LAMPIRAN

A. TRAJECTORY
Casing
Section Depth (ft) Bit (in)
OD (in) ID (in)
Casing Conductor 0 200 - 30 28,75
Casing Surface 0 4200 26 20 19
Casing Intermediate I 0 7500 17 1/2 13 3/8 12,415
Casing Intermediate II 0 9514 12 1/4 9 5/8 8,835
Casing Production 0 11302,49 7,875 5 1/2 4,67

B. UJI LABORATORIUM
a. Komposisi Semen
Wsemen = 350 gr
Wbarite = 12 gr
WNaCl =3 gr
Volume air = 163,46 ml
b. Hasil Uji Laboratorium
Densitas = 15,2 ppg
C600 = 178
C300 = 96
PV = C600 - C300 = 82 cp
YP = C300 – PV = 14 lb/100ft2
Filtration Loss = 12,5 ml @5 menit

C. PERENCANAAN
1) INTERMEDIET CASING 1
a. Material Design
- Berat semen (Ws) = 350 gr
- Berat barite = 12 gr
- Berat garam =3 gr
- BWOC barite = 0,20 %
- BWOC garam = 0,02 %
- Densitas barite = 4,48 gr/cc
- Densitas garam = 1,095 gr/cc
- Densitas Semen = 3,14 gr/cc
Perhitungan :
Volume Air Total =

%WCR+ ( %BWOC barite x % Additive )


( ) x Berat Semen
100
0,46 + ( 0,2 x 3,428571 )
=( ) x 350
100
= 163,46 ml
Wadditive 12
Volume barite = = = 2,678571 ml
ρadditive 4,48
Wadditive 3
Volume garam = = = 2,739726
ρadditive 1,095
ml
W semen 350
Volume semen (Vs) = ρsemen = 3,14 = 111,465 ml
W air + W add + W semen
ρsemen teoritis = ( V air + V add + V semen )
× 8,33

= 1,885 × 8,33
= 15,702 ppg
% Kesalahan =

Densitas teoritis−densitas ukur


( Densitas teoritis
x 100 % )
= (15, 702 - 1 5,52
15, 702 ) x 100%
= 3,199724 %
Pengujian Rheology :
C600 = 178
C300 = 96
PV = C600 - C300 = 82 cp
YP = C300 – PV = 14 lb/100ft2
Filtration Loss = 12,5 ml @5 menit
b. Cement Volume
Data :
Intermediate I
Depth 7500 ft
Perforasi 7299,869-7309,711 ft
Interval Perfo 9,842 ft
Kedalaman 7299,869 ft
  7309,711 ft
Gradien rekah (Gr) 0,865 psi/ft
SF 100
Densitas Semen (roS) 15,2 ppg
Densitas Fluida Pendorong (roC) 15 ppg
Kedalman Packer (D1) 7269,869 ft
Selisih perfo dan packer (D2) 30 ft
Psq 0 psi

Data Laboratorium
Densitas 15,2 ppg
PV 82 cp
YP 14 lb/ft^2
Filtration loss 61,724599 ml
Data Trayek Intermediete I
OD Casing 13,375 in
ID Casing 12,415 in
Tubing Production
OD tubing 2,875 inch
ID tubing 2,441 inch

Fraksi Slurry
Semen 0,3976

Air 0,5831
Additive 1 0,0096

Additive 2 0,0098
Total 1

Perhitungan :
Perhitungan volume semen
- Kapasitas tubing

π idt 2 3,14 x 2,4412


Ct =
4 x 144 = 4 x 144 = 0,0324 ft^3

- Tinggi kolom semen

L=
[ ( Gr H − SF ) − ( 0 . 052 H ρ c ) ]
0 .052 ( ρ − ρ c ) = 2003,489 ft
- Volume semen
Vs = Ct x L
= 0,0324 x 2003,489
= 65,0773 ft^3
- Yield
Yield = Vs / 7,48
= 65,0773 / 7,48
= 8,700 ft^3/sak
- Semen yang dibutuhkan
S = Vs / yield
= 65,0773 ft^3/8,700 ft^3/sak
= 55,95 sak
- Tekanan eksternal
Pe = Psq + (0.052 x D1 x rs) - (0.052 x D2 x rc)
= 5722,704458 psi
- Tekanan hidrostatik fluida
Ph = 0.052 x D1 x rc
= 5670,498 psi
Perhitungan Spacer dan displacement
- Level slurry = 2003,489 ft
- Volume water ahead = 10 bbl
- Volume water behind
Vwa x C tubing
Vwb = = 2,293 bbl
C annulus
- Total volume spacer
Vspacer = Vwa + Wwb
= 10 + 2,293 = 12,293 bbl
- h Spacer
Total Spacer (bbls)
h spacer (ft)= Cap. annulus bbl +cap . tubing bbl
( )
ft ( )
ft ¿
¿
= 70,571 ft
- Level Spacer
Level spacer = Lever slurry – h spacer
= 2003,489 - 70,571
= 1932,918 ft
- Displacement volume
Dis. Volume = (Open end – (h slurry + h spacer)) x Cap. Tubing
= 169,016 bbl

Pehitungan lapangan
Volume di lapangan = Vs x Fraksi Slurry
Massa di lapangan = Densitas semen x volume semen lapangan
Volume Massa
cuf 2301,82 k
Volume semen 25,8879814 t Massa semen 7 g
cuf 78,9197 k
Volume air 37,9639406 t Massa Barite 9 g
cuf 19,7299 k
Volume Barite 0,62210404 t Massa NaCl 5 g
cuf
Volume NaCl 0,63630733 t      

c. Thickening Time
- Saat ditubing
Target NRe = 4100
Nre×PV
Valir @tubing =
928 ×ρsemen×ID  Tubing
4100 × 82
=
928 × 15,2 x 2,441
= 9,764 ft/s
= 585,854 ft/min
Rate Pompa =

Kecepatan Alir   (ftmin ) × (IDcasing 2  - ODtubing 2 )


24,5
585,854 × (12,415 2  - 2,875 2 )
=
24,5
= 142,482 gpm
Volume Semen Total ( bbl ) × 42 gal/bbl
Waktu Pompa =
Rate Pompa  (gpm)
11,597 × 42 gal/bbl
=
142,482
= 3,418 menit
- Saat dicasing
Target NRe = 100
Nre×PV
Valir @tubing =
928 ×ρsemen×ID   Casin g
100 × 82
=
928 × 15,2 x 12,415
= 0,047 ft/s
= 2,809 ft/min

Rate Pompa =
Kecepatan Alir   (ftmin ) × (IDcasing 2)
24,5
2,809 × (12,415 2 )
=
24,5
= 17,675 gpm
Volume Semen Total ( bbl ) × 42 gal/bbl
Waktu Pompa =
Rate Pompa  (gpm)
11,597 × 42 gal/bbl
=
17,675
= 27,557 menit
- Thickening time
Thickening Time = Waktu pemompaan (@casing +@tubing) + 90
= 3,418 + 27,557 + 90
= 120,975 menit
= 2,016 jam
d. Pump Plan
- Perhitungan rate
Rate total = Rate tubing + Rate casing
= 142,4817 gpm + 17,6747 gpm
= 160,1564 gpm
Effisiensi = 80%
Rate effisiensi = Rate total x Effisiensi
= 0,8 x 160,1564 gpm
= 200,1956 gpm
Rate pompa = 200 gpm
- Perhitungan pressure lost
Desitas semen = 15,2 ppg
PV = 82 cP
YP = 14 lb/100ft^2
ID casing = 12 2/5 in
OD casing = 2 7/8 in
ID tubing = 2 4/9 in
Kedalaman tubing = 7304,79 ft
Kecepatan alir casing = 0,0047 ft/s
Pressure Lost =

0.0000765 x (PV )0.18 x (ρ slury )0.82 x (Qpompa)1.82 xdept h packer


ID Tubing 4.82
0.0000765 x (82)0.18 x(15,2)0.82 x (200)1.82 x 7304,79
=
2,44 4.82
= 2402,51 psi
- Perhitungan horse power
Pf @7304,79 ft = 3397 psi
P Pompa = 100 psi
Hp =

( Pf @ kedalaman pemboran+ Ppompa )∗Qpompa(gpm)


1714
( 3379+ 100 )∗200( gpm)
=
1714
= 408,02 Hp
e. Economical
Harga
Rp 65.000,00 /50kg
Semen
Rp 1.300,00 /kg
Barite Rp 15.000,00 /kg
Nacl Rp 5.000,00 /kg
Rp 16.435.225 /Ton
CMHEC
Rp 16.435 /kg
CaCo3 Rp 5.000,00 /kg
Spacer Fluid Rp 9.000,00 /Liter
Pompa Rp 48.500.000,00 Sewa

Pada squeeze cementing dibutuhkan :


- Semen
2301,82 Kg × Rp 1.300 = Rp 2.999.375,45
- Barite
79,92 Kg × Rp 15.000 = Rp 1.183.796,88
- NaCl
19,73 Kg × Rp 5.000 = Rp 98.649,74
- Spacer Fluids
1954,5 Liter× Rp 9.000 = Rp 17.590.503,54
- Total = Rp 21.865.325,62
2) INTERMEDIET CASING II
a. Material Design
 Lead slurry
- Berat semen (Ws) = 350 gr
- Berat barite = 35 gr
- Berat CMHEC =3 gr
- BWOC barite = 0,2 %
- BWOC CMHEC = 0,3 %
- Densitas barite = 4,48 gr/cc
- Densitas CMHEC = 1,9 gr/cc
- Densitas Semen = 3,14 gr/cc
0,46 + ( 0,2 x 10 ) +(0,3 x 0,8571)
Volume Air Total =( ) x 350
100
= 168,9 ml
Wadditive 35
Volume barite = = = 7,8125 ml
ρadditive 4,48
Wadditive 3
Volume CMHEC = = = 1,5789 ml
ρadditive 1,9
W semen
350
Volume semen (Vs) = ρsemen = 3,14 = 111,465 cc

W air + W add + W semen


ρsemen teoritis = ( )
V air + V add + V semen
× 8,33

= 1,922× 8,33
= 16,01 ppg
 Tail Slurry
- Berat semen (Ws) = 350 gr
- Berat barite = 135 gr
- Berat CMHEC =3 gr
- BWOC barite = 0,2 %
- BWOC CMHEC = 0,3 %
- Densitas barite = 4,48 gr/cc
- Densitas CMHEC = 1,9 gr/cc
- Densitas Semen = 3,14 gr/cc
Volume Air Total =

0,46 + ( 0,2 x 38,571 ) +(0,3 x 0,8571)


( ) x 350
100
= 188,9 ml
Wadditive 135
Volume barite = = = 30,134 ml
ρadditive 4,48
Wadditive 3
Volume CMCHEC = = = 1,5789 ml
ρadditive 1,9
W semen
350
Volume semen (Vs) = ρsemen = 3,14 = 111,465 cc

W air + W add + W semen


ρsemen teoritis = ( V air + V add + V semen )
× 8,33

= 2,038 × 8,33
= 16,98 ppg
b. Cement Volume
Data :
INTERMEDIATE II
ID 8,835 inch
OD 9 5/8 inch
OH 12 1/4 inch
%excess 1  
L C-C (lead) 7500 ft
LC-OH (lead) 1007 ft
L C-OH (tail) 1007 ft
L C-ST (tail) 14,146 ft
L pocket (tail) 6,890 Ft

Fraksi Slury Intermediete II


Lead Tail
0,3846850 0,3356591
semen 74 semen 54
0,5829034 0,5688425
air 01 air 27
0,0269623 0,0907435
barite 02 barite 68
CMHE 0,0054492 CMHE 0,0047547
C 23 C 51
Total 1 Total 1
Perhitungan volume semen :
Volume C-C lead = [(ID1)2 – (OD2)2] x 0,005454 x L
= 2515,314 cuft
Volume C-OH lead = [(OH)2 –(OD2)2 x 0,005454 x L x (%excess+1)
= 630,742 cuft
Volume C-OH tail = [(OH)2 – (OD2)2 x 0,005454 x L x
(%excess+1)
= 630,742 cuft
Volume Shoe Track = (ID2)2 x 0,005454 x L
= 6,022 cuft
Volume Pocket = (OH)2 x 0,005454 x L x (%excess+1)
= 11,278 cuft
Volume Lead Slurry = Volume C-C + Volume C-OH lead
= 3146 cuft
Volume Tail Slurry = Volume C-OH tail + V. Shoetrack + V.
Pocket
= 648 cuft
Total Volume slurry = Volume Lead Slurry + Volume Tail Slurry
= 3794 cuft
Displacement volume = ID x 0,005454 x kedalaman
= 457,810 cuft
Perhitungan volume semen lapangan
Volume di lapangan = Vs x Fraksi Slurry
Massa di lapangan = Densitas semen x volume semen lapangan
VOLUME MASSA
Lead (di Lapangan) Lead (di Lapangan)
cuf 107608,4
Volume semen 1210,241 t Massa semen 5 kg
cuf
Volume air 1833,847 t Massa barite 10760,84 kg
cuf Massa
Volume Barite 84,825 t CMHEC 52,82 kg
Volume 17,144 cuf Tail (di Lapangan)
CMHEC t
Tail (di Lapangan) Massa semen 19340,88 kg
cuf
Volume semen 217,521 t Massa barite 7460,056 kg
cuf Massa
Volume air 368,634 t CMHEC 165,779 kg
cuf
Volume Barite 58,806 t Total Massa
Volume cuf 126949,3
CMHEC 3,081 t Massa semen 3 kg
Massa barite 18220,9 kg
Massa
  CMHEC 218,60 kg

c. Thickening Time
- Lead saat di casing
Target NRe = 4100
Nre×PV
Valir @tubing =
928 ×ρsemen×ID   Casing
4100 × 82
=
928 × 16,01 x 8,835
= 1,562 ft/s
= 93,705 ft/min

Rate Pompa =
Kecepatan Alir   (ftmin ) × (IDcasing 2)
24,5
93,705 × (8,835 2 )
=
24,5
= 298,544 gpm
Volume Semen Total ( bbl ) × 42 gal/bbl
Waktu Pompa =
Rate Pompa  (gpm)
2067,47 × 42 gal/bbl
=
142,482
= 290,857 menit
- Lead saat di annulus
Target NRe = 100
Nre×PV
Valir @tubing =
928 ×ρsemen× (Bit size - OD  Casin g )
100 × 82
=
928 × 16,01 x (12,25 - 9,625)
= 2,308 ft/s
= 138,461 ft/min
Rate Pompa =

Kecepatan Alir   (ftmin ) × (Bit size2 - ODcasing 2)


24,5
2,809 × (12,25 2 - 9,625 2 )
=
24,5
= 324,518 gpm
Volume Semen Total ( bbl ) × 42 gal/bbl
Waktu Pompa =
Rate Pompa  (gpm)
2067,47 × 42 gal/bbl
=
17,675
= 267,578 menit
- Thickening Time Lead
Thickening Time
= Waktu pemompaan (@casing +@annulus) + 90
= 290,857 + 267,578 + 90
= 648,435 menit
= 10,807 jam
- Tail saat di casing
Target NRe = 4100
Nre×PV
Valir @tubing =
928 ×ρsemen×ID   Casing
4100 × 82
=
928 × 16,98 x 8,835
= 1,178 ft/s
= 70,682 ft/min
Rate Pompa =
Kecepatan Alir   (ftmin ) × (IDcasing 2)
24,5
70,682 × (8,835 2 )
=
24,5
= 225,195 gpm
Volume Semen Total ( bbl ) × 42 gal/bbl
Waktu Pompa =
Rate Pompa  (gpm)
2067,47 × 42 gal/bbl
=
225,195
= 21,527 menit
- Tail saat di annulus
Target NRe = 100
Nre×PV
Valir @tubing =
928 ×ρsemen× (Bit size - OD  Casin g )
100 × 82
=
928 × 16,98 x (12,25 - 9,625)
= 1,741 ft/s
= 104,442 ft/min
Rate Pompa =

Kecepatan Alir   (ftmin ) × (Bit size2 - ODcasing 2)


24,5
104,442 × (12,25 2 - 9,625 2 )
=
24,5
= 244,787 gpm
Volume Semen Total ( bbl ) × 42 gal/bbl
Waktu Pompa =
Rate Pompa  (gpm)
225,195 × 42 gal/bbl
=
104,442
= 354,732 menit
- Thickening Time Tail
Thickening Time
= Waktu pemompaan (@casing +@annulus) + 90
= 21,527 + 354,732 + 90
= 466,259 menit
= 7,771 jam
d. Pump Plan
- Perhitungan rate
 Lead Slurry
Rate total = Rate tubing + Rate casing
= 298,544 gpm + 324,518 gpm
= 632,062 gpm
Effisiensi = 80%
Rate effisiensi = Rate total x Effisiensi
= 0,8 x 632,062 gpm
= 778,824gpm
Rate pompa = 800 gpm
 Tail Slurry
Rate total = Rate tubing + Rate casing
= 225,195 gpm + 244,787 gpm
= 469,981 gpm
Effisiensi = 80%
Rate effisiensi = Rate total x Effisiensi
= 0,8 x 469,981 gpm
= 587,477 gpm
Rate pompa = 600 gpm
- Perhitungan pressure lost
 Lead Slurry
Desitas semen = 16,010 ppg
PV = 82 cP
YP = 14 lb/100ft^2
Bit Size = 12 ¼ in
ID casing = 8,835 in
OD casing = 9 5/8 in
Kedalaman Casing soe = 7486,877 ft
Kecepatan alir@annulus = 2,308 ft/s
Pressure loss @casing = 10,81 psi
Pressure loss @annulus = 314,54 psi
Pressure Lost Total = Presloss @casing + Presloss @annulus
= 10,81 + 314,54
= 325,35 psi
 Tail Slurry
Desitas semen = 16,980 ppg
PV = 82 cP
YP = 14 lb/100ft^2
Bit Size = 12 ¼ in
ID casing = 8,835 in
OD casing = 9 5/8 in
Kedalaman Casing shoe = 7486,877 ft
Kecepatan alir@annulus = 1,178 ft/s
Pressure loss @casing = 40,412 psi
Pressure loss @annulus = 247,44 psi
Pressure Lost Total = Presloss @casing + Presloss @annulus
= 40,412 + 247,44
= 287,85 psi
- Perhitungan horse power
Pf @7304,79 ft = 5168 psi
P Pompa = 100 psi
Hp =
( Pf @ kedalaman pemboran+ Ppompa )∗Qpompa(gpm)
1714
( 5168+ 100 )∗600+ 800(gpm)
=
1714
= 2151,25 Hp
e. Economical
Harga
Rp 65.000,00 /50kg
Semen
Rp 1.300,00 /kg
Barite Rp 15.000,00 /kg
Nacl Rp 5.000,00 /kg
Rp 16.435.225 /Ton
CMHEC
Rp 16.435 /kg
CaCo3 Rp 5.000,00 /kg
Spacer Fluid Rp 9.000,00 /Liter
Pompa Rp 48.500.000,00 Sewa

Pada Intermediate II cementing dibutuhkan :


- Semen
416383,05 Kg × Rp 1.300 = Rp 541.297.960,33
- Barite
47164,27 Kg × Rp 15.000 = Rp 707.464.075,20
- CMHEC
360,68 kg x Rp 16.435 = Rp 5.927.918,50
- Total = Rp 1.254.689.954,04

3) PRODUCTION CASING
a. Material Design
 Lead Slurry
- Berat semen (Ws) = 350 gr
- Berat CMHEC = 12 gr
- BWOC CMHEC = 0,3 %
- Densitas CMHEC = 1,9 gr/cc
- Densitas Semen = 3,14 gr/cc
0,46 + ( 0,3 x 3,42857143)
Volume Air Total =( ) x 350
100
= 164,6 ml
Wadditive 12
Volume CMHEC = = = 6,31578947 ml
ρadditive 1,9
W semen 350
Volume semen (Vs) = ρsemen = 3,14 = 111,465 cc
W air + W add + W semen
ρsemen teoritis =( )
V air + V add + V semen
× 8,33

=1,86 × 8,33
= 15,53 ppg
 Tail Slurry
- Berat semen (Ws) = 350 gr
- Berat CaCO3 = 154 gr
- Berat CMHEC = 12 gr
- BWOC CaCO3 = 0,05 %
- BWOC CMHEC = 0,3 %
- Densitas CaCO3 = 2,71 gr/cc
- Densitas CMHEC = 1,9 gr/cc
- Densitas Semen = 3,14 gr/cc
Volume Air Total =

0,46 + ( 0,3 x 3,4286 ) +(0,05 x 44)


( ) x 350
100
= 172,3 ml
Wadditive 154
Volume CaCO3 = = = 58, 827 ml
ρadditive 2,71
Wadditive 12
Volume CMHEC = = = 6,3158 ml
ρadditive 1,9
W semen 350
Volume semen (Vs) = ρsemen = 3,14 = 111,465 ml
W air + W add + W semen
ρsemen teoritis =( )
V air + V add + V semen
× 8,33

= 1,984 × 8,33
= 16,53 ppg
b. Cement Volume
PRODUCTION
ID 4,67 inch
OD 5 1/2 inch
OH 7,875 inch
%excess 1  
L C-C (lead) 9514 ft
LC-OH (lead) 894,245 ft
LC-OH (tail) 894,245 ft
L C-ST (tail) 31,743 ft
L pocket (tail) 6,890 ft

Fraksi Slury Production


Lead Tail
semen 0,395 semen 0,321
air 0,583 air 0,497
CMHEC 0,022 CaCO3 0,164
additive 0 CMHEC 0,018
Total 1 Total 1

Perhitungan volume semen :


Volume C-C lead = [(ID1)2 – (OD2)2] x 0,005454 x L
= 2480,686 cuft
Volume C-OH lead = [(OH)2 –(OD2)2 x 0,005454 x L x (%excess+1)
= 309,855 cuft
Volume C-OH tail = [(OH)2 – (OD2)2 x 0,005454 x L x
(%excess+1)
= 309,855 cuft
Volume Shoe Track = (ID2)2 x 0,005454 x L
= 3,776 cuft
Volume Pocket = (OH)2 x 0,005454 x L x (%excess+1)
= 4,661cuft
Volume Lead Slurry = Volume C-C + Volume C-OH lead
= 2790,54 cuft
Volume Tail Slurry = Volume C-OH tail + V. Shoetrack + V.
Pocket
= 318,29 cuft
Total Volume slurry = Volume Lead Slurry + Volume Tail Slurry
= 3108,833 cuft
Displacement volume = ID x 0,005454 x kedalaman
= 287,542 cuft
Perhitungan volume semen lapangan
Volume di lapangan = Vs x Fraksi Slurry
Massa di lapangan = Densitas semen x volume semen lapangan
Volume Massa
Lead (di Lapangan) Lead (di Lapangan)
Volume semen 1101,518 cuft Massa semen 97941,4 kg
Massa
Volume air 1626,609 cuft CMHEC 4789,556 kg
Volume
CMHEC 62,41386 cuft Massa additive 0 kg
Volume additive 0 cuft Tail (di Lapangan)
9093,36
Tail (di Lapangan) Massa semen 9 kg
Volume semen 102,2705 cuft Massa CaCO3 4001,083 kg
Massa
Volume air 158,0874 cuft CMHEC 311,7727 kg
Volume CaCO3 52,13908 cuft Total Massa
Volume
CMHEC 5,794815 cuft Massa semen 107034,8 kg
Massa 5101,32
CMHEC 8 kg
4001,08
  Massa CaCO3 3 kg

c. Thickening Time
- Lead saat di casing
Target NRe = 4100
Nre×PV
Valir @casing =
928 ×ρsemen×ID   Casing
4100 × 82
=
928 × 15,53 x 4,67
= 3,654 ft/s
= 219,246 ft/min

Rate Pompa =
Kecepatan Alir   (ftmin ) × (IDcasing 2)
24,5
219,246 × (4,67 2 )
=
24,5
= 195,163 gpm
Volume Semen Total ( bbl ) × 42 gal/bbl
Waktu Pompa =
Rate Pompa  (gpm)
497,017 × 42 gal/bbl
=
195,163
= 106,69 menit
- Lead saat di annulus
Target NRe = 100
Nre×PV
Valir @tubing =
928 ×ρsemen× (Bit size - OD  Casin g )
100 × 82
=
928 × 16,98 x (7,875 - 5,5)
= 2,308 ft/s
= 138,461 ft/min
Rate Pompa =

Kecepatan Alir   (ftmin ) × (Bit size2 - ODcasing 2)


24,5
138,461 × (7,8752 - 5,5 2 )
=
24,5
= 245,394 gpm
Volume Semen Total ( bbl ) × 42 gal/bbl
Waktu Pompa =
Rate Pompa  (gpm)
497,017 × 42 gal/bbl
=
245,394
= 85,066 menit
- Thickening Time Lead
Thickening Time
= Waktu pemompaan (@casing +@annulus) + 90
= 106,69 + 85,066 + 90
= 282,03 menit
= 4,7 jam
- Tail saat di casing
Target NRe = 4100
Nre×PV
Valir @casing =
928 ×ρsemen×ID   Casing
4100 × 82
=
928 × 16,53 x 4,67
= 2,29 ft/s
= 137,379 ft/min

Rate Pompa =
Kecepatan Alir   (ftmin ) × (IDcasing 2)
24,5
137,379 × (4,67 2 )
=
24,5
= 122,289 gpm
Volume Semen Total ( bbl ) × 42 gal/bbl
Waktu Pompa =
Rate Pompa  (gpm)
56,69 × 42 gal/bbl
=
122,289
= 19,47 menit
- Tail saat di annulus
Target NRe = 100
Nre×PV
Valir @tubing =
928 ×ρsemen× (Bit size - OD  Casin g )
100 × 82
=
928 × 16,53 x (7,875 - 5,5)
= 1,977 ft/s
= 118,594 ft/min
Rate Pompa =

Kecepatan Alir   (ftmin ) × (Bit size2 - ODcasing 2)


24,5
118,594 × (7,875 2 - 5,5 2 )
=
24,5
= 153,764 gpm
Volume Semen Total ( bbl ) × 42 gal/bbl
Waktu Pompa =
Rate Pompa  (gpm)
56,69 × 42 gal/bbl
=
153,764
= 15,485 menit
- Thickening Time Tail
Thickening Time
= Waktu pemompaan (@casing +@annulus) + 90
= 19,47 + 15,485 + 90
= 124,95 menit
= 2,08 jam
d. Pump Plan
- Perhitungan rate
 Lead slurry
Rate total = Rate annulus + Rate casing
= 195,1634 gpm + 254,394 gpm
= 440,557 gpm
Effisiensi = 80%
Rate effisiensi = Rate total x Effisiensi
= 0,8 x 440,557 gpm
= 550,697 gpm
Rate pompa = 550 gpm
 Tail slurry
Rate total = Rate anulus + Rate casing
= 122,298 gpm + 153,764 gpm
= 276,053 gpm
Effisiensi = 80%
Rate effisiensi = Rate total x Effisiensi
= 0,8 x 276,053 gpm
= 345,06 gpm
Rate pompa = 350 gpm
- Perhitungan pressure lost
 Lead slurry
Desitas semen = 15,53 ppg
PV = 82 cP
YP = 14 lb/100ft^2
Bit Size = 7,875 in
ID casing = 4,67 in
OD casing = 5,5 in
Kedalaman Casing soe = 11298,367 ft
Kecepatan alir@annulus = 3,154 ft/s
Pressure loss @casing = 1044,789 psi
Pressure loss @annulus = 640,901 psi
Pressure Lost Total = Presloss @casing + Presloss @annulus
= 1044,789 + 640,901
= 1685,690 psi
 Tail slurry
Desitas semen = 15,53 ppg
PV = 82 cP
YP = 14 lb/100ft^2
Bit Size = 7,875 in
ID casing = 4,67 in
OD casing = 5,5 in
Kedalaman Casing soe = 11298,367 ft
Kecepatan alir@annulus = 1,977 ft/s
Pressure loss @casing = 482,887 psi
Pressure loss @annulus = 512,028 psi
Pressure Lost Total = Presloss @casing + Presloss @annulus
= 482,887 + 512,028
= 994,916 psi
- Perhitungan horse power
Pf @7304,79 ft = 7279 psi
P Pompa = 100 psi
Hp =
( Pf @ kedalaman pemboran+ Ppompa )∗Qpompa(gpm)
1714
( 7279+ 100 )∗350+550 (gpm )
=
1714
= 1937,26 Hp
e. Economical
Harga
Rp 65.000,00 /50kg
Semen
Rp 1.300,00 /kg
Barite Rp 15.000,00 /kg
Nacl Rp 5.000,00 /kg
Rp 16.435.225 /Ton
CMHEC
Rp 16.435 /kg
CaCo3 Rp 5.000,00 /kg
Spacer Fluid Rp 9.000,00 /Liter
Pompa Rp 48.500.000,00 Sewa

Pada Production Cementing dibutuhkan :


- Semen
107034,77 Kg × Rp 1.300 = Rp 139.145.206,35
- CMHEC
5101,33 Kg × Rp 16.435 = Rp 83.841.478,00
- CaCo3
4001,08 Kg × Rp 5.000 = Rp 20.005.412,85
- Total = Rp 243.992.097,21
D. TOTAL BUDGET
a. Squeeze cementing = Rp 21.865.325,62
b. Intermediate II cementing = Rp 1.274.009.897,69
c. Production cementing = Rp 516.243.598,46
d. Pump = Rp 48.500.000
Total budget = Rp. 1860618821,77
= $ 130361,65