Professional Documents
Culture Documents
A. Site Quality Plans
A. Site Quality Plans
2.1.1 1. WPS
2.1.3 3. Drawings
2.4 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
2.6 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
2.7 Front release Critical Measurements Water level,tape,dumpy level 100% Tech specification/Drawings Tech specification/Drawings Front release report. S EF
2.8 Check that surface is clean and dressed Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
3.1 Check tht the dimention,oriantation is as per drawing. Major Measurements Water level,tape,dumpy level 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
3.2 Check centre line marking on foundation Major Measurements Water level,tape,dumpy level 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
3.4 Check depth of sump Major Visual/Mesurement Water level,tape,dumpy level 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
3.7 Setting of foundation bolts Critical Visual/Mesurement Water level,tape,dumpy level 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
3.8 Check filling condition of mortar Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
3.9 Grouting Critical Visual/Mesurement Water level,tape,dumpy level 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
4.4 Final grouting of base frame Critical Visual/Mesurement Water level,tape,dumpy level 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
4.7 Fit up inspection Major Measurements Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
4.8 Dimention and alingment of piping Major Measurements Water level,tape,dumpy level 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
4.9 Final weld inspection Major Measurements Weld gauge/Template Random WPS/Drawing WPS/Drawing/ASME/ANSI/API/AWS/DIN/IBR/IS/BS S E
6.1 Final Inspection Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Coat meter or
7.1 Painting thikness and shade Major Measurements Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Elcometer
7.1 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.1.3 3. Drawings
2.4 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
Check for cleanliness of EOT equpments before Outer and inner surfaces to be free from
2.5 Major Verification Nil 100% Nil ITSR S E
erection. dust and sticking dirts.
2.7 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
Measurement
3.2 Final weld inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing/ASME/ANSI/API/AWS/DIN/IBR/IS/BS WISR S E
s
Gantry rails
5.1 check for LT wheel free movement on gantry rail. Major Visual NIL 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
Crab assembly
DSL erection
Safe travel with full load( long travel and cross Measurement
7.8 Critical NIL 100% Tech specification/Drawings Tech specification/Drawings EOT inspection report S EF
travel ) s
Measurement
7.9 Abnormal sound or vibration Critical NIL 100% Tech specification/Drawings No abnormal sound or vibration during test ITSR S EF
s
8.1 Final Inspection Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
10 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.1.3 3. Drawings
RT/Mechanic
2.3 Welder Qualification Test Critical Lab Test 100% Standard WPS/ASME Sec IX. ASME Sec IX. Welder Qualification record and welder's
S EFID.
al test
2.4 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
2.7 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
3.1 Check that surface is clean and dressed Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
Measurement
4.1 Dimention and levelling Major Water level,tape 100% Tech specification/Drawings Tech specification/Drawings SIR S E
s
4.2 Develop welding sequence Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings WISR S EF
Measurement
4.3 Fit up inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
s
Every day
Backing oven with temp
4.4 Check for the baking of electrodes (if applicable) Major Verification before start of WPS/Electrode manufatures recomandations
WPS/Electrode manufatures recomandations Backing registar S E
recorder
welding
Measurement Thermal chalk /thermo
4.5 Pre Heating Major As per WPS WPS WPS Heat treatment chart S E
s couple
4.6 Weld root penetration Minor Visual NIL 100% WPS/Drawing WPS/Drawing WISR S S
4.7 Inter pass cleaning Minor Visual NIL 100% WPS/Drawing WPS/Drawing WISR S S
5.1 Check installation of all internals Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings SIR S E
7.1 Check free sliding of base plate. Major Visual NIL 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
Measurement
8.1 Welding dearator with FWST Major Weld gauge/Template Random WPS/Drawing WPS/Drawing/ASME/ANSI/API/AWS/DIN/IBR/IS/BS WISR S E
s
Measurement
8.2 NDT on welding Critical NDT report S EF
s
9.1 Final Inspection Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
11 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.1.3 3. Drawings
RT/Mechanic
2.3 Welder Qualification Test Critical Lab Test 100% Standard WPS/ASME Sec IX. ASME Sec IX. Welder Qualification record and welder's
S EFID.
al test
2.4 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
2.6 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
3.1 Check that surface is clean and dressed Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
3.5 Develop welding sequence Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings WISR S EF
3.6 Check free sliding of base plate. Major Visual NIL 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
Measurement
3.7 Fit up inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
s
Measurement
3.8 Final weld inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing/ASME/ANSI/API/AWS/DIN/IBR/IS/BS WISR S E
s
Measurement
3.9 NDT on welding Critical NDT report S EF
s
4.1 Final Inspection Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
5 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.1.3 3. Drawings
RT/Mechanic
2.3 Welder Qualification Test Critical Lab Test 100% Standard WPS/ASME Sec IX. ASME Sec IX. Welder Qualification record and welder's
S EFID.
al test
2.4 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
2.7 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
3.1 Develop welding sequence Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings WISR S EF
Measurement
3.2 Fit up inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
s
Every day
Backing oven with temp
3.3 Check for the baking of electrodes (if applicable) Major Verification before start of WPS/Electrode manufatures recomandations
WPS/Electrode manufatures recomandations Backing registar S E
recorder
welding
Measurement Thermal chalk /thermo
3.4 Pre Heating Major As per WPS WPS WPS Heat treatment chart S E
s couple
3.5 Weld root penetration Minor Visual NIL 100% WPS/Drawing WPS/Drawing WISR S S
3.6 Inter pass cleaning Minor Visual NIL 100% WPS/Drawing WPS/Drawing WISR S S
4.1 Develop welding sequence Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings WISR S EF
Measurement
4.2 Fit up inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
s
Every day
Backing oven with temp
4.3 Check for the baking of electrodes (if applicable) Major Verification before start of WPS/Electrode manufatures recomandations
WPS/Electrode manufatures recomandations Backing registar S E
recorder
welding
4.5 Weld root penetration Minor Visual NIL 100% WPS/Drawing WPS/Drawing WISR S S
4.6 Inter pass cleaning Minor Visual NIL 100% WPS/Drawing WPS/Drawing WISR S S
5.1 Develop welding sequence Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings WISR S EF
Measurement
5.2 Fit up inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
s
Every day
Backing oven with temp
5.3 Check for the baking of electrodes (if applicable) Major Verification before start of WPS/Electrode manufatures recomandations
WPS/Electrode manufatures recomandations Backing registar S E
recorder
welding
Measurement Thermal chalk /thermo
5.4 Pre Heating Major As per WPS WPS WPS Heat treatment chart S E
s couple
5.5 Weld root penetration Minor Visual NIL 100% WPS/Drawing WPS/Drawing WISR S S
5.6 Inter pass cleaning Minor Visual NIL 100% WPS/Drawing WPS/Drawing WISR S S
Measurement
6.2 Fit up inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
s
Every day
Backing oven with temp
6.3 Check for the baking of electrodes (if applicable) Major Verification before start of WPS/Electrode manufatures recomandations
WPS/Electrode manufatures recomandations Backing registar S E
recorder
welding
Measurement Thermal chalk /thermo
6.4 Pre Heating Major As per WPS WPS WPS Heat treatment chart S E
s couple
6.5 Weld root penetration Minor Visual NIL 100% WPS/Drawing WPS/Drawing WISR S S
6.6 Inter pass cleaning Minor Visual NIL 100% WPS/Drawing WPS/Drawing WISR S S
7.4 Weld root penetration Minor Visual NIL 100% WPS/Drawing WPS/Drawing WISR S S
7.5 Inter pass cleaning Minor Visual NIL 100% WPS/Drawing WPS/Drawing WISR S S
Measurement
7.7 Final weld inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing/ASME/ANSI/API/AWS/DIN/IBR/IS/BS WISR S E
s
Measurement
7.8 NDT on welding Critical NDT report S EF
s
Condenser Tubes
8 Check for suppliers material test certificates. Critical Visual Nil 100% Tech specification/Drawings Availability of MTC ITSR S EF
8.2 Check of cleanliness prior to tubing. Minor Visual NIL 100% Tech specification/Drawings Surfaces to be free from dust and sticking dirts. ITSR S S
8.4 Check of cleanliness , prior to roller expanding. Major Visual NIL 100% Tech specification/Drawings Surfaces to be free from dust and sticking dirts. ITSR S E
9.1 Develop welding sequence Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings WISR S EF
Measurement
9.2 Fit up inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
s
Every day
Backing oven with temp
9.3 Check for the baking of electrodes (if applicable) Major Verification before start of WPS/Electrode manufatures recomandations
WPS/Electrode manufatures recomandations Backing registar S E
recorder
welding
Measurement Thermal chalk /thermo
9.4 Pre Heating Major As per WPS WPS WPS Heat treatment chart S E
s couple
9.5 Weld root penetration Minor Visual NIL 100% WPS/Drawing WPS/Drawing WISR S S
9.6 Inter pass cleaning Minor Visual NIL 100% WPS/Drawing WPS/Drawing WISR S S
10 Pressure test on water side Critical Visual Pressure Gauge 100% Tech specification/Drawings Tech specification/Drawings Pressure test report S EF
10.1 Pressure test on shell side. Critical Visual Pressure Gauge 100% Tech specification/Drawings Tech specification/Drawings Pressure test report S EF
11 Check of water box prior to coating Major Visual NIL 100% Tech specification/Drawings Surfaces to be free from dust and sticking dirts. ITSR S E
11.1 Check of tubesheets prior to coating Major Visual NIL 100% Tech specification/Drawings Surfaces to be free from dust and sticking dirts. ITSR S E
12 Final Inspection Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
14 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.1.3 3. Drawings
RT/Mechanic
2.3 Welder Qualification Test Critical Lab Test 100% Standard WPS/ASME Sec IX. ASME Sec IX. Welder Qualification record and welder's
S EFID.
al test
2.4 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
2.7 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
Alignment of flange connections and bolt Measurement Sprit level and hand
3.1 Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
tightening s tightning
Measurement
4 Fit up inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
s
Measurement Water level,tape,dumpy
4.1 Dimention and alingment of piping Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
s level
Every day
Backing oven with temp
4.2 Check for the baking of electrodes (if applicable) Major Verification before start of WPS/Electrode manufatures recomandations
WPS/Electrode manufatures recomandations Backing registar S E
recorder
welding
Measurement Thermal chalk /thermo
4.3 Pre Heating Major As per WPS WPS WPS Heat treatment chart S E
s couple
4.4 Weld root penetration Minor Visual NIL 100% WPS/Drawing WPS/Drawing WISR S S
4.5 Inter pass cleaning Minor Visual NIL 100% WPS/Drawing WPS/Drawing WISR S S
5 Final inspection before pressure test / leak test Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
6 Pressure test/Leak test/ Hydrotest/Pneumatic test Critical Visual Pressure Gauge 100% Tech specification/Drawings Tech specification/Drawings Pressure test report S EF
10 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.3 1. Drawings
2.7 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
Thermal Insulation.
3 Surface cleanliness Minor Visual Nil 100% ------ Free from foreign particles. Insulation test record S S
3.1 Placement of spacers Minor Measurement Measuring tape 100% Specific Drg. as per SpecificDrg. Insulation test record S S
3.2 Support stud welding -completeness Minor Visual Nil 100% Specific Drg. as per Specific Drg. Insulation test record S S
3.3 Placing of correct insulation material Major Verification Nil 100% Specific Drg. or Datas sheet As per specific Drg. or Data sheet Insulation test record S E
3.4 Thickness of each layer Major Measurement Measuring tape Random Specific Drg. as per Specific Drg. Insulation test record S E
Clading
4 Use of correct fastners Major Verification Nil Random Specific Drg. or Datas sheet Data sheet Insulation test record S E
4.1 Void between insulation and cladding Major Verification Nil Random ------------- Free of voids Insulation test record S E
4.2 Overlap of cladding sheets Major Verification Nil 100% Specific Drg. As per specific Drg. Insulation test record S E
4.3 Flushing of vertical cladding Major Verification Nil 100% Specific Drg. As per specific Drg. Insulation test record S E
4.4 Sealing of cut outs Major Verification Nil 100% Specific Drg. As per specific Drg. Insulation test record S E
4.5 Damages to cladding Major Visual Nil 100% ----- Freedom from damages Insulation test record S E
4.6 Color coding/ band/ flow direction Major Verification Nil 100% Specific Drg. or Datas sheet As per specific Drg. or Data sheet Insulation test record S E
5 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.1.3 3. Drawings
RT/Mechanic
2.3 Welder Qualification Test Critical Lab Test 100% Standard WPS/ASME Sec IX. ASME Sec IX. Welder Qualification record and welder's
S EFID.
al test
2.4 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
2.7 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
Valve Blocks.
Measurement
3.3 visual check on swing arm support weld. Major Weld gauge/Template Random WPS/Drawing WPS/Drawing/ASME/ANSI/API/AWS/DIN/IBR/IS/BS WISR S E
s
3.4 NDT-DPT check on swing arm support weld. Critical Visual DPT Kit 5% Tech specification/Drawings Tech specification/Drawings/AWS D 1.1 DPT report S EF
check for correct assembly and tighting torqe of Visual/Mesur Water level,tape,dumpy
3.6 Major 100% Tech specification/Drawings Tech specification/Drawings Turbine inspection reports S E
the seal ring ement level
check for correct assembly and tighting torqe of Visual/Mesur Water level,tape,dumpy
3.7 Major 100% Tech specification/Drawings Tech specification/Drawings Turbine inspection reports S E
the valve steam packing. ement level
check of the bolt prestress on the stop valve and Visual/Mesur Water level,tape,dumpy
3.8 Major 100% Tech specification/Drawings Tech specification/Drawings Turbine inspection reports S E
on the control valve (torque and cold tightened) ement level
check for correct execution of all connections and Visual/Mesur Water level,tape,dumpy
4.3 Major 100% Tech specification/Drawings Tech specification/Drawings Turbine inspection reports S E
of all locks. ement level
General
Measurement
4.4 general record of turbine and shaft line. Major tape Random Tech specification/Drawings Tech specification/Drawings Turbine inspection reports S E
s
Measurement
4.5 check of foundation leveling point. Major tape Random Tech specification/Drawings Tech specification/Drawings Turbine inspection reports S E
s
Measurement
4.6 check of shaft defelection line Major tape Random Tech specification/Drawings Tech specification/Drawings Turbine inspection reports S E
s
LP-Turbine
5 arrangments of slings for the turbine parts Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Turbine inspection reports S E
check of pre stress of the flange bolting of the Visual/Mesur Water level,tape,dumpy
6.2 Major 100% Tech specification/Drawings Tech specification/Drawings Turbine inspection reports S E
outer casing. ement level
check of flange bolting (without specific recording) Visual/Mesur Water level,tape,dumpy
6.3 Major 100% Tech specification/Drawings Tech specification/Drawings Turbine inspection reports S E
of LP casing parts. ement level
Visual/Mesur Water level,tape,dumpy
6.4 check of LP-Outer casing foundation supports Major 100% Tech specification/Drawings Tech specification/Drawings Turbine inspection reports S E
ement level
Visual/Mesur Water level,tape,dumpy
6.5 check of pre stress of foundation bolts Major 100% Tech specification/Drawings Tech specification/Drawings Turbine inspection reports S E
ement level
position check of rotor to LP-Gland seal / coupling Visual/Mesur Water level,tape,dumpy
6.6 Major 100% Tech specification/Drawings Tech specification/Drawings Turbine inspection reports S E
cover. ement level
dimentional check of clearances of differential Visual/Mesur Water level,tape,dumpy
6.7 Major 100% Tech specification/Drawings Tech specification/Drawings Turbine inspection reports S E
expantion transmitters ement level
check of connection dimention,coupling cover / Visual/Mesur Water level,tape,dumpy
6.8 Major 100% Tech specification/Drawings Tech specification/Drawings Turbine inspection reports S E
LP-Casing ement level
HP-Turbine
7 arrangments of slings for the turbine parts Major Visual NIL 100% Tech specification/Drawings Tech specification/Drawings Turbine inspection reports S E
IP-Turbine
7.8 arrangments of slings for the turbine parts Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Turbine inspection reports S E
Bearing Pedestal
10.4 Develop welding sequence for fixing plates Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings WISR S EF
Measurement
10.5 Welding visual inspection of fixing plates Major Weld gauge/Template Random WPS/Drawing WPS/Drawing/ASME/ANSI/API/AWS/DIN/IBR/IS/BS WISR S E
s
Measurement
10.6 NDT on welding of fixing plates Critical NDT report S EF
s
12.3 Develop welding sequence for foundation keys. Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings WISR S EF
Measurement
12.4 Welding visual inspection of foundation keys. Major Weld gauge/Template Random WPS/Drawing WPS/Drawing/ASME/ANSI/API/AWS/DIN/IBR/IS/BS WISR S E
s
Measurement
12.5 NDT on welding of foundation keys. Critical NDT report S EF
s
Check of finally assembled bearing pedestal lower Visual/Mesur Water level,tape,dumpy
12.6 Major 100% Tech specification/Drawings Tech specification/Drawings Turbine inspection reports S E
half-alingment and adjustment of foundation key. ement level
Positioning check of rotor in the bearing pedestal
Visual/Mesur Water level,tape,dumpy
12.7 and dimentional check of clearancess of journal Major 100% Tech specification/Drawings Tech specification/Drawings Turbine inspection reports S E
ement level
bearing.
dimentional check of clearences of journal Visual/Mesur Water level,tape,dumpy
12.8 Major 100% Tech specification/Drawings Tech specification/Drawings Turbine inspection reports S E
bearing. ement level
check of prestress of the bolts of installed bearing Visual/Mesur Water level,tape,dumpy
12.9 Major 100% Tech specification/Drawings Tech specification/Drawings Turbine inspection reports S E
pedestal cover. ement level
Visual/Mesur Water level,tape,dumpy
13 dimentional check of clearences of oil shields. Major 100% Tech specification/Drawings Tech specification/Drawings Turbine inspection reports S E
ement level
Thermal Insulations
check that the anchor bolts have only been welded Visual/Mesur Water level,tape,dumpy
13.4 Major 100% Tech specification/Drawings Tech specification/Drawings Turbine inspection reports S E
to the appropriate places(discs,screw heads,etc…) ement level
check that the areas specified in the drawing have Visual/Mesur Water level,tape,dumpy
13.5 Major 100% Tech specification/Drawings Tech specification/Drawings Turbine inspection reports S E
been insulated by preformed,removable pieces. ement level
Check that the insulation thickness (in relation to Visual/Mesur Water level,tape,dumpy
13.7 Major 100% Tech specification/Drawings Tech specification/Drawings Turbine inspection reports S E
the temp) is accroding to the supplier specification. ement level
Check that the casing lower part has been Visual/Mesur Water level,tape,dumpy
13.8 Major 100% Tech specification/Drawings Tech specification/Drawings Turbine inspection reports S E
insulated 20% thicker than the upper part. ement level
15 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.1.3 3. Drawings
RT/Mechanic
2.3 Welder Qualification Test Critical Lab Test 100% Standard WPS/ASME Sec IX. ASME Sec IX. Welder Qualification record and welder's
S EFID.
al test
2.4 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
2.6 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
check radial clearancess between gas guide rings Visual/Mesur Water level,tape,dumpy
4.4 Major 100% Tech specification/Drawings Tech specification/Drawings Generator inspecton report S E
and rotor shaft ement level
7 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
No Quality detoriaration,
Storage manual,
1.1 Material storage and preservation. Major Visual Nil Random Preservation measures are intactStore in JVR E E
Manufacturer’s Instructions
cool ,dryplace.
Measurement Water level,tape,dumpy
2 Front release Critical 100% Tech specification/Drawings Tech specification/Drawings Front release report. S EF
s level
3 Surface preparation Major Visual Nil Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Primer coat
Intermediate coat
Final coat
Coat meter or
6.1 Dry film thickness Critical Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S EF
Elcometer
Tech specification/Drawings
6.2 Color Major Verification Shade card Random Tech specification/Drawings Painting report S E
Check for shade and uniformity.
7 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.1.3 3. Drawings
2.4 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
2.7 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
Measurement
4 Fit up inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
s
4.4 Weld root penetration Minor Visual NIL 100% WPS/Drawing WPS/Drawing WISR S S
4.5 Inter pass cleaning Minor Visual NIL 100% WPS/Drawing WPS/Drawing WISR S S
Measurement
4.8 Post Weld heat treatment Critical Tempreature recorder As per WPS WPS/PQR WPS/PQR Heat treatment chart S EF
s
Measurement Tape,
4.9 Pipe supports Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
s Spirit level,water level
5 Final inspection before pressure test / leak test Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Testing of pipelines
6.1 Water lines-Hydraulic test Critical Visual Pressure Gauge 100% Tech specification/Drawings Tech specification/Drawings Pressure test report S EF
7 Surface preparation Major Visual Nil Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Primer coat
7.1 Correct primer paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
Coat meter or
7.2 Dry film thickness Major Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Elcometer
Intermediate coat
7.3 Correct paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
Coat meter or
7.4 Dry film thickness Major Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Elcometer
Final coat
7.5 Correct paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
Coat meter or
7.6 Dry film thickness Critical Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S EF
Elcometer
7.7 Color Major Verification Shade card Random Tech specification/Drawings Tech specification/Drawings Painting report S E
7.8 Adhesion test Critical Verification Sharp knife,Adhesive tape Random Tech specification/Drawings Tech specification/Drawings Painting report S EF
8 Surface preparation Major Visual Nil Random Tech specification/Drawings Tech specification/Drawings Insulation test record S E
8.1 Thickness of layers Major Measurement Sharp knife, tape random Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
8.2 Adhesion test Major Physical Sharp Knife random Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
8.4 Final inspection before laying underground Major Visual Nil 100% Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
9 Final Inspection of the system. Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.1.3 3. Drawings
RT/Mechanic
2.3 Welder Qualification Test Critical Lab Test 100% Standard WPS/ASME Sec IX. ASME Sec IX. Welder Qualification record and welder's
S EFID.
al test
2.4 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
2.6 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
2.8 Check that surface is clean and dressed Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
3.8 Check filling condition of mortar Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.1.3 3. Drawings
RT/Mechanic
2.3 Welder Qualification Test Critical Lab Test 100% Standard WPS/ASME Sec IX. ASME Sec IX. Welder Qualification record and welder's
S EFID.
al test
2.4 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
Check for cleanliness of EOT equpments before Outer and inner surfaces to be free from
2.5 Major Verification Nil 100% Nil ITSR S E
erection. dust and sticking dirts.
2.7 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
Measurement
3.2 Final weld inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing/ASME/ANSI/API/AWS/DIN/IBR/IS/BS WISR S E
s
Gantry rails
5.1 check for LT wheel free movement on gantry rail. Major Visual NIL 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
Crab assembly
DSL erection
Safe travel with full load( long travel and cross Measurement
7.8 Critical NIL 100% Tech specification/Drawings Tech specification/Drawings EOT inspection report S EF
travel ) s
Measurement
7.9 Abnormal sound or vibration Critical NIL 100% Tech specification/Drawings No abnormal sound or vibration during test ITSR S EF
s
8.1 Final Inspection Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.1.3 3. Drawings
RT/Mechanic
2.3 Welder Qualification Test Critical Lab Test 100% Standard WPS/ASME Sec IX. ASME Sec IX. Welder Qualification record and welder's
S EFID.
al test
HYDRANT SYSTEM.
3 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
3.3 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
3.6 Check that surface is clean and dressed Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
4.4 Check filling condition of mortar Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
Measurement
5.4 Final weld inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing/ASME/ANSI/API/AWS/DIN/IBR/IS/BS WISR S E
s
Water level,tape,dumpy
Check lift of pump rotor Measurement
5.5 Major level,Feeler gauge,dial 100% Tech specification/Drawings Tech specification/Drawings Alingment report S E
only for vertiical pumps s
gauge
Water level,tape,dumpy
Measurement
5.6 Rotation check for pump coupled with motor Major level,Feeler gauge,dial 100% Tech specification/Drawings Tech specification/Drawings Alingment report S E
s
gauge
5.7 Final Inspection Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Alignment of flange connections and bolt Measurement Sprit level and hand
6.1 Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
tightening s tightning
Measurement
6.2 Fit up inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
s
Measurement Water level,tape,dumpy
6.3 Dimention and alingment of piping Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
s level
Every day
Backing oven with temp
6.4 Check for the baking of electrodes (if applicable) Major Verification before start of WPS/Electrode manufatures recomandations
WPS/Electrode manufatures recomandations Backing registar S E
recorder
welding
Measurement
6.5 Final weld inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing/ASME/ANSI/API/AWS/DIN/IBR/IS/BS WISR S E
s
Measurement Tape,
6.6 Pipe supports Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
s Spirit level,water level
6.7 Final inspection before pressure test / leak test Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
6.9 Water lines-Hydraulic test Critical Visual Pressure Gauge 100% Tech specification/Drawings Tech specification/Drawings Pressure test report S EF
7 Air lines-Air test Critical Visual Pressure Gauge 100% Tech specification/Drawings Tech specification/Drawings Pressure test report S EF
7.2 Surface preparation Major Visual Nil Random Tech specification/Drawings Tech specification/Drawings Painting report S E
7.4 Correct primer paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
Coat meter or
7.5 Dry film thickness Major Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Elcometer
7.7 Correct paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
Coat meter or
7.8 Dry film thickness Major Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Elcometer
Coat meter or
8.1 Dry film thickness Critical Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S EF
Elcometer
8.2 Color Major Verification Shade card Random Tech specification/Drawings Tech specification/Drawings Painting report S E
8.3 Adhesion test Critical Verification Sharp knife,Adhesive tape Random Tech specification/Drawings Tech specification/Drawings Painting report S EF
8.5 Surface preparation Major Visual Nil Random Tech specification/Drawings Tech specification/Drawings Insulation test record S E
8.6 Thickness of layers Major Measurement Sharp knife, tape random Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
8.7 Adhesion test Major Physical Sharp Knife random Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
8.9 Final inspection before laying underground Major Visual Nil 100% Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
9 Air compressers.
9.1 Check that surface is clean and dressed Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
9.6 Check filling condition of mortar Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
10.1 Steadiness of fixing, interconnection of panels Major Major Visual 100% Approved drawings Approved drawings
10.3 Proper mounting Major Major Visual 100% Approved drawings & mfg. Catalogues Approved drawings & mfg. Catalogues
10.6 Ferruling, lugs, crimping, dressing, continuity Major Major Visual, testing 100% Approved drawings Approved drawings, wiring diagram
Connection, dressing, sealing of openings in gland Approved cable schedule & As per approved cable schedule &
10.8 Major Major Visual 100%
plate. interconnection drawings interconnection drawings
11 Accessibility & resetting of all operating points Major Major Visual 100% Approved drawings Approved drawings
11.1 KKS Labeling Major Visual Nil 100% Approved drawings Approved drawings SIR
11.4 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
11.7 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
12 Check that surface is clean and dressed Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
check adequate distance between wall and centre Visual/Mesur Water level,tape,dumpy
12.5 Major 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
of pumps. ement level
Water level,tape,dumpy
Intial/rough leveling,orientation and alingment of all Measurement
12.6 Critical level,Feeler gauge,dial 100% Tech specification/Drawings Tech specification/Drawings Alingment report S EF
equipment s
gauge
Visual/Mesur Water level,tape,dumpy
12.7 Setting of foundation bolts Critical 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
ement level
12.8 Check filling condition of mortar Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
14.1 Final Inspection Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Alignment of flange connections and bolt Measurement Sprit level and hand
14.5 Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
tightening s tightning
Measurement
14.6 Fit up inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
s
Measurement Water level,tape,dumpy
14.7 Dimention and alingment of piping Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
s level
Every day
Backing oven with temp
14.8 Check for the baking of electrodes (if applicable) Major Verification before start of WPS/Electrode manufatures recomandations
WPS/Electrode manufatures recomandations Backing registar S E
recorder
welding
Measurement
14.9 Final weld inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing/ASME/ANSI/API/AWS/DIN/IBR/IS/BS WISR S E
s
Measurement Tape,
15 Pipe supports Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
s Spirit level,water level
15.1 Final inspection before pressure test / leak test Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
15.3 Water lines-Hydraulic test Critical Visual Pressure Gauge 100% Tech specification/Drawings Tech specification/Drawings Pressure test report S EF
15.4 Air lines-Air test Critical Visual Pressure Gauge 100% Tech specification/Drawings Tech specification/Drawings Pressure test report S EF
15.6 Surface preparation Major Visual Nil Random Tech specification/Drawings Tech specification/Drawings Painting report S E
15.8 Correct primer paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
Coat meter or
15.9 Dry film thickness Major Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Elcometer
16 Intermediate coat
16.1 Correct paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
Coat meter or
16.2 Dry film thickness Major Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Elcometer
16.4 Correct paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
Coat meter or
16.5 Dry film thickness Critical Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S EF
Elcometer
16.6 Color Major Verification Shade card Random Tech specification/Drawings Tech specification/Drawings Painting report S E
16.7 Adhesion test Critical Verification Sharp knife,Adhesive tape Random Tech specification/Drawings Tech specification/Drawings Painting report S EF
16.9 Check that surface is clean and dressed Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
17.4 Check filling condition of mortar Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
17.7 Proper mounting Major Major Visual 100% Approved drawings & mfg. Catalogues Approved drawings & mfg. Catalogues
18 Ferruling, lugs, crimping, dressing, continuity Major Major Visual, testing 100% Approved drawings Approved drawings, wiring diagram
Connection, dressing, sealing of openings in gland Approved cable schedule & As per approved cable schedule &
18.2 Major Major Visual 100%
plate. interconnection drawings interconnection drawings
18.4 Accessibility & resetting of all operating points Major Major Visual 100% Approved drawings Approved drawings
18.5 KKS Labeling Major Visual Nil 100% Approved drawings Approved drawings SIR
18.6 Final Inspection OF SPRAY SYSTEM. Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
18.8 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
19.1 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
Measurement
19.6 Fit up inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
s
Measurement Water level,tape,dumpy
19.7 Dimention and alingment of piping Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
s level
Every day
Backing oven with temp
19.8 Check for the baking of electrodes (if applicable) Major Verification before start of WPS/Electrode manufatures recomandations
WPS/Electrode manufatures recomandations Backing registar S E
recorder
welding
Measurement
19.9 Final weld inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing/ASME/ANSI/API/AWS/DIN/IBR/IS/BS WISR S E
s
Measurement Tape,
20 Pipe supports Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
s Spirit level,water level
20.1 Final inspection before pressure test / leak test Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
20.3 Water lines-Hydraulic test Critical Visual Pressure Gauge 100% Tech specification/Drawings Tech specification/Drawings Pressure test report S EF
20.4 Air lines-Air test Critical Visual Pressure Gauge 100% Tech specification/Drawings Tech specification/Drawings Pressure test report S EF
20.6 Surface preparation Major Visual Nil Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Coat meter or
20.9 Dry film thickness Major Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Elcometer
21 Intermediate coat
21.1 Correct paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
Coat meter or
21.2 Dry film thickness Major Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Elcometer
21.4 Correct paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
Coat meter or
21.5 Dry film thickness Critical Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S EF
Elcometer
21.6 Color Major Verification Shade card Random Tech specification/Drawings Tech specification/Drawings Painting report S E
21.7 Adhesion test Critical Verification Sharp knife,Adhesive tape Random Tech specification/Drawings Tech specification/Drawings Painting report S EF
21.9 Check that surface is clean and dressed Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
22.4 Check filling condition of mortar Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
22.6 Water fill test Critical Visual Pressure Gauge 100% Tech specification/Drawings Tech specification/Drawings Pressure test report S EF
22.8 Proper mounting Major Major Visual 100% Approved drawings & mfg. Catalogues Approved drawings & mfg. Catalogues
23.1 Ferruling, lugs, crimping, dressing, continuity Major Major Visual, testing 100% Approved drawings Approved drawings, wiring diagram
Connection, dressing, sealing of openings in gland Approved cable schedule & As per approved cable schedule &
23.3 Major Major Visual 100%
plate. interconnection drawings interconnection drawings
23.5 Accessibility & resetting of all operating points Major Major Visual 100% Approved drawings Approved drawings
23.6 KKS Labeling Major Visual Nil 100% Approved drawings Approved drawings SIR
23.7 Final Inspection OF FOAM SYSTEM. Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
23.9 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
24.1 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
24.4 Steadiness of fixing, interconnection of panels Major Verification Visual 100% Approved drawings Approved drawings
24.5 Functional inspection check for completeness Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Detectors,MCP's,hooters,response indicatoretc-
24.6 Major Verification NIL 100% Tech specification/Drawings Tech specification/Drawings SIR S E
fixing at appropriate location.
Measurement
24.7 Detectors-functional check Critical NIL 100% Tech specification/Drawings Tech specification/Drawings SIR S E
s
24.8 KKS Labeling Major Visual Nil 100% Approved drawings Approved drawings SIR
24.9 Final Inspection OF HYDRANT SYSTEM Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
25 CO2 SYSTEM.
25.1 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
25.3 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
Measurement Tape,
25.6 Placement ,leveling and alingment Minor 100% Tech specification/Drawings Tech specification/Drawings SIR S S
s Spirit level,water level
25.7 Instruments
25.8 Proper mounting Major Major Visual 100% Approved drawings & mfg. Catalogues Approved drawings & mfg. Catalogues
25.9 KKS Labeling Major Visual Nil 100% Approved drawings Approved drawings SIR
26 Final Inspection OF CO2 SYSTEM. Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.1.3 3. Drawings
RT/Mechanic
2.3 Welder Qualification Test Critical Lab Test 100% Standard WPS/ASME Sec IX. ASME Sec IX. Welder Qualification record and welder's
S EFID.
al test
3 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
3.3 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
Alignment of flange connections and bolt Measurement Sprit level and hand
6.1 Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
tightening s tightning
Measurement
6.2 Fit up inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
s
Measurement Water level,tape,dumpy
6.3 Dimention and alingment of piping Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
s level
Every day
Backing oven with temp
6.4 Check for the baking of electrodes (if applicable) Major Verification before start of WPS/Electrode manufatures recomandations
WPS/Electrode manufatures recomandations Backing registar S E
recorder
welding
Measurement
6.5 Final weld inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing/ASME/ANSI/API/AWS/DIN/IBR/IS/BS WISR S E
s
Measurement Tape,
6.6 Pipe supports Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
s Spirit level,water level
6.7 Final inspection before pressure test / leak test Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
6.9 Water lines-Hydraulic test Critical Visual Pressure Gauge 100% Tech specification/Drawings Tech specification/Drawings Pressure test report S EF
7 Air lines-Air test Critical Visual Pressure Gauge 100% Tech specification/Drawings Tech specification/Drawings Pressure test report S EF
7.2 Surface preparation Major Visual Nil Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Coat meter or
7.5 Dry film thickness Major Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Elcometer
7.7 Correct paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
Coat meter or
7.8 Dry film thickness Major Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Elcometer
8 Correct paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
Coat meter or
8.1 Dry film thickness Critical Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S EF
Elcometer
8.2 Color Major Verification Shade card Random Tech specification/Drawings Tech specification/Drawings Painting report S E
8.3 Adhesion test Critical Verification Sharp knife,Adhesive tape Random Tech specification/Drawings Tech specification/Drawings Painting report S EF
8.5 Surface preparation Major Visual Nil Random Tech specification/Drawings Tech specification/Drawings Insulation test record S E
8.6 Thickness of layers Major Measurement Sharp knife, tape random Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
8.7 Adhesion test Major Physical Sharp Knife random Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
8.9 Final inspection before laying underground Major Visual Nil 100% Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
9 Air compressers.
9.1 Check that surface is clean and dressed Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
9.6 Check filling condition of mortar Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
9 Air Recivers
9.1 Check that surface is clean and dressed Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
9.6 Check filling condition of mortar Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
9.1 Check that surface is clean and dressed Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
9.6 Check filling condition of mortar Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
10.1 Steadiness of fixing, interconnection of panels Major Major Visual 100% Approved drawings Approved drawings
10.3 Proper mounting Major Major Visual 100% Approved drawings & mfg. Catalogues Approved drawings & mfg. Catalogues
10.6 Ferruling, lugs, crimping, dressing, continuity Major Major Visual, testing 100% Approved drawings Approved drawings, wiring diagram
Connection, dressing, sealing of openings in gland Approved cable schedule & As per approved cable schedule &
10.8 Major Major Visual 100%
plate. interconnection drawings interconnection drawings
11 Accessibility & resetting of all operating points Major Major Visual 100% Approved drawings Approved drawings
12 KKS Labeling Major Visual Nil 100% Approved drawings Approved drawings SIR
13 Final Inspection OF SYSTEM Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
2.2 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
Measurement Tape,
3 Placement ,leveling and alingment Minor 100% Tech specification/Drawings Tech specification/Drawings SIR S S
s Spirit level,water level
Free movements of stoplogs and trash racks in
3.1 Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings SIR S E
respective guides.
Intergengability of trashrack/stoplogs in their
3.2 Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings SIR S E
respective guides to be checked.
3.3 Leakage test for the stop logs Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings SIR S EF
4 KKS Labeling Major Visual Nil 100% Approved drawings Approved drawings SIR
5 Final Inspection Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.1.3 3. Drawings
RT/Mechanic
2.3 Welder Qualification Test Critical Lab Test 100% Standard WPS/ASME Sec IX. ASME Sec IX. Welder Qualification record and welder's
S EFID.
al test
3 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
3.3 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
3.6 Check that surface is clean and dressed Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
4.4 Check filling condition of mortar Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
5.7 Final Inspection Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Measurement
6.2 Fit up inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
s
Measurement Water level,tape,dumpy
6.3 Dimention and alingment of piping Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
s level
Every day
Backing oven with temp
6.4 Check for the baking of electrodes (if applicable) Major Verification before start of WPS/Electrode manufatures recomandations
WPS/Electrode manufatures recomandations Backing registar S E
recorder
welding
Measurement
6.5 Final weld inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing/ASME/ANSI/API/AWS/DIN/IBR/IS/BS WISR S E
s
Measurement Tape,
6.6 Pipe supports Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
s Spirit level,water level
6.7 Final inspection before pressure test / leak test Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
6.9 Water lines-Hydraulic test Critical Visual Pressure Gauge 100% Tech specification/Drawings Tech specification/Drawings Pressure test report S EF
7 Air lines-Air test Critical Visual Pressure Gauge 100% Tech specification/Drawings Tech specification/Drawings Pressure test report S EF
7.2 Surface preparation Major Visual Nil Random Tech specification/Drawings Tech specification/Drawings Painting report S E
7.4 Correct primer paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
Coat meter or
7.5 Dry film thickness Major Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Elcometer
7.7 Correct paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
Coat meter or
7.8 Dry film thickness Major Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Elcometer
8 Correct paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
8.2 Color Major Verification Shade card Random Tech specification/Drawings Tech specification/Drawings Painting report S E
8.3 Adhesion test Critical Verification Sharp knife,Adhesive tape Random Tech specification/Drawings Tech specification/Drawings Painting report S EF
8.5 Surface preparation Major Visual Nil Random Tech specification/Drawings Tech specification/Drawings Insulation test record S E
8.6 Thickness of layers Major Measurement Sharp knife, tape random Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
8.7 Adhesion test Major Physical Sharp Knife random Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
8.9 Final inspection before laying underground Major Visual Nil 100% Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
9.1 Check that surface is clean and dressed Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
Check bolt holes and pocket straightness and Visual/Mesur Water level,tape,dumpy
9.4 Major 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
cleanliness. ement level
Visual/Mesur Water level,tape,dumpy
9.5 Setting of foundation bolts Critical 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
ement level
9.6 Check filling condition of mortar Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
10.1 Steadiness of fixing, interconnection of panels Major Visual Nil 100% Approved drawings Approved drawings
10.3 Proper mounting Major Visual Nil 100% Approved drawings & mfg. Catalogues Approved drawings & mfg. Catalogues
10.6 Ferruling, lugs, crimping, dressing, continuity Major Visual Nil 100% Approved drawings Approved drawings, wiring diagram
Connection, dressing, sealing of openings in gland Approved cable schedule & As per approved cable schedule &
10.8 Major Visual Nil 100%
plate. interconnection drawings interconnection drawings
11 Accessibility & resetting of all operating points Major Visual Nil 100% Approved drawings Approved drawings
KKS Labeling Major Visual Nil 100% Approved drawings Approved drawings SIR
11.1 Final Inspection OF ETP SYSTEM Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.1.3 3. Drawings
RT/Mechanic
2.3 Welder Qualification Test Critical Lab Test 100% Standard WPS/ASME Sec IX. ASME Sec IX. Welder Qualification record and welder's
S EFID.
al test
3 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
3.3 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
3.6 Check that surface is clean and dressed Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
4.4 Check filling condition of mortar Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
5.7 Final Inspection Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Measurement
6.2 Fit up inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
s
Measurement Water level,tape,dumpy
6.3 Dimention and alingment of piping Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
s level
Every day
Backing oven with temp
6.4 Check for the baking of electrodes (if applicable) Major Verification before start of WPS/Electrode manufatures recomandations
WPS/Electrode manufatures recomandations Backing registar S E
recorder
welding
Measurement
6.5 Final weld inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing/ASME/ANSI/API/AWS/DIN/IBR/IS/BS WISR S E
s
Measurement Tape,
6.6 Pipe supports Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
s Spirit level,water level
6.7 Final inspection before pressure test / leak test Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
6.9 Water lines-Hydraulic test Critical Visual Pressure Gauge 100% Tech specification/Drawings Tech specification/Drawings Pressure test report S EF
7 Air lines-Air test Critical Visual Pressure Gauge 100% Tech specification/Drawings Tech specification/Drawings Pressure test report S EF
7.2 Surface preparation Major Visual Nil Random Tech specification/Drawings Tech specification/Drawings Painting report S E
7.4 Correct primer paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
Coat meter or
7.5 Dry film thickness Major Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Elcometer
7.7 Correct paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
Coat meter or
7.8 Dry film thickness Major Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Elcometer
8 Correct paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
8.2 Color Major Verification Shade card Random Tech specification/Drawings Tech specification/Drawings Painting report S E
8.3 Adhesion test Critical Verification Sharp knife,Adhesive tape Random Tech specification/Drawings Tech specification/Drawings Painting report S EF
8.5 Surface preparation Major Visual Nil Random Tech specification/Drawings Tech specification/Drawings Insulation test record S E
8.6 Thickness of layers Major Measurement Sharp knife, tape random Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
8.7 Adhesion test Major Physical Sharp Knife random Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
8.9 Final inspection before laying underground Major Visual Nil 100% Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
9.1 Check that surface is clean and dressed Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
Check bolt holes and pocket straightness and Visual/Mesur Water level,tape,dumpy
9.4 Major 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
cleanliness. ement level
Visual/Mesur Water level,tape,dumpy
9.5 Setting of foundation bolts Critical 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
ement level
9.6 Check filling condition of mortar Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
10.1 Steadiness of fixing, interconnection of panels Major Visual Nil 100% Approved drawings Approved drawings
10.3 Proper mounting Major Visual Nil 100% Approved drawings & mfg. Catalogues Approved drawings & mfg. Catalogues
10.6 Ferruling, lugs, crimping, dressing, continuity Major Visual Nil 100% Approved drawings Approved drawings, wiring diagram
Connection, dressing, sealing of openings in gland Approved cable schedule & As per approved cable schedule &
10.8 Major Visual Nil 100%
plate. interconnection drawings interconnection drawings
11 Accessibility & resetting of all operating points Major Visual Nil 100% Approved drawings Approved drawings
12 KKS Labeling Major Visual Nil 100% Approved drawings Approved drawings SIR
13 Final Inspection OF SYSTEM Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.1.3 3. Drawings
RT/Mechanic
2.3 Welder Qualification Test Critical Lab Test 100% Standard WPS/ASME Sec IX. ASME Sec IX. Welder Qualification record and welder's
S EFID.
al test
3 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
3.3 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
3.6 Check that surface is clean and dressed Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
4.4 Check filling condition of mortar Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
5.7 Final Inspection Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Measurement
6.2 Fit up inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
s
Measurement Water level,tape,dumpy
6.3 Dimention and alingment of piping Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
s level
Every day
Backing oven with temp
6.4 Check for the baking of electrodes (if applicable) Major Verification before start of WPS/Electrode manufatures recomandations
WPS/Electrode manufatures recomandations Backing registar S E
recorder
welding
Measurement
6.5 Final weld inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing/ASME/ANSI/API/AWS/DIN/IBR/IS/BS WISR S E
s
Measurement Tape,
6.6 Pipe supports Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
s Spirit level,water level
6.7 Final inspection before pressure test / leak test Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
6.9 Water lines-Hydraulic test Critical Visual Pressure Gauge 100% Tech specification/Drawings Tech specification/Drawings Pressure test report S EF
7 Air lines-Air test Critical Visual Pressure Gauge 100% Tech specification/Drawings Tech specification/Drawings Pressure test report S EF
7.2 Surface preparation Major Visual Nil Random Tech specification/Drawings Tech specification/Drawings Painting report S E
7.4 Correct primer paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
Coat meter or
7.5 Dry film thickness Major Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Elcometer
7.7 Correct paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
Coat meter or
7.8 Dry film thickness Major Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Elcometer
8 Correct paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
8.2 Color Major Verification Shade card Random Tech specification/Drawings Tech specification/Drawings Painting report S E
8.3 Adhesion test Critical Verification Sharp knife,Adhesive tape Random Tech specification/Drawings Tech specification/Drawings Painting report S EF
8.5 Surface preparation Major Visual Nil Random Tech specification/Drawings Tech specification/Drawings Insulation test record S E
8.6 Thickness of layers Major Measurement Sharp knife, tape random Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
8.7 Adhesion test Major Physical Sharp Knife random Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
8.9 Final inspection before laying underground Major Visual Nil 100% Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
9.1 Check that surface is clean and dressed Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
Check bolt holes and pocket straightness and Visual/Mesur Water level,tape,dumpy
9.4 Major 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
cleanliness. ement level
Visual/Mesur Water level,tape,dumpy
9.5 Setting of foundation bolts Critical 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
ement level
9.6 Check filling condition of mortar Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
10.1 Steadiness of fixing, interconnection of panels Major Visual Nil 100% Approved drawings Approved drawings
10.3 Proper mounting Major Visual Nil 100% Approved drawings & mfg. Catalogues Approved drawings & mfg. Catalogues
10.6 Ferruling, lugs, crimping, dressing, continuity Major Visual Nil 100% Approved drawings Approved drawings, wiring diagram
Connection, dressing, sealing of openings in gland Approved cable schedule & As per approved cable schedule &
10.8 Major Visual Nil 100%
plate. interconnection drawings interconnection drawings
11 Accessibility & resetting of all operating points Major Visual Nil 100% Approved drawings Approved drawings
12 KKS Labeling Major Visual Nil 100% Approved drawings Approved drawings SIR
13 Final Inspection OF SYSTEM Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.1.3 3. Drawings
RT/Mechanic
2.3 Welder Qualification Test Critical Lab Test 100% Standard WPS/ASME Sec IX. ASME Sec IX. Welder Qualification record and welder's
S EFID.
al test
3 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
3.3 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
3.6 Check that surface is clean and dressed Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
4.4 Check filling condition of mortar Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
5.7 Final Inspection Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Measurement
6.2 Fit up inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
s
Measurement Water level,tape,dumpy
6.3 Dimention and alingment of piping Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
s level
Every day
Backing oven with temp
6.4 Check for the baking of electrodes (if applicable) Major Verification before start of WPS/Electrode manufatures recomandations
WPS/Electrode manufatures recomandations Backing registar S E
recorder
welding
Measurement
6.5 Final weld inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing/ASME/ANSI/API/AWS/DIN/IBR/IS/BS WISR S E
s
Measurement Tape,
6.6 Pipe supports Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
s Spirit level,water level
6.7 Final inspection before pressure test / leak test Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
6.9 Water lines-Hydraulic test Critical Visual Pressure Gauge 100% Tech specification/Drawings Tech specification/Drawings Pressure test report S EF
7 Air lines-Air test Critical Visual Pressure Gauge 100% Tech specification/Drawings Tech specification/Drawings Pressure test report S EF
7.2 Surface preparation Major Visual Nil Random Tech specification/Drawings Tech specification/Drawings Painting report S E
7.4 Correct primer paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
Coat meter or
7.5 Dry film thickness Major Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Elcometer
7.7 Correct paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
Coat meter or
7.8 Dry film thickness Major Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Elcometer
8 Correct paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
8.2 Color Major Verification Shade card Random Tech specification/Drawings Tech specification/Drawings Painting report S E
8.3 Adhesion test Critical Verification Sharp knife,Adhesive tape Random Tech specification/Drawings Tech specification/Drawings Painting report S EF
8.5 Surface preparation Major Visual Nil Random Tech specification/Drawings Tech specification/Drawings Insulation test record S E
8.6 Thickness of layers Major Measurement Sharp knife, tape random Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
8.7 Adhesion test Major Physical Sharp Knife random Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
8.9 Final inspection before laying underground Major Visual Nil 100% Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
9.1 Check that surface is clean and dressed Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
Check bolt holes and pocket straightness and Visual/Mesur Water level,tape,dumpy
9.4 Major 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
cleanliness. ement level
Visual/Mesur Water level,tape,dumpy
9.5 Setting of foundation bolts Critical 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
ement level
9.6 Check filling condition of mortar Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
10.1 Steadiness of fixing, interconnection of panels Major Visual Nil 100% Approved drawings Approved drawings
10.3 Proper mounting Major Visual Nil 100% Approved drawings & mfg. Catalogues Approved drawings & mfg. Catalogues
10.6 Ferruling, lugs, crimping, dressing, continuity Major Visual Nil 100% Approved drawings Approved drawings, wiring diagram
Connection, dressing, sealing of openings in gland Approved cable schedule & As per approved cable schedule &
10.8 Major Visual Nil 100%
plate. interconnection drawings interconnection drawings
11 Accessibility & resetting of all operating points Major Visual Nil 100% Approved drawings Approved drawings
12 KKS Labeling Major Visual Nil 100% Approved drawings Approved drawings SIR
13 Final Inspection OF SYSTEM Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.1.3 3. Drawings
RT/Mechanic
2.3 Welder Qualification Test Critical Lab Test 100% Standard WPS/ASME Sec IX. ASME Sec IX. Welder Qualification record and welder's
S EFID.
al test
3 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
3.3 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
3.6 Check that surface is clean and dressed Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
4.4 Check filling condition of mortar Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
5.7 Final Inspection Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Measurement
6.2 Fit up inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
s
Measurement Water level,tape,dumpy
6.3 Dimention and alingment of piping Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
s level
Every day
Backing oven with temp
6.4 Check for the baking of electrodes (if applicable) Major Verification before start of WPS/Electrode manufatures recomandations
WPS/Electrode manufatures recomandations Backing registar S E
recorder
welding
Measurement
6.5 Final weld inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing/ASME/ANSI/API/AWS/DIN/IBR/IS/BS WISR S E
s
Measurement Tape,
6.6 Pipe supports Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
s Spirit level,water level
6.7 Final inspection before pressure test / leak test Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
6.9 Water lines-Hydraulic test Critical Visual Pressure Gauge 100% Tech specification/Drawings Tech specification/Drawings Pressure test report S EF
7 Air lines-Air test Critical Visual Pressure Gauge 100% Tech specification/Drawings Tech specification/Drawings Pressure test report S EF
7.2 Surface preparation Major Visual Nil Random Tech specification/Drawings Tech specification/Drawings Painting report S E
7.4 Correct primer paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
Coat meter or
7.5 Dry film thickness Major Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Elcometer
7.7 Correct paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
Coat meter or
7.8 Dry film thickness Major Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Elcometer
8 Correct paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
8.2 Color Major Verification Shade card Random Tech specification/Drawings Tech specification/Drawings Painting report S E
8.3 Adhesion test Critical Verification Sharp knife,Adhesive tape Random Tech specification/Drawings Tech specification/Drawings Painting report S EF
8.5 Surface preparation Major Visual Nil Random Tech specification/Drawings Tech specification/Drawings Insulation test record S E
8.6 Thickness of layers Major Measurement Sharp knife, tape random Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
8.7 Adhesion test Major Physical Sharp Knife random Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
8.9 Final inspection before laying underground Major Visual Nil 100% Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
9.1 Check that surface is clean and dressed Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
Check bolt holes and pocket straightness and Visual/Mesur Water level,tape,dumpy
9.4 Major 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
cleanliness. ement level
Visual/Mesur Water level,tape,dumpy
9.5 Setting of foundation bolts Critical 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
ement level
9.6 Check filling condition of mortar Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
10.1 Steadiness of fixing, interconnection of panels Major Visual Nil 100% Approved drawings Approved drawings
10.3 Proper mounting Major Visual Nil 100% Approved drawings & mfg. Catalogues Approved drawings & mfg. Catalogues
10.6 Ferruling, lugs, crimping, dressing, continuity Major Visual Nil 100% Approved drawings Approved drawings, wiring diagram
Connection, dressing, sealing of openings in gland Approved cable schedule & As per approved cable schedule &
10.8 Major Visual Nil 100%
plate. interconnection drawings interconnection drawings
11 Accessibility & resetting of all operating points Major Visual Nil 100% Approved drawings Approved drawings
12 KKS Labeling Major Visual Nil 100% Approved drawings Approved drawings SIR
13 Final Inspection OF SYSTEM Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.1.3 3. Drawings
RT/Mechanic
2.3 Welder Qualification Test Critical Lab Test 100% Standard WPS/ASME Sec IX. ASME Sec IX. Welder Qualification record and welder's
S EFID.
al test
3 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
3.3 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
3.6 Check that surface is clean and dressed Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
4.4 Check filling condition of mortar Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
5.7 Final Inspection Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Measurement
6.2 Fit up inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
s
Measurement Water level,tape,dumpy
6.3 Dimention and alingment of piping Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
s level
Every day
Backing oven with temp
6.4 Check for the baking of electrodes (if applicable) Major Verification before start of WPS/Electrode manufatures recomandations
WPS/Electrode manufatures recomandations Backing registar S E
recorder
welding
Measurement
6.5 Final weld inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing/ASME/ANSI/API/AWS/DIN/IBR/IS/BS WISR S E
s
Measurement Tape,
6.6 Pipe supports Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
s Spirit level,water level
6.7 Final inspection before pressure test / leak test Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
6.9 Water lines-Hydraulic test Critical Visual Pressure Gauge 100% Tech specification/Drawings Tech specification/Drawings Pressure test report S EF
7 Air lines-Air test Critical Visual Pressure Gauge 100% Tech specification/Drawings Tech specification/Drawings Pressure test report S EF
7.2 Surface preparation Major Visual Nil Random Tech specification/Drawings Tech specification/Drawings Painting report S E
7.4 Correct primer paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
Coat meter or
7.5 Dry film thickness Major Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Elcometer
7.7 Correct paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
Coat meter or
7.8 Dry film thickness Major Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Elcometer
8 Correct paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
8.2 Color Major Verification Shade card Random Tech specification/Drawings Tech specification/Drawings Painting report S E
8.3 Adhesion test Critical Verification Sharp knife,Adhesive tape Random Tech specification/Drawings Tech specification/Drawings Painting report S EF
8.5 Surface preparation Major Visual Nil Random Tech specification/Drawings Tech specification/Drawings Insulation test record S E
8.6 Thickness of layers Major Measurement Sharp knife, tape random Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
8.7 Adhesion test Major Physical Sharp Knife random Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
8.9 Final inspection before laying underground Major Visual Nil 100% Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
9.1 Check that surface is clean and dressed Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
Check bolt holes and pocket straightness and Visual/Mesur Water level,tape,dumpy
9.4 Major 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
cleanliness. ement level
Visual/Mesur Water level,tape,dumpy
9.5 Setting of foundation bolts Critical 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
ement level
9.6 Check filling condition of mortar Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
10.1 Steadiness of fixing, interconnection of panels Major Visual Nil 100% Approved drawings Approved drawings
10.3 Proper mounting Major Visual Nil 100% Approved drawings & mfg. Catalogues Approved drawings & mfg. Catalogues
10.6 Ferruling, lugs, crimping, dressing, continuity Major Visual Nil 100% Approved drawings Approved drawings, wiring diagram
Connection, dressing, sealing of openings in gland Approved cable schedule & As per approved cable schedule &
10.8 Major Visual Nil 100%
plate. interconnection drawings interconnection drawings
11 Accessibility & resetting of all operating points Major Visual Nil 100% Approved drawings Approved drawings
12 KKS Labeling Major Visual Nil 100% Approved drawings Approved drawings SIR
13 Final Inspection OF SYSTEM Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.1.3 3. Drawings
RT/Mechanic
2.3 Welder Qualification Test Critical Lab Test 100% Standard WPS/ASME Sec IX. ASME Sec IX. Welder Qualification record and welder's
S EFID.
al test
3 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
3.3 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
3.6 Check that surface is clean and dressed Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
4.4 Check filling condition of mortar Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
5.7 Final Inspection Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Measurement
6.2 Fit up inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
s
Measurement Water level,tape,dumpy
6.3 Dimention and alingment of piping Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
s level
Every day
Backing oven with temp
6.4 Check for the baking of electrodes (if applicable) Major Verification before start of WPS/Electrode manufatures recomandations
WPS/Electrode manufatures recomandations Backing registar S E
recorder
welding
Measurement
6.5 Final weld inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing/ASME/ANSI/API/AWS/DIN/IBR/IS/BS WISR S E
s
Measurement Tape,
6.6 Pipe supports Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
s Spirit level,water level
6.7 Final inspection before pressure test / leak test Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
6.9 Water lines-Hydraulic test Critical Visual Pressure Gauge 100% Tech specification/Drawings Tech specification/Drawings Pressure test report S EF
7 Air lines-Air test Critical Visual Pressure Gauge 100% Tech specification/Drawings Tech specification/Drawings Pressure test report S EF
7.2 Surface preparation Major Visual Nil Random Tech specification/Drawings Tech specification/Drawings Painting report S E
7.4 Correct primer paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
Coat meter or
7.5 Dry film thickness Major Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Elcometer
7.7 Correct paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
Coat meter or
7.8 Dry film thickness Major Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Elcometer
8 Correct paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
8.2 Color Major Verification Shade card Random Tech specification/Drawings Tech specification/Drawings Painting report S E
8.3 Adhesion test Critical Verification Sharp knife,Adhesive tape Random Tech specification/Drawings Tech specification/Drawings Painting report S EF
8.5 Surface preparation Major Visual Nil Random Tech specification/Drawings Tech specification/Drawings Insulation test record S E
8.6 Thickness of layers Major Measurement Sharp knife, tape random Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
8.7 Adhesion test Major Physical Sharp Knife random Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
8.9 Final inspection before laying underground Major Visual Nil 100% Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
9.1 Check that surface is clean and dressed Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
Check bolt holes and pocket straightness and Visual/Mesur Water level,tape,dumpy
9.4 Major 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
cleanliness. ement level
Visual/Mesur Water level,tape,dumpy
9.5 Setting of foundation bolts Critical 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
ement level
9.6 Check filling condition of mortar Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
10.1 Steadiness of fixing, interconnection of panels Major Visual Nil 100% Approved drawings Approved drawings
10.3 Proper mounting Major Visual Nil 100% Approved drawings & mfg. Catalogues Approved drawings & mfg. Catalogues
10.6 Ferruling, lugs, crimping, dressing, continuity Major Visual Nil 100% Approved drawings Approved drawings, wiring diagram
Connection, dressing, sealing of openings in gland Approved cable schedule & As per approved cable schedule &
10.8 Major Visual Nil 100%
plate. interconnection drawings interconnection drawings
11 Accessibility & resetting of all operating points Major Visual Nil 100% Approved drawings Approved drawings
12 KKS Labeling Major Visual Nil 100% Approved drawings Approved drawings SIR
13 Final Inspection OF SYSTEM Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.1.3 3. Drawings
RT/Mechanic
2.3 Welder Qualification Test Critical Lab Test 100% Standard WPS/ASME Sec IX. ASME Sec IX. Welder Qualification record and welder's
S EFID.
al test
3 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
3.3 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
3.6 Check that surface is clean and dressed Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
4.4 Check filling condition of mortar Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
5.7 Final Inspection Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Measurement
6.2 Fit up inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
s
Measurement Water level,tape,dumpy
6.3 Dimention and alingment of piping Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
s level
Every day
Backing oven with temp
6.4 Check for the baking of electrodes (if applicable) Major Verification before start of WPS/Electrode manufatures recomandations
WPS/Electrode manufatures recomandations Backing registar S E
recorder
welding
Measurement
6.5 Final weld inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing/ASME/ANSI/API/AWS/DIN/IBR/IS/BS WISR S E
s
Measurement Tape,
6.6 Pipe supports Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
s Spirit level,water level
6.7 Final inspection before pressure test / leak test Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
6.9 Water lines-Hydraulic test Critical Visual Pressure Gauge 100% Tech specification/Drawings Tech specification/Drawings Pressure test report S EF
7 Air lines-Air test Critical Visual Pressure Gauge 100% Tech specification/Drawings Tech specification/Drawings Pressure test report S EF
7.2 Surface preparation Major Visual Nil Random Tech specification/Drawings Tech specification/Drawings Painting report S E
7.4 Correct primer paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
Coat meter or
7.5 Dry film thickness Major Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Elcometer
7.7 Correct paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
Coat meter or
7.8 Dry film thickness Major Measurement Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Elcometer
8 Correct paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
8.2 Color Major Verification Shade card Random Tech specification/Drawings Tech specification/Drawings Painting report S E
8.3 Adhesion test Critical Verification Sharp knife,Adhesive tape Random Tech specification/Drawings Tech specification/Drawings Painting report S EF
8.5 Surface preparation Major Visual Nil Random Tech specification/Drawings Tech specification/Drawings Insulation test record S E
8.6 Thickness of layers Major Measurement Sharp knife, tape random Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
8.7 Adhesion test Major Physical Sharp Knife random Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
8.9 Final inspection before laying underground Major Visual Nil 100% Manufacturer’s Manual/ Specification Drawing/ Specification Insulation test record S E
9.1 Check that surface is clean and dressed Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
Check bolt holes and pocket straightness and Visual/Mesur Water level,tape,dumpy
9.4 Major 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
cleanliness. ement level
Visual/Mesur Water level,tape,dumpy
9.5 Setting of foundation bolts Critical 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
ement level
9.6 Check filling condition of mortar Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
10.1 Steadiness of fixing, interconnection of panels Major Visual Nil 100% Approved drawings Approved drawings
10.3 Proper mounting Major Visual Nil 100% Approved drawings & mfg. Catalogues Approved drawings & mfg. Catalogues
10.6 Ferruling, lugs, crimping, dressing, continuity Major Visual Nil 100% Approved drawings Approved drawings, wiring diagram
Connection, dressing, sealing of openings in gland Approved cable schedule & As per approved cable schedule &
10.8 Major Visual Nil 100%
plate. interconnection drawings interconnection drawings
11 Accessibility & resetting of all operating points Major Visual Nil 100% Approved drawings Approved drawings
12 KKS Labeling Major Visual Nil 100% Approved drawings Approved drawings SIR
13 Final Inspection OF SYSTEM Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
1. Drawings
2. Constrution guidelines
4 Stripping of area Minor visual Random Tech specification/Drawings Tech specification/Drawings Inspection reports S S
Longnitudanal and
Measurement
5 Spot levels Major cross profile at 10mts Tech specification/Drawings Tech specification/Drawings Inspection reports S E
s
interval.
Measurement
6 Final ground level Major Random Tech specification/Drawings Tech specification/Drawings Inspection reports S E
s
once for each type
7 OMC/Dry density of soil for filling Critical visual and source of fill IS 2720 Part VII/Tech specification/Drawings IS 2720 Part VII/Tech specification/Drawings Inspection reports S EF
material
8 Moisture content Critical visual On each source of fill IS 2720 Part II/Tech specification/Drawings IS 2720 Part II/Tech specification/Drawings Inspection reports S EF
At every 2500sqmt. Of
9 Dry density by core cutter method Critical visual Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
each layer.
Measurement one set of 5 samples
10 Earth work in filling/cutting Critical IS 2720 Part VII/Tech specification/Drawings 95% maximum dry density at OMC Inspection reports S EF
s every 5000cum.
Subgrade.
13 Final Inspection of the system Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
14 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
1. Drawings
2. Constrution guidelines
Tack Coat
9 Bitumen content Critical visual random IRC-14 IRC -14 clause A.2.2.1 Inspection reports S EF
10 Laying of tack coat Critical visual random IRC -14 clause A.3.2 IRC -14 clause A.3.2 Inspection reports S EF
Bitumen Laying
11 Heating of Bitumen before Mixing Critical visual random IS 73, IS 454 IS 73, IS 454 Inspection reports S EF
14 Gradation of Aggregate Critical visual Set of sieves One per 500 CUM IS 2386 Part I IRC - 27 Inspection reports S EF
Impact testing
15 Impact , Crushing value of Aggregate Critical visual Once per source IS 2386 Part IV IRC - 14 Inspection reports S EF
machine
16 Gradation of Aggregate Critical visual Set of sieves One per 500 CUM IS 2386 Part I IRC - 14 Inspection reports S EF
Maximum
17 Aggregate impact value Critical visual Once per source IS 2386 Part IV Inspection reports S EF
30 %
Maximum
18 Flakiness Index Critical visual Once per source IS 2386 Part I Lab test reports S EF
30 %
Maximum
19 Stripping value. Critical visual Once per source IS 6241 Inspection reports S EF
25 %
Maximum
20 Water absorption Critical visual Once per source IS 2386 Part III Inspection reports S EF
2%
Maximum
21 Soundness Critical visual Once per source IS 2386 Part V Inspection reports S EF
12 %
22 Bulk density Critical visual Once per source IS 2386 Part V Minimum 1120 Kg per CUM Inspection reports S EF
23 Grit for seal coat Critical visual Set of Sieves Once per 50 CUM IS 2386 Part I IRC - 14 Inspection reports S EF
24 Bitumen content Critical visual Once per 50 CUM IRC IRC - 14 Inspection reports S EF
Long and cross
25 Final finished level Major visual profiles at 10 M Tech specification/Drawings Tech specification/Drawings Inspection reports S E
interval
26 Final Inspection of the system Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
27 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
1. Drawings
2. Constrution guidelines
Coarse Aggregate
Sleeves,
9 Soundness Critical visual perforated Once per source IS : 2386 Part-V IS : 383 ,Cl.3 Inspection reports S EF
container
Scale, weights,
10 Acid and Alkali -Reactivity Critical visual sleeves, moulds Once per source IS : 2386,Part-VII IS: 2386 Part VII Page 24 Inspection reports S EF
etc
Fine Aggregates
Sleeves,
15 Soundness Critical visual perforated Twice per source IS : 2386 Part-V IS : 383 ,Cl.3 Inspection reports S EF
container
18 Check silt and clay content Critical visual Once per source IS : 2386,Part-II Max.5% Inspection reports S EF
Reinforcement steel
Cement
Water
24 Tests for neutralization of water by using indicator Critical visual Once per source IS : 3025/Tech. Spec. IS : 456, Cl. 4.3 Inspection reports S EF
25 Test for ascertaining limits of solids Critical visual Once per source IS : 3025/Tech. Spec. IS : 456, Cl. 4.3 Inspection reports S EF
26 Tests for PH valve Critical visual Once per source IS : 3025/Tech. Spec. IS : 456, Cl. 4.3 Inspection reports S EF
Concrete
27 Staging Major visual 100% Tech specification/Drawings Tech specification/Drawings S E
pour card
Form work
Placing of Reinforcement
Measurement Concrete
33 Check cutting and bending of reinforcement bars Major Measuring tape Random Bar bending schedule Bar bending schedule S E
s pour card
Concrete
Measurement Concrete
35 Mixing of concrere Critical 100% Tech specification/Drawings Tech specification/Drawings S EF
s pour card
Measurement Concrete
36 Laying of concrete Critical 100% Tech specification/Drawings Tech specification/Drawings S EF
s pour card
37 Workability or slump test Major visual Slump cone Random IS : 456, IS : 1199 IS : 456, Cl. 6 Lab test report S E
38 Compaction factor test Major visual Slump cone Random IS : 456, IS : 1199 IS : 456, Cl. 6 Lab test report S E
Measurement
40 Water cement ratio Critical Random Specific mix design As per specific mix design. Lab test report S EF
s
Measurement
41 Check cement content Critical Random IS : 456 , IS :3025, Specific mix design As per specific mix design. Lab test report S EF
s
45 Curing Major visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
Bitumin
Bricks
Measurement
62 Warpage Critical Measuring scale Random IS:3495 Part-IV Free from warpages Inspection reports S EF
s
Measurement
63 Dimensions and appearance Critical Measuring scale Random IS 1077 I S 1077 Clause -5 Inspection reports S EF
s
64 Brick work Major visual pumpbob/linedori 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
Grouting
66 Grouting pressure Major visual Random Tech specification/Drawings Tech specification/Drawings Inspection reports S E
67 Composition of grout Major visual Random Tech specification/Drawings Tech specification/Drawings Inspection reports S E
Measurement
68 Compressive strength Critical Random Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
s
69 Final Inspection of the system Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
70 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
1. Drawings
2. Constrution guidelines
Measurement
4 Dimension of pit Minor Measurement Tape Random Tech specification/Drawings Tech specification/Drawings Inspection reports S S
s
Measurement
Measurement
5 Final bed level Major Tape/ Level Random Tech specification/Drawings Tech specification/Drawings Concrete pour card S E
s
instrument
6 Filling and compaction Critical visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
Degree of compaction
12 Final Inspection of the system Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
13 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
1. Drawings
2. Constrution guidelines
Measurement
4 Dimension of pit Minor Measurement Tape Random Tech specification/Drawings Tech specification/Drawings Inspection reports S S
s
Measurement
Measurement
5 Final bed level Major Tape/ Level Random Tech specification/Drawings Tech specification/Drawings Concrete pour card S E
s
instrument
6 Filling and compaction Critical visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
Degree of compaction
10 Mix major visual measuring boxes Random IS 2185 Part II IS 2185 Part II Inspection reports S E
Measurement
11 Compressive strength Major testing machines 3 nos for/5000 nos IS 2185 Part II IS 2185 Part II Inspection reports S E
s
Measurement
12 Block density Major Weighing machine 3 nos for/5000 nos IS 2185 Part II IS 2185 Part II Inspection reports S E
s
Measurement
13 Water absorption Major Weighing machine 3 nos for/5000 nos IS 2185 Part II IS 2185 Part II Inspection reports S E
s
Measurement
14 Drying shrinkage Major tape 3 nos for/5000 nos IS 2185 Part II IS 2185 Part II Inspection reports S E
s
Measurement
15 Dimensions and appearance Critical Measuring scale Random IS 1077 I S 1077 Clause -5 Inspection reports S EF
s
16 Solid Block Masonary work Major visual pumpbob/linedori 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
17 Final Inspection of the system Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
1. Drawings
2. Constrution guidelines
Measurement
4 Dimension of pit Minor Measurement Tape Random Tech specification/Drawings Tech specification/Drawings Inspection reports S S
s
Measurement
Measurement
5 Final bed level Major Tape/ Level Random Tech specification/Drawings Tech specification/Drawings Concrete pour card S E
s
instrument
6 Filling and compaction Critical visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
Degree of compaction
Coarse Aggregate
Scale, weights,
16 Acid and Alkali -Reactivity Critical visual sleeves, moulds Once per source IS : 2386,Part-VII IS: 2386 Part VII Page 24 Inspection reports S EF
etc
Fine Aggregates
Sleeves,
21 Soundness Critical visual perforated Twice per source IS : 2386 Part-V IS : 383 ,Cl.3 Inspection reports S EF
container
Scale, weights,
22 Acid and Alkali -Reactivity Critical visual sleeves, moulds Once per source IS : 2386,Part-VII IS: 2386 Part VII Page 24 Inspection reports S EF
etc
24 Check silt and clay content Critical visual Once per source IS : 2386,Part-II Max.5% Inspection reports S EF
Reinforcement steel
Cement
Water
30 Tests for neutralization of water by using indicator Critical visual Once per source IS : 3025/Tech. Spec. IS : 456, Cl. 4.3 Inspection reports S EF
31 Test for ascertaining limits of solids Critical visual Once per source IS : 3025/Tech. Spec. IS : 456, Cl. 4.3 Inspection reports S EF
32 Tests for PH valve Critical visual Once per source IS : 3025/Tech. Spec. IS : 456, Cl. 4.3 Inspection reports S EF
Concrete
33 Staging Major visual 100% Tech specification/Drawings Tech specification/Drawings S E
pour card
Form work
Measurement Concrete
36 Shape, alignment Major Plump , Line dori. 100% Tech specification/Drawings Tech specification/Drawings S E
s pour card
Measurement Cleanliness from foreign materials and Concrete
37 cleaning and oiling Major 100% IS : 456 Cl .10.2 S E
s oily surface pour card
Placing of Reinforcement
Measurement Concrete
39 Check cutting and bending of reinforcement bars Major Measuring tape Random Bar bending schedule Bar bending schedule S E
s pour card
Concrete
Measurement Concrete
41 Mixing of concrere Critical 100% Tech specification/Drawings Tech specification/Drawings S EF
s pour card
Measurement Concrete
42 Laying of concrete Critical 100% Tech specification/Drawings Tech specification/Drawings S EF
s pour card
43 Workability or slump test Major visual Slump cone Random IS : 456, IS : 1199 IS : 456, Cl. 6 Lab test report S E
44 Compaction factor test Major visual Slump cone Random IS : 456, IS : 1199 IS : 456, Cl. 6 Lab test report S E
Every 100 M 3 or
IS : 516,
part thereof for each
45 Crushing strength Major visual Cube testing machine IS : 1199, IS : 456,Cl. 14 and 15 Lab test report S E
grade of concrete per
IS : 456
8 hrs. or part thereof
Measurement
46 Water cement ratio Critical Random Specific mix design As per specific mix design. Lab test report S EF
s
Measurement
47 Check cement content Critical Random IS : 456 , IS :3025, Specific mix design As per specific mix design. Lab test report S EF
s
Measurement
49 Dimensional , Damages , Distortion Major Measurement tape. 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
s
Measurement 1% or one piece from
50 Pre-cast RCC items Critical Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
s each lot of items
51 Curing Major visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
Bitumin
Physical properties of bitumen for expansion Measurement One sample per each IS : 1201, IS :1220 IS : 1201, IS :1220
53 Critical Inspection reports S EF
joints s lot / batch IS : 838 IS : 838
Measurement One sample per each
54 Bitumen filled in damp proofing check Critical IS :1322, IS : 1340 IS :1322, IS : 1340 Inspection reports S EF
s lot / batch
Bricks
Measurement
58 Warpage Critical Measuring scale Random IS:3495 Part-IV Free from warpages Inspection reports S EF
s
Measurement
59 Dimensions and appearance Critical Measuring scale Random IS 1077 I S 1077 Clause -5 Inspection reports S EF
s
60 Brick work Major visual pumpbob/linedori 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
Grouting
62 Grouting pressure Major visual Random Tech specification/Drawings Tech specification/Drawings Inspection reports S E
63 Composition of grout Major visual Random Tech specification/Drawings Tech specification/Drawings Inspection reports S E
Measurement
64 Compressive strength Critical Random Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
s
66 bed mortar preparation Critical visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
67 laying of tiles Critical visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
Measurement
68 top level Major level instrument 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
s
69 Gap mortor filling Critical visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
70 curing Major visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
Plastering
Measurement
71 Thick ness of plaster Minor tape 100 sqm Tech specification/Drawings Tech specification/Drawings Inspection reports S S
s
72 surface preparation. Critical visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
Measurement
73 mix of mortar Critical box Random Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
s
74 plastering work Minor visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S S
75 Curing Major visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
76 surface preparation. Major visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
77 colour wash work Minor visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S S
Painting
78 surface preparation. Major visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
79 Painting work Minor visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S S
80 Quality of wood Critical visual once per source Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
Measurement
81 size of frames Major tape 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
s
83 Dimention and class Major visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
Measurement
84 mix of mortar Critical box Random Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
s
85 laying Minor visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S S
86 Curing Major visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
Measurement
87 thickness of glass Major screw gauge Random Tech specification/Drawings Tech specification/Drawings Inspection reports S E
s
88 warpage Major visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
90 level alingment and clearences Major visual tape,tube levels,plumb 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
91 jointing Critical visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
92 leakage test Critical visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
water line
93 pressure test Critical visual pressure gauge 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
Subgrade.
102 Bitumen content Critical visual random IRC-14 IRC -14 clause A.2.2.1 Inspection reports S EF
103 Laying of tack coat Critical visual random IRC -14 clause A.3.2 IRC -14 clause A.3.2 Inspection reports S EF
Bitumen Laying
104 Heating of Bitumen before Mixing Critical visual random IS 73, IS 454 IS 73, IS 454 Inspection reports S EF
107 Gradation of Aggregate Critical visual Set of sieves One per 500 CUM IS 2386 Part I IRC - 27 Inspection reports S EF
108 Impact , Crushing value of Aggregate Critical visual Impact testing machine Once per source IS 2386 Part IV IRC - 14 Inspection reports S EF
109 Gradation of Aggregate Critical visual Set of sieves One per 500 CUM IS 2386 Part I IRC - 14 Inspection reports S EF
Maximum
110 Aggregate impact value Critical visual Once per source IS 2386 Part IV Inspection reports S EF
30 %
Maximum
111 Flakiness Index Critical visual Once per source IS 2386 Part I Lab test reports S EF
30 %
Maximum
112 Stripping value. Critical visual Once per source IS 6241 Inspection reports S EF
25 %
Maximum
113 Water absorption Critical visual Once per source IS 2386 Part III Inspection reports S EF
2%
Maximum
114 Soundness Critical visual Once per source IS 2386 Part V Inspection reports S EF
12 %
115 Bulk density Critical visual Once per source IS 2386 Part V Minimum 1120 Kg per CUM Inspection reports S EF
Seal coat
116 Grit for seal coat Critical visual Set of Sieves Once per 50 CUM IS 2386 Part I IRC - 14 Inspection reports S EF
117 Bitumen content Critical visual Once per 50 CUM IRC IRC - 14 Inspection reports S EF
Long and cross
118 Final finished level Major visual profiles at 10 M Tech specification/Drawings Tech specification/Drawings Inspection reports S E
interval
119 Final Inspection of the system Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
120 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
1. Drawings
2. Constrution guidelines
Measurement
4 Dimension of pit Minor Measurement Tape Random Tech specification/Drawings Tech specification/Drawings Inspection reports S S
s
Measurement
Measurement
5 Final bed level Major Tape/ Level Random Tech specification/Drawings Tech specification/Drawings Concrete pour card S E
s
instrument
Earth work in filling
6 Filling and compaction Critical visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
Degree of compaction
Coarse Aggregate
Sleeves,
15 Soundness Critical visual perforated Once per source IS : 2386 Part-V IS : 383 ,Cl.3 Inspection reports S EF
container
Scale, weights,
16 Acid and Alkali -Reactivity Critical visual sleeves, moulds Once per source IS : 2386,Part-VII IS: 2386 Part VII Page 24 Inspection reports S EF
etc
Fine Aggregates
Sleeves,
21 Soundness Critical visual perforated Twice per source IS : 2386 Part-V IS : 383 ,Cl.3 Inspection reports S EF
container
Scale, weights,
22 Acid and Alkali -Reactivity Critical visual sleeves, moulds Once per source IS : 2386,Part-VII IS: 2386 Part VII Page 24 Inspection reports S EF
etc
24 Check silt and clay content Critical visual Once per source IS : 2386,Part-II Max.5% Inspection reports S EF
Reinforcement steel
Cement
Water
30 Tests for neutralization of water by using indicator Critical visual Once per source IS : 3025/Tech. Spec. IS : 456, Cl. 4.3 Inspection reports S EF
31 Test for ascertaining limits of solids Critical visual Once per source IS : 3025/Tech. Spec. IS : 456, Cl. 4.3 Inspection reports S EF
32 Tests for PH valve Critical visual Once per source IS : 3025/Tech. Spec. IS : 456, Cl. 4.3 Inspection reports S EF
Concrete
33 Staging Major visual 100% Tech specification/Drawings Tech specification/Drawings S E
pour card
Form work
Measurement Concrete
35 Dimensions Major 100% Tech specification/Drawings IS:456 clause-10 S E
s pour card
Measurement Concrete
36 Shape, alignment Major Plump , Line dori. 100% Tech specification/Drawings Tech specification/Drawings S E
s pour card
Measurement Cleanliness from foreign materials and Concrete
37 cleaning and oiling Major 100% IS : 456 Cl .10.2 S E
s oily surface pour card
Placing of Reinforcement
Measurement Concrete
39 Check cutting and bending of reinforcement bars Major Measuring tape Random Bar bending schedule Bar bending schedule S E
s pour card
Measurement Specific Drgs. and Concrete
40 Check bays, ties,chairs, bends, cover and laps Major Measuring tape Random IS : 456 ,clause 11 S E
s bar bending schedule / Tech. Spec pour card
Concrete
Measurement Concrete
41 Mixing of concrere Critical 100% Tech specification/Drawings Tech specification/Drawings S EF
s pour card
Measurement Concrete
42 Laying of concrete Critical 100% Tech specification/Drawings Tech specification/Drawings S EF
s pour card
43 Workability or slump test Major visual Slump cone Random IS : 456, IS : 1199 IS : 456, Cl. 6 Lab test report S E
44 Compaction factor test Major visual Slump cone Random IS : 456, IS : 1199 IS : 456, Cl. 6 Lab test report S E
Every 100 M 3 or
IS : 516,
part thereof for each
45 Crushing strength Major visual Cube testing machine IS : 1199, IS : 456,Cl. 14 and 15 Lab test report S E
grade of concrete per
IS : 456
8 hrs. or part thereof
Measurement
46 Water cement ratio Critical Random Specific mix design As per specific mix design. Lab test report S EF
s
Measurement
47 Check cement content Critical Random IS : 456 , IS :3025, Specific mix design As per specific mix design. Lab test report S EF
s
51 Curing Major visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
Bitumin
Bricks
Measurement
58 Warpage Critical Measuring scale Random IS:3495 Part-IV Free from warpages Inspection reports S EF
s
Measurement
59 Dimensions and appearance Critical Measuring scale Random IS 1077 I S 1077 Clause -5 Inspection reports S EF
s
60 Brick work Major visual pumpbob/linedori 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
Grouting
62 Grouting pressure Major visual Random Tech specification/Drawings Tech specification/Drawings Inspection reports S E
63 Composition of grout Major visual Random Tech specification/Drawings Tech specification/Drawings Inspection reports S E
Measurement
64 Compressive strength Critical Random Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
s
66 bed mortar preparation Critical visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
67 laying of tiles Critical visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
Measurement
68 top level Major level instrument 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
s
69 Gap mortor filling Critical visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
70 curing Major visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
Plastering
Measurement
71 Thick ness of plaster Minor tape 100 sqm Tech specification/Drawings Tech specification/Drawings Inspection reports S S
s
72 surface preparation. Critical visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
Measurement
73 mix of mortar Critical box Random Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
s
74 plastering work Minor visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S S
75 Curing Major visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
76 surface preparation. Major visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
77 colour wash work Minor visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S S
Painting
78 surface preparation. Major visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
79 Painting work Minor visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S S
80 Quality of wood Critical visual once per source Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
Measurement
81 size of frames Major tape 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
s
83 Dimention and class Major visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
Measurement
84 mix of mortar Critical box Random Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
s
85 laying Minor visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S S
86 Curing Major visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
Measurement
87 thickness of glass Major screw gauge Random Tech specification/Drawings Tech specification/Drawings Inspection reports S E
s
88 warpage Major visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
tape,tube
90 level alingment and clearences Major visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
levels,plumb
91 jointing Critical visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
92 leakage test Critical visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
water line
93 pressure test Critical visual pressure gauge 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
Subgrade.
102 Bitumen content Critical visual random IRC-14 IRC -14 clause A.2.2.1 Inspection reports S EF
103 Laying of tack coat Critical visual random IRC -14 clause A.3.2 IRC -14 clause A.3.2 Inspection reports S EF
Bitumen Laying
104 Heating of Bitumen before Mixing Critical visual random IS 73, IS 454 IS 73, IS 454 Inspection reports S EF
107 Gradation of Aggregate Critical visual Set of sieves One per 500 CUM IS 2386 Part I IRC - 27 Inspection reports S EF
Impact testing
108 Impact , Crushing value of Aggregate Critical visual Once per source IS 2386 Part IV IRC - 14 Inspection reports S EF
machine
109 Gradation of Aggregate Critical visual Set of sieves One per 500 CUM IS 2386 Part I IRC - 14 Inspection reports S EF
Maximum
110 Aggregate impact value Critical visual Once per source IS 2386 Part IV Inspection reports S EF
30 %
Maximum
111 Flakiness Index Critical visual Once per source IS 2386 Part I Lab test reports S EF
30 %
Maximum
112 Stripping value. Critical visual Once per source IS 6241 Inspection reports S EF
25 %
Maximum
113 Water absorption Critical visual Once per source IS 2386 Part III Inspection reports S EF
2%
Maximum
114 Soundness Critical visual Once per source IS 2386 Part V Inspection reports S EF
12 %
115 Bulk density Critical visual Once per source IS 2386 Part V Minimum 1120 Kg per CUM Inspection reports S EF
Seal coat
116 Grit for seal coat Critical visual Set of Sieves Once per 50 CUM IS 2386 Part I IRC - 14 Inspection reports S EF
117 Bitumen content Critical visual Once per 50 CUM IRC IRC - 14 Inspection reports S EF
Long and cross
118 Final finished level Major visual profiles at 10 M Tech specification/Drawings Tech specification/Drawings Inspection reports S E
interval
119 Final Inspection of the system Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
120 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
1. Drawings
2. Constrution guidelines
Measurement
4 Site cleaning and layout. Minor visual Tape/ Level Random Tech specification/Drawings Tech specification/Drawings Inspection reports S S
instrument
Measurement
5 Coordinate fixing Major visual Tape/ Level 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
instrument
Measurement
6 Temporary bench mark fixing Minor visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S S
Tape
Measurement
7 Dimension of pit Minor Measurement Tape Random Tech specification/Drawings Tech specification/Drawings Inspection reports S S
s
Measurement
8 Side slope Critical Measurement Tape Random Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
s
Measurement
Measurement
9 Final bed level Major Tape/ Level Random Tech specification/Drawings Tech specification/Drawings Concrete pour card S E
s
instrument
11 Filling and compaction Critical visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
Degree of compaction
Coarse Aggregate
Scale, weights,
23 Acid and Alkali -Reactivity Critical visual sleeves, moulds Once per source IS : 2386,Part-VII IS: 2386 Part VII Page 24 Inspection reports S EF
etc
Flakiness and
24 Flakiness and elongation index. Critical visual elongation Twice per source IS : 2386,Part-VII IS: 2386 Part VII Page 24 Inspection reports S EF
apparutus.
Fine Aggregates
Sleeves,
29 Soundness Critical visual perforated Twice per source IS : 2386 Part-V IS : 383 ,Cl.3 Inspection reports S EF
container
Scale, weights,
30 Acid and Alkali -Reactivity Critical visual sleeves, moulds Once per source IS : 2386,Part-VII IS: 2386 Part VII Page 24 Inspection reports S EF
etc
32 Check silt and clay content Critical visual Once per source IS : 2386,Part-II Max.5% Inspection reports S EF
Reinforcement steel
37 Storage Minor visual nil random nil no quality deterioation Inspection reports S S
Cement
42 Storage Minor visual nil random nil no quality deterioation Inspection reports S S
Water
43 Tests for neutralization of water by using indicator Critical visual Once per source IS : 3025/Tech. Spec. IS : 456, Cl. 4.3 Inspection reports S EF
44 Test for ascertaining limits of solids Critical visual Once per source IS : 3025/Tech. Spec. IS : 456, Cl. 4.3 Inspection reports S EF
45 Tests for PH valve Critical visual Once per source IS : 3025/Tech. Spec. IS : 456, Cl. 4.3 Inspection reports S EF
Concrete
46 Staging Major visual 100% Tech specification/Drawings Tech specification/Drawings S E
pour card
Form work
Placing of Reinforcement
Measurement Concrete
50 Check cutting and bending of reinforcement bars Major Measuring tape Random Bar bending schedule Bar bending schedule S E
s pour card
Measurement Specific Drgs. and Concrete
51 Check bays, ties,chairs, bends, cover and laps Major Measuring tape Random IS : 456 ,clause 11 S E
s bar bending schedule / Tech. Spec pour card
Concrete
Measurement Concrete
52 Mixing of concrere Critical 100% Tech specification/Drawings Tech specification/Drawings S EF
s pour card
Measurement Concrete
53 Laying of concrete Critical 100% Tech specification/Drawings Tech specification/Drawings S EF
s pour card
54 Workability or slump test Major visual Slump cone Random IS : 456, IS : 1199 IS : 456, Cl. 6 Lab test report S E
55 Compaction factor test Major visual Slump cone Random IS : 456, IS : 1199 IS : 456, Cl. 6 Lab test report S E
Every 100 M 3 or
IS : 516,
Cube testing part thereof for each
56 Crushing strength Major visual IS : 1199, IS : 456,Cl. 14 and 15 Lab test report S E
machine grade of concrete per
IS : 456
8 hrs. or part thereof
Measurement
57 Water cement ratio Critical Random Specific mix design As per specific mix design. Lab test report S EF
s
62 Curing Major visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
Every 24 hrs
concreting or
Measurement plump , Line
63 Verticality / centre Critical whenever the Tech specification/Drawings Tech specification/Drawings slip form twist format S EF
s dori./laser
concreate starts after
a stoppage.
Every 24 hrs
concreting or
Measurement
65 Wall thickness Major plump , Line dori./laser whenever the wall Tech specification/Drawings Tech specification/Drawings slip form twist format S E
s
thickness variation is
more.
67 Final Inspection of the system Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
68 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
1. Drawings
2. Constrution guidelines
4 Stripping of area Minor visual Random Tech specification/Drawings Tech specification/Drawings Inspection reports S S
Longnitudanal and
Measurement
5 Spot levels Major cross profile at 10mts Tech specification/Drawings Tech specification/Drawings Inspection reports S E
s
interval.
Measurement
6 Final ground level Major Random Tech specification/Drawings Tech specification/Drawings Inspection reports S E
s
once for each type
7 OMC/Dry density of soil for filling Critical visual and source of fill IS 2720 Part VII/Tech specification/Drawings IS 2720 Part VII/Tech specification/Drawings Inspection reports S EF
material
8 Moisture content Critical visual On each source of fill IS 2720 Part II/Tech specification/Drawings IS 2720 Part II/Tech specification/Drawings Inspection reports S EF
At every 2500sqmt. Of
9 Dry density by core cutter method Critical visual Tech specification/Drawings Tech specification/Drawings Inspection reports S EF
each layer.
Measurement one set of 5 samples
10 Earth work in filling/cutting Critical IS 2720 Part VII/Tech specification/Drawings 95% maximum dry density at OMC Inspection reports S EF
s every 5000cum.
Subgrade.
mpact testing
m/c,
Los Angeles
Mechanical properties including impact, abrasion and IS : 2386
21 Critical visual m/c, Twice per source IS : 383,Cl. 3, Inspection reports S EF
crushing value (Part-IV)
compressive test
m/c and other
appliances
IS : 2386 (Part-III) IS : 383 clause-3
22 Deleterious Materials Critical visual Physical balance Once per source Inspection reports S EF
Tech. Spec and Table-I
Sleeves,
23 Soundness Critical visual perforated Once per source IS : 2386 Part-V IS : 383 ,Cl.3 Inspection reports S EF
container
Scale, weights,
24 Acid and Alkali -Reactivity Critical visual sleeves, moulds Once per source IS : 2386,Part-VII IS: 2386 Part VII Page 24 Inspection reports S EF
etc
Fine Aggregates
Sleeves,
29 Soundness Critical visual perforated Twice per source IS : 2386 Part-V IS : 383 ,Cl.3 Inspection reports S EF
container
Scale, weights,
30 Acid and Alkali -Reactivity Critical visual sleeves, moulds Once per source IS : 2386,Part-VII IS: 2386 Part VII Page 24 Inspection reports S EF
etc
32 Check silt and clay content Critical visual Once per source IS : 2386,Part-II Max.5% Inspection reports S EF
Cement
Water
37 Tests for neutralization of water by using indicator Critical visual Once per source IS : 3025/Tech. Spec. IS : 456, Cl. 4.3 Inspection reports S EF
38 Test for ascertaining limits of solids Critical visual Once per source IS : 3025/Tech. Spec. IS : 456, Cl. 4.3 Inspection reports S EF
39 Tests for PH valve Critical visual Once per source IS : 3025/Tech. Spec. IS : 456, Cl. 4.3 Inspection reports S EF
Concrete
40 Staging Major visual 100% Tech specification/Drawings Tech specification/Drawings S E
pour card
44 Curing Major visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
Bricks
Measurement
48 Warpage Critical Measuring scale Random IS:3495 Part-IV Free from warpages Inspection reports S EF
s
Measurement
49 Dimensions and appearance Critical Measuring scale Random IS 1077 I S 1077 Clause -5 Inspection reports S EF
s
50 Brick work Major visual pumpbob/linedori 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
Geo Membrane
51 Check for smooth surface of bed before membrane lining Major visual nil 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
Measurement
52 Field joints air pressure test/vaccume test Critical vaccume test kit 100% Tech specification/Drawings Tech specification/Drawings Vaccume test report S EF
s
55 Final Inspection of the system Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
56 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
1. Drawings
2. Constrution guidelines
Concrete
Measurement Concrete
4 Mixing of concrere Critical 100% Tech specification/Drawings Tech specification/Drawings S EF
s pour card
Measurement Concrete
5 Laying of concrete Critical 100% Tech specification/Drawings Tech specification/Drawings S EF
s pour card
6 Workability or slump test Major visual Slump cone Random IS : 456, IS : 1199 IS : 456, Cl. 6 Lab test report S E
7 Compaction factor test Major visual Slump cone Random IS : 456, IS : 1199 IS : 456, Cl. 6 Lab test report S E
Every 100 M 3 or
IS : 516,
part thereof for each
8 Crushing strength Major visual Cube testing machine IS : 1199, IS : 456,Cl. 14 and 15 Lab test report S E
grade of concrete per
IS : 456
8 hrs. or part thereof
Measurement
9 Water cement ratio Critical Random Specific mix design As per specific mix design. Lab test report S EF
s
Measurement
10 Check cement content Critical Random IS : 456 , IS :3025, Specific mix design As per specific mix design. Lab test report S EF
s
14 Curing Major visual 100% Tech specification/Drawings Tech specification/Drawings Inspection reports S E
Pile boring
Testing
Measurement
17 pull out test Critical equipments and 1-2 % or as specified IS 2911 Part IV IS 2911 Part IV Inspection reports S EF
s
loads.
Testing
Measurement
18 Axial load test Critical equipments and 1-2 % or as specified IS 2911 Part IV IS 2911 Part IV Inspection reports S EF
s
loads.
Testing
Measurement
19 Lateral load test Critical equipments and 1-2 % or as specified IS 2911 Part IV IS 2911 Part IV Inspection reports S EF
s
loads.
21 Final Inspection of the system Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
22 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: `
1. WPS
3. Drawings
6 Fabrication Work
6.1 Marking and cutting Major Measurements Water level,tape 100% Tech specification/Drawings Tech specification/Drawings Log Book
6.2 Fit up inspection Major Measurements Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
Every day
Backing oven with temp WPS/Electrode manufatures WPS/Electrode manufatures
6.3 Check for the baking of electrodes (if applicable) Major Verification before start of Backing registar S E
recorder recomandations recomandations
welding
7.1 Fillet welds Major Visual Nil 100% WPS/Drawing/AWS D 1.1 WPS/Drawing/AWS D 1.1 NDT report S E
Major Measurement Weld gauge Random WPS/Drawing/AWS D 1.1 WPS/Drawing/AWS D 1.1 NDT report S E
Major LPT Test kit 5% Drawing/AWS D 1.1 Drawing/AWS D 1.1 NDT report S E
7.2 Butt welds Major Visual Nil 100% WPS/Drawing/AWS D 1.1 WPS/Drawing/AWS D 1.1 NDT report S EF
Critical RT 100%Film
for tension
viewer flange of crane girder,10% for remaining
WPS/Drawing/AWS
butt welds D 1.1 WPS/Drawing/AWS D 1.1 NDT report S EF
9 Final inspection Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings SIR
10.1 Surface preparation Major Visual Nil Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Primer coat
10.2.1 Correct primer paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
10.2.2 Dry film thickness Major Measurement Coat meter or Elcometer Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Intermediate coat
10.3.1 Correct paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
10.3.2 Dry film thickness Major Measurement Coat meter or Elcometer Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Final coat
10.4.1 Correct paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
10.4.2 Dry film thickness Critical Measurements Coat meter or Elcometer Random Tech specification/Drawings Tech specification/Drawings Painting report S EF
11 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
12 Erection Works
12.1 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
Check for cleanliness of structures before Outer and inner surfaces to be free from
12.2 Major Verification Nil 100% Nil ITSR S E
erection. dust and sticking dirts.
12.4 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
Water level,tape,dumpy
12.5 Front release Critical Measurements 100% Tech specification/Drawings Tech specification/Drawings Front release report. S EF
level
12.6 Check for the coloumn oriantation Major Visual Water level,tape,theodolite 100% Tech specification/Drawings Tech specification/Drawings Coloumn Verticality report S E
12.7 Check for coloumn axis and level Major Measurements Water level,tape,theodolite 100% Tech specification/Drawings Tech specification/Drawings Coloumn Verticality report S E
12.8 Check for coloumn verticality-before grouting Major Measurements Water level,tape,theodolite 100% Tech specification/Drawings Tech specification/Drawings Coloumn Verticality report S E
Visual/Mesurem
12.9 Grouting Critical Tape 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
ent
13 Check for coloumn verticality-after grouting. Critical Measurements Water level,tape,theodolite 100% Tech specification/Drawings Tech specification/Drawings Coloumn Verticality report S EF
14 NDT on structural welding Critical Visual NDT kit As per NDT plan Tech specification/Drawings/AWS D 1.1 Tech specification/Drawings/AWS D 1.1 NDT report S EF
17 Dry film thickness Major Measurements Coat meter or Elcometer Random Tech specification/Drawings Tech specification/Drawings Painting report S E
18 Final Inspection of the system Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
19 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
1. Drawings
Pre Erection
Final check
Check that materials stored are covered as per
Minor Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Register at site
manufacturer's instructions
Final check
Check proper size of cable is being laid and in the direction
Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Register at site
it is to be unrolled.
Final check
Measurement
Check continuity of cable in drum Major Continuity Tester 100% Tech specification/Drawings Tech specification/Drawings Register at site
s
Final check
Measurement
Check IR of cable Major 500 V Megger 100% Tech specification/Drawings Tech specification/Drawings Register at site
s
Final check
Check that all relevant cable schedule termination details
Minor Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Register at site
are received .
Final check
Check that the various openings, pockets,etc. have been
Minor Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Register at site
provided as per drawings.
Final check
Check that all tools, tackles and machines are available at
Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Register at site
site for erection
Final check
Check for the qualifications of technicians for cable
Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Register at site
termination and jointing.
Final check
Check supports are strong and painted Minor Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Register at site
Final check
Check tray route is free from obstruction Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Register at site
Final check
Ensure that if there is any change in the cable layout
Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Register at site
drawings, it has the approval of APIL
Check WPS/WPQ/PQR Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Checklist
Welder qualification
Ensure that qualified persons are employed for welding Critical Visual Nil 100% WPS/ASME SEC IX WPS/ASME SEC IX
report.
Erection
Final check
Check clean/ tight fitting of conductor Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Register at site
Final check
Check proper bending of all conductors Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Register at site
Final check
Check proper alignment of complete jointing or termination Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Register at site
Final check
Check / identify each phase before jointing Major Visual Continuity Tester 100% Tech specification/Drawings Tech specification/Drawings Register at site
Final check
Check whether all components are fixed properly Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Register at site
Final check
Ensure that entire work is done as per manufacturer's
Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Register at site
instructions
Final check
Ensure that adequate space is available in the proposed
Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Register at site
cable route
Final check
While pulling the cables, by machinery, tension should not Measurement
Minor Nil 100% Tech specification/Drawings Tech specification/Drawings Register at site
exceed the recommended limit s
Final check
Ensure that cables are pulled through hume/ steel pipes for
Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Register at site
road crossing, etc.as per drwg
Final check
Ensure that laying procedures are followed while laying
Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Register at site
cables in excavated trenches
Final check
Ensure cable tags are fixed as per specs. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Register at site
Ensure that all continuous length of cable trays are earthed Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Inspection reports
Check Galvanising of tray / absence of rust Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Inspection reports
Check continuity of cable tray route Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Inspection reports
Check the spacing between the supports of cable trays Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Inspection reports
Check all trays and covers are fixed properly Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Inspection reports
Check that no deflections in tray due to improper support Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Inspection reports
9 Final Inspection of the system Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
1. Drawings
Pre Erection
Check that panel is placed on foundation as per drawing . Minor Visual Nil 100% Layout drawings Layout drawings Site register
Check that terminations are proper Major Visual Nil 100% Approved External Connection Drawing Approved External Connection Drawing Site register
9 Final Inspection of the system Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
10 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
1. Drawings
Pre Erection
Erection
Check sequence wise (starting from one end or bus duct Spirit level and
Major Visual 100% Tech specification/Drawings Tech specification/Drawings Site register
pannel) installation, final levelling and bolting-up Torque wrench
Check main busbar connection Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Site register
9 Final Inspection of the system Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
10 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
1. Drawings
Pre Erection
Check that CTs, CVTs, CBs etc. are in good conditions and
Major Visual Nil 100% O E M Manual O E M Manual Record register
are ready for assemblies/erection
Check that all tools & tackles, instruments etc. required for
Minor Visual Nil 100% List of tools & tackles In working condition Record register
erection are available at site.
Erection
General
Check that all assemblies required are available at site. Major Visual Nil 100% Equipment drawing Equipment drawing Record register
Check oil levels Major Visual Nil 100% Instruction manual Instruction manual Record register
Circuit Breakers
Measurement Multimeter,
Check continuity of electrical connections. Major 100% Single line diagram, breaker schematic diagram O E M Manual Record register
s continuity tester
Check alignment of structures Major Visual Nil 100% Structure drawing O E M Manual Record register
Check erection & alignment of air receiver Major Visual Nil 100% Equipment drawing O E M Manual Record register
Ensure proper tightening of density monitor and SF6 piping. Critical Visual Torque wrench 100% Equipment drawing O E M Manual Record register
Check SF6 gas leakage Critical Visual Pr. Gauge 100% Equipment drawing O E M Manual Record register
Current Transformer
Measurement
Check insulation resistance before & after erection. Critical 500 V Megger 100% Instruction manual O E M Manual Record register
s
Check all CT secondary cores are connected or cores Measurement
Critical Nil 100% Instruction manual O E M Manual Record register
shorted. s
Check oil level of CT Major Visual Nil 100% Instruction manual O E M Manual Record register
Voltage Transformer/CVT
Check case for oil marks/damage Major Visual Nil 100% Equipment drawing O E M Manual Record register
Ensure lifting of CVT using lifting lugs only Major Visual Nil 100% Instruction manual O E M Manual Record register
Measurement
Check secondary fuses for continuity and rating Major Continuity tester 100% Instruction manual O E M Manual Record register
s
Check for level of oil in the tank Major Visual Nil 100% Instruction manual O E M Manual Record register
Check removal of breather plug(if any) Major Visual Nil 100% Instruction manual O E M Manual Record register
Check rigidity of foundation bolts Major Visual Nil 100% Structure drawing O E M Manual Record register
Check erection & alignment of structure Major Visual Nil 100% Structure drawing O E M Manual Record register
Check level of the base, housing assembly and flange. Major Visual Spirit level 100% Equipment drawing O E M Manual Record register
Lightning Arrester
Check for order of assembly as per drawing. Major Visual Nil 100% Equipment drawing O E M Manual Record register
Ensure erection with proper lifting device. Major Visual Nil 100% Instruction manual layout drawing O E M Manual Record register
Inspect the tube visually for damages Major Visual Nil 100% Bill of material No deep cuts Record register
Check soundness of aluminium pipe joints-DPT/RT Critical Visual TEST KIT 100% ANSI ANSI TEST REPORT
Ensure use of correct type of insulator Major Visual Nil 100% Bill of material Erection Drawing Record register
9 Final Inspection of the system Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
10 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
1. Drawings
Pre-Erection
Check the Earthing scheme Major Physical Nil 100% Earthing layout /equipment. earthing Drg. All necessary points should be available do
Boost capacity Major Visual Nil 100% O.E.M. Manual O.E.M. Manual Register
Air Tightness Major Visual Nil 100% O.E.M. Manual O.E.M. Manual do
Interior of Tank should be painted with oil resistant paint Major Visual Nil 100% O.E.M. Manual O.E.M. Manual do
Gas pressure Critical Physical Nil 100% O.E.M. Manual O.E.M. Manual Register
Check for Dirt / Dust on terminals Major Visual Nil 100% O.E.M.Manual should be clean do
Oil level ( if oil filled) Critical Visual Nil 100% O.E.M. Manual O.E.M. Manual do
Check on Gaskets for leakage Major Visual Nil 100% O.E.M. Manual O.E.M. Manual do
Condenser Bushing
Physical check for Damage Major Visual Nil 100% O.E.M. Manual O.E.M. Manual do
Oil leakage’s Critical Visual Nil 100% O.E.M. Manual O.E.M. Manual do
Check for Bushing leads sufficient length. Major Physical Measuring tape 100% O.E.M.Manual O.E.M. Manual Register
elec-
Insulation Resistance and tan dellta Major 5 KV Megger &TanDelta kit 100% O.E.M. Manual > 5000M ohms. do
measurement
Oil flushing Major Physical Oil filteration Unit 100% free of foreign mtls do
Resistivity Major Measurement Lab Testing Sample O.E.M. Manual O.E.M. Manual do
Break Down Voltage Major -do- Lab Testing Sample O.E.M. Manual O.E.M. Manual do
Erection
Civil Foundation
Dimensions levels etc. Major Physical do 100% ABB.Drgs/ Site Drgs. ABB Drgs / Site Drgs. do
Transformer Placement
Placing main tank on plinth and centring on both axes Major Physical do 100% do do do
Conformity with approved drgs Major Physical do 100% Instruction manual/GA Drawings Instruction manual / GA Drawings do
Check for absence of physical damages Major Visual Nil 100% O.E.M. Manual O.E.M. Manual do
Check for IR. Values Major Measurement 500 V Megger 100% O.E.M. Manual O.E.M. Manual Report
Check for Alignment Major Visual Nil 100% O.E.M. Manual O.E.M. Manual do
Paper insertion test on gasketting Major Physical Paper 100% Appd. Drg./ O.E.M. Manual Appd. Drg./ O.E.M. Manual do
To be Tested in
Oil Test after filling(filling to be done under vacuum) Major Phys./Elect. 100% O.E.M. Manual/Tech. Spec. O.E.M. Manual do
Near by lab
Check for oil level(after filling) Major Visual Nil 100% O.E.M. Manual O.E.M. Manual do
9 Final Inspection of the system Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
10 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
1. Drawings
Pre Erection
Check if all erection drawings are available Major Visual Nil 100% Master Drawing List Master Drawing List Register at site
Check if all safety clearance have been obtained Major Visual Nil 100% O E M Manual O E M Manual -do-
Check if all components of lighting fixtures are available Major Visual Nil 100% Mfg. Manuals / Appd. Drwg Mfg. Manuals / Appd. Drwg -do-
Lighting Wires
Check if all the sizes and colours are available Major Visual Nil 100% -do- -do- -do-
Check for the plan and layouts Major Visual Nil 100% -do- -do- -do-
Check if all fittings are also available Major Visual Nil 100% -do- -do- -do-
Check if all poles and coundits have protective coatings Major Visual Nil 100% -do- -do- -do-
Erection
Check the alignment of the receptacle Major Visual Nil 100% -do- -do- -do-
Check that earth line is connected to the earth pin Major Visual Nil 100% -do- -do- -do-
Check that switches are properly identified Major Visual Nil 100% -do- -do- -do-
Check the continuity of earth wire and IR of the cables Major Visual Nil 100% -do- -do- -do-
Check the making of the portion that would go in the earth Major Visual Nil 100% -do- -do- -do-
Check if the poles are standing straight Major Visual Nil 100% -do- -do- -do-
Check if the poles are in line with others Major Visual Nil 100% -do- -do- -do-
Check if GI condiuts is also plumbed Major Visual Nil 100% Mfg. Manuals / Appd. Drwg Mfg. Manuals / Appd. Drwg Register at site
Check if T arms are properly bolted Major Visual Nil 100% -do- -do- -do-
Lighting Panels
Check that panel is placed on foundation properly Major Visual Nil 100% -do- -do- -do-
Check proper drilling of gland plates Major Visual Nil 100% -do- -do- -do-
Check that connections are tight Major Physical Hand tight 100% -do- -do- -do-
Check if paint touch up is done proplerly Major Visual Nil 100% -do- -do- -do-
9 Final Inspection of the system Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
10 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
1. Drawings
Measurement
Check tightness of nuts and bolts with torque wrench. Major Torque wrench 100% Instruction manual O E M Manual Record register
s
Measurement Multimeter,
Check continuity of electrical connections. Major 100% Single line diagram, breaker schematic diagram O E M Manual Record register
s continuity tester
Check alignment of structures Major Visual Nil 100% Structure drawing O E M Manual Record register
Check erection & alignment of air receiver Major Visual Nil 100% Equipment drawing O E M Manual Record register
Ensure proper tightening of density monitor and SF6 piping. Critical Visual Torque wrench 100% Equipment drawing O E M Manual Record register
Check SF6 gas leakage Critical Visual Pr. Gauge 100% Equipment drawing O E M Manual Record register
9 Final Inspection of the system Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
10 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
1. Drawings
Measurement
Check insulation resistance before & after erection. Critical 500 V Megger 100% Instruction manual O E M Manual Record register
s
Check all CT secondary cores are connected or cores Measurement
Critical Nil 100% Instruction manual O E M Manual Record register
shorted. s
Check oil level of CT Major Visual Nil 100% Instruction manual O E M Manual Record register
9 Final Inspection of the system Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
10 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
1. Drawings
Check case for oil marks/damage Major Visual Nil 100% Equipment drawing O E M Manual Record register
Ensure lifting of CVT using lifting lugs only Major Visual Nil 100% Instruction manual O E M Manual Record register
Measurement
Check secondary fuses for continuity and rating Major Continuity tester 100% Instruction manual O E M Manual Record register
s
Check for level of oil in the tank Major Visual Nil 100% Instruction manual O E M Manual Record register
Check removal of breather plug(if any) Major Visual Nil 100% Instruction manual O E M Manual Record register
9 Final Inspection of the system Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
10 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
1. Drawings
Check rigidity of foundation bolts Major Visual Nil 100% Structure drawing O E M Manual Record register
Check erection & alignment of structure Major Visual Nil 100% Structure drawing O E M Manual Record register
Check level of the base, housing assembly and flange. Major Visual Spirit level 100% Equipment drawing O E M Manual Record register
9 Final Inspection of the system Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
10 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
1. Drawings
Check for order of assembly as per drawing. Major Visual Nil 100% Equipment drawing O E M Manual Record register
Ensure erection with proper lifting device. Major Visual Nil 100% Instruction manual layout drawing O E M Manual Record register
9 Final Inspection of the system Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
10 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
1. Drawings
Position of Panel
Steadiness of fixing, interconnection of panels Major Major Visual 100% Approved drawings Approved drawings
Proper mounting Major Major Visual 100% Approved drawings & mfg. Catalogues Approved drawings & mfg. Catalogues
Proper earthing of all panels (continuity of earthing) Major Major Visual 100% Approved drawings Approved drawings
Ferruling, lugs, crimping, dressing, continuity Major Major Visual, testing 100% Approved drawings Approved drawings, wiring diagram
Control cables
Approved cable schedule & interconnection As per approved cable schedule &
Connection, dressing, sealing of openings in gland plate. Major Major Visual 100%
drawings interconnection drawings
Knobs of relays
Accessibility & resetting of all operating points Major Major Visual 100% Approved drawings Approved drawings
Earth continuity Major Major Testing 100% Approved drawings Approved drawings
Insulation Resistance Withstand test Critical Major Measuring 100% As per tech. spec. & relevant Standards As per tech. spec. & relevant Standards
Meters
Relays
Protection alarm, trip ckt. Annunciation, Indicating Operation, fault Commissioning Test
Critical Critical 100% Approved drawings. Approved drawings. Y
lamps,operation of bell/ hooter etc. simulation Report
COMMISSIONING :
Commissioning Test
Performance Critical Critical Visual 100% Approved drawings. No abnormality Y
Report
9 Final Inspection of the system Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
1. Drawings
Record reading of impact recorder Minor Visual impact recorder on recipt erection and maintaince manual erection and maintaince manual MIER
Checkthat the equipment is never stored in a polluted area Minor Visual Nil at the time of storage erection and maintaince manual unpolluted ITSR
Oil drum
check that drum are stored in protected area and not stored
Minor Visual Nil at the time of storage erection and maintaince manual seals intact and no leakages MIER
on their face side
bushing
Marshalling box
check that the marshalling box are stored vertical Minor Visual Nil at the time of storage erection and maintaince manual no physical damage MIER
9 Final Inspection of the system Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
10 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
1. WPS
3. Drawings
6 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
Check for cleanliness of structures before Outer and inner surfaces to be free from
7 Major Verification Nil 100% Nil ITSR S E
erection. dust and sticking dirts.
9 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
11 Check for the coloumn oriantation Major Visual Water level,tape,theodolite 100% Tech specification/Drawings Tech specification/Drawings Coloumn Verticality report S E
Measurement
12 Check for coloumn axis and level Major Water level,tape,theodolite 100% Tech specification/Drawings Tech specification/Drawings Coloumn Verticality report S E
s
Measurement
13 Check for coloumn verticality-before grouting Major Water level,tape,theodolite 100% Tech specification/Drawings Tech specification/Drawings Coloumn Verticality report S E
s
Visual/Mesur
14 Grouting Critical Tape 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
ement
Measurement
15 Check for coloumn verticality-after grouting. Critical Water level,tape,theodolite 100% Tech specification/Drawings Tech specification/Drawings Coloumn Verticality report S EF
s
19 NDT on structural welding Critical Visual NDT kit As per NDT plan Tech specification/Drawings/AWS D 1.1 Tech specification/Drawings/AWS D 1.1 NDT report S EF
24 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
1. WPS
3. Drawings
6 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
9 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
Measurement
10 Fit up inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
s
Measurement Water level,tape,dumpy
11 Dimention and alingment of piping Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
s level
Every day
Backing oven with temp
12 Check for the baking of electrodes (if applicable) Major Verification before start of WPS/Electrode manufatures recomandations
WPS/Electrode manufatures recomandations Backing registar S E
recorder
welding
Measurement Thermal chalk /temp
13 Pre Heating Major As per WPS WPS/PQR WPS/PQR Heat treatment chart S E
s recorder
14 Weld root penetration Minor Visual NIL 100% WPS/Drawing WPS/Drawing WISR S S
15 Inter pass cleaning Minor Visual NIL 100% WPS/Drawing WPS/Drawing WISR S S
Measurement Tape,
22 Cold and hot settings of Pipe supports/hangers Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
s Spirit level,water level
Final setting of disc spring plates for walls and
23 Major Visual NIL 100% Tech specification/Drawings Tech specification/Drawings SIR S E
tubes
Measurement Tape,
24 Tube pitch and tube to wall distances Major 100% Tech specification/Drawings Tech specification/Drawings SIR S E
s Spirit level,water level
Measurement
26 Boiler bank tube + furnance expantion Critical Micrometer/go-nogo gauge 100% Boiler bank tube expantion procedure Boiler bank tube expantion procedure Expantion reports. S EF
s
27 Final inspection before pressure test / leak test Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
28 Pressure test/Leak test/ Hydrotest/Pneumatic test Critical Visual Pressure Gauge 100% Tech specification/Drawings/IBR rules Tech specification/Drawings/IBR rules Pressure test report S EF
29 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.4 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
Check for cleanliness of air pre heaters before Outer and inner surfaces to be free from
2.5 Major Verification Nil 100% Nil ITSR S E
erection. dust and sticking dirts.
Pre assembly level,straightness,diagonal,bolt Measurement Water level,tape,torque
2.6 Major 100% Tech specification/Drawings Tech specification/Drawings SIR S E
tightness. s wrench.
2.7 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
4.4 NDT- DPT on housing edge welds Critical Visual DPT Kit 5% Tech specification/Drawings Tech specification/Drawings/ANSI NDT report S EF
5.1 Final Inspection Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Measurement
6.1 Painting thikness and shade Major Coat meter or Elcometer Random Tech specification/Drawings Tech specification/Drawings Painting report S E
s
7 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.4 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
Check for cleanliness of air pre heaters before Outer and inner surfaces to be free from
2.5 Major Verification Nil 100% Nil ITSR S E
erection. dust and sticking dirts.
Pre assembly level,straightness,diagonal,bolt Measurement Water level,tape,torque
2.6 Major 100% Tech specification/Drawings Tech specification/Drawings SIR S E
tightness. s wrench.
2.7 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
Tubes
8 Check for suppliers material test certificates. Critical Visual Nil 100% Tech specification/Drawings Availability of MTC ITSR S EF
8.2 Check of cleanliness prior to tubing. Minor Visual NIL 100% Tech specification/Drawings Surfaces to be free from dust and sticking dirts. ITSR S S
8.4 Check of cleanliness , prior to roller expanding. Major Visual NIL 100% Tech specification/Drawings Surfaces to be free from dust and sticking dirts. ITSR S E
5.1 Final Inspection Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Measurement
6.1 Painting thikness and shade Major Coat meter or Elcometer Random Tech specification/Drawings Tech specification/Drawings Painting report S E
s
7 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.1.3 3. Drawings
2.4 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
Check for cleanliness of ateam air heaters before Outer and inner surfaces to be free from
2.5 Major Verification Nil 100% Nil ITSR S E
erection. dust and sticking dirts.
2.7 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
Measurement
4.1 Fit up inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
s
Measurement
4.2 Final weld inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing/ASME/ANSI/API/AWS/DIN/IBR/IS/BS WISR S E
s
4.3 Tubular expanstion Critical Verification Nil 100% Tech specification/Drawings Tech specification/Drawings SIR S EF
5.1 Final Inspection Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Measurement
6.1 Painting thikness and shade Major Coat meter or Elcometer Random Tech specification/Drawings Tech specification/Drawings Painting report S E
s
7 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.1.3 3. Drawings
2.4 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
Check for cleanliness of equpment before Outer and inner surfaces to be free from
2.5 Major Verification Nil 100% Nil ITSR S E
erection. dust and sticking dirts.
2.7 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
Visual/Mesur
3.4 Grouting Critical Tape 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
ement
4.1 Flange connection of inlet and outlet ducts Major Verification Torque wrench. 100% Tech specification/Drawings Tech specification/Drawings SIR S E
Measurement
4.2 Fit up inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
s
Measurement
4.3 Final weld inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing/ASME/ANSI/API/AWS/DIN/IBR/IS/BS WISR S E
s
5.1 Final Inspection Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Measurement
6.1 Painting thikness and shade Major Coat meter or Elcometer Random Tech specification/Drawings Tech specification/Drawings Painting report S E
s
7 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.1.3 3. Drawings
2.4 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
2.7 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
5.1 KALEN plates installation Major Visual NIL 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
5.2 Tiling works Major Visual NIL 100% Tech specification/Drawings Tech specification/Drawings SIR S E
6.1 Final Inspection Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Measurement
7.1 Painting thikness and shade Major Coat meter or Elcometer Random Tech specification/Drawings Tech specification/Drawings Painting report S E
s
7 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.1.3 3. Drawings
2.4 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
2.7 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
Visual/Mesur
3.4 Grouting Critical Tape 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
ement
4.1 Flange connection of inlet and outlet ducts Major Verification Torque wrench. 100% Tech specification/Drawings Tech specification/Drawings SIR S E
Measurement
4.2 Fit up inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
s
Measurement
4.3 Final weld inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing/ASME/ANSI/API/AWS/DIN/IBR/IS/BS WISR S E
s
5.1 Final Inspection Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Measurement
6.1 Painting thikness and shade Major Coat meter or Elcometer Random Tech specification/Drawings Tech specification/Drawings Painting report S E
s
7 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.1.3 3. Drawings
2.4 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
Check for cleanliness of coal feeders before Outer and inner surfaces to be free from
2.5 Major Verification Nil 100% Nil ITSR S E
erection. dust and sticking dirts.
2.7 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
5.1 Final Inspection Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Measurement
6.1 Painting thikness and shade Major Coat meter or Elcometer Random Tech specification/Drawings Tech specification/Drawings Painting report S E
s
7 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.1.3 3. Drawings
2.4 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
2.7 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
Measurement Tape,
3.4 Level and straitness of piping Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
s Spirit level,water level
Measurement
3.5 Fit up inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
s
Measurement
3.6 Final weld inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing/ASME/ANSI/API/AWS/DIN/IBR/IS/BS WISR S E
s
4.1 Final Inspection Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Measurement
5.1 Painting thikness and shade Major Coat meter or Elcometer Random Tech specification/Drawings Tech specification/Drawings Painting report S E
s
6 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.1.3 3. Drawings
2.4 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
2.7 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
Measurement Tape,
3.4 Level and straitness of piping Major 100% Tech specification/Drawings Tech specification/Drawings Pipe alingment report S E
s Spirit level,water level
Measurement
3.5 Fit up inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
s
Measurement
3.6 Final weld inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing/ASME/ANSI/API/AWS/DIN/IBR/IS/BS WISR S E
s
4.1 Final Inspection Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Measurement
5.1 Painting thikness and shade Major Coat meter or Elcometer Random Tech specification/Drawings Tech specification/Drawings Painting report S E
s
6 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.1.3 3. Drawings
2.4 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
2.7 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
3.2 Tiling works Major Visual NIL 100% Tech specification/Drawings Tech specification/Drawings SIR S E
Measurement
3.3 Fit up inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
s
Measurement
3.4 Final weld inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing/ASME/ANSI/API/AWS/DIN/IBR/IS/BS WISR S E
s
Measurement
4.1 Painting thikness and shade Major Coat meter or Elcometer Random Tech specification/Drawings Tech specification/Drawings Painting report S E
s
5.1 Final Inspection Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
Measurement
6.1 Painting thikness and shade Major Coat meter or Elcometer Random Tech specification/Drawings Tech specification/Drawings Painting report S E
s
7 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.1.3 3. Drawings
2.4 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
2.7 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
3.5 NDT-DPT Critical Visual DPT Kit 5% Tech specification/Drawings Tech specification/Drawings/AWS D 1.1 NDT report S EF
Measurement Tape,
4.1 Hanger supports Major 100% Tech specification/Drawings Tech specification/Drawings SIR S E
s Spirit level,water level
5.1 Final Inspection Critical Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S EF
6 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.1.3 3. Drawings
2.4 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
2.6 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
2.8 Check that surface is clean and dressed Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Front release report. S E
3.8 Check filling condition of mortar Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
Measurement
7.1 Painting thikness and shade Major Coat meter or Elcometer Random Tech specification/Drawings Tech specification/Drawings Painting report S E
s
8 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
3 Surface preparation Major Visual Nil Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Primer coat
4 Correct primer paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
4.1 Dry film thickness Major Measurement Coat meter or Elcometer Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Intermediate coat
5 Correct paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
5.1 Dry film thickness Major Measurement Coat meter or Elcometer Random Tech specification/Drawings Tech specification/Drawings Painting report S E
Final coat
6 Correct paint Major Verification Nil 100% Tech specification/Drawings Tech specification/Drawings Painting report S E
Measurement
6.1 Dry film thickness Critical Coat meter or Elcometer Random Tech specification/Drawings Tech specification/Drawings Painting report S EF
s
6.2 Color Major Verification Shade card Random Tech specification/Drawings Tech specification/Drawings Painting report S E
6.3 Adhesion test Critical Verification Sharp knife,Adhesive tape Random Tech specification/Drawings Tech specification/Drawings Painting report S EF
7 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.3 1. Drawings
2.7 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
3.1 Surface preparation Major Visual NIL 100% Tech specification/Drawings Tech specification/Drawings SIR S E
Measurement
4.1 Water quality (PH,NH4,Ca,Cl,kand So4 values) Critical Lab test Once per source Tech specification/Drawings Tech specification/Drawings Lab Test report S EF
s
Measurement
4.2 Quantity of fiber added Major NIL 100% Tech specification/Drawings Tech specification/Drawings Log sheet S E
s
Measurement
4.3 Quantity of water added Major NIL 100% Tech specification/Drawings Tech specification/Drawings Log sheet S E
s
Measurement
4.4 Selection of samples and testing Major Random Tech specification/Drawings Tech specification/Drawings Log sheet S E
s
Measurement
4.5 Mixing time Major NIL 100% Tech specification/Drawings Tech specification/Drawings Log sheet S E
s
5 Final inspection before insullation. Major Verification NIL 100% Tech specification/Drawings Tech specification/Drawings Check list S E
Thermal Insulation.
6 Surface cleanliness Minor Visual Nil 100% ------ Free from foreign particles. Insulation test record S S
6.1 Placement of spacers Minor Measurement Measuring tape 100% Specific Drg. as per SpecificDrg. Insulation test record S S
6.2 Support stud welding -completeness Minor Visual Nil 100% Specific Drg. as per Specific Drg. Insulation test record S S
6.3 Placing of correct insulation material Major Verification Nil 100% Specific Drg. or Datas sheet As per specific Drg. or Data sheet Insulation test record S E
6.4 Thickness of each layer Major Measurement Measuring tape Random Specific Drg. as per Specific Drg. Insulation test record S E
Clading
7 Use of correct fastners Major Verification Nil Random Specific Drg. or Datas sheet Data sheet Insulation test record S E
7.1 Void between insulation and cladding Major Verification Nil Random ------------- Free of voids Insulation test record S E
7.2 Overlap of cladding sheets Major Verification Nil 100% Specific Drg. As per specific Drg. Insulation test record S E
7.3 Flushing of vertical cladding Major Verification Nil 100% Specific Drg. As per specific Drg. Insulation test record S E
7.4 Sealing of cut outs Major Verification Nil 100% Specific Drg. As per specific Drg. Insulation test record S E
7.5 Damages to cladding Major Visual Nil 100% ----- Freedom from damages Insulation test record S E
8 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer
2.1.1 1. WPS
2.1.3 3. Drawings
2.4 Erection marking before release for erection. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
2.7 Readiness of all safety aspects before erection. Major Verification Nil 100% Safety guidelines/manual Safety guidelines/manual Safety check list. S E
3 Check for the coloumn oriantation Major Visual Water level,tape,theodolite 100% Tech specification/Drawings Tech specification/Drawings Coloumn Verticality report S E
Measurement
3.1 Check for coloumn axis and level Major Water level,tape,theodolite 100% Tech specification/Drawings Tech specification/Drawings Coloumn Verticality report S E
s
Measurement
3.2 Check for coloumn verticality-before grouting Major Water level,tape,theodolite 100% Tech specification/Drawings Tech specification/Drawings Coloumn Verticality report S E
s
Visual/Mesur
3.3 Grouting Critical Tape 100% Tech specification/Drawings Tech specification/Drawings Grouting release reports S EF
ement
Measurement
3.4 Check for coloumn verticality-after grouting. Critical Water level,tape,theodolite 100% Tech specification/Drawings Tech specification/Drawings Coloumn Verticality report S EF
s
Level of supports of beams,trusses,purlins,girders Measurement
3.5 Major Water level,tape,theodolite Random Tech specification/Drawings Tech specification/Drawings Coloumn Verticality report S E
etc. s
Torque tightening of nuts and bolts(whereever
3.6 Major Verification Torque wrench. Random Tech specification/Drawings Tech specification/Drawings Torque tighting report S E
applicable)
Welding on attachments,brazing,etc where ever
3.7 Major Visual Nil Random Tech specification/Drawings Tech specification/Drawings/AWS D 1.1 WISR S E
applicable
Casing
Measurement
5.1 Diagonal checkbefore welding Major level,tape 100% Tech specification/Drawings Tech specification/Drawings ESP Inspection report S E
s
Measurement
5.2 Fit up inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
s
Measurement
5.3 Final weld inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing/ASME/ANSI/API/AWS/DIN/IBR/IS/BS WISR S E
s
5.4 NDT- DPT on casing welding. Critical Visual DPT Kit 5% Tech specification/Drawings Tech specification/Drawings/AWS D 1.1 NDT report S EF
6.4 NDT- DPT on hooper and funnels. Critical Visual DPT Kit 5% Tech specification/Drawings Tech specification/Drawings/AWS D 1.1 NDT report S EF
Outer roof
Measurement
7 Dimention,levelling and diagonals of outer roof Major level,tape 100% Tech specification/Drawings Tech specification/Drawings ESP Inspection report S E
s
Measurement
7.1 Diagonal checkbefore welding of outer roof Major level,tape 100% Tech specification/Drawings Tech specification/Drawings ESP Inspection report S E
s
Measurement
7.2 Fit up inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing Fit Up inspection report S E
s
Measurement
7.3 Final weld inspection Major Weld gauge/Template Random WPS/Drawing WPS/Drawing/ASME/ANSI/API/AWS/DIN/IBR/IS/BS WISR S E
s
7.4 NDT- DPT on outer roof Critical Visual DPT Kit 5% Tech specification/Drawings Tech specification/Drawings/AWS D 1.1 NDT report S EF
Measurement
8 Dimention and levelling Major level,tape 100% Tech specification/Drawings Tech specification/Drawings ESP Inspection report S E
s
Water level,tape,dumpy
Measurement
8.1 Motor (rapping) alingment Major level,Feeler gauge,dial 100% Tech specification/Drawings Tech specification/Drawings Alingment report S E
s
gauge
Emitting suspention
Measurement
9 Dimention and levelling Major level,tape 100% Tech specification/Drawings Tech specification/Drawings ESP Inspection report S E
s
9.1 Cleaning Major Visual Nil Random Nil Surfaces to be free from dust and sticking dirts. ITSR S E
Water level,tape,dumpy
Measurement
9.2 Motor alingment Major level,Feeler gauge,dial 100% Tech specification/Drawings Tech specification/Drawings Alingment report S E
s
gauge
Emitting electrodes
Measurement
10 Dimention and levelling Major level,tape 100% Tech specification/Drawings Tech specification/Drawings ESP Inspection report S E
s
For first 20
electrodes
100% checking
Measurement tobe carried
10.1 Streaching values Critical Tape Tech specification/Drawings Tech specification/Drawings ESP Inspection report S EF
s out.Thereafter
one out of every
50 electrodes is
to be checked.
Measurement
11 Positioning of rapping shafts Major level,tape 100% Tech specification/Drawings Tech specification/Drawings ESP Inspection report S E
s
11.2 Engagment of pin wheel Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ITSR S E
11.3 Locking of bolts and nuts and tack welds Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ESP Inspection report S E
Water level,tape,dumpy
Measurement
11.4 Checking of hammer assy motor alingment Major level,Feeler gauge,dial 100% Tech specification/Drawings Tech specification/Drawings Alingment report S E
s
gauge
Collecting frame/rapping/drive.
Measurement
12 Dimention and levelling Major level,tape 100% Tech specification/Drawings Tech specification/Drawings ESP Inspection report S E
s
Measurement
12.1 straightness/buckling/twisting Major level,tape 100% Tech specification/Drawings Tech specification/Drawings ESP Inspection report S E
s
Water level,tape,dumpy
Measurement
12.2 Checking of hammer assy motor alingment Major level,Feeler gauge,dial 100% Tech specification/Drawings Tech specification/Drawings Alingment report S E
s
gauge
Measurement
13 Dimention and levelling Major level,tape 100% Tech specification/Drawings Tech specification/Drawings ESP Inspection report S E
s
13.1 Tightness of insulator housing casing Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ESP Inspection report S E
Inspection door
14 Tightness ,easy to open and close. Major Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ESP Inspection report S E
Measurement
15 Dimention and levelling Major level,tape 100% Tech specification/Drawings Tech specification/Drawings ESP Inspection report S E
s
Measurement
15.1 Oil test for TR sets Critical Transformer oil testing kit 100% Tech specification/Drawings Tech specification/Drawings ESP Inspection report S EF
s
Measurement
16 Dimention and levelling Major level,tape 100% Tech specification/Drawings Tech specification/Drawings ESP Inspection report S E
s
Measurement
16.1 straightness/buckling/twisting Major level,tape 100% Tech specification/Drawings Tech specification/Drawings ESP Inspection report S E
s
Torque tightening of nuts and bolts(whereever
16.2 Major Verification Torque wrench. Random Tech specification/Drawings Tech specification/Drawings Torque tighting report S E
applicable)
16.3 Gas tightness test Critical Visual Nil 100% Tech specification/Drawings Tech specification/Drawings ESP Inspection report S EF
17 Verification of quality records for completeness Critical Verification NIL 100% Field quality plan Field quality plan ITSR S EF
Note: Abbreviations: P - Performed by, W - Witnessed by, H-Witness by customer, S – Avlon Supervisor, E – Avlon Engineer, F – Avlon Manager, C – Customer