precedence.

6.4 Emergency power

6.4.1 Emergency power is provided in accordance with Article 700 of NFPA 70 and Chapter
4 of NFPA 110. The supply system for emergency purposes, in addition to the normal
services to the station building, is one or more of the types of systems described in
subsections 700.12(A) through 700.12(E) of NFPA 70. All cabling is fire resistive per
6.3.2 above.

6.4.2 The following emergency systems are connected to the emergency power supply:

i. fire detection and alarm system (BY ALYSA JV and others);


ii. emergency lighting and signage systems;
iii. emergency communication system; (by others)
iv. public address system (by others);
v. Incident command centre (by others);
vi. the stairwell, lobby and lift pressurization system within the escape shaft;
vii. fire-fighting lift
viii. escalators (in stations);
ix. the Building Automation Control System (BACS) (also called the Building
Management System (BMS));
x. tunnel ventilation system (by others);
xi. fire protection systems
xii. UPS and relevant sub-circuits

6.4.3 Per Qatar Rail letter M006-GDB-ENG-LTR-00516 (Low voltage power distribution
system guidelines) the power supply for various systems shall be as follows:

Document Number: M006-GDB-ARC-RPT-00188 Rev 2 Page 24 of 29 24-Apr-2017


Uncontrolled if printed, refer to EDMS for current version
Right First Time, Every Time – Zero Defect

Table 4: Power supply

Item Normal Life Central UPS By


power Safety Battery others
supply System (MSI)
Emergency lighting facilities for Yes
means of escape (escape route
luminaires) and signage
Fire pump (i.e. in stations) Yes
Fire-fighting lift within Al Sharq EE Yes
shaft
Smoke management systems Yes
(stairwell, lift lobby and lift shaft
pressurization fan) within Al Sharq
EE shaft
Fire detection and alarm system Yes
Clean Agent Yes
Building Automation Control Yes
System
Smoke management systems in the Yes
tunnels
Emergency communication system Yes

6.5 Fire command centre

6.5.1 The station control room in Bin Mahmoud Station fulfils the role of a fire command
centre and is designed in accordance with NFPA 72 and the relevant Qatar standards
QCDFSS 8.2.3. The room is enclosed in 2 hour rated construction, approached via a 2
hour protected corridor from the fire-fighting staircase and is protected from the ingress
of smoke (ER 6-10.4.7.5a i-iii, ER 6-10.8.5.8 and ER6-11.4.6.4).

6.6 Lifts

6.6.1 The switchbox box evacuation shaft contains a staggered lift arrangement for
emergency services access and the evacuation of injured or disabled persons.
Consequently the design of each lift complies with the requirements of QCDFSS 6.6.3
per ER 6-10.5.1.3.b.j and section 54 of NFPA 5000 as this is now directed by Civil
Defence.

Fire fighter lift requirements include:

 enclosure within a fire rated protected shaft;


 provision of a fire-fighting lobby within a fire rated enclosure at each level;
 pressurization of the fire-fighting lobby to prevent smoke ingress;
 equipment for the fire services to take control of the Lift;
 protection of the power supply;
 they shall not be used primarily as goods Lifts (QCDFSS 6.6.3 – 5); and
 be large enough to accommodate a 610mm x 2030mm ambulance stretcher with
minimum 125mm radius corners (NFPA 5000, Chapter 54) in the horizontal open
position.

Document Number: M006-GDB-ARC-RPT-00188 Rev 2 Page 25 of 29 24-Apr-2017


Uncontrolled if printed, refer to EDMS for current version
Right First Time, Every Time – Zero Defect

The lift lobbies and transfer corridor (exit passageway) can accommodate the turning
movements required by a 610mm x 2030mm ambulance stretcher.

Document Number: M006-GDB-ARC-RPT-00188 Rev 2 Page 26 of 29 24-Apr-2017


Uncontrolled if printed, refer to EDMS for current version
Right First Time, Every Time – Zero Defect

7 APPENDIX A - DRAWINGS
The following drawings have been produced to accompany this report:
Discipline: Architecture
Location: Bin Mahmoud switchbox
Title: Fire Policy Drawings

Table 5: Relevant drawings


Level
code Number Model or drawing title Scale
M006-GDB-ARC-DWG-YCAGAAA
AA 25251 ARCHITECTURAL SYMBOLS

M006-GDB-ARC-DWG-YWSB010
AG 32340 Ground level Fire policy 1-100
IL 32341 Intermediate level Fire policy 1-100
ZZ 32342 Intermediate, Track & Undertrack Fire policy 1-100
ZZ 32343 Longitudinal section Fire policy 1-100

Document Number: M006-GDB-ARC-RPT-00188 Rev 2 Page 27 of 29 24-Apr-2017


Uncontrolled if printed, refer to EDMS for current version
Right First Time, Every Time – Zero Defect

CONCLUSION
This Fire Life Safety Report addresses the FLS requirements for Bin Mahmoud switchbox.
The station design complies with the requirements of NFPA 130:2014 and QCDD and no
waivers are required for fire and life safety compliance.

Document Number: M006-GDB-ARC-RPT-00188 Rev 2 Page 28 of 29 24-Apr-2017


Uncontrolled if printed, refer to EDMS for current version
Right First Time, Every Time – Zero Defect

END OF REPORT

Document Number: M006-GDB-ARC-RPT-00188 Rev 2 Page 29 of 29 24-Apr-2017


Uncontrolled if printed, refer to EDMS for current version
Qatar Rail
......... Document Review Sheet (Engineer)
RA I L ...J---,J _,J I Company M anagement System
~

BOR I General I 3 r.;-_,-_:_ ;:.:..: :: ~:.--·: ---- ·- -~:·.- - ...... ---- ----------· :-.. :.. -.__.. -· I ii

Interim DVE Design and Verification Certificate (M006-GDB-


~ .. -.;-CER-00125 REV 1) includes EIGHT conditions.
I Discussions have been held between QRIPMC, JV, DVE, Arcadis
and Atkins on 27th March 2017. caveats will be removed as far as
possible, but some will be remaining on MSI and until the MEP
2 I IMC
I M006-GDB-ENG-CER-~ 1 'Therefore cannot be considered as Design Verification Certification.
00125 REV 1 ii design is issued ..
Provide DVE c ertificate w it h the submission without
conditions or assumptions.

None of the assumptions are required to be submitted through the


RFI process as [Tunnel ventilation, Emergency power, Traction
The same assumptions as the DD1 report (M006-GDB-ARC-RPT- power, Vehicles, Emergency Management, Public address and
ooog8 Rev 1) are listed here. State which assumptions have now CCTV] are all by other contractors and largely a repetition of the ERs
Page 12 of 28
3 I IMC I Section 1.6 I 1
1
been confinned through RFis or Workshops.
This is a DD2 (Detailed Design) submission and should not include
i and NFPA; a single fire event is an industry nonn and repeated in th
ERs; protection against terrorist acts is outside the ERs. Repeat of
assumptions or rely on future workshops. 001 response.

The term "assumption" has been relaced by "basis of design"

All design is being based on a SIL-2 system and thus compliant with
'Confirm the Fire Detection System within the Switch Box Technical I l theER
Page 21 of 28
4 I IMC I Section 5.1 .1 I 1 Rooms will be designed and installed to SIL-2 as per the Employers
Requirements. Any discussion for an alternative system will be conducted by the JV
outside the design.

Include all life safety and critical systems (e.g. Signalling systems,
Communication systems, Fare collections gates, Emergency I I
We note that the majority of items listed by the reviewer are already
5 I IMC I
Page 24 of 28
Section 6.4.2 I 1
I
lighting system, Fire command centre, Emergency mechanical
ventilation system, Fire fighting pumps, Fire fighting lifts, etc.), shall
nnected to the Emergency Power System. Comply with ER
ii included. The switch box does not contain fare collection gates. We
do not see that the signalling system is relevant to this FLS report.
13.3.2.5.b.iv

fire extinguishers shall be provided in such numbers, sizes


Page 22 of 28 and types and at such locations as detennined by the authority
6 IMC Confinned in FLS report revision 2 section 5.6.2
Section 5.6. 1 having jurisdiction in accordance with NFPA 130: 5.4.6. Specify the
proposalforthesv·"·• • - .. •- ·"- ~~~~·- -- -- ---
-· ~·

LEADING EXCELLENCE I TM-203 -F03 Rev. >.0, 31/10/16 Page 1 of 2


Qatar Rail
\
'1 Document Review Sheet (Engineer)
RAILJ...-l.rJI Company Management System
..
A

Remove the reference to "anomoly" and clearly state the design


loading for fire trucks on the access road and on the hard standing carrying capacity figures quoted in the report come straight from
Page 23 of 28
7 IMC to allow QCDD to approve. standards so must be assummed to be to their satisfaction.
Section 5.9.4
is is a DD2 (Detailed Design) submission and should not include reference to an anamoly has been removed.
assumptions or rely on future workshops.

Clause states that "Concrete is proposed for the switchbox walking


Page 15 of 28 has been updated. Refer to updated report and drawings
8 IMC surfaces". Drawing M006-GDB-STR-DWG-YWSB010-IL-53100
Section 3.1. 2 now showing Steel.
details the STEELWORK WALKWAY PLAN for the Switch box.

c. SONO E. FaiVNot approved


Document Review Status Code: D

ourad Zouyene SA 1-1 Mngr Samuel Adair McChesney

Benjamin O'Regan FLS Engineer Engineer's Assistant

James Quinlan Arch Fin Mngr

Kerry Jothy Architect

Mousa D Abulhawa HVAC/MEP Manager

lain Mclean E&M Elec. Engr I Date: I I Date : Date: Date:

LEADING EXCEllENCE 11M 203-FO~ Ro>v ~ 0. ll/10/16 Page 2 of 2

You might also like