Professional Documents
Culture Documents
WORKSHEET 3 Trucks v01
WORKSHEET 3 Trucks v01
DATE:
WORKSHEET 3
Formula:
1. Using normal (P1) and queuing theory method (P2), determine the expected production, unit cost of excavation and haul, and number of days (8 working hours/day) to complete
the work based on the following data:
Total volume of Hoe Loading rate Job efficy Cost of hoe/hr Truck size Cost of truck/hr
excavation (lcm) Transit time
(lcm/60 min) (min) (RM) (lcm) (RM)
268 55 102 10.53 29 0.45
15,367
432 45 144 14.16 38 0.51
150 50 95 9.50 30 0.55
45,656
200 50 115 11.50 35 0.58
* The actual number of truck will be assign on the 3rd row of the table. For example, N=12.2 12, fill in the table from the top 14, 13, 12 (coloured row), 11, 10, 9, 8.
Page | 1
NAME:
DATE:
Adjmt
Truck Load No of Production Production Cost per Cost per Days Days
to r PO Pt Fleet cost P1/day P2/day
size time haul 1 2 unit P1 unit P2 for P1 for P2
haul no
13
17
Page | 2
NAME:
DATE:
Adjmt
Truck Load No of Production Production Cost per Cost per Days Days
to r PO Pt Fleet cost P1/day P2/day
size time haul 1 2 unit P1 unit P2 for P1 for P2
haul no
13
17
Page | 3
NAME:
DATE:
Page | 4