Professional Documents
Culture Documents
WORK INSTRUCTION
Page No: 1 of 2
Issue No.:
GEAR AND SHAFT
Date :
Purpose / Objective This process describes by gear & shaft for spindle rotation
Select the raw material as per drawing referents. Before select the raw material refers the item code
1
and color coding for Table 1.1.
2 Machine on and ensure the oil level, coolant level, air pressure and lubrication.
3 Select the tools and measuring instruments as per drawing. With Reference process cord xxxxxx.
Ensure the raw Material as per drawing after loading the machine. Material lording purpose used for
4
crane.
Set the cutting length to the machine as per drawing dimension. After clam the material and set the
5 machine parameters (rpm and federate) after run the machine.
6 Clamping and cutting process follow the below step 6.1 (Fig-1).
6.1
Fig-1
Cutting process will be completed. Fist component check and verify the QA inspector as per drawing
7 dimension. And operator also checking the fist component dimension as per drawing then continuously
runs the machine as per production plane.
8 Collect the cutting material on the pine and put the material identification card.
Total cutting material issue the bin card and reties the total stock. After remove the material on the
9
machine then put the location.
Ensure the cutting length and pine card. After move to next process for turning machine. Moving
10
process used by Crane, Forklift, traly.
11 Machine on and ensure the oil level, coolant level, air pressure and lubrication.
First operation wise select the machine jaws, tools and measuring instruments as per drawing. With
12
Reference process cord xxxxxx
Clamp the jaws in the chuck after clamping the raw material. First operation clamping method follow the
13
below step 14.1 (Fig-2).
Step by step create the programs and take the offset after run the machine step by step sequences.
14
First operation sequences follow the below step 15.
14.1
Fig-2
Fig-3
♦ Outer finishing
23
♦ Vertical milling
♦ Horizontal milling
24 First component finish and check as per drawing dimensions. After informer the QA inspector.
QA inspection it will be ok. Then collect the first inspection report after continues the production as per
25
production planning. Operator every five component check and writing the inspection report.
Finally operation finished component inspection by as per drawing tolerance. And check the visual
26
inspection.
27 Finish component show on the below step 27.10 (Fig -4, Fig-5).
27.1
Fig-4 Fig-5
27 Finish component move to final inspection for QA section. Inspection is ok put approval pine card.
Table: 1.1
2 Machine on and ensure the spin oil level, cutting oil level, air pressure, lubrication, scrap and chips.
Select the tools and measuring instruments as per drawing. With Reference process cord xxxxxx.
3
(ex: tools: hob, gearing gears, fixtures, spanners and allenkey / flange mice, vernier, dial with stand etc)
As per process suitable machining setting us preplanned and ensured.
4
(Ex: gearing, hob mounting, fixture mounting, stopper setting, fixture and job dialing etc.)
Check the job run out, after clamp us job properly, and Set the cutting depth as per machine standard
5 dimension (rpm and federate)., after then run the machine
6 Clamping and cutting process follow the below step 6.1 (Fig-1).
6.1
Fig-1
Cutting process will be completed. Fist component check and verify the QA inspector as per drawing
7 dimension. And operator also checking the fist component dimension as per drawing then continuously
runs the machine as per production plane.
8 Ensure the process and completed gear material on the bines and put the material identification card.
9 Inspection completed After then moves to next step process, Moving process used by Forklift, trolley
10 .
Machine on and ensure the spin oil level, cutting oil level, air pressure,
2
lubrication, scrap and chips.
Select the tools and measuring instruments as per drawing. With Reference process cord xxxxxx.
3
(ex: tools: hob, gearing gears, fixtures, spanners and allenkey / flange mice, vernier, dial with stand etc)
As per process suitable machining setting us preplanned and ensured.
4
(Ex: gearing, cutter mounting, fixture mounting, stopper setting, fixture and job dialing etc.)
Check the job run out, after clamp us job properly, and Set the cutting depth as per machine standard
5 dimension (rpm and federate)., after then run the machine
6 Clamping and cutting process follow the below step 6.1 (Fig-1).
6.1
Fig-1
Cutting process will be completed. Fist component check and verify the QA inspector as per drawing
7 dimension. And operator also checking the fist component dimension as per drawing then continuously
runs the machine as per production plane.
8 Ensure the process and completed gear material on the bines and put the material identification card..
9 Inspection completed After then moves to next step process, Moving process used by Forklift, trolley
2 Machine on and ensure the spin oil level, cutting oil level, air pressure, lubrication, scrap and chips.
Select the tools and measuring instruments as per drawing. With Reference process cord xxxxxx.
3
(ex: tools: hob, gearing gears, fixtures, spanners and allenkey / flange mice, vernier, dial with stand etc)
As per process suitable machining setting us preplanned and ensured.
4
(Ex: gearing, cutter mounting, fixture mounting, stopper setting, fixture and job dialing etc.)
Check the job run out, after clamp us job properly, and Set the cutting depth as per machine standard
5 dimension (rpm and federate)., after then run the machine
6 Clamping and cutting process follow the below step 6.1 (Fig-1).
6.1
Fig-1
Milling process will be completed. Fist component check and verify the QA inspector as per drawing
7 dimension. And operator also checking the fist component dimension as per drawing then continuously
runs the machine as per production plane.
8 Ensure the process and completed gear material on the bines and put the material identification card..
9 Inspection completed After then moves to next step process, Moving process used by Forklift, trolley
10 .
2 Machine on and ensure the spin oil level, cutting oil level, air pressure, lubrication, scrap and chips.
Select the tools and measuring instruments as per drawing. With Reference process cord xxxxxx.
3
(ex: broach, fixtures, spanners and allenkey / vernier, dial with stand etc)
As per process suitable machining setting us preplanned and ensured.
4
(Ex: broaching tool mounting, fixture mounting, stopper setting, fixture and job dialing etc.)
Check the job run out, after clamp us job properly, and Set the cutting depth as per machine standard
5 dimension (rpm and federate)., after then run the machine
6 Clamping and cutting process follow the below step 6.1 (Fig-1) & (Fig-2)
6.1
Fig-1 Fig-2
Broaching process will be completed. Fist component check and verify the QA inspector as per drawing
7 dimension. And operator also checking the fist component dimension as per drawing then continuously
runs the machine as per production plane.
8 Ensure the process and completed gear material on the bines and put the material identification card.
9 Inspection completed After then moves to next step process, Moving process used by Forklift, trolley
10 .
2 Machine on and ensure the spin oil level, cutting oil level, air pressure, lubrication, scrap and chips.
Select the tools and measuring instruments as per drawing. With Reference process cord xxxxxx.
3
(ex: slotting tool, fixtures, spanners and allenkey / vernier, dial with stand etc)
As per process suitable machining setting us preplanned and ensured.
4
(Ex: slotting tool mounting, fixture mounting, stopper setting, fixture and job dialing etc.)
Check the job run out, after clamp us job properly, and Set the cutting depth as per machine standard
5 dimension (rpm and federate)., after then run the machine
6 Clamping and cutting process follow the below step 6.1 (Fig-1)
6.1
Fig-1
Slotting process will be completed. Fist component check and verify the QA inspector as per drawing
7 dimension. And operator also checking the fist component dimension as per drawing then continuously
runs the machine as per production plane.
8 Ensure the process and completed gear material on the bines and put the material identification card.
9 Inspection completed After then moves to next step process, Moving process used by Forklift, trolley
2 Machine on and ensure the spin oil level, cutting oil level, air pressure, lubrication, scrap and chips.
Select the tools and measuring instruments as per drawing. With Reference process cord xxxxxx.
3
(ex: cutting tool, fixtures, spanners and allenkey / vernier, dial with stand etc)
As per process suitable machining setting us preplanned and ensured.
4
(Ex: tool mounting, fixture mounting, stopper setting, fixture and job dialing etc.)
Check the job run out, after clamp us job properly, and Set the cutting depth as per machine standard
5 dimension (rpm and federate)., after then run the machine
6 Clamping and cutting process follow the below step 6.1 (Fig-1)
6.1
Fig-1
Tooth rounding process will be completed. Fist component check and verify the QA inspector as per
7 drawing dimension. And operator also checking the fist component dimension as per drawing then
continuously runs the machine as per production plane.
8 Ensure the process and completed gear material on the bines and put the material identification card.
9 Inspection completed After then moves to next step process, Moving process used by Forklift, trolley
10 .
2 Machine on and ensure the spin oil level, cutting oil level, air pressure, lubrication, scrap and chips.
Select the tools and measuring instruments as per drawing. With Reference process cord xxxxxx.
3
(ex: wheel, fixtures, spanners and allenkey / dial with stand etc)
As per process suitable machining setting us preplanned and ensured.
4
(Ex: wheel mounting, fixture mounting, stopper setting, fixture and job dialing etc.)
Check the job run out, after clamp us job properly, and Set the cutting depth as per machine standard
5 dimension (rpm and federate)., after then run the machine
6 Clamping and cutting process follow the below step 6.1 (Fig-1)
6.1
Fig-1
Tooth debarring process will be completed. Fist component check and verify the QA inspector as per
7 drawing dimension. And operator also checking the fist component dimension as per drawing then
continuously runs the machine as per production plane.
8 Ensure the process and completed gear material on the bines and put the material identification card.
9 Inspection completed After then moves to next step process, Moving process used by Forklift, trolley
10 .
2 This process Send to out of source within D.C reference (job work)
3 Clamping and heat process follow the below step 3.1 (Fig-1)
3.1
Fig-1
Job work supplier as maintained as gear material required standard tolerance as
Process: case Hardening
HRC-56 TO 60
4
Case depth: 1.2 to 1.5
Bend removing : 0.04 to 0.08
5 Received the process completed gear material on the bines and put the material identification card.
6 Inspection completed After then moves to next step process, Moving process used by Forklift, trolley
Select the tools and measuring instruments as per drawing. With Reference process cord xxxxxx.
3 (ex: wheel, hard inserts, boring & facing bars, fixtures, spanners and allenkey / bore gauge, mice’s,
dial with stand etc)
As per process suitable machining setting us preplanned and ensured.
4 (Ex: wheel mounting, fixture mounting, stopper setting, jaws with chuck mounting, programming edit,
required tool arrangement, fixture and job dialing etc.)
Check the job run out, after clamp us job properly, edit on programming and Set the cutting depth as
5 per machine standard dimension (rpm and federate)., after then run the machine
6 Clamping and cutting process follow the below step 6.1 (Fig-1) (Fig-2)
6.1
Hard turning process will be completed. First component check and verify the QA inspector as per
7 drawing dimension. And operator also checking the fist component dimension as per drawing then
continuously runs the machine as per production plane.
8 Ensure the process and completed gear material on the bines and put the material identification card.
9 Inspection completed After then moves to next step process, Moving process used by Forklift, trolley
(Ex: wheel mounting, fixture mounting, stopper setting, jaws with chuck and centers mounting,
programming edit, required tool arrangement, fixture and job dialing etc.)
Check the job run out, after clamp us job properly, edit on programming and Set the cutting depth as
5 per machine standard dimension (rpm and federate)., after then run the machine
6 Clamping and cutting process follow the below step 6.1 (Fig-1)
6.1
Fig-1
O.D grinding process will be completed. Fist component check and verify the QA inspector as per
7 drawing dimension. And operator also checking the fist component dimension as per drawing then
continuously runs the machine as per production plane.
8 Ensure the process and completed gear material on the bines and put the material identification card.
9 Inspection completed After then moves to next step process, Moving process used by Forklift, trolley
10 .
(Ex: wheel mounting, fixture mounting, stopper setting, jaws with chuck and centers mounting,
programming edit, required tool arrangement, fixture and job dialing etc.)
Check the job run out, after clamp us job properly, edit on programming and Set the cutting depth as
5 per machine standard dimension (rpm and federate)., after then run the machine
6 Clamping and cutting process follow the below step 6.1 (Fig-1)
6.1
Fig-6.1
SPLINE grinding process will be completed. Fist component check and verify the QA inspector as per
7 drawing dimension. And operator also checking the fist component dimension as per drawing then
continuously runs the machine as per production plane.
8 Ensure the process and completed gear material on the bines and put the material identification card.
9 Inspection completed After then moves to next step process, Moving process used by Forklift, trolley
per machine standard dimension (rpm and federate)., after then run the machine
6 Clamping and cutting process follow the below step 6.1 (Fig-1)
6.1
Fig-6.1
Gear grinding process will be completed. Fist component check and verify the QA inspector as per
7 drawing dimension. And operator also checking the fist component dimension as per drawing then
continuously runs the machine as per production plane.
8 Ensure the process and completed gear material on the bines and put the material identification card.
9 Inspection completed After then moves to next step process, Moving process used by Forklift, trolley