Midterm Examination

Date:
Subject: Professional Practice 3

Name: clark harley brinas Year and Section: 4rth year

Matching Type
Part I. ( 1 point each ) - 5 points
Select the corresponding word below that describes the statement.

1. architect - will set the project against present and future


trends and forecast how it will perform overtime.
2. client - a call upon the Architect to give oral or
written advice and direction.
3. Value management - is a technique applied in the cost management
process to minimize negative effect of simplified operation and
to achieve an unimpaired program at minimum cost.
4. Terms of reference - shall states the project terms of reference
including concept and objectives.
5. Architectural research - is an analytical problem-seeking process that
leads to the statement and identification of both horizontal and
vertical requirements in offering solutions.

Design Brief Preparation Consultation Value Management


Feasibility Studies Site Selection Pre-Feasibility Studies

Part II. ( 2 points each ) - 4 points


Selection Type.
1. Type of Lighting which act as reflector and maximize shadows.

a. Task Light answer: a


b. Hidden Light
c. Indirect Light
d. Diffused Light
2. Light that falls from luminaires and in partly directional manner

a. Task Light answer: b


b. Direct Light
c. Task Light
d. Diffused Light

Part III. – 8 points


Enumerate.
Indicate Four Technical Aid/Tool in Architectural Interior Services.
1.sketchpad
2.pen/pencil
3.color swatches
4.interior rendering sofware/sketchup/vray/lumion

Indicate Four Work Processes in Site Development Planning.


1.site exploration

2.site investigation
3.foundation investigation
4.tracking/evaluation maintenance

Part IV.
Select the correct term. (2 points each ) – 10 points
1. LA (on CDP Implementation)

a.Land Allocation
b.Legal Assessment
c.Low Asset
d.Legislative Agenda
Answer:d
2. LGPMS (on CDP Evaluation)

a. Local Governance Performance Management System


b.Local Governance Performance Monitoring Sytem
c.Local Governance Productivity Monitoring Sytem
d.Local Governance Productivity Management System

Answer: a
3. EIA/S (on CDP Services)
a. Environmental Impact Attributes/System
b.Environmental Impact Assessment/Statement
c.Environmental Issuance Approval/Support
d.Environmental Issuance Access/System

Answer:b

4. CLUP ( on CDP Services)

a. Comprehensive Local Utilization Plan


b.Comprehensive Land Utilization Plan
c.Comprehensive Land Use Plan
d.Comprehensive Legal Utilization Plan

Answer: c
5. PPA’s ( on CDP Services) a.Personnel,

Project, Assessments
b.Professionals, Personnel, Assistants
c.Program, Project, Activities
d.Planning, Proposals, Action Plan
answer : c
Part V. ( Category ) 2 points each - 10 Points
Select the corresponding tools and elements.

1. Design aspect of Acoustic Design

1. Room Volume,Structural Precaution,Balance


2. Blend, Insulation, Air Transmission
3. Room Volume, Geometry,Placement of Materials
4. Definition ,Blend, Geometry
Answer: 3

2.4 plan, monitoring and evaluation

3.2 CDP preparation

4.1 organization and and mobilization of planning structure

5.3 CDP implementation

Part IV:

Scope of service of acoustic design


-SchematicDesign Determine volumes anddimensions,Determine room
locationsand adjacencies,Determine amount ofadjustable acoustic
material and Broad discussion of roomfinishes.
DesignDevelopment Determine adjustableacoustic material and locations
And Discuss room finishoptions also Provide layouts for orches-tra
shell and risers. ConstructionDocuments Provide guideline specifica-
tions for acoustic materialsand constructions,Review theater consul-
tant’s documents Review architect’s documents.
ConstructionAdministration Prepare submittal review list, Review
submittals andshop drawings of acousticmaterials.
Postconstruction Tune adjustable acousticsystems for each programuse
Set the orchestra shell foreach program use and Measure RT60and
otherarchitectural acousticalparameters .

Part VII:

If I will be choosing an advance study to support the allied service


I’d choose “BUILDING TESTING AND COMMISSIONING”. because if I practiced
this service I am sure as an aspiring architect that I can ensure that
the success of the project’s will be 100% guaranteed to be
efficient,and the building will perform as it intends to be.I can
verify that when a building is taking over by the owner that I am
assured that all of the phases architecturl, electrical,plumbing,
mechanical is built well to reach the clients expectation.