You are on page 1of 106

No Manuver Loading Hauling Ke Transito

T Time Time Time


G 1 12.24 159.83 756.07
L 2 19.11 135.18 480.6
3 16.16 128.7 532.95
2 4 18.07 140.71 538.9
8 5 23.92 144.26 681.47
6 21.14 153.36 591.96
A 7 18.75 133.72 529.86
P 8 60.24 99.56 521.4
R 9 20.8 149.15 569.8
I 10 22.42 138.96 632.34
L 11 23.58 146.97 639.87
12 15.53 126.47 659.89
2 13 26.63 136.67 618.78
0 14 25.76 118.1 596.07
1 15 18.95 152.96 636.38
8 16 19.91 138.28 710.82
17 29.97 147.45 512.26
18 18.45 137.35 521.29
19 23.84 129.93 492.58
20 16.12 143.03 485.05
21 22.21 109.54 733.87
9 22 30.8 134.22 666.29
23 11.07 131.24 646.89
J 24 27.44 114.44 650.67
U 25 10.73 121 677.21
N 26 23.2 126.89 632.89
I 27 22.67 142.08 641.86
28 28.3 150.31 616.96
2 29 24.82 123.27 578.37
0 30 56.79 135 633.89
1 31 30.58 161.8 658.23
8 32 37.15 151.18 665.54
33 29.49 165.59 664.61
34 36.75 154.63 689.38
35 32.82 172.81 698.13
36 20.07 160.2 581.4
37 36.2 143.26 629.33
38 33.75 88.19 656.62

K = 1 + 3.33 log n
= 6.26067937673398
dibulatka = 6

Waktu Manuver Kosong

X max = 60.24
X min = 10.73

Ci = ( X max - X min ) / K
= 8.25

K = 1 + 3.33 log n
= 6.26067937673398
dibulatka = 6

Waktu Loading

X max = 172.81
X min = 88.19

Ci = ( X max - X min ) / K
= 14.10

K = 1 + 3.33 log n
= 6.26067937673398
dibulatka = 6

Waktu Hauling
X max = 756.07
X min = 480.6

Ci = ( X max - X min ) / K
= 45.91

K = 1 + 3.33 log n
= 6.26067937673398
dibulatka = 6

Waktu Timbang Antri Isi

X max = 108.76
X min = 0

Ci = ( X max - X min ) / K
= 18.13

K = 1 + 3.33 log n
= 6.26067937673398
dibulatka = 6

Waktu Timbang Isi

X max = 26.5
X min = 9.73

Ci = ( X max - X min ) / K
= 2.80

K = 1 + 3.33 log n
= 6.26067937673398
dibulatka = 6

Waktu Timbang Antri Kosong


X max = 100.87
X min = 0

Ci = ( X max - X min ) / K
= 16.81

K = 1 + 3.33 log n
= 6.26067937673398
dibulatka = 6

Waktu Timbang Kosong

X max = 31.74
X min = 0

Ci = ( X max - X min ) / K
= 5.29

K = 1 + 3.33 log n
= 6.26067937673398
dibulatka = 6

Waktu Manuver isi

X max = 36.19
X min = 8.24

Ci = ( X max - X min ) / K
= 4.66

K = 1 + 3.33 log n
= 6.26067937673398
dibulatka = 6
Waktu Dumping

X max = 40.57
X min = 12.36

Ci = ( X max - X min ) / K
= 4.70

K = 1 + 3.33 log n
= 6.26067937673398
dibulatka = 6

Waktu Return

X max = 936.21
X min = 182.96

Ci = ( X max - X min ) / K
= 125.54

K = 1 + 3.33 log n
= 6.26067937673398
dibulatka = 6

Waktu Waiting

X max = 1918.81
X min = 0

Ci = ( X max - X min ) / K
= 319.80
Timbang
Antri Isi Isi Antri Kosong Kosong
24.97 16.43 0 0
0 17.29 0 18.64
0 14.35 0 0
0 26.5 0 16.19
108.76 12.44 0 0
18.48 17.36 0 21.25
0 10.06 0 0
0 11.89 29.01 16.46
0 16.61 0 0
0 12.22 10.89 23.25
0 13.76 0 16.32
0 16.18 0 0
0 26.28 9.37 31.74
0 13.61 0 18.2
0 21.42 0 0
0 22.63 25.13 21.25
0 15.63 38.96 30.47
0 17.47 0 0
0 14.68 0 0
0 18.54 32.58 14.43
0 18.22 0 0
0 18.05 56.49 22.29
0 16.95 0 0
45.3 11.79 38.85 16.4
0 11.01 0 0
0 16.85 67.45 12.37
0 18.15 0 0
0 14.3 0 22.15
0 19.65 0 0
0 21.38 0 0
21.02 24.17 23.43 15.31
0 22.41 0 0
25.94 12.68 32.7 14.28
33.26 20.2 0 0
0 21.87 42.81 20.4
0 18.69 0 0
35.1 18.72 100.87 21.68
0 9.73 0 0

Ci
10.73 - 18.98
18.99 - 27.24
27.25 - 35.51
35.52 - 43.77
43.78 - 52.03
52.04 - 60.29

Ci
88.19 - 102.29
102.30 - 116.41
116.42 - 130.52
130.53 - 144.63
144.64 - 158.75
158.76 - 172.86
Ci
480.6 - 526.51
526.52 - 572.43
572.44 - 618.36
618.37 - 664.28
664.29 - 710.20
710.21 - 756.12

Ci
0 - 18.13
18.14 - 36.26
36.27 - 54.40
54.41 - 72.54
72.55 - 90.67
90.68 - 108.81

Ci
9.73 - 12.53
12.54 - 15.33
15.34 - 18.14
18.15 - 20.94
20.95 - 23.75
23.76 - 26.55
Ci
0 - 16.81
16.82 - 33.63
33.64 - 50.46
50.47 - 67.28
67.29 - 84.10
84.11 - 100.92

Ci
0 - 5.29
5.30 - 10.59
10.60 - 15.89
15.90 - 21.19
21.20 - 26.49
26.50 - 31.79

Ci
8.24 - 12.90
12.91 - 17.57
17.58 - 22.24
22.25 - 26.90
26.91 - 31.57
31.58 - 36.24
Ci
12.36 - 17.06
17.07 - 21.77
21.78 - 26.49
26.50 - 31.20
31.21 - 35.91
35.92 - 40.62

Ci
182.96 - 308.50
308.51 - 434.05
434.06 - 559.61
559.62 - 685.16
685.17 - 810.71
810.72 - 936.26

Ci
0 - 319.80
319.81 - 639.61
639.62 - 959.43
959.44 - 1279.24
1279.25 - 1599.05
1599.06 - 1918.86
Manuver Dumping Return Tunggu
Time Time Time Time
33.76 17.69 312.18 80.37
19.8 15.89 499.5 0
12.76 16.44 329.82 0
13.05 17.33 532.82 0
16.85 19.68 327.81 0
15.11 18.36 530.13 0
18.11 15.25 376.29 0
20.12 17.49 605.29 0
14.04 20.8 440.12 0
20.24 18 691.4 0
12.21 19.81 936.21 480
13.89 16.09 384.93 0
8.93 12.36 643.45 0
12.66 17.84 688.06 0
11.21 21.58 466.67 0
15.9 16.88 693.26 0
14.52 19.35 386.8 616.2
12.53 20.47 423.58 0
17.8 14.18 420.9 0
14.44 17.91 380.27 0
18.43 26.69 421.04 1918.81
36.19 24.28 571.76 88.48
15.75 38.69 418.49 0
16.03 24.79 560.23 101.97
20.18 19.15 480.16 0
18.23 29.39 572.19 0
20.98 26.07 420 0
16.42 40.57 505.53 0
22.99 26.71 326.54 294.81
13.45 15.26 375.25 905
16.02 24.57 533.35 0
16.21 28.08 368.87 0
14.99 23.85 547.43 0
18.86 21.23 412.29 146.38
13.47 21.6 455.76 43.59
8.24 28.39 329.12 25.25
8.93 24.76 478.15 88.19
13.65 22.27 182.96 0

Fi Xi Fi . Xi X
10 14.86 148.56
25 23.12 577.94
33 31.38 1035.51 39.59
36 39.64 1427.07
36 47.90 1724.49
38 56.16 2134.24
178 7047.81

Fi Xi Fi . Xi X
0 95.24 0.00
4 109.36 437.42
11 123.47 1358.15 149.02
25 137.58 3439.54
33 151.70 5005.94
38 165.81 6300.72
111 16541.77
Fi Xi Fi . Xi X
6 503.56 3021.34
10 549.48 5494.78
15 595.40 8930.99 661.50
28 641.32 17956.98
35 687.24 24053.49
38 733.16 27860.24
132 87317.81

Fi Xi Fi . Xi X
30 9.06 271.90
36 27.20 979.20
37 45.34 1677.46 56.22
37 63.47 2348.51
37 81.61 3019.57
38 99.75 3790.37
215 12087.01

Fi Xi Fi . Xi X
7 11.13 77.89
13 13.93 181.12
23 16.74 384.96 20.33
30 19.54 586.28
35 22.35 782.16
38 25.15 955.80
146 2968.21
Fi Xi Fi . Xi X
27 8.41 226.96
32 25.23 807.28
35 42.05 1471.72 53.37
36 58.87 2119.35
37 75.69 2800.62
38 92.51 3515.54
205 10941.47

Fi Xi Fi . Xi X
19 2.65 50.26
19 7.95 150.96
23 13.25 304.64 18.35
30 18.55 556.35
36 23.85 858.42
38 29.15 1107.51
165 3028.13

Fi Xi Fi . Xi X
8 10.57 84.55
25 15.24 380.94
35 19.91 696.70 24.65
36 24.57 884.67
36 29.24 1052.73
38 33.91 1288.61
178 4388.21
Fi Xi Fi . Xi X
8 14.71 117.69
24 19.42 466.14
31 24.13 748.16 29.09
36 28.85 1038.45
36 33.56 1208.07
38 38.27 1454.23
173 5032.73

Fi Xi Fi . Xi X
1 245.73 245.73
18 371.28 6683.09
29 496.83 14408.19 658.37
34 622.39 21161.12
37 747.94 27673.69
38 873.49 33192.59
157 103364.40

Fi Xi Fi . Xi X
34 159.90 5436.63
36 479.71 17269.65
37 799.52 29582.39 976.22
37 1119.34 41415.43
37 1439.15 53248.46
38 1758.96 66840.45
219 213793.00
Cycle Time Bucket Efisiensi Kerja Efektif Ket
Menit (Minimal)
1413.54 10 461 SUDAH
1206.01 10
1051.18 10
1303.57 10
1335.19 10
1387.15 10
1102.04 10
1381.46 10
1231.32 10
1569.72 10
2288.73 10
1232.98 10
1514.21 10
1490.3 10
1329.17 10
1664.06 10
1811.61 10
1151.14 10
1113.91 10
1122.37 10
3268.81 8 467
1648.85 10
1279.08 10
1607.91 10
1339.44 10
1499.46 10
1291.81 10
1394.54 10
1417.16 10
2156.02 10
1508.48 10
1289.44 10
1531.56 10
1532.98 10
1523.26 10
1171.36 10
1585.19 10
1007.17 10
464
K =
=
dibulatkan =

Bucket

Fi X max =
10 X min =
15
8 Ci =
3 =
0
2
38

Waktu Kerja Efektif

X max =
X min =

Fi Ci =
0 =
4
7
14
8
5
38
Fi
6
4
5
13
7
3
38

Fi
30
6
1
0
0
1
38

Fi
7
6
10
7
5
3
38
Fi
27
5
3
1
1
1
38

Fi
19
0
4
7
6
2
38

Fi
8
17
10
1
0
2
38
Fi
8
16
7
5
0
2
38

Fi
1
17
11
5
3
1
38

Fi
34
2
1
0
0
1
38
TGL 28 April 2018

NO HAMBATAN MENIT
1 MULAI 32
2 SAFETY TALK 0
3 BERHENTI SEBELUM JAM ISTIRAHAT 3
4 MULAI SETELAH JAM ISTIRAHAT 0
5 BERHENTI SEBELUM JAM KERJA USAI 14
6 MUAT BOULDER
TOTAL 49
46

TOTAL CYCLE TIME

Loading Manuver = 39.59 dtk


Loading = 149.02 dtk
Hauling Ke stockyard = 661.50 dtk
Timbangan (Antri) = 56.22 dtk
Timbangan (Timbang) = 20.33 dtk
Dump Manuver = 24.65 dtk
Dumping = 29.09 dtk
Timbangan (Antri) = 53.37 dtk
Timbangan (Timbang) = 18.35 dtk
Return = 658.37 dtk
Waiting = 976.22 dtk
total = 2686.73 dtk
= 44.78 menit
1 + 3.33 log n
6.26067938
6

10 Ci
8 8 -
8.34 -
( X max - X min ) / K 8.69 -
0.33 9.03 -
9.37 -
9.72 -

467 Ci
461 461 -
462.01 -
( X max - X min ) / K 463.02 -
1.00 464.03 -
465.04 -
466.05 -
TGL 9 Juni 2018

NO HAMBATAN MENIT
1 MULAI 10
2 SAFETY TALK 0
3 BERHENTI SEBELUM JAM ISTIRAHAT -14
4 MULAI SETELAH JAM ISTIRAHAT 1
5 BERHENTI SEBELUM JAM KERJA USAI 22
6 MUAT BOULDER 24
TOTAL 43
467

Eff real dan ful spek real


TOTAL PRODUKSI
CYCLE TIME 44.78 Q = 60/𝐶𝑇 𝑥 𝑘𝑎𝑝𝑎𝑠𝑖𝑡𝑎𝑠 𝑏𝑎𝑘
KAPASITAS BAK 15.54
EFFISIENSI KERJA 90.99
EFFISIENSI KERJA = W/WT x 100%
JUMLAH DT 1
WAKTU KERJA EFFEKTIF 464.03
JUMLAH RIT 38
PRODUKTIFITAS (TON/HARI) 161

EFFISIENSI KERJA = 90.9852941176


DUMP TRUCK = 1
JUMLAH RITASE = 30
WAKTU KERJA TERSEDIA = 510
Fi Xi Fi . Xi X
8.33 1 8.17 8.17
8.68 1 8.51 0.00
9.02 1 8.85 0.00 9.84
9.36 1 9.20 0.00
9.71 1 9.54 0.00
10.05 38 9.88 365.68
43 373.85

Fi Xi Fi . Xi X
462.00 1 461.50 461.50
463.01 1 462.51 0.00
464.02 1 463.52 0.00 464.03
465.03 1 464.53 0.00
466.04 1 465.54 0.00
467.05 2 466.55 466.55
7 928.05
= 60/𝐶𝑇 𝑥 𝑘𝑎𝑝𝑎𝑠𝑖𝑡𝑎𝑠 𝑏𝑎𝑘 (𝑡𝑜𝑛) 𝑥 𝐸𝐾 𝑥 𝑊.𝐾.𝑇 𝑥 𝐷𝑇

ERJA = W/WT x 100%


Fi
1
0
0
0
0
37
38

Fi
1
0
0
0
0
1
2
Eff 95% dan full spek real
TOTAL PRODUKSI
CYCLE TIME 44.78
KAPASITAS BAK 15.5442894736842
EFFISIENSI KERJA 95.00
JUMLAH DT 1
WAKTU KERJA EFFEKTIF 464.03
JUMLAH RIT 38
PRODUKTIFITAS (TON/HARI) 168

EFFISIENSI KERJA = 90.9852941176471


DUMP TRUCK = 1
JUMLAH RITASE = 30
WAKTU KERJA TERSEDIA = 510
Q = 60/𝐶𝑇 𝑥 𝑘𝑎𝑝𝑎𝑠𝑖𝑡𝑎𝑠 𝑏𝑎𝑘 (𝑡𝑜𝑛) 𝑥 𝐸𝐾 𝑥 𝑊.𝐾.𝑇 𝑥 𝐷𝑇

EFFISIENSI KERJA = W/WT x 100%


TOTAL PRODUKSI

PRODUKTIFITAS (TON/HARI)

EFFISIENSI KERJA
DUMP TRUCK
JUMLAH RITASE
WAKTU KERJA TERSEDIA
Eff sesuai target produksi dan full spek real

CYCLE TIME 44.78


KAPASITAS BAK 15.5442894736842
EFFISIENSI KERJA 40.00
JUMLAH DT 1
WAKTU KERJA EFFEKTIF 464.03
JUMLAH RIT 38
71

= 90.9852941176471
= 1
= 30
= 510
Q = 60/𝐶𝑇 𝑥 𝑘𝑎𝑝𝑎𝑠𝑖𝑡𝑎𝑠 𝑏𝑎𝑘 (𝑡𝑜𝑛) 𝑥 𝐸𝐾 𝑥 𝑊.𝐾.𝑇 𝑥 𝐷𝑇

EFFISIENSI KERJA = W/WT x 100%


Eff real dan full spek bak
TOTAL PRODUKSI
CYCLE TIME 44.78
KAPASITAS BAK 21
EFFISIENSI KERJA 90.99
JUMLAH DT 1
WAKTU KERJA EFFEKTIF 464.03
JUMLAH RIT 38
PRODUKTIFITAS (TON/HARI) 218

EFFISIENSI KERJA = 90.9852941176471


DUMP TRUCK = 1
JUMLAH RITASE = 30
WAKTU KERJA TERSEDIA = 510
Q = 60/𝐶𝑇 𝑥 𝑘𝑎𝑝𝑎𝑠𝑖𝑡𝑎𝑠 𝑏𝑎𝑘 (𝑡𝑜𝑛) 𝑥 𝐸𝐾 𝑥 𝑊.𝐾.𝑇 𝑥 𝐷𝑇

EFFISIENSI KERJA = W/WT x 100%


Eff 95% dan full spek bak
TOTAL PRODUKSI
CYCLE TIME 44.78
KAPASITAS BAK 21
EFFISIENSI KERJA 95.00
JUMLAH DT 1
WAKTU KERJA EFFEKTIF 464.03
JUMLAH RIT 38
PRODUKTIFITAS (TON/HARI) 227

EFFISIENSI KERJA = 90.9852941176471


DUMP TRUCK = 1
JUMLAH RITASE = 30
WAKTU KERJA TERSEDIA = 510
Q = 60/𝐶𝑇 𝑥 𝑘𝑎𝑝𝑎𝑠𝑖𝑡𝑎𝑠 𝑏𝑎𝑘 (𝑡𝑜𝑛) 𝑥 𝐸𝐾 𝑥 𝑊.𝐾.𝑇 𝑥 𝐷𝑇

EFFISIENSI KERJA = W/WT x 100%


Eff sesuai target produksi dan full spek bak
TOTAL PRODUKSI
CYCLE TIME
KAPASITAS BAK
EFFISIENSI KERJA
JUMLAH DT
WAKTU KERJA EFFEKTIF
JUMLAH RIT
PRODUKTIFITAS (TON/HARI)

EFFISIENSI KERJA =
DUMP TRUCK =
JUMLAH RITASE =
WAKTU KERJA TERSEDIA =
t produksi dan full spek bak

44.78 Q = 60/𝐶𝑇 𝑥 𝑘𝑎𝑝𝑎𝑠𝑖𝑡𝑎𝑠 𝑏𝑎𝑘 (𝑡𝑜𝑛) 𝑥 𝐸𝐾 𝑥 𝑊.𝐾.𝑇 𝑥 𝐷𝑇


21
30.00 EFFISIENSI KERJA = W/WT x 100%
1
464.03
38
72

90.9852941176471
1
30
510
No rata2 RATA2 BUCKET
waktu kerja efektif No Parameter
1 Manuver L 25.43237 9.947368 464 TL
2 Loading 138.0603 7.733333
3 Hauling 616.5916 1 Cycle Time 24.45
4 Antri Timba8.232368 2 Kapasitas Bak (ton)
15.72
5 Timbang isi17.10974 3 Jumlah bucket 9.95

6 Manuver d 16.49868 4 Efesiensi Kerja 9098%

7 Dumping 21.57237 5 Waktu Kerja Efektif7.73


8 Return 474.4371 6 Jumlah DT 1
9 Antri Timb 13.38263 Produktifitas Dump Truck / hari ( Ton ) 271.33
10 Timbang K 9.817895
11 Waiting 126.0276
Jumlah 1467.163 Produktivitas Alat Angkut / jam
24.45271 Menit Kapasitas Bucket
Density 1.58 Ton
jumlah Pengisian9.95 Bucket
Jumlah Alat angkut 1 Unit
Kapasitas bak 15.72 Ton
Waktu Kerja Efektif
7.733333 Jam
cycle time 24.45271 Menit
Efisiensi Kerja (Eff)
90.98039

Pa = (Kapasitas Bak × Eff × 60 Menit × n.A × D

Pa = 55.43632 ton/Jam
Pa = 428.7076 ton/hari
W S WKE
501 37 464
7.73

WKE Waktu KerjUA (%)


464 510 91

Kap Bak
34.02 90.98039
0.909804

× Eff × 60 Menit × n.A × D)/ Ct


9
11
12
13
14

Berhenti : 16.42
Cuaca : Cerah
No Manuver Load Loading Hauling Ke Stock Yard
Time Time Time
T 1 23.24 130.48 773.37
G 2 26.55 145.65 691.73
L 3 33.36 152.85 680.22
4 31.97 136.87 768.53
1 5 34.91 127.6 661.75
6 6 31.39 117.07 680.84
7 31.56 122.37 755.16
M 8 32.12 125.47 727.07
E 9 10.42 126.45 708.38
I 10 24.66 144.59 718.14
11 25.56 126.72 593.24
2 12 35.68 154.27 624.6
0 13 33.81 126.68 801.81
1 14 37.51 164 741.8
8 15 44.1 170.34 734.06
16 32.9 124.97 640.25
T 17 33.1 141.86 809.31
G 18 32.95 190.72 736.12
L 19 51.49 161.91 737.76
20 44.72 155.14 735.14
1 21 45.07 143.9 709.68
8 22 25.94 132.77 675.35
23 46.17 112.07 779.24
M 24 24.78 112.52 760.73
E 25 20.45 130.15 720.37
I 26 6.68 123.18 815.58
2018 27 36.88 135.62 1376.51
T 28 30.98 140 802.33
G 29 24.65 146 696.44
L 30 21.65 152.22 711.41
31 19.6 139.13 846.4
2 32 24.25 144.34 661.24
3 33 30.68 170.75 710.84
34 20.94 161.63 667.39
M 35 25.53 151.21 869.46
E 36 22.31 145.25 695.81
I 37 24.81 149.2 796.23
2018 38 36.39 156.06 908.07

TOTAL CYCLE TIME

Loading Manuver = 40.13


Loading = 167.12
Hauling Ke stockyard = 1067.63
Antri Timbang isi = 42.73
Timbang isi = 19.63
Dump Manuver = 35.04
Dumping = 49.70
Return = 821.62
Antri Timbang kosong = 41.91
Timbang kosong = 25.44
Waiting = 254.44
total = 2565.40
= 42.76

TOTAL CYCLE TIME

Loading Manuver = 40.13


Loading = 167.12
Hauling Ke stockyard = 1067.63
Antri Timbang isi = 42.73
Timbang isi = 19.63
Dump Manuver = 35.04
Dumping = 49.70
Return = 821.62
Antri Timbang kosong = 41.91
Timbang kosong = 25.44
Waiting = 254.44
total = 2565.40
= 42.76

TOTAL CYCLE TIME


Loading Manuver = 40.13
Loading = 167.12
Hauling Ke stockyard = 1067.63
Antri Timbang isi = 42.73
Timbang isi = 19.63
Dump Manuver = 35.04
Dumping = 49.70
Return = 821.62
Antri Timbang kosong = 41.91
Timbang kosong = 25.44
Waiting = 254.44
total = 2565.40
= 42.76

TOTAL CYCLE TIME

Loading Manuver = 40.13


Loading = 167.12
Hauling Ke stockyard = 1067.63
Antri Timbang isi = 42.73
Timbang isi = 19.63
Dump Manuver = 35.04
Dumping = 49.70
Return = 821.62
Antri Timbang kosong = 41.91
Timbang kosong = 25.44
Waiting = 254.44
total = 2565.40
= 42.76

TOTAL CYCLE TIME

Loading Manuver = 40.13


Loading = 167.12
Hauling Ke stockyard = 1067.63
Antri Timbang isi = 42.73
Timbang isi = 19.63
Dump Manuver = 35.04
Dumping = 49.70
Return = 821.62
Antri Timbang kosong = 41.91
Timbang kosong = 25.44
Waiting = 254.44
total = 2565.40
= 42.76

TOTAL CYCLE TIME

Loading Manuver = 40.13


Loading = 167.12
Hauling Ke stockyard = 1067.63
Antri Timbang isi = 42.73
Timbang isi = 19.63
Dump Manuver = 35.04
Dumping = 49.70
Return = 821.62
Antri Timbang kosong = 41.91
Timbang kosong = 25.44
Waiting = 254.44
total = 2565.40
= 42.76
No rata2 RATA2 BUCKET waktu kerja efektif
1 Manuver L 29.9936842105263 11.2631578947368 363.666666666667
2 Loading 141.895 6.06111111111111
3 Hauling 750.588421052632
4 Antri Timb 3.31289473684211
5 Timbang is 6.45815789473684
6 Manuver 19.4365789473684
7 Dumping 31.3505263157895
8 Return 703.554736842105
9 Antri Tim 2.38315789473684
10 Timbang K 4.83368421052632
11 Waiting 32.4476315789474
Jumlah 1726.25447368421
28.7709078947368 Menit
540 780
660 1320
720
780
840

Loading : Top Loading

Timbang
Antri Isi Isi Antri Kosong Kosong
0 12.48 0 0
0 0 0 0
0 0 0 6.68
0 15.35 0 0
0 0 0 0
0 0 0 20.49
0 29.93 0 0
0 0 0 0
0 0 0 11.05
0 12.07 0 0
0 0 0 0
0 0 0 20.22
0 18.28 0 0
0 0 0 0
0 0 0 11.2
0 19.75 0 0
0 21.91 0 0
0 0 0 0
0 0 0 18.01
0 22.07 0 0
0 0 0 0
0 0 0 43.63
0 32.26 0 0
0 0 0 0
0 0 0 13.85
0 13.59 0 0
0 0 0 12.78
75.45 20.88 0 0
0 0 0 0
0 0 16.14 13.4
16.12 13.72 0 0
0 0 0 0
0 0 0 0
0 0 74.42 12.37
34.32 13.12 0 0
0 0 0 0
0 0 0 0
0 0 0 0

eff real dan full spek real


TOTAL PRODUKSI
CYCLE TIME
dtk KAPASITAS BAK
dtk EFFISIENSI KERJA
dtk JUMLAH DT
dtk WAKTU KERJA EFFEKTIF
dtk JUMLAH RIT
dtk PRODUKTIFITAS (TON/HARI)
dtk
dtk EFFISIENSI KERJA =
dtk DUMP TRUCK =
dtk JUMLAH RITASE =
dtk WAKTU KERJA TERSEDIA =
dtk
menit

eff 95% dan full spek real

TOTAL PRODUKSI
CYCLE TIME
dtk KAPASITAS BAK
dtk EFFISIENSI KERJA
dtk JUMLAH DT
dtk WAKTU KERJA EFFEKTIF
dtk JUMLAH RIT
dtk PRODUKTIFITAS (TON/HARI)
dtk
dtk EFFISIENSI KERJA =
dtk DUMP TRUCK =
dtk JUMLAH RITASE =
dtk WAKTU KERJA TERSEDIA =
dtk
menit

eff sesuai target produksi


TOTAL PRODUKSI
CYCLE TIME
dtk KAPASITAS BAK
dtk EFFISIENSI KERJA
dtk JUMLAH DT
dtk WAKTU KERJA EFFEKTIF
dtk JUMLAH RIT
dtk PRODUKTIFITAS (TON/HARI)
dtk
dtk EFFISIENSI KERJA =
dtk DUMP TRUCK =
dtk JUMLAH RITASE =
dtk WAKTU KERJA TERSEDIA =
dtk
menit

eff real dan full spek

TOTAL PRODUKSI
CYCLE TIME
dtk KAPASITAS BAK
dtk EFFISIENSI KERJA
dtk JUMLAH DT
dtk WAKTU KERJA EFFEKTIF
dtk JUMLAH RIT
dtk PRODUKTIFITAS (TON/HARI)
dtk
dtk EFFISIENSI KERJA =
dtk DUMP TRUCK =
dtk JUMLAH RITASE =
dtk WAKTU KERJA TERSEDIA =
dtk
menit

eff 95% dan full spekbak

TOTAL PRODUKSI
CYCLE TIME
dtk KAPASITAS BAK
dtk EFFISIENSI KERJA
dtk JUMLAH DT
dtk WAKTU KERJA EFFEKTIF
dtk JUMLAH RIT
dtk PRODUKTIFITAS (TON/HARI)
dtk
dtk EFFISIENSI KERJA =
dtk DUMP TRUCK =
dtk JUMLAH RITASE =
dtk WAKTU KERJA TERSEDIA =
dtk
menit

eff turun dan full spek bak

TOTAL PRODUKSI
CYCLE TIME
dtk KAPASITAS BAK
dtk EFFISIENSI KERJA
dtk JUMLAH DT
dtk WAKTU KERJA EFFEKTIF
dtk JUMLAH RIT
dtk PRODUKTIFITAS (TON/HARI)
dtk
dtk EFFISIENSI KERJA =
dtk DUMP TRUCK =
dtk JUMLAH RITASE =
dtk WAKTU KERJA TERSEDIA =
dtk
menit
No Parameter
TL

1 Cycle Time 28.77


2 Kapasitas Bak (ton) 17.80
3 Jumlah bucket 11.26
4 Efesiensi Kerja 7131%
5 Waktu Kerja Efektif 6.06
6 Jumlah DT 1
Produktifitas Dump Truck / hari ( Ton ) 160.40

Produktivitas Alat Angkut / jam


Kapasitas Bucket
Density 1.58 Ton
jumlah Pengisian 11.26 Bucket
Jumlah Alat angkut 1 Unit
Kapasitas bak 17.80 Ton
Waktu Kerja Efektif 6.06111111111111 Jam
cycle time 28.7709078947368 Menit
Efisiensi Kerja (Eff) 71.3071895424837

Pa = (Kapasitas Bak × Eff × 60 Menit × n.A × D)/ Ct

Pa = 41.8124243885671 ton/Jam
Pa = 253.429750044037 ton/hari
480

Manuver Dumping Dumping Return Tunggu


Time Time Time Time
20.58 39.54 704.77 0
14.81 59.99 618.55 0
14.99 21.65 819.66 107.87
14.77 31.06 634.99 0
17.83 24.04 597.38 0
14.59 38.72 871.33 0
17.66 42.93 552.63 0
13.34 48.83 528.93 18.32
51.06 37.44 756.04 91.3
43.02 45.3 603.88 0
20.25 42.7 598.26 0
35.37 39.86 746.12 0
21.76 25.93 665.09 0
25.94 36.52 715.33 0
16.71 20.01 948.8 0
17.35 68 603.17 0
19.61 24.72 635.15 0
14.45 30.1 653.76 0
17.97 26.45 768.38 0
16.68 25.13 643.73 0
10.94 18.48 685.84 32.32
19.72 25.03 762.15 0
14.27 18.85 737.08 0
8.41 27.29 709.18 0
6.08 22.41 822.28 0
27.99 16.12 954.65 0
16.39 24.76 834.55 165.89
21.11 24.7 649.87 0
19.29 15.63 615.36 0
15.08 18.96 881.66 24.25
12.89 39.14 638.04 0
2.27 31.79 581.06 0
20.83 35.09 875.32 443.47
20.98 30.07 798.69 0
20.42 24.51 627.36 0
16.28 32.62 682.68 0
11.3 27.32 617.54 135.08
45.6 29.63 595.82 214.51

k real
42.76 Q = 60/𝐶𝑇 𝑥 𝑘𝑎𝑝𝑎𝑠𝑖𝑡𝑎𝑠 𝑏𝑎𝑘 (𝑡𝑜𝑛) 𝑥 𝐸𝐾 𝑥 𝑊.𝐾.𝑇 𝑥 𝐷𝑇
17.745477675841
71.60 EFFISIENSI KERJA = W/WT x 100%
1
365.18
38
152

71.6045751633987
1
38
510

42.76 Q = 60/𝐶𝑇 𝑥 𝑘𝑎𝑝𝑎𝑠𝑖𝑡𝑎𝑠 𝑏𝑎𝑘 (𝑡𝑜𝑛) 𝑥 𝐸𝐾 𝑥 𝑊.𝐾.𝑇 𝑥 𝐷𝑇


95
71.60 EFFISIENSI KERJA = W/WT x 100%
1
365.18
38
811

71.6045751633987
1
338
510

42.76 Q = 60/𝐶𝑇 𝑥 𝑘𝑎𝑝𝑎𝑠𝑖𝑡𝑎𝑠 𝑏𝑎𝑘 (𝑡𝑜𝑛) 𝑥 𝐸𝐾 𝑥 𝑊.𝐾.𝑇 𝑥 𝐷𝑇


17.745477675841
91.00 EFFISIENSI KERJA = W/WT x 100%
1
365.18
38
193

71.6045751633987
1
338
510

eff real dan full spek bak

42.76 Q = 60/𝐶𝑇 𝑥 𝑘𝑎𝑝𝑎𝑠𝑖𝑡𝑎𝑠 𝑏𝑎𝑘 (𝑡𝑜𝑛) 𝑥 𝐸𝐾 𝑥 𝑊.𝐾.𝑇 𝑥 𝐷𝑇


21
71.60 EFFISIENSI KERJA = W/WT x 100%
1
365.18
38
179

0
1
338
510

42.76 Q = 60/𝐶𝑇 𝑥 𝑘𝑎𝑝𝑎𝑠𝑖𝑡𝑎𝑠 𝑏𝑎𝑘 (𝑡𝑜𝑛) 𝑥 𝐸𝐾 𝑥 𝑊.𝐾.𝑇 𝑥 𝐷𝑇


21
95.00 EFFISIENSI KERJA = W/WT x 100%
1
365.18
38
238
0
1
338
510

42.76 Q = 60/𝐶𝑇 𝑥 𝑘𝑎𝑝𝑎𝑠𝑖𝑡𝑎𝑠 𝑏𝑎𝑘 (𝑡𝑜𝑛) 𝑥 𝐸𝐾 𝑥 𝑊.𝐾.𝑇 𝑥 𝐷𝑇


21
87.00 EFFISIENSI KERJA = W/WT x 100%
1
365.18
38
218

0
1
338
501
W S WKE
501 137.333333333333 363.666666666667
6.06

WKE Waktu Kerja Total UA (%)


363.666666666667 510 71

Kap Bak
38.52 71.3071895424837
0.713071895424836
26329.54
438.825666666667
Cycle Time Bucket Efisiensi Kerja Efektif Ket
Menit (Minimal)
1704.46 12
1557.28 12 07.32 - 08.05 muat boulder
1837.28 12
1633.54 12 438
1463.51 12
1774.43 12
1552.24 12
1494.08 12
1792.14 12
1591.66 12
1406.73 12
1656.12 10
1693.36 12
1721.1 12
1945.22 12
1506.39 12
1685.66 12
1658.1 12
1781.97 12 07.22 - 08.43 muat boulder 5 rit
1642.61 11 329
1646.23 10
1684.59 10
1739.94 10
1642.91 10
1735.59 10
1957.79 10
2603.38 10
1765.32 12 07.31 - 09.31 muat boulder 2 rit
1517.37 12
1854.77 12
1725.04 12
1444.95 12
2286.98 10 324
1786.49 10
1765.93 10
1594.95 10
1761.48 10
1986.08 11
363.666666666667
146.333333333333
TGL 16 Mei 2018

NO HAMBATAN MENIT
1 MULAI 32
2 SAFETY TALK 0
3 BERHENTI SEBELUM JAM ISTIRAHAT -9
4 MULAI SETELAH JAM ISTIRAHAT -2
5 BERHENTI SEBELUM JAM KERJA USAI 18
6 MUAT BOULDER 33
TOTAL 72
438

Tgl 18 Mei 2018


NO HAMBATAN MENIT
1 MULAI 22
2 SAFETY TALK 0
3 BERHENTI SEBELUM JAM ISTIRAHAT -5
4 MULAI SETELAH JAM ISTIRAHAT -2
5 BERHENTI SEBELUM JAM KERJA USAI 25
6 MUAT BOULDER 141
TOTAL 181
329

Tgl 23 Mei 2018


NO HAMBATAN MENIT
1 MULAI 31
2 SAFETY TALK 0
3 BERHENTI SEBELUM JAM ISTIRAHAT -22
4 MULAI SETELAH JAM ISTIRAHAT -2
5 BERHENTI SEBELUM JAM KERJA USAI 59
6 MUAT BOULDER 120
TOTAL 186

324
146.333333333333
K = 1 + 3.33 log n
= 6.260679377
dibulatkan = 6.26

Waktu Manuver Load

X max = 51.49
X min = 6.68

Ci = ( X max - X min ) / K
= 7.16

K = 1 + 3.33 log n
= 6.260679377
dibulatkan = 6.26

Loading

X max = 190.72
X min = 112.07

Ci = ( X max - X min ) / K
= 12.56

K = 1 + 3.33 log n
= 6.260679377
dibulatkan = 6.26
Hauling Ke Stock Yard

X max = 1376.51
X min = 593.24

Ci = ( X max - X min ) / K
= 125.12

K = 1 + 3.33 log n
= 6.260679377
dibulatkan = 6.26

Antri Timbang Isi

X max = 75.45
X min = 0

Ci = ( X max - X min ) / K
= 12.05

K = 1 + 3.33 log n
= 6.260679377
dibulatkan = 6.26

Timbang Isi

X max = 32.26
X min = 0

Ci = ( X max - X min ) / K
= 5.15
K = 1 + 3.33 log n
= 6.260679377
dibulatkan = 6.26

Antri Timbang Kosong

X max = 74.42
X min = 0

Ci = ( X max - X min ) / K
= 11.89

K = 1 + 3.33 log n
= 6.260679377
dibulatkan = 6.26

Timbang Kosong

X max = 43.63
X min = 0

Ci = ( X max - X min ) / K
= 6.97
K = 1 + 3.33 log n
= 6.260679377
dibulatkan = 6.26

Manuver Dumping

X max = 51.06
X min = 2.27

Ci = ( X max - X min ) / K
= 7.79

K = 1 + 3.33 log n
= 6.260679377
dibulatkan = 6.26

Dumping

X max = 68
X min = 15.63

Ci = ( X max - X min ) / K
= 8.37

K = 1 + 3.33 log n
= 6.260679377
dibulatkan = 6.26

Return
X max = 954.65
X min = 528.93

Ci = ( X max - X min ) / K
= 68.01

K = 1 + 3.33 log n
= 6.260679377
dibulatkan = 6.26

Tunggu/Delay

X max = 443.47
X min = 0

Ci = ( X max - X min ) / K
= 70.84

K = 1 + 3.33 log n
= 6.2606793767
dibulatkan = 6

Bucket

X max = 12
X min = 10

Ci = ( X max - X min ) / K
= 0.33

Waktu Kerja Efektif

X max = 438
X min = 324

Ci = ( X max - X min ) / K
= 19.00
Ci
6.68 - 13.84
13.85 - 21.01
21.02 - 28.17
28.18 - 35.34
35.35 - 42.51
42.52 - 49.68
49.69 - 56.85

Ci
112.07 - 124.63
124.64 - 137.21
137.22 - 149.78
149.79 - 162.36
162.37 - 174.93
174.94 - 187.50
187.51 - 200.08
Ci
593.24 - 718.36
718.37 - 843.50
843.51 - 968.63
968.64 - 1093.76
1093.77 - 1218.90
1218.91 - 1344.03
1344.04 - 1469.16

Ci
0 - 12.05
12.06 - 24.12
24.13 - 36.18
36.19 - 48.24
48.25 - 60.30
60.31 - 72.37
72.38 - 84.43

Ci
0 - 5.15
5.16 - 10.32
10.33 - 15.48
15.49 - 20.64
20.65 - 25.81
25.82 - 30.97
30.98 - 36.13

Ci
0 - 11.89
11.90 - 23.79
23.80 - 35.68
35.69 - 47.58
47.59 - 59.48
59.49 - 71.38
71.39 - 83.28

Ci
0 - 6.97
6.98 - 13.95
13.96 - 20.93
20.94 - 27.91
27.92 - 34.89
34.90 - 41.87
41.88 - 48.85
Ci
2.27 - 10.06
10.07 - 17.87
17.88 - 25.67
25.68 - 33.48
33.49 - 41.28
41.29 - 49.08
49.09 - 56.89

Ci
15.63 - 24.00
24.01 - 32.37
32.38 - 40.75
40.76 - 49.12
49.13 - 57.50
57.51 - 65.87
65.88 - 74.25
Ci
528.93 - 596.94
596.95 - 664.95
664.96 - 732.97
732.98 - 800.99
801.00 - 869.00
869.01 - 937.02
937.03 - 1005.03

Ci
0 - 70.84
70.85 - 141.69
141.70 - 212.55
212.56 - 283.40
283.41 - 354.25
354.26 - 425.10
425.11 - 495.95

Ci
10 - 10.33
10.34 - 10.68
10.69 - 11.02
11.03 - 11.36
11.37 - 11.71
11.72 - 12.05

Ci
324 - 343.00
343.01 - 362.01
362.02 - 381.02
381.03 - 400.03
400.04 - 419.04
419.05 - 438.05
Fi Xi Fi . Xi X Fi
2 10.26 20.52 2
5 17.43 87.14 3
17 24.60 418.12 40.13 12
29 31.76 921.14 12
33 38.93 1284.74 4
37 46.10 1705.69 4
38 53.267955271566 2024.18 1
161 6461.54 38

Fi Xi Fi . Xi X Fi
5 118.35 591.76 5
16 130.93 2094.81 11
26 143.50 3730.99 167.12 10
14 156.07 2185.03 -12
37 168.65 6239.96 23
37 181.22 6705.19 0
38 193.79533546326 7364.22 1
173 28911.97 38
Fi Xi Fi . Xi X Fi
17 655.80 11148.63 17
34 780.93 26551.77 17
37 906.07 33524.50 1067.63 3
37 1031.20 38154.42 0
37 1156.33 42784.34 0
37 1281.47 47414.26 0
38 1406.5995207668 53450.78 1
237 253028.70 38

Fi Xi Fi . Xi X Fi
35 6.03 210.92 35
36 18.09 651.21 1
37 30.15 1115.62 42.73 1
37 42.21 1561.94 0
37 54.28 2008.26 0
37 66.34 2454.58 0
38 78.402651757189 2979.30 1
257 10981.82 38

Fi Xi Fi . Xi X Fi
25 2.58 64.42 25
25 7.74 193.50 0
31 12.90 400.00 19.63 6
33 18.07 596.20 2
36 23.23 836.28 3
37 28.39 1050.56 1
38 33.556805111821 1275.16 1
225 4416.12 38

Fi Xi Fi . Xi X Fi
36 5.94 213.99 36
37 17.84 660.16 1
37 29.74 1100.40 41.91 0
37 41.64 1540.63 0
37 53.54 1980.86 0
37 65.43 2421.09 0
38 77.333162939297 2938.66 1
259 10855.79 38

Fi Xi Fi . Xi X Fi
28 3.48 97.58 28
34 10.46 355.79 6
37 17.44 645.43 25.44 3
37 24.42 903.68 0
37 31.40 1161.93 0
37 38.38 1420.17 0
38 45.362715654952 1723.78 1
248 6308.36 38
Fi Xi Fi . Xi X Fi
3 6.17 18.50 3
21 13.97 293.39 18
32 21.77 696.79 35.04 11
34 29.58 1005.68 2
35 37.38 1308.39 1
37 45.19 1671.90 2
38 52.99054313099 2013.64 1
200 7008.30 38

Fi Xi Fi . Xi X Fi
8 19.81 158.50 8
24 28.19 676.53 16
32 36.56 1170.07 49.70 8
36 44.94 1617.85 4
36 53.32 1919.38 0
37 61.69 2282.60 1
38 70.067795527157 2662.58 1
211 10487.51 38
Fi Xi Fi . Xi X Fi
4 562.93 2251.73 4
18 630.95 11357.09 14
24 698.97 16775.18 821.62 6
30 766.98 23009.47 6
33 835.00 27554.96 3
36 903.02 32508.55 3
38 971.03153354633 36899.20 2
183 150356.18 38

Fi Xi Fi . Xi X Fi
32 35.42 1133.47 32
35 106.27 3719.55 3
36 177.12 6376.49 254.44 1
37 247.98 9175.13 1
37 318.83 11796.65 0
37 389.68 14418.17 0
38 460.53204472844 17500.22 1
252 64119.67 38

Fi Xi Fi . Xi X Fi
13 10.17 132.17 13
13 10.51 136.63 0
15 10.85 162.80 11.23 2
15 11.20 167.95 0
15 11.54 173.10 0
38 11.88 451.57 23
109 1224.21 38

Fi Xi Fi . Xi X Fi
2 333.50 667.00 2
2 352.51 0.00 0
2 371.52 0.00 365.18 0
2 390.53 0.00 0
2 409.54 0.00 0
3 428.55 428.55 1
13 1095.55 3
DATA HASIL PENGAMATAN WAKT
DUMP TRUCK HINO DIESEL FM 23
NO Manuver Loading Hauling Manuver
dtk dtk dtk dtk
1 15.31 127 255 7.54
7 2 12.67 120.71 263.19 15
3 11.45 123.1 270 12
J 4 8.75 110 435.22 20.15
U 5 20.7 114.9 344.29 15.07
L 6 20.66 118.12 241.22 11.15
I 7 21.23 119.67 240 8.63
8 13.71 107.82 244.11 9.15
2 9 27.14 112.14 211.71 6.17
0 10 33.01 96.46 362.05 10.05
1 11 13.83 108.78 242 16
8 12 6.78 125.18 258 10.57
13 21.06 129.1 190 12.26
14 8.03 123.46 295 15
15 16.7 116.16 223.55 5.2
16 12.02 142.86 240 15
17 16.52 130.57 269.25 8.4
18 23.63 139.08 245.21 5.7
19 23.18 130.49 255.25 11.78
20 19.22 167.08 240 10.76
21 30.13 125.85 250.21 15.29
22 22.2 142.01 245.2 7.81
23 34.16 144.95 379 11.95
24 18.94 144.09 261 19.8
25 6.48 127.43 245 12.46
26 7.95 78.24 265 13.58
27 9.95 111.88 258.95 15.31
28 9.83 130.2 270 16.8
29 9.07 96.52 263 5.82
30 34.58 105.99 320 8.17
31 12.57 129.69 315.8 8.4
32 11.43 122.83 279 4.64

K = 1 + 3.33 log n
= 6.01214942780529
dibulatk = 6

Waktu Manuver Kosong

X max = 34.58
X min = 6.48
Ci = ( X max - X min ) / K
= 4.68

K = 1 + 3.33 log n
= 6.01214942780529
dibulatk = 6

Waktu Loading

X max = 167.08
X min = 78.24

Ci = ( X max - X min ) / K
= 14.81

K = 1 + 3.33 log n
= 6.01214942780529
dibulatk = 6

Waktu Hauling Waste Dum

X max = 435.22
X min = 190

Ci = ( X max - X min ) / K
= 40.87

K = 1 + 3.33 log n
= 6.01214942780529
dibulatk = 6

Waktu Manuver isi


X max = 20.15
X min = 4.64

Ci = ( X max - X min ) / K
= 2.59

K = 1 + 3.33 log n
= 6.01214942780529
dibulatk = 6

Waktu Dumping

X max = 37.5
X min = 10

Ci = ( X max - X min ) / K
= 4.58

K = 1 + 3.33 log n
= 6.01214942780529
dibulatk = 6

Waktu Return

X max = 344.78
X min = 153

Ci = ( X max - X min ) / K
= 31.96

K = 1 + 3.33 log n
= 6.01214942780529
dibulatk = 6

Waktu Waiting

X max = 6354.34
X min = 0

Ci = ( X max - X min ) / K
= 1059.06
DATA HASIL PENGAMATAN WAKTU EDAR ALAT ANGKUT ( FRONT CHEROKEE ) PENGUPASSAN OB
DUMP TRUCK HINO DIESEL FM 235/260 JD YANG DILAYANI OLEH BACKHOE KOMATSU PC - 200
Dumping Return Tunggu Cycle time BUCKET
dtk dtk dtk
12 153 6354.34 6924.19 10
19.98 221.81 0 653.36 10
17 180 0 613.55 10
15.7 344.78 0 934.6 10
37.5 185.71 0 718.17 10
13.35 215.5 0 620 10
26 182 0 597.53 10
10.16 181.89 0 566.84 10
14.03 258.59 0 629.78 10
24.43 228.9 0 754.9 10
20.02 258 0 658.63 10
22 180 0 602.53 10
15 245 0 612.42 10
20.15 245 132.11 838.75 10
11 180.25 211.35 764.21 10
19.34 205 42.72 676.94 10
17.41 190.75 0 632.9 10
10.04 154.79 0 578.45 10
13.5 251.25 0 685.45 10
15 230 0 682.06 10
34.71 244 0 700.19 10
21.75 215.05 0 654.02 10
20 301 0 891.06 10
20.04 219 147.83 830.7 10
20 235 184.03 830.4 10
20.03 235.02 0 619.82 10
21.05 300 0 717.14 10
27.04 240.06 0 693.93 10
29.89 242 0 646.3 10
10 240 0 718.74 10
20.4 164.2 151.81 802.87 10
11 180 0 608.9 10

Ci Fi Xi
6.48 - 11.16 8 8.82
11.17 - 15.86 16 13.52
15.87 - 20.55 20 18.21
20.56 - 25.24 27 22.90
25.25 - 29.94 28 27.60
29.95 - 34.63 32 32.29
131

Ci Fi Xi
78.24 - 93.05 1 85.64
93.06 - 107.86 5 100.46
107.87 - 122.68 14 115.28
122.69 - 137.50 26 130.09
137.51 - 152.31 31 144.91
152.32 - 167.13 32 159.73
109

Ci Fi Xi
190 - 230.87 3 210.44
230.88 - 271.75 24 251.32
271.76 - 312.63 26 292.20
312.64 - 353.51 29 333.08
353.52 - 394.39 31 373.96
394.40 - 435.27 32 414.84
145
Ci Fi Xi
4.64 - 7.23 5 5.93
7.24 - 9.82 12 8.53
9.83 - 12.42 20 11.12
12.43 - 15.01 25 13.72
15.02 - 17.61 30 16.31
17.62 - 20.20 32 18.91
124

Ci Fi Xi
10 - 14.58 9 12.29
14.59 - 19.18 14 16.89
19.19 - 23.77 26 21.48
23.78 - 28.36 29 26.07
28.37 - 32.96 30 30.67
32.97 - 37.55 32 35.26
140

Ci Fi Xi
153 - 184.96 9 168.98
184.97 - 216.94 14 200.96
216.95 - 248.91 26 232.93
248.92 - 280.88 29 264.90
280.89 - 312.86 31 296.88
312.87 - 344.83 32 328.85
141
Ci Fi Xi
0 - 1059.06 31 529.53
1059.07 - 2118.12 31 1588.60
2118.13 - 3177.19 31 2647.66
3177.20 - 4236.26 31 3706.73
4236.27 - 5295.32 31 4765.80
5295.33 - 6354.39 32 5824.86
187
Waktu Kerja Efektif KET

374 07.15 - 0 8.59muat boulder 2 rit

2.39
3.35

Fi . Xi X Fi
70.57 8
216.24 8
364.17 23.47 4
618.35 7
772.66 1
1033.23 4
3075.21 32

Fi . Xi X Fi
85.64 1
502.30 4
1613.87 139.34 9
3382.43 12
4492.21 5
5111.25 1
15187.71 32

Fi . Xi X Fi
631.31 3
6031.56 21
7597.07 336.46 2
9659.18 3
11592.61 2
13274.72 1
48786.44 32
Fi . Xi X Fi
29.66 5
102.33 7
222.45 14.45 8
342.94 5
489.38 5
605.04 2
1791.80 32

Fi . Xi X Fi
110.63 9
236.39 5
558.44 26.50 12
756.08 3
919.95 1
1128.27 2
3709.75 32

Fi . Xi X Fi
1520.84 9
2813.37 5
6056.14 268.08 12
7682.15 3
9203.13 2
10523.15 1
37798.76 32
Fi . Xi X Fi
16415.38 31
49246.45 0
82077.51 3191.35 0
114908.58 0
147739.65 0
186395.57 1
596783.13 32
TOTAL CYCLE TIME

Loading Manuver = 23.47 dtk


Loading = 139.34 dtk
Hauling Ke Waste Dump = 336.46 dtk
Dump Manuver = 14.45 dtk
Dumping = 26.50 dtk
Return = 268.08 dtk
Waiting = 3191.35 dtk
total = 3999.65 dtk
= 66.66 menit

TGL 16 Mei 2018

NO HAMBATAN MENIT
1 MULAI 15
2 SAFETY TALK 0
3 BERHENTI SEBELUM JAM ISTIRAHAT -8
4 MULAI SETELAH JAM ISTIRAHAT 0
5 BERHENTI SEBELUM JAM KERJA USAI 25
6 MUAT BOULDER 104
TOTAL 136
374

K = 1 + 3.33 log n
= 6.01214942780529
dibulatkan = 6

Bucket

X max = 10
X min = 10

Ci = ( X max - X min ) / K
= 0.00

Waktu Kerja Efektif

X max = 374
X min = 374

Ci = ( X max - X min ) / K
= 0.00
eff real dan full spek real

TOTAL PRODUKSI
1 CYCLE TIME 66.66 Q = 60/𝐶𝑇 𝑥 𝑘𝑎𝑝𝑎𝑠𝑖𝑡𝑎𝑠 𝑏𝑎𝑘 (𝑡𝑜𝑛) 𝑥 𝐸𝐾 𝑥
2 KAPASITAS BAK 15.8158
3 EFFISIENSI KERJA 73.34EFFISIENSI KERJA = W/WT x 100%
4 JUMLAH DT 1
5 WAKTU KERJA EFFEKTIF 374.01
6 JUMLAH RIT 32
PRODUKTIFITAS (TON/HARI) 89

EFFISIENSI KERJA = 73.3352941176471


DUMP TRUCK = 1
JUMLAH RITASE = 31
WAKTU KERJA TERSEDIA = 510

Ci Fi Xi
10 - 10.00 0 10.00
10.01 - 10.01 32 10.01
10.02 - 10.02 32 10.02
10.03 - 10.03 32 10.03
10.04 - 10.04 32 10.04
10.05 - 10.05 32 10.05
160

Ci Fi Xi
374 - 374.00 0 374.00
374.01 - 374.01 1 374.01
374.02 - 374.02 1 374.02
374.03 - 374.03 1 374.03
374.04 - 374.04 1 374.04
374.05 - 374.05 1 374.05
5
TOTAL PRODUKSI
𝑇 𝑥 𝑘𝑎𝑝𝑎𝑠𝑖𝑡𝑎𝑠 𝑏𝑎𝑘 (𝑡𝑜𝑛) 𝑥 𝐸𝐾 𝑥 𝑊.𝐾.𝑇 𝑥 𝐷𝑇 1
2
3
4
5
6
PRODUKTIFITAS (TON/HARI)

EFFISIENSI KERJA
DUMP TRUCK
JUMLAH RITASE
WAKTU KERJA TERSEDIA

Fi . Xi X Fi
0.00 0
320.32 32
0.00 10.01 0
0.00 0
0.00 0
0.00 0
320.32 32

Fi . Xi X Fi
0.00 0
374.01 1
0.00 374.01 0
0.00 0
0.00 0
0.00 0
374.01 1
eff 95% dan full spek real

CYCLE TIME 66.66 Q = 60/𝐶𝑇 𝑥 𝑘𝑎𝑝𝑎𝑠𝑖𝑡𝑎𝑠 𝑏𝑎𝑘 (𝑡𝑜𝑛) 𝑥 𝐸𝐾 𝑥 𝑊.𝐾.𝑇 𝑥 𝐷𝑇


KAPASITAS BAK 15.8158
EFFISIENSI KERJA 95.00 EFFISIENSI KERJA = W/WT x 100%
JUMLAH DT 1
WAKTU KERJA EFFEKTIF 374.01
JUMLAH RIT 32
115

= 73.3352941176471
= 1
= 31
= 510
𝑎𝑠 𝑏𝑎𝑘 (𝑡𝑜𝑛) 𝑥 𝐸𝐾 𝑥 𝑊.𝐾.𝑇 𝑥 𝐷𝑇
TOTAL PRODUKSI
1 CYCLE TIME
2 KAPASITAS BAK
3 EFFISIENSI KERJA
4 JUMLAH DT
5 WAKTU KERJA EFFEKTIF
6 JUMLAH RIT
PRODUKTIFITAS (TON/HARI)

EFFISIENSI KERJA =
DUMP TRUCK =
JUMLAH RITASE =
WAKTU KERJA TERSEDIA =
eff sesuai target
66.66 Q = 60/𝐶𝑇 𝑥 𝑘𝑎𝑝𝑎𝑠𝑖𝑡𝑎𝑠 𝑏𝑎𝑘 (𝑡𝑜𝑛) 𝑥 𝐸𝐾 𝑥 𝑊.𝐾.𝑇 𝑥 𝐷𝑇
15.8158
80.00 EFFISIENSI KERJA = W/WT x 100%
1
374.01
32
97

73.3352941176471
1
31
510
eff real dan full spek bak

TOTAL PRODUKSI
1 CYCLE TIME 66.66 Q = 60/𝐶𝑇 𝑥 𝑘𝑎𝑝𝑎𝑠𝑖𝑡𝑎𝑠 𝑏𝑎𝑘 (𝑡𝑜𝑛) 𝑥 𝐸𝐾 𝑥 𝑊.𝐾
2 KAPASITAS BAK 21
3 EFFISIENSI KERJA 73.34
EFFISIENSI KERJA = W/WT x 100%
4 JUMLAH DT 1
5 WAKTU KERJA EFFEKTIF 374.01
6 JUMLAH RIT 32
PRODUKTIFITAS (TON/HARI) 118

EFFISIENSI KERJA = 73.3352941176471


DUMP TRUCK = 1
JUMLAH RITASE = 31
WAKTU KERJA TERSEDIA = 510
TOTAL PRODUKSI
𝑇 𝑥 𝑘𝑎𝑝𝑎𝑠𝑖𝑡𝑎𝑠 𝑏𝑎𝑘 (𝑡𝑜𝑛) 𝑥 𝐸𝐾 𝑥 𝑊.𝐾.𝑇 𝑥 𝐷𝑇 1
2
3
4
5
6
PRODUKTIFITAS (TON/HARI)

EFFISIENSI KERJA
DUMP TRUCK
JUMLAH RITASE
WAKTU KERJA TERSEDIA
eff 95% dan full spek bak

CYCLE TIME 66.66 Q = 60/𝐶𝑇 𝑥 𝑘𝑎𝑝𝑎𝑠𝑖𝑡𝑎𝑠 𝑏𝑎𝑘 (𝑡𝑜𝑛) 𝑥 𝐸𝐾 𝑥 𝑊.𝐾.𝑇 𝑥 𝐷𝑇


KAPASITAS BAK 21
EFFISIENSI KERJA 95.00EFFISIENSI KERJA = W/WT x 100%
JUMLAH DT 1
WAKTU KERJA EFFEKTIF 374.01
JUMLAH RIT 32
153

= 73.3352941176471
= 1
= 31
= 510
eff turun dan full spek bak

TOTAL PRODUKSI
1 CYCLE TIME 66.66 Q = 60/𝐶𝑇 𝑥 𝑘𝑎𝑝𝑎𝑠𝑖𝑡𝑎𝑠
2 KAPASITAS BAK 21
3 EFFISIENSI KERJA 79.00
EFFISIENSI KERJA = W/WT x 100%
4 JUMLAH DT 1
5 WAKTU KERJA EFFEKTIF 374.01
6 JUMLAH RIT 32
PRODUKTIFITAS (TON/HARI) 127

EFFISIENSI KERJA = 73.3352941176471


DUMP TRUCK = 1
JUMLAH RITASE = 31
WAKTU KERJA TERSEDIA = 510
TOTAL PRODUKSI
Q = 60/𝐶𝑇 𝑥 𝑘𝑎𝑝𝑎𝑠𝑖𝑡𝑎𝑠 𝑏𝑎𝑘 (𝑡𝑜𝑛) 𝑥 𝐸𝐾 𝑥 𝑊.𝐾.𝑇 𝑥 𝐷𝑇 1
2
KERJA = W/WT x 100% 3
4
5
6
PRODUKTIFITAS (TON/HARI)

EFFISIENSI KERJA
DUMP TRUCK
JUMLAH RITASE
WAKTU KERJA TERSEDIA
eff turun dan full spek bak

CYCLE TIME 66.66 Q = 60/𝐶𝑇 𝑥 𝑘𝑎𝑝𝑎𝑠𝑖𝑡𝑎𝑠 𝑏𝑎𝑘 (𝑡𝑜𝑛) 𝑥 𝐸𝐾 𝑥 𝑊.𝐾.𝑇 𝑥 𝐷𝑇


KAPASITAS BAK 21
EFFISIENSI KERJA 77.00
EFFISIENSI KERJA = W/WT x 100%
JUMLAH DT 1
WAKTU KERJA EFFEKTIF 0.00
JUMLAH RIT 32
124

= 0
= 1
= 31
= 510
belum di edit

No rata2 RATA2 BUCKET


waktu kerja efektif

1 Manuver Lo17.277813 10 374


2 Loading 122.57375 6.2333333
3 Hauling 271.16281
4 Manuver du11.425313
5 Dumping 19.0475
6 Return 222.11094
7 Waiting 225.75594
Jumlah 889.35406
14.822568 Menit Produktifitas Dump Truck / h

Kapasitas Bucket

jumlah Pengisian
Jumlah Alat angkut
Kapasitas bak DT
Waktu Kerja Efekti

Efisiensi Kerja (Eff)


No Parameter W S WKE

TL 501 127 374


6.23
1 Cycle Time 14.82
2 Kapasitas Bak (ton)15.80
3 Jumlah bucket 10.00
4 Efesiensi Kerja 7333% WKE Waktu KerjaUA (%)
5 Waktu Kerja Efektif6.23 374 510 73
6 Jumlah DT 1
Produktifitas Dump Truck / hari ( Ton ) 292.35 Kap Bak
34.2 73.333333
0.7333333
Produktivitas Alat Angkut / jam
Kapasitas Bucket
Density 1.58 Ton
jumlah Pengisian10.00 Bucket
Jumlah Alat angkut 1 Unit
Kapasitas bak DT15.80 Ton
Waktu Kerja Efektif
6.233333 Jam
cycle time 14.82257 Menit
Efisiensi Kerja (Eff)
73.33333

Pa = (Kapasitas Bak × Eff × 60 Menit × n.A × D)/ Ct

Pa = 74.1043 ton/Jam
Pa = 461.9168 ton/hari