You are on page 1of 49

PROJECT RAIL VIKAS NIGAM LIMITED

CALCULATIONS
DesignFOR
& Construction of Viaduct and Stations (Extension of North South Corridor) from Naupura to Dakshineswar.
Description MGC FILE NO. BH-T2 Rev.D-1
VERTICAL CAPACITY OF PILES Cal By AKD DATE 9/3/2016 SHEET
Checked By MSP DATE 9/3/2016 OF
Sec. Reference
n
I
(
Q u = A p∗( 0. 5 DγN γ + Pd N q ) + ∑ KP di tan δA si +α CA S
i =1
) (As per IS2911 Part I/Sec 2)

Length of Pile below Ground Level L = 31.5 m


Dia of Pile D = 1.2 m
Effective Unit weight of soil at Pile Tip γ = 0.820 t/m3
Bearing Capacity Factor Nq = 35.00
Bearing Capacity Factor Nγ = 37.77
Depth of Pile Cap = 0m
Area of Pile Ap = 1.1310 m2
Earth Pressure Coefficient k = 1 (As per ODC Clause - 7.17a)
Overburden Considered for a depth of = 15 times the dia of pile (As per ODC Clause - 7.17a)
Overburden Pdi = 15.1 t/m2
Overburden Pd = 15.1 t/m2
Angle of Internal Friction at toe Φ = 33.00 deg (As per GIR)
DepthOveral γsub d*γsub Pdi As Σ K x Pdi x Corrected
layer Φ δ tanδ C α α x C x As
m Depth t/m3 t/m2 t/m2 m2 tan (δ) x Asi N Value
- 4 4 ### 3.40 1.70 15.08 0 0 0.00 0.00 0 0.4 0.00 (As per ODC Clause - 7.17a)
I 1 5 ### 0.78 3.79 3.77 0 0 0.00 0.00 0 0.4 0.00 (As per ODC Clause - 7.17a)
I 2.5 7.5 ### 1.95 5.16 9.42 0 0 0.00 0.00 2.2 0.4 8.29 2.00
I 6 13.5 ### 4.80 8.53 22.62 0 0 0.00 0.00 2.2 0.4 19.91 2.00
II 3 16.5 ### 2.76 12.31 11.31 0 0 0.00 0.00 6 0.4 27.14 9.00
II 1.5 18 ### 1.38 14.38 5.65 0 0 0.00 0.00 6 0.4 13.57 9.00
III 3 21 ### 2.40 15.07 11.31 0 0 0.00 0.00 6 0.4 27.14 9.00
IV 7 28 ### 7.14 15.07 26.39 33 33 0.65 258.26 0 0.4 0.00
IV 3 31 ### 3.06 15.07 11.31 0 0 0.00 0.00 13 0.4 58.81 20.00
V 0.5 31.5 ### 0.41 15.07 1.88 33 33 0.65 18.45 0.00
276.71 154.87
= %
End Bearing Component for Sand layer = 617.55 T
Friction Bearing Component for Sand layer = 276.71 T
End Bearing Resistance for Clay Layer = 0 T
Friction Bearing Resistance for Clay Layer = 154.87 T
Total End Bearing Resistance = 617.55 T
Total Friction Bearing Resistance = 431.58 T
Total Bearing Resistance including both cohessive & granular so = 1049.13 T
Factor of safety = 2.5 (As per IS2911 Part I/Sec 2)
Safe Bearing Capacity = 419.65 T

Pile Cut Off level from GL = 2.5 m


Length of Pile below Cut-off Level Level = 29.0 m
Project RAIL VIKAS NIGAM LIMITED

Calculations for Decipline MGC File CAL 104 / Rev D-1


Cal. By AKD Date 03/09/16
VERTICAL CAPACITY OF PILE SUMMARY SHEET
Chkd. By MSP Date 03/09/16
Sec.

Table: 1 PILE DIA. = 1.2 m COL = 2.5 m bgl

1 2 3 4 5 6 7 8 9 10 11

End of Available
Pile Pile
Nearest Sand Sand Working Recommended
Critical Ground Pile Tip termination termination
Pier No. Influencing Layer / Clay layer Load Vertical Working
Borehole Level (m) Level (m) depth below depth below
Boreholes Layer Start below Pile Capacity (t) Load (t)
EGL, (m) COL, (m)
Level (m) Toe (m)

P 01 ABH-1 ABH-1
Borehole Investigation in Progress
P 02 ABH-1 ABH-1

P 03 ABH-1, BH-T2 BH-T2 + 4.46 - 27.04 31.50 29.00 -40.00 8.50 422
400.00
P 04 BH-T2 BH-T2 + 4.46 - 27.04 31.50 29.00 -40.00 8.50 422

P 05 BH-T1 BH-T1 + 3.90 - 21.60 25.50 23.00 -28.00 2.50 403


400.00
P 06 BH-T1 BH-T1 + 3.90 - 21.60 25.50 23.00 -28.00 2.50 403

P 07 BH-T1, ABH-2 -

P 08 ABH-2, ABH-3 ABH-2 Borehole Investigation in Progress


P 09 ABH-3 ABH-3

P 10 ABH-3, BH-T3 BH-T3 + 3.30 - 27.20 30.50 28.00 -33.50 3.00 428
400.00
P 11 BH-T3 BH-T3 + 3.30 - 27.20 30.50 28.00 -33.50 3.00 428

P 12 BH-T3, BH-T4 BH-T4 Borehole Investigation in Progress


P 13 BH-T4 BH-T4 + 3.42 - 26.58 30.00 27.50 -50.00 20.00 481
400.00
P 14 BH-T4 BH-T4 + 3.42 - 26.58 30.00 27.50 -50.00 20.00 481

P 15 ABH-4 ABH-4

P 16 ABH-4 ABH-4

P 17 ABH-5 ABH-5
Borehole Investigation in Progress
P 18 ABH-5, ABH-6 ABH-5

P 19 ABH-6 ABH-6

P 20 ABH-6, BH-T5 -

P 21 BH-T5 BH-T5 + 5.69 - 27.81 33.50 31.00 -50.00 16.50 428


400.00
P 22 BH-T5, ABH-7 BH-T5 + 5.69 - 27.81 33.50 31.00 -50.00 16.50 428

P 23 ABH-7 ABH-7

P 24 ABH-7 ABH-7

P 25 ABH-8 ABH-8 Borehole Investigation in Progress


P 26 ABH-8 ABH-8

P 27 ABH-8 ABH-8

P 28 BH-T6 BH-T6 + 6.54 - 23.47 30.00 27.50 -50.00 20.00 447


400.00
P 29 BH-T6 BH-T6 + 6.54 - 23.47 30.00 27.50 -50.00 20.00 447

P 30 BH-T6 BH-T6 + 6.54 - 23.47 30.00 27.50 -50.00 20.00 447

P 31 ABH-9 ABH-9

P 32 ABH-9 ABH-9
Borehole Investigation in Progress
P 33 ABH-10 ABH-10

P 34 ABH-10 ABH-10
Project RAIL VIKAS NIGAM LIMITED

Calculations for Decipline MGC File CAL 104 / Rev D-1


Cal. By AKD Date 03/09/16
VERTICAL CAPACITY OF PILE SUMMARY SHEET
Chkd. By MSP Date 03/09/16
Sec.

Table: 1 PILE DIA. = 1.2 m COL = 2.5 m bgl

1 2 3 4 5 6 7 8 9 10 11

End of Available
Pile Pile
Nearest Sand Sand Working Recommended
Critical Ground Pile Tip termination termination
Pier No. Influencing Layer / Clay layer Load Vertical Working
Borehole Level (m) Level (m) depth below depth below
Boreholes Layer Start below Pile Capacity (t) Load (t)
EGL, (m) COL, (m)
Level (m) Toe (m)

P 35 BH-T13 BH-T13 + 7.98 - 37.02 45.00 42.50 -50.45 5.45 437


400.00
P 36 BH-T13, ABH-11 BH-T13 + 7.98 - 37.02 45.00 42.50 -50.45 5.45 437

P 37 ABH-11 ABH-11

P 38 ABH-11 ABH-11

P 39 ABH-12 ABH-12

P 40 ABH-12 ABH-12

P 41 ABH-13 ABH-13

P 42 ABH-13 ABH-13

P 43 ABH-14 ABH-14

P 44 ABH-14 ABH-14 Borehole Investigation in Progress


P 45 ABH-14, ABH-15 -

P 46 ABH-15 ABH-15

P 47 ABH-15 ABH-15

P 48 ABH-16 ABH-16

P 49 ABH-16 ABH-16

P 50 ABH-16 ABH-16

P 51 ABH-16, BH-C18 -

P 52 BH-C18 BH-C18 + 8.20 - 24.80 33.00 30.50 -36.00 3.00 405


400.00
P 53 BH-C18 BH-C18 + 8.20 - 24.80 33.00 30.50 -36.00 3.00 405

P 54 BH-C18, ABH-17 -

P 55 BH-C18, ABH-17 ABH-17

P 56 ABH-17 ABH-17 Borehole Investigation in Progress


P 57 ABH-17 ABH-17

P 58 ABH-17, BH-C17 -

P 59 BH-C17 BH-C17 + 9.40 - 32.60 42.00 39.50 -46.50 4.50 411 400.00

P 60 BH-C17, ABH-18 -
Borehole Investigation in Progress
P 61 ABH-18 ABH-18

P 62 BH-C16 BH-C16 + 11.30 - 35.70 47.00 44.50 -50.10 3.10 435 400.00

P 63 BH-C16, ABH-19 -

P 64 ABH-19 ABH-19

P 65 ABH-19, ABH-20 -

P 66 ABH-20 ABH-20 Borehole Investigation in Progress


P 67 ABH-20, ABH-21 -

P 68 ABH-21 ABH-21

P 69 ABH-21,BH-C15 BH-C15 + 11.80 - 34.70 46.50 44.00 -50.10 3.60 430

P 70 BH-C15 BH-C15 + 11.80 - 34.70 46.50 44.00 -50.10 3.60 430 400.00

P 71 BH-C14, BH-C15 BH-C15 + 11.80 - 34.70 46.50 44.00 -50.10 3.60 430

P 72 BH-C14 BH-C14 + 10.40 - 34.10 44.50 42.00 -47.00 2.50 461


400.00
P 73 BH-C14 BH-C14 + 10.40 - 34.10 44.50 42.00 -47.00 2.50 461

P 74 ABH-22 ABH-22
Borehole Investigation in Progress
Project RAIL VIKAS NIGAM LIMITED

Calculations for Decipline MGC File CAL 104 / Rev D-1


Cal. By AKD Date 03/09/16
VERTICAL CAPACITY OF PILE SUMMARY SHEET
Chkd. By MSP Date 03/09/16
Sec.

Table: 1 PILE DIA. = 1.2 m COL = 2.5 m bgl

1 2 3 4 5 6 7 8 9 10 11

End of Available
Pile Pile
Nearest Sand Sand Working Recommended
Critical Ground Pile Tip termination termination
Pier No. Influencing Layer / Clay layer Load Vertical Working
Borehole Level (m) Level (m) depth below depth below
Boreholes Layer Start below Pile Capacity (t) Load (t)
EGL, (m) COL, (m)
Level (m) Toe (m)

Borehole Investigation in Progress


P 75 BH-C13, ABH-22 -
Project RAIL VIKAS NIGAM LIMITED

Calculations for Decipline MGC File CAL 104 / Rev D-1


Cal. By AKD Date 03/09/16
VERTICAL CAPACITY OF PILE SUMMARY SHEET
Chkd. By MSP Date 03/09/16
Sec.

Table: 1 PILE DIA. = 1.2 m COL = 2.5 m bgl

1 2 3 4 5 6 7 8 9 10 11

End of Available
Pile Pile
Nearest Sand Sand Working Recommended
Critical Ground Pile Tip termination termination
Pier No. Influencing Layer / Clay layer Load Vertical Working
Borehole Level (m) Level (m) depth below depth below
Boreholes Layer Start below Pile Capacity (t) Load (t)
EGL, (m) COL, (m)
Level (m) Toe (m)

P 76 BH-C13 BH-C13 + 8.80 - 31.20 40.00 37.50 -46.50 6.50 458


400.00
P 77 BH-C13 BH-C13 + 8.80 - 31.20 40.00 37.50 -46.50 6.50 458

P 78 BH-C12 BH-C12 + 9.00 - 30.50 39.50 37.00 -42.00 2.50 416 400.00

P 79 BH-C10 BH-C10
Bridge
P 80 BH-C10 BH-C10

P 81 BH-C9 BH-C9
Bridge
P 82 BH-C9 BH-C9

P 83 BH-C6 BH-C6
Bridge
P 84 BH-C6 BH-C6

P 85 BH-C4, BH-C5 BH-C4 + 5.00 - 25.00 30.00 27.50 -33.50 3.50 436
400.00
P 86 BH-C4 BH-C4 + 5.00 - 25.00 30.00 27.50 -33.50 3.50 436

P 87 ABH-23, BH-C4 ABH-23


Borehole Investigation in Progress
P 88 ABH-23 ABH-23

P 89 BH-C3 BH-C3 + 5.70 - 24.30 30.00 27.50 -33.00 3.00 408


400.00
P 90 BH-C3 BH-C3 + 5.70 - 24.30 30.00 27.50 -33.00 3.00 408

P 91 BH-C3, ABH-24 ABH-24

P 92 ABH-24 ABH-24 Borehole Investigation in Progress


P 93 BH-C19, ABH-24 -

P 94 BH-C19, BH-C2 BH-C19 + 4.60 - 25.40 30.00 27.50 -33.00 3.00 443 400.00

P 95 BH-C2 BH-C2 + 5.50 - 24.50 30.00 27.50 -33.00 3.00 457 400.00

P 96 BH-C1, BH-C2 BH-C1 + 4.60 - 24.40 29.00 26.50 -35.50 6.50 410

P 97 BH-C1 BH-C1 + 4.60 - 24.40 29.00 26.50 -35.50 6.50 410

P 98 BH-C1 BH-C1 + 4.60 - 24.40 29.00 26.50 -35.50 6.50 410 400.00

P 99 BH-C1 BH-C1 + 4.60 - 24.40 29.00 26.50 -35.50 6.50 410

P 100 BH-20, BH-C1 BH-C1 + 4.60 - 24.40 29.00 26.50 -35.50 6.50 410

P 101 BH-C20 BH-C20

P 102 BH-C20 BH-C20

P 103 BH-C20, ABH-25 -

P 104 ABH-25 ABH-25

P 105 ABH-25 ABH-25

P 106 ABH-25, BH-C21 -

P 107 BH-C21 BH-C21


Borehole Investigation in Progress
P 108 BH-C21 BH-C21

P 109 BH-C21, ABH-26 -

P 110 ABH-26 ABH-26

P 111 ABH-26 ABH-26

P 112 ABH-26, ABH-27 -

P 113 ABH-27 ABH-27


Project RAIL VIKAS NIGAM LIMITED

Calculations for Decipline MGC File CAL 104 / Rev D-1


Cal. By AKD Date 03/09/16
VERTICAL CAPACITY OF PILE SUMMARY SHEET
Chkd. By MSP Date 03/09/16
Sec.

Table: 1 PILE DIA. = 1.2 m COL = 2.5 m bgl

1 2 3 4 5 6 7 8 9 10 11

End of Available
Pile Pile
Nearest Sand Sand Working Recommended
Critical Ground Pile Tip termination termination
Pier No. Influencing Layer / Clay layer Load Vertical Working
Borehole Level (m) Level (m) depth below depth below
Boreholes Layer Start below Pile Capacity (t) Load (t)
EGL, (m) COL, (m)
Level (m) Toe (m)
PROJECT RAIL VIKAS NIGAM LIMITED
CALCULATIONS
DesignFOR
& Construction of Viaduct and Stations (Extension of North South Corridor) from Naupura to Dakshineswar.
Description MGC FILE NO. BH-T1 Rev.D-1
VERTICAL CAPACITY OF PILES Cal By AKD DATE 9/3/2016 SHEET
Checked By MSP DATE 9/3/2016 OF
Sec. Reference
n
I
(
Q u = A p∗( 0. 5 DγN γ + Pd N q ) + ∑ KP di tan δA si +α CA S
i =1
) (As per IS2911 Part I/Sec 2)

Length of Pile below Ground Level L = 25.5 m


Dia of Pile D = 1.2 m
Effective Unit weight of soil at Pile Tip γ = 0.850 t/m3
Bearing Capacity Factor Nq = 35.00
Bearing Capacity Factor Nγ = 37.77
Depth of Pile Cap = 0m
Area of Pile Ap = 1.1310 m2
Earth Pressure Coefficient k = 1 (As per ODC Clause - 7.17a)
Overburden Considered for a depth of = 15 times the dia of pile (As per ODC Clause - 7.17a)
Overburden Pdi = 15.5 t/m2
Overburden Pd = 15.5 t/m2
Angle of Internal Friction at toe Φ = 33.00 deg (As per GIR)
DepthOveral γsub d*γsub Pdi As Σ K x Pdi x Corrected
layer Φ δ tanδ C α α x C x As
m Depth t/m3 t/m2 t/m2 m2 tan (δ) x Asi N Value
- 5 5 ### 4.10 2.05 18.85 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 1.5 6.5 ### 1.23 4.72 5.65 0 0 0.00 0.00 2.25 0.7 8.91 2.00 (As per ODC Clause - 7.17a)
II 2.5 9 ### 2.00 6.33 9.42 0 0 0.00 0.00 1.8 0.7 11.88 2.00
II 3 12 ### 2.55 8.61 11.31 0 0 0.00 0.00 1.8 0.7 14.25 2.00
III 3 15 ### 2.76 11.26 11.31 0 0 0.00 0.00 5.8 0.5 32.80 7.00
III 3 18 ### 2.88 14.08 11.31 0 0 0.00 0.00 5.8 0.5 32.80 7.00
III 0.5 18.5 ### 0.48 15.52 1.88 0 0 0.00 0.00 5.8 0.5 5.47 7.00
IV 7 25.5 ### 5.95 15.52 26.39 33 33 0.65 265.97 0.00
265.97 106.09
= %
End Bearing Component for Sand layer = 636.13 T
Friction Bearing Component for Sand layer = 265.97 T
End Bearing Resistance for Clay Layer = 0 T
Friction Bearing Resistance for Clay Layer = 106.09 T
Total End Bearing Resistance = 636.13 T
Total Friction Bearing Resistance = 372.07 T
Total Bearing Resistance including both cohessive & granular so = 1008.20 T
Factor of safety = 2.5
Safe Bearing Capacity = 403.28 T (As per IS2911 Part I/Sec 2)

Pile Cut Off level from GL = 2.5 m


Length of Pile below Cut-off Level Level = 23.0 m
PROJECT RAIL VIKAS NIGAM LIMITED
CALCULATIONS
DesignFOR
& Construction of Viaduct and Stations (Extension of North South Corridor) from Naupura to Dakshineswar.
Description MGC FILE NO. BH-T2 Rev.D-1
VERTICAL CAPACITY OF PILES Cal By AKD DATE 9/3/2016 SHEET
Checked By MSP DATE 9/3/2016 OF
Sec. Reference
n
I
(
Q u = A p∗( 0. 5 DγN γ + Pd N q ) + ∑ KP di tan δA si +α CA S
i =1
) (As per IS2911 Part I/Sec 2)

Length of Pile below Ground Level L = 31.5 m


Dia of Pile D = 1.2 m
Effective Unit weight of soil at Pile Tip γ = 0.820 t/m3
Bearing Capacity Factor Nq = 35.00
Bearing Capacity Factor Nγ = 37.77
Depth of Pile Cap = 0m
Area of Pile Ap = 1.1310 m2
Earth Pressure Coefficient k = 1 (As per ODC Clause - 7.17a)
Overburden Considered for a depth of = 15 times the dia of pile (As per ODC Clause - 7.17a)
Overburden Pdi = 15.1 t/m2
Overburden Pd = 15.1 t/m2
Angle of Internal Friction at toe Φ = 33.00 deg (As per GIR)
DepthOveral γsub d*γsub Pdi As Σ K x Pdi x Corrected
layer Φ δ tanδ C α α x C x As
m Depth t/m3 t/m2 t/m2 m2 tan (δ) x Asi N Value
- 4 4 ### 3.40 1.70 15.08 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 1 5 ### 0.78 3.79 3.77 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 2.5 7.5 ### 1.95 5.16 9.42 0 0 0.00 0.00 2.2 0.7 14.51 2.00
I 6 13.5 ### 4.80 8.53 22.62 0 0 0.00 0.00 2.2 0.7 34.83 2.00
II 3 16.5 ### 2.76 12.31 11.31 0 0 0.00 0.00 6 0.4 27.14 9.00
II 1.5 18 ### 1.38 14.38 5.65 0 0 0.00 0.00 6 0.4 13.57 9.00
III 3 21 ### 2.40 15.07 11.31 0 0 0.00 0.00 6 0.4 27.14 9.00
IV 7 28 ### 7.14 15.07 26.39 33 33 0.65 258.26 0 0 0.00
IV 3 31 ### 3.06 15.07 11.31 0 0 0.00 0.00 13 0.3 44.11 20.00
V 0.5 31.5 ### 0.41 15.07 1.88 33 33 0.65 18.45 0.00
276.71 161.31
= %
End Bearing Component for Sand layer = 617.55 T
Friction Bearing Component for Sand layer = 276.71 T
End Bearing Resistance for Clay Layer = 0 T
Friction Bearing Resistance for Clay Layer = 161.31 T
Total End Bearing Resistance = 617.55 T
Total Friction Bearing Resistance = 438.02 T
Total Bearing Resistance including both cohessive & granular so = 1055.57 T
Factor of safety = 2.5 (As per IS2911 Part I/Sec 2)
Safe Bearing Capacity = 422.23 T

Pile Cut Off level from GL = 2.5 m


Length of Pile below Cut-off Level Level = 29.0 m
PROJECT RAIL VIKAS NIGAM LIMITED
CALCULATIONS
DesignFOR
& Construction of Viaduct and Stations (Extension of North South Corridor) from Naupura to Dakshineswar.
Description MGC FILE NO. BH-T3 Rev.D-1
VERTICAL CAPACITY OF PILES Cal By AKD DATE 9/3/2016 SHEET
Checked By MSP DATE 9/3/2016 OF
Sec. Reference
n
I
(
Q u = A p∗( 0. 5 DγN γ + Pd N q ) + ∑ KP di tan δA si +α CA S
i =1
) (As per IS2911 Part I/Sec 2)

Length of Pile below Ground Level L = 30.5 m


Dia of Pile D = 1.2 m
Effective Unit weight of soil at Pile Tip γ = 0.840 t/m3
Bearing Capacity Factor Nq = 35.00
Bearing Capacity Factor Nγ = 37.77
Depth of Pile Cap = 0m
Area of Pile Ap = 1.1310 m2
Earth Pressure Coefficient k = 1 (As per ODC Clause - 7.17a)
Overburden Considered for a depth of = 15 times the dia of pile (As per ODC Clause - 7.17a)
Overburden Pdi = 14.3 t/m2
Overburden Pd = 14.3 t/m2
Angle of Internal Friction at toe Φ = 33.00 deg (As per GIR)
DepthOveral γsub d*γsub Pdi As Σ K x Pdi x Corrected
layer Φ δ tanδ C α α x C x As
m Depth t/m3 t/m2 t/m2 m2 tan (δ) x Asi N Value
- 1.5 1.5 ### 1.20 0.60 5.65 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 3.5 5 ### 2.80 2.60 13.19 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 1.5 6.5 ### 1.17 4.59 5.65 0 0 0.00 0.00 2.3 0.7 9.10 3.00
I 3 9.5 ### 2.34 6.34 11.31 0 0 0.00 0.00 2.3 0.7 18.21 3.00
I 3 12.5 ### 2.46 8.74 11.31 0 0 0.00 0.00 2.3 0.7 18.21 3.00
II 5.5 18 ### 4.29 12.12 20.73 31 31 0.60 150.94 0 0 0.00
II 3 21 ### 2.85 14.26 11.31 31 31 0.60 96.90 0 0 0.00
III 5.5 26.5 ### 5.23 14.26 20.73 0 0 0.00 0.00 8 0.3 49.76 21.00
IV 4 30.5 ### 3.36 14.26 15.08 33 33 0.65 139.65 0.00
387.49 95.28
= %
End Bearing Component for Sand layer = 586.00 T
Friction Bearing Component for Sand layer = 387.49 T
End Bearing Resistance for Clay Layer = 0 T
Friction Bearing Resistance for Clay Layer = 95.28 T
Total End Bearing Resistance = 586.00 T
Total Friction Bearing Resistance = 482.77 T
Total Bearing Resistance including both cohessive & granular so = 1068.77 T
Factor of safety = 2.5 (As per IS2911 Part I/Sec 2)
Safe Bearing Capacity = 427.51 T

Pile Cut Off level from GL = 2.5 m


Length of Pile below Cut-off Level Level = 28 m
PROJECT RAIL VIKAS NIGAM LIMITED
CALCULATIONS
DesignFOR
& Construction of Viaduct and Stations (Extension of North South Corridor) from Naupura to Dakshineswar.
Description MGC FILE NO. BH-T4 Rev.D-1
VERTICAL CAPACITY OF PILES Cal By AKD DATE 9/3/2016 SHEET
Checked By MSP DATE 9/3/2016 OF
Sec. Reference
n
I
(
Q u = A p∗( 0. 5 DγN γ + Pd N q ) + ∑ KP di tan δA si +α CA S
i =1
) (As per IS2911 Part I/Sec 2)

Length of Pile below Ground Level L = 30.0 m


Dia of Pile D = 1.2 m
Effective Unit weight of soil at Pile Tip γ = 0.840 t/m3
Bearing Capacity Factor Nq = 35.00
Bearing Capacity Factor Nγ = 37.77
Depth of Pile Cap = 0m
Area of Pile Ap = 1.1310 m2
Earth Pressure Coefficient k = 1 (As per ODC Clause - 7.17a)
Overburden Considered for a depth of = 15 times the dia of pile (As per ODC Clause - 7.17a)
Overburden Pdi = 14.6 t/m2
Overburden Pd = 14.6 t/m2
Angle of Internal Friction at toe Φ = 33.00 deg (As per GIR)
DepthOveral γsub d*γsub Pdi As Σ K x Pdi x Corrected
layer Φ δ tanδ C α α x C x As
m Depth t/m3 t/m2 t/m2 m2 tan (δ) x Asi N Value
- 0.75 0.75 ### 0.60 0.30 2.83 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 4.25 5 ### 3.40 2.30 16.02 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 4 9 ### 3.12 5.56 15.08 0 0 0.00 0.00 3.1 0.5 23.37 4.00
I 4.5 13.5 ### 3.74 8.99 16.96 0 0 0.00 0.00 3.1 0.5 26.30 4.00
II 4.5 18 ### 3.74 12.72 16.96 30 30 0.58 124.61 0 0 0.00
II 12 30 ### 10.08 14.59 45.24 33 33 0.65 428.63 0 0 0.00
553.24 49.67
= %
End Bearing Component for Sand layer = 599.06 T
Friction Bearing Component for Sand layer = 553.24 T
End Bearing Resistance for Clay Layer = 0T
Friction Bearing Resistance for Clay Layer = 49.67 T
Total End Bearing Resistance = 599.06 T
Total Friction Bearing Resistance = 602.91 T
Total Bearing Resistance including both cohessive & granular so = 1201.97 T
Factor of safety = 2.5 (As per IS2911 Part I/Sec 2)
Safe Bearing Capacity = 480.79 T

Pile Cut Off level from GL = 2.5 m


Length of Pile below Cut-off Level Level = 27.5 m
PROJECT RAIL VIKAS NIGAM LIMITED
CALCULATIONS
DesignFOR
& Construction of Viaduct and Stations (Extension of North South Corridor) from Naupura to Dakshineswar.
Description MGC FILE NO. BH-T5 Rev.D-1
VERTICAL CAPACITY OF PILES Cal By AKD DATE 9/3/2016 SHEET
Checked By MSP DATE 9/3/2016 OF
Sec. Reference
n
I
( i =1
)
Qu = A p∗( 0. 5 DγN γ + Pd N q ) + ∑ KP di tan δA si +α CA S (As per IS2911 Part I/Sec 2)

Length of Pile below Ground Level L = 32.0 m


Dia of Pile D = 1.2 m
Effective Unit weight of soil at Pile Tip γ = 0.830 t/m3
Bearing Capacity Factor Nq = 35.00
Bearing Capacity Factor Nγ = 37.77
Depth of Pile Cap = 0m
Area of Pile Ap = 1.1310 m2
Earth Pressure Coefficient k = 1 (As per ODC Clause - 7.17a)
Overburden Considered for a depth of = 15 times the dia of pile (As per ODC Clause - 7.17a)
Overburden Pdi = 13.1 t/m2
Overburden Pd = 13.1 t/m2
Angle of Internal Friction at toe Φ = 33.00 deg (As per GIR)
DepthOveral γsub d*γsub Pdi As Σ K x Pdi x Corrected
layer Φ δ tanδ C α α x C x As
m Depth t/m3 t/m2 t/m2 m2 tan (δ) x Asi N Value
- 2.5 2.5 ### 0.00 0.00 9.42 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 2.5 5 ### 2.05 1.03 9.42 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 3 8 ### 2.46 3.28 11.31 0 0 0.00 0.00 3.3 0.5 18.66 4.00
I 3 11 ### 2.46 5.74 11.31 0 0 0.00 0.00 3.3 0.5 18.66 4.00
II 4 15 ### 3.28 8.61 15.08 0 0 0.00 0.00 10 0.5 75.40 4.00
III 3 18 ### 2.85 11.68 11.31 0 0 0.00 0.00 10 0.3 33.93 14.00
III 3 21 ### 2.76 13.10 11.31 0 0 0.00 0.00 9 0.3 30.54 14.00
IV 11 32 ### 9.13 13.10 41.47 33 33 0.65 352.79 0.00
352.79 177.19
= %
End Bearing Component for Sand layer = 539.82 T
Friction Bearing Component for Sand layer = 352.79 T
End Bearing Resistance for Clay Layer = 0T
Friction Bearing Resistance for Clay Layer = 177.19 T
Total End Bearing Resistance = 539.82 T
Total Friction Bearing Resistance = 529.97 T
Total Bearing Resistance including both cohessive & granular so = 1069.80 T
Factor of safety = 2.5 (As per IS2911 Part I/Sec 2)
Safe Bearing Capacity = 427.92 T

Pile Cut Off level from GL = 2.5 m


Length of Pile below Cut-off Level Level = 29.5 m
PROJECT RAIL VIKAS NIGAM LIMITED
CALCULATIONS
DesignFOR
& Construction of Viaduct and Stations (Extension of North South Corridor) from Naupura to Dakshineswar.
Description MGC FILE NO. BH-T6 Rev.D-1
VERTICAL CAPACITY OF PILES Cal By AKD DATE 9/3/2016 SHEET
Checked By MSP DATE 9/3/2016 OF
Sec. Reference
n
I
(
Q u = A p∗( 0. 5 DγN γ + Pd N q ) + ∑ KP di tan δA si +α CA S
i =1
) (As per IS2911 Part I/Sec 2)

Length of Pile below Ground Level L = 30.0 m


Dia of Pile D = 1.2 m
Effective Unit weight of soil at Pile Tip γ = 0.900 t/m3
Bearing Capacity Factor Nq = 35.00
Bearing Capacity Factor Nγ = 37.77
Depth of Pile Cap = 0m
Area of Pile Ap = 1.1310 m2
Earth Pressure Coefficient k = 1 (As per ODC Clause - 7.17a)
Overburden Considered for a depth of = 15 times the dia of pile (As per ODC Clause - 7.17a)
Overburden Pdi = 15.3 t/m2
Overburden Pdi = 15.3 t/m2
Angle of Internal Friction at toe Φ = 33.00 deg (As per GIR)
DepthOveral γsub d*γsub Pdi As Σ K x Pdi x Corrected
layer Φ δ tanδ C α α x C x As
m Depth t/m3 t/m2 t/m2 m2 tan (δ) x Asi N Value
- 5 5 ### 4.10 2.05 18.85 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 1 6 ### 0.81 4.51 3.77 0 0 0.00 0.00 3.5 0.5 6.60 4.00 (As per ODC Clause - 7.17a)
II 4.5 10.5 ### 3.69 6.76 16.96 0 0 0.00 0.00 2.3 0.5 19.51 4.00
II 3 13.5 ### 2.46 9.83 11.31 0 0 0.00 0.00 2.3 0.5 13.01 4.00
II 2.5 16 ### 2.05 12.09 9.42 0 0 0.00 0.00 2.3 0.5 10.84 4.00
II 0.5 16.5 ### 0.91 13.57 1.88 0 0 0.00 0.00 6.5 0.4 4.90 11.00
II 1.5 18 ### 1.32 13.77 5.65 0 0 0.00 0.00 6.5 0.4 14.70 11.00
II 1 19 ### 0.88 15.34 3.77 0 0 0.00 0.00 2.5 0.4 3.77 11.00
III 11 30 ### 9.90 15.34 41.47 33 33 0.65 413.11 0 0 0.00
413.11 73.32
= %
End Bearing Component for Sand layer = 630.29 T
Friction Bearing Component for Sand layer = 413.11 T
End Bearing Resistance for Clay Layer = 0 T
Friction Bearing Resistance for Clay Layer = 73.32 T
Total End Bearing Resistance = 630.29 T
Total Friction Bearing Resistance = 486.44 T
Total Bearing Resistance including both cohessive & granular so = 1116.72 T (As per IS2911 Part I/Sec 2)
Factor of safety = 2.5
Safe Bearing Capacity = 446.69 T

Pile Cut Off level from GL = 2.5 m


Length of Pile below Cut-off Level Level = 27.5 m
PROJECT RAIL VIKAS NIGAM LIMITED
CALCULATIONS
DesignFOR
& Construction of Viaduct and Stations (Extension of North South Corridor) from Naupura to Dakshineswar.
Description MGC FILE NO. BH-T13 Rev.D-1
VERTICAL CAPACITY OF PILES Cal By AKD DATE 9/3/2016 SHEET
Checked By MSP DATE 9/3/2016 OF
Sec. Reference
n
I
(
Q u = A p∗( 0. 5 DγN γ + Pd N q ) + ∑ KP di tan δA si +α CA S
i =1
) (As per IS2911 Part I/Sec 2)

Length of Pile below Ground Level L = 45.0 m


Dia of Pile D = 1.2 m
Effective Unit weight of soil at Pile Tip γ = 0.820 t/m3
Bearing Capacity Factor Nq = 35.00
Bearing Capacity Factor Nγ = 37.77
Depth of Pile Cap = 0m
Area of Pile Ap = 1.1310 m2
Earth Pressure Coefficient k = 1 (As per ODC Clause - 7.17a)
Overburden Considered for a depth of = 15 times the dia of pile (As per ODC Clause - 7.17a)
Overburden Pdi = 14.7 t/m2
Overburden Pd = 14.7 t/m2
Angle of Internal Friction at toe Φ = 33.00 deg (As per GIR)
DepthOveral γsub d*γsub Pdi As Σ K x Pdi x Corrected
layer Φ δ tanδ C α α x C x As
m Depth t/m3 t/m2 t/m2 m2 tan (δ) x Asi N Value
- 3.5 3.5 ### 2.80 1.40 13.19 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 1.5 5 ### 1.22 3.41 5.65 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 1 6 ### 0.82 4.43 3.77 0 0 0.00 0.00 3.7 0.5 6.97 4.00
I 3 9 ### 2.46 6.07 11.31 0 0 0.00 0.00 3.7 0.5 20.92 4.00
I 3 12 ### 2.40 8.50 11.31 0 0 0.00 0.00 3.7 0.5 20.92 4.00
I 2 14 ### 1.60 10.50 7.54 0 0 0.00 0.00 3.7 0.5 13.95 4.00
II 4 18 ### 3.44 13.02 15.08 0 0 0.00 0.00 5.5 0.3 24.88 13.00
II 26 44 ### 25.22 14.74 98.02 0 0 0.00 0.00 12.4 0.3 364.63 13.00
II 1 45 ### 0.82 14.74 3.77 33 33 0.65 36.07 0 0 0.00
36.07 452.28
= %
End Bearing Component for Sand layer = 604.29 T
Friction Bearing Component for Sand layer = 36.07 T
End Bearing Resistance for Clay Layer = 0 T
Friction Bearing Resistance for Clay Layer = 452.28 T
Total End Bearing Resistance = 604.29 T
Total Friction Bearing Resistance = 488.35 T
Total Bearing Resistance including both cohessive & granular so = 1092.64 T
Factor of safety = 2.5 (As per IS2911 Part I/Sec 2)
Safe Bearing Capacity = 437.06 T

Pile Cut Off level from GL = 2.5 m


Length of Pile below Cut-off Level Level = 42.5 m
PROJECT RAIL VIKAS NIGAM LIMITED
CALCULATIONS
DesignFOR
& Construction of Viaduct and Stations (Extension of North South Corridor) from Naupura to Dakshineswar.
Description MGC FILE NO. BH-C1 Rev.D-1
VERTICAL CAPACITY OF PILES Cal By AKD DATE 9/3/2016 SHEET
Checked By MSP DATE 9/3/2016 OF
Sec. Reference
n
I
(
Q u = A p∗( 0. 5 DγN γ + Pd N q ) + ∑ KP di tan δA si +α CA S
i =1
) (As per IS2911 Part I/Sec 2)

Length of Pile below Ground Level L = 29.0 m


Dia of Pile D = 1.2 m
Effective Unit weight of soil at Pile Tip γ = 1.020 t/m3
Bearing Capacity Factor Nq = 35.00
Bearing Capacity Factor Nγ = 37.77
Depth of Pile Cap = 0m
Area of Pile Ap = 1.1310 m2
Earth Pressure Coefficient k = 1 (As per ODC Clause - 7.17a)
Overburden Considered for a depth of = 15 times the dia of pile (As per ODC Clause - 7.17a)
Overburden Pdi = 14.3 t/m2
Overburden Pd = 14.3 t/m2
Angle of Internal Friction at toe Φ = 33.00 deg (As per GIR)
DepthOveral γsub d*γsub Pdi As Σ K x Pdi x Corrected
layer Φ δ tanδ C α α x C x As
m Depth t/m3 t/m2 t/m2 m2 tan (δ) x Asi N Value
4.5 4.5 ### 3.81 1.90 16.96 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 0.5 5 ### 0.31 3.96 1.88 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
II 7 12 ### 4.40 6.32 26.39 0 0 0.00 0.00 2.2 0.5 29.03 5.00
IIIA 4 16 ### 3.88 10.46 15.08 0 0 0.00 0.00 9 0.4 54.29 12.00
IIIB 2 18 ### 1.89 13.35 7.54 0 0 0.00 0.00 7.5 0.4 22.62 13.00
IIIB 3 21 ### 2.96 14.29 11.31 0 0 0.00 0.00 10.5 0.4 47.50 13.00
IV 7.5 28.5 ### 7.24 14.29 28.27 33 33 0.65 262.43 0 0 0.00
IV 0.5 29 ### 0.51 14.29 1.88 33 33 0.65 17.50 0 0 0.00
279.93 153.44
End Bearing Component for Sand layer = 591.90 T
Friction Bearing Component for Sand layer = 279.93 T
End Bearing Resistance for Clay Layer = 0T
Friction Bearing Resistance for Clay Layer = 153.44 T
Total End Bearing Resistance = 591.90 T
Total Friction Bearing Resistance = 433.36 T
Total Bearing Resistance including both cohessive & granular so = 1025.26 T
Factor of safety = 2.5 (As per IS2911 Part I/Sec 2)
Safe Bearing Capacity = 410.10 T
Pile Cut Off level from GL = 2.5 m
Length of Pile below Cut-off Level Level = 26.5 m
PROJECT RAIL VIKAS NIGAM LIMITED
CALCULATIONS
DesignFOR
& Construction of Viaduct and Stations (Extension of North South Corridor) from Naupura to Dakshineswar.
Description MGC FILE NO. BH-C2 Rev. D-1
VERTICAL CAPACITY OF PILES Cal By AKD DATE 9/3/2016 SHEET
Checked By MSP DATE 9/3/2016 OF
Sec. Reference
n
I
(
Q u = A p∗( 0. 5 DγN γ + Pd N q ) + ∑ KP di tan δA si +α CA S
i =1
) (As per IS2911 Part I/Sec 2)

Length of Pile below Ground Level L = 30 m


Dia of Pile D = 1.2 m
Effective Unit weight of soil at Pile Tip γ = 0.965 t/m3
Bearing Capacity Factor Nq = 35.00
Bearing Capacity Factor Nγ = 37.77
Depth of Pile Cap = 0m
Area of Pile Ap = 1.1310 m2
Earth Pressure Coefficient k = 1 (As per ODC Clause - 7.17a)
Overburden Considered for a depth of = 15 times the dia of pile (As per ODC Clause - 7.17a)
Overburden Pdi = 14.4 t/m2
Overburden Pd = 14.4 t/m2
Angle of Internal Friction at toe Φ = 33.00 deg (As per GIR)
DepthOveral γsub d*γsub Pdi As Σ K x Pdi x Corrected
layer Φ δ tanδ C α α x C x As
m Depth t/m3 t/m2 t/m2 m2 tan (δ) x Asi N Value
- 2.5 2.5 ### 2.00 1.00 9.42 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 2.5 5 ### 2.11 3.05 9.42 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 1 6 ### 0.84 4.53 3.77 0 0 0.00 0.00 2.9 0.5 5.47 4.00
II 4.5 10.5 ### 2.93 6.41 16.96 0 0 0.00 0.00 2.2 0.5 18.66 4.00
IIIA 3 13.5 ### 2.62 9.18 11.31 0 0 0.00 0.00 6.65 0.4 30.08 11.00
IIIA 1.5 15 ### 1.47 11.23 5.65 0 0 0.00 0.00 6.65 0.4 15.04 11.00
IIIB 3 18 ### 2.42 13.17 11.31 30 30 0.58 85.97 0 0 0.00
IIIB 7.5 25.5 ### 6.04 14.37 28.27 30 30 0.58 234.64 0 0 0.00
IV 4.5 30 ### 4.34 14.37 16.96 33 33 0.65 158.35 0 0 0.00
478.96 69.25
= %
End Bearing Component for Sand layer = 593.69 T
Friction Bearing Component for Sand layer = 478.96 T
End Bearing Resistance for Clay Layer = 0 T
Friction Bearing Resistance for Clay Layer = 69.25 T
Total End Bearing Resistance = 593.69 T
Total Friction Bearing Resistance = 548.21 T
Total Bearing Resistance including both cohessive & granular so = 1141.91 T (As per IS2911 Part I/Sec 2)
Factor of safety = 2.5
Safe Bearing Capacity = 456.76 T

Pile Cut Off level from GL = 2.5 m


Length of Pile below Cut-off Level Level = 27.5 m
PROJECT RAIL VIKAS NIGAM LIMITED
CALCULATIONS
DesignFOR
& Construction of Viaduct and Stations (Extension of North South Corridor) from Naupura to Dakshineswar.
Description MGC FILE NO. BH-C3 Rev.D-1
VERTICAL CAPACITY OF PILES Cal By AKD DATE 9/3/2016 SHEET
Checked By MSP DATE 9/3/2016 OF
Sec. Reference
n
I
(
Q u = A p∗( 0. 5 DγN γ + Pd N q ) + ∑ KP di tan δA si +α CA S
i =1
) (As per IS2911 Part I/Sec 2)

Length of Pile below Ground Level L = 30.0 m


Dia of Pile D = 1.2 m
Effective Unit weight of soil at Pile Tip γ = 1.020 t/m3
Bearing Capacity Factor Nq = 35.00
Bearing Capacity Factor Nγ = 37.77
Depth of Pile Cap = 0m
Area of Pile Ap = 1.1310 m2
Earth Pressure Coefficient k = 1 (As per ODC Clause - 7.17a)
Overburden Considered for a depth of = 15 times the dia of pile (As per ODC Clause - 7.17a)
Overburden Pdi = 15.0 t/m2
Overburden Pd = 15.0 t/m2
Angle of Internal Friction at toe Φ = 33.00 deg (As per GIR)
DepthOveral γsub d*γsub Pdi As Σ K x Pdi x Corrected
layer Φ δ tanδ C α α x C x As
m Depth t/m3 t/m2 t/m2 m2 tan (δ) x Asi N Value
- 2.5 2.5 ### 2.00 1.00 9.42 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 2.5 5 ### 2.10 3.05 9.42 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 2 7 ### 1.68 4.94 7.54 0 0 0.00 0.00 2.9 0.5 10.93 4.00
II 5.5 12.5 ### 3.98 7.77 20.73 0 0 0.00 0.00 2.6 0.5 26.95 4.00
IIIA 4 16.5 ### 3.76 11.64 15.08 0 0 0.00 0.00 6.6 0.4 39.81 8.00
IIIB 1.5 18 ### 1.44 14.24 5.65 0 0 0.00 0.00 8.5 0.4 19.23 11.00
IIIB 3 21 ### 2.88 14.96 11.31 0 0 0.00 0.00 8.5 0.4 38.45 11.00
IIIB 4.5 25.5 ### 4.64 14.96 16.96 0 0 0.00 0.00 15 0.4 101.79 11.00
IV 4.5 30 ### 4.59 14.96 16.96 33 33 0.65 164.77 0 0 0.00
164.77 237.17
= %
End Bearing Component for Sand layer = 618.18 T
Friction Bearing Component for Sand layer = 164.77 T
End Bearing Resistance for Clay Layer = 0 T
Friction Bearing Resistance for Clay Layer = 237.17 T
Total End Bearing Resistance = 618.18 T
Total Friction Bearing Resistance = 401.94 T
Total Bearing Resistance including both cohessive & granular so = 1020.12 T
Factor of safety = 2.5 (As per IS2911 Part I/Sec 2)
Safe Bearing Capacity = 408.05 T

Pile Cut Off level from GL = 2.5 m


Length of Pile below Cut-off Level Level = 27.5 m
PROJECT RAIL VIKAS NIGAM LIMITED
CALCULATIONS
DesignFOR
& Construction of Viaduct and Stations (Extension of North South Corridor) from Naupura to Dakshineswar.
Description MGC FILE NO. BH-C4 Rev.D-1
VERTICAL CAPACITY OF PILES Cal By AKD DATE 9/3/2016 SHEET
Checked By MSP DATE 9/3/2016 OF
Sec. Reference
n
I
(
Q u = A p∗( 0. 5 DγN γ + Pd N q ) + ∑ KP di tan δA si +α CA S
i =1
) (As per IS2911 Part I/Sec 2)

Length of Pile below Ground Level L = 30.0 m


Dia of Pile D = 1.2 m
Effective Unit weight of soil at Pile Tip γ = 1.010 t/m3
Bearing Capacity Factor Nq = 35.00
Bearing Capacity Factor Nγ = 37.77
Depth of Pile Cap = 0m
Area of Pile Ap = 1.1310 m2
Earth Pressure Coefficient k = 1 (As per ODC Clause - 7.17a)
Overburden Considered for a depth of = 15 times the dia of pile (As per ODC Clause - 7.17a)
Overburden Pdi = 14.8 t/m2
Overburden Pd = 14.8 t/m2
Angle of Internal Friction at toe Φ = 33.00 deg (As per GIR)
DepthOveral γsub d*γsub Pdi As Σ K x Pdi x Corrected
layer Φ δ tanδ C α α x C x As
m Depth t/m3 t/m2 t/m2 m2 tan (δ) x Asi N Value
- 2.5 2.5 ### 2.00 1.00 9.42 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 2.5 5 ### 2.10 3.05 9.42 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 1 6 ### 0.84 4.52 3.77 0 0 0.00 0.00 2.9 0.7 7.65 3.00
II 7 13 ### 5.07 7.47 26.39 0 0 0.00 0.00 2.5 0.5 32.99 5.00
IIIA 3.5 16.5 ### 3.35 11.68 13.19 0 0 0.00 0.00 8 0.4 42.22 11.00
IIIB 1.5 18 ### 1.43 14.07 5.65 0 0 0.00 0.00 8 0.4 18.10 12.00
IIIB 1.5 19.5 ### 1.43 14.79 5.65 0 0 0.00 0.00 8 0.4 18.10 12.00
IIIB 1.5 21 ### 1.55 14.79 5.65 0 0 0.00 0.00 15 0.4 33.93 12.00
IV 9 30 ### 9.09 14.79 33.93 33 33 0.65 325.79 0 0 0.00
325.79 152.98
= %
End Bearing Component for Sand layer = 611.18 T
Friction Bearing Component for Sand layer = 325.79 T
End Bearing Resistance for Clay Layer = 0 T
Friction Bearing Resistance for Clay Layer = 152.98 T
Total End Bearing Resistance = 611.18 T
Total Friction Bearing Resistance = 478.78 T
Total Bearing Resistance including both cohessive & granular so = 1089.95 T
Factor of safety = 2.5 (As per IS2911 Part I/Sec 2)
Safe Bearing Capacity = 435.98 T

Pile Cut Off level from GL = 2.5 m


Length of Pile below Cut-off Level Level = 27.5 m
PROJECT RAIL VIKAS NIGAM LIMITED
CALCULATIONS
DesignFOR
& Construction of Viaduct and Stations (Extension of North South Corridor) from Naupura to Dakshineswar.
Description MGC FILE NO. BH-C12 Rev.D-1
VERTICAL CAPACITY OF PILES Cal By AKD DATE 9/3/2016 SHEET
Checked By MSP DATE 9/3/2016 OF
Sec. Reference
n
I
(
Q u = A p∗( 0. 5 DγN γ + Pd N q ) + ∑ KP di tan δA si +α CA S
i =1
) (As per IS2911 Part I/Sec 2)

Length of Pile below Ground Level L = 39.0 m


Dia of Pile D = 1.2 m
Effective Unit weight of soil at Pile Tip γ = 1.010 t/m3
Bearing Capacity Factor Nq = 35.00
Bearing Capacity Factor Nγ = 37.77
Depth of Pile Cap = 0m
Area of Pile Ap = 1.1310 m2
Earth Pressure Coefficient k = 1 (As per ODC Clause - 7.17a)
Overburden Considered for a depth of = 15 times the dia of pile (As per ODC Clause - 7.17a)
Overburden Pdi = 14.4 t/m2
Overburden Pd = 14.4 t/m2
Angle of Internal Friction at toe Φ = 33.00 deg (As per GIR)
DepthOveral γsub d*γsub Pdi As Σ K x Pdi x Corrected
layer Φ δ tanδ C α α x C x As
m Depth t/m3 t/m2 t/m2 m2 tan (δ) x Asi N Value
- 3 3 ### 2.40 1.20 11.31 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 2 5 ### 1.71 3.25 7.54 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
II 6 11 ### 5.12 6.67 22.62 0 0 0.00 0.00 3.4 0.5 38.45 4.00
IIIA 5 16 ### 3.31 10.88 18.85 0 0 0.00 0.00 2.2 0.5 20.73 4.00
IIIA 2 18 ### 1.85 13.46 7.54 0 0 0.00 0.00 5.9 0.5 22.24 4.00
IIIB 12 30 ### 11.12 14.38 45.24 0 0 0.00 0.00 5.9 0.5 133.45 4.00
IIIB 1.5 31.5 ### 1.46 14.38 5.65 0 0 0.00 0.00 9.5 0.4 21.49 10.00
IIIB 4.5 36 ### 4.64 14.38 16.96 0 0 0.00 0.00 15 0.4 101.79 10.00
IV 3 39 ### 3.03 14.38 11.31 33 33 0.65 105.64 0 0 0.00
105.64 338.16
= %
End Bearing Component for Sand layer = 595.22 T
Friction Bearing Component for Sand layer = 105.64 T
End Bearing Resistance for Clay Layer = 0 T
Friction Bearing Resistance for Clay Layer = 338.16 T
Total End Bearing Resistance = 595.22 T
Total Friction Bearing Resistance = 443.80 T
Total Bearing Resistance including both cohessive & granular so = 1039.02 T (As per IS2911 Part I/Sec 2)
Factor of safety = 2.5
Safe Bearing Capacity = 415.61 T

Pile Cut Off level from GL = 2.5 m


Length of Pile below Cut-off Level Level = 36.5 m
PROJECT RAIL VIKAS NIGAM LIMITED
CALCULATIONS
DesignFOR
& Construction of Viaduct and Stations (Extension of North South Corridor) from Naupura to Dakshineswar.
Description MGC FILE NO. BH-C13 Rev.D-1
VERTICAL CAPACITY OF PILES Cal By AKD DATE 9/3/2016 SHEET
Checked By MSP DATE 9/3/2016 OF
Sec. Reference
n
I
(
Q u = A p∗( 0. 5 DγN γ + Pd N q ) + ∑ KP di tan δA si +α CA S
i =1
) (As per IS2911 Part I/Sec 2)

Length of Pile below Ground Level L = 40.0 m


Dia of Pile D = 1.2 m
Effective Unit weight of soil at Pile Tip γ = 1.000 t/m3
Bearing Capacity Factor Nq = 35.00
Bearing Capacity Factor Nγ = 37.77
Depth of Pile Cap = 0m
Area of Pile Ap = 1.1310 m2
Earth Pressure Coefficient k = 1 (As per ODC Clause - 7.17a)
Overburden Considered for a depth of = 15 times the dia of pile (As per ODC Clause - 7.17a)
Overburden Pdi = 15.3 t/m2
Overburden Pd = 15.3 t/m2
Angle of Internal Friction at toe Φ = 33.00 deg (As per GIR)
DepthOveral γsub d*γsub Pdi As Σ K x Pdi x Corrected
layer Φ δ tanδ C α α x C x As
m Depth t/m3 t/m2 t/m2 m2 tan (δ) x Asi N Value
- 4.5 4.5 ### 3.60 1.80 16.96 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 0.5 5 ### 0.44 3.82 1.88 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 3.5 8.5 ### 3.05 5.56 13.19 0 0 0.00 0.00 4.2 0.5 27.71 6.00
I 2.5 11 ### 2.21 8.19 9.42 0 0 0.00 0.00 4.2 0.5 19.79 7.00
II 3 14 ### 2.15 10.37 11.31 0 0 0.00 0.00 2.6 0.5 14.70 5.00
IIIA 4 18 ### 3.84 13.36 15.08 0 0 0.00 0.00 7.6 0.5 57.30 6.00
IIIA 13.5 31.5 ### 12.95 15.27 50.89 0 0 0.00 0.00 7.6 0.5 193.40 6.00
IIIB 4.5 36 ### 4.34 15.27 16.96 0 0 0.00 0.00 12 0.4 81.43 9.00
IIIB 1.5 37.5 ### 1.55 15.27 5.65 0 0 0.00 0.00 12 0.4 27.14 9.00
IV 2.5 40 ### 2.50 15.27 9.42 33 33 0.65 93.48 0 0 0.00
93.48 421.48
= %
End Bearing Component for Sand layer = 630.22 T
Friction Bearing Component for Sand layer = 93.48 T
End Bearing Resistance for Clay Layer = 0 T
Friction Bearing Resistance for Clay Layer = 421.48 T
Total End Bearing Resistance = 630.22 T
Total Friction Bearing Resistance = 514.96 T
Total Bearing Resistance including both cohessive & granular so = 1145.18 T (As per IS2911 Part I/Sec 2)
Factor of safety = 2.5
Safe Bearing Capacity = 458.07 T

Pile Cut Off level from GL = 2.5 m


Length of Pile below Cut-off Level Level = 37.5 m
PROJECT RAIL VIKAS NIGAM LIMITED
CALCULATIONS
DesignFOR
& Construction of Viaduct and Stations (Extension of North South Corridor) from Naupura to Dakshineswar.
Description MGC FILE NO. BH-C14 Rev.D-1
VERTICAL CAPACITY OF PILES Cal By AKD DATE 9/3/2016 SHEET
Checked By MSP DATE 9/3/2016 OF
Sec. Reference
n
I
(
Q u = A p∗( 0. 5 DγN γ + Pd N q ) + ∑ KP di tan δA si +α CA S
i =1
) (As per IS2911 Part I/Sec 2)

Length of Pile below Ground Level L = 42.5 m


Dia of Pile D = 1.2 m
Effective Unit weight of soil at Pile Tip γ = 0.980 t/m3
Bearing Capacity Factor Nq = 35.00
Bearing Capacity Factor Nγ = 37.77
Depth of Pile Cap = 0m
Area of Pile Ap = 1.1310 m2
Earth Pressure Coefficient k = 1 (As per ODC Clause - 7.17a)
Overburden Considered for a depth of = 15 times the dia of pile (As per ODC Clause - 7.17a)
Overburden Pdi = 14.8 t/m2
Overburden Pd = 14.8 t/m2
Angle of Internal Friction at toe Φ = 33.00 deg (As per GIR)
DepthOveral γsub d*γsub Pdi As Σ K x Pdi x Corrected
layer Φ δ tanδ C α α x C x As
m Depth t/m3 t/m2 t/m2 m2 tan (δ) x Asi N Value
- 6 6 ### 4.80 2.40 22.62 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 3 9 ### 2.52 6.06 11.31 0 0 0.00 0.00 3.8 0.5 21.49 5.00 (As per ODC Clause - 7.17a)
I 3 12 ### 2.71 8.67 11.31 0 0 0.00 0.00 3.8 0.5 21.49 7.00
II 3 15 ### 2.10 11.07 11.31 0 0 0.00 0.00 2 0.7 15.83 3.00
IIIA 3 18 ### 2.63 13.44 11.31 0 0 0.00 0.00 3.8 0.5 21.49 7.00
IIIA 3.5 21.5 ### 3.07 14.75 13.19 0 0 0.00 0.00 8.5 0.5 56.08 7.00
IIIA 10.5 32 ### 9.72 14.75 39.58 0 0 0.00 0.00 8.5 0.5 168.23 7.00
IIIA 3 35 ### 2.87 14.75 11.31 0 0 0.00 0.00 8.5 0.5 48.07 7.00
IIIB 3 38 ### 2.88 14.75 11.31 0 0 0.00 0.00 12 0.4 54.29 9.00
IIIB 1.5 39.5 ### 1.55 14.75 5.65 0 0 0.00 0.00 12 0.4 27.14 9.00
IV 3 42.5 ### 2.94 14.75 11.31 33 33 0.65 108.36 0 0 0.00
108.36 434.11
= %
End Bearing Component for Sand layer = 609.14 T
Friction Bearing Component for Sand layer = 108.36 T
End Bearing Resistance for Clay Layer = 0 T
Friction Bearing Resistance for Clay Layer = 434.11 T
Total End Bearing Resistance = 609.14 T
Total Friction Bearing Resistance = 542.47 T
Total Bearing Resistance including both cohessive & granular so = 1151.61 T
Factor of safety = 2.5 (As per IS2911 Part I/Sec 2)
Safe Bearing Capacity = 460.64 T

Pile Cut Off level from GL = 2.5 m


Length of Pile below Cut-off Level Level = 40.0 m
PROJECT RAIL VIKAS NIGAM LIMITED
CALCULATIONS
Design
FOR
& Construction of Viaduct and Stations (Extension of North South Corridor) from Naupura to Dakshineswar.
Description MGC FILE NO. BH-C15 Rev.D-1
VERTICAL CAPACITY OF PILES Cal By BPH DATE 9/3/2016 SHEET
Checked By MSP DATE 9/3/2016 OF
Sec. Reference
n
I
(
Qu = A p∗( 0. 5 DγN γ + Pd N q ) + ∑ KP di tan δA si +α CA S
i =1
) (As per IS2911 Part I/Sec 2)

Length of Pile below Ground Level L = 46.5 m


Dia of Pile D = 1.2 m
Effective Unit weight of soil at Pile Tip γ = 0.980 t/m3
Bearing Capacity Factor Nq = 35.00
Bearing Capacity Factor Nγ = 37.77
Depth of Pile Cap = 0 m
Area of Pile Ap = 1.1310 m2
Earth Pressure Coefficient k = 1 (As per ODC Clause - 7.17a)
Overburden Considered for a depth of = 15 times the dia of pile (As per ODC Clause - 7.17a)
Overburden Pdi = 14.9 t/m2
Overburden Pd = 14.9 t/m2
Angle of Internal Friction at toe Φ = 33.00 deg (As per GIR)
DepthOveral γsub d*γsub Pdi As Σ K x Pdi x Corrected
layer Φ δ tanδ C α α x C x As
m Depth t/m3 t/m2 t/m2 m2 tan (δ) x Asi N Value
- 3 3 ### 2.40 1.20 11.31 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 2 5 ### 1.67 3.23 7.54 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 4 9 ### 3.33 5.73 15.08 0 0 0.00 0.00 3.8 0.5 28.65 4.00
I 6 15 ### 5.38 10.09 22.62 0 0 0.00 0.00 3.8 0.5 42.98 6.00
II 3 18 ### 2.15 13.85 11.31 0 0 0.00 0.00 2.5 0.5 14.14 5.00
II 1.5 19.5 ### 1.07 14.92 5.65 0 0 0.00 0.00 2.5 0.5 7.07 5.00
IIIA 6 25.5 ### 5.66 14.92 22.62 0 0 0.00 0.00 7.3 0.5 82.56 6.00
IIIA 13.5 39 ### 13.08 14.92 50.89 0 0 0.00 0.00 7.3 0.4 148.61 6.00
IIIB 4.5 43.5 ### 4.32 14.92 16.96 0 0 0.00 0.00 12 0.3 61.07 9.00
IIIB 1.5 45 ### 1.55 14.92 5.65 0 0 0.00 0.00 12 0.3 20.36 9.00
IV 1.5 46.5 ### 1.47 14.92 5.65 33 33 0.65 54.80 0 0 0.00
54.80 405.44
End Bearing Component for Sand layer = 615.79 T
Friction Bearing Component for Sand layer = 54.80 T
End Bearing Resistance for Clay Layer = 0T
Friction Bearing Resistance for Clay Layer = 405.44 T
Total End Bearing Resistance = 615.79 T
Total Friction Bearing Resistance = 460.23 T
Total Bearing Resistance including both cohessive & granular soi = 1076.02 T
Factor of safety = 2.5 (As per IS2911 Part I/Sec 2)
Safe Bearing Capacity = 430.41 T
Pile Cut Off level from GL = 2.5 m
Length of Pile below Cut-off Level Level = 44.0 m
PROJECT RAIL VIKAS NIGAM LIMITED
CALCULATIONS
DesignFOR
& Construction of Viaduct and Stations (Extension of North South Corridor) from Naupura to Dakshineswar.
Description MGC FILE NO. BH-C16 Rev.D-1
VERTICAL CAPACITY OF PILES Cal By BPH DATE 9/3/2016 SHEET
Checked By MSP DATE 9/3/2016 OF
Sec. Reference
n
I
(
Q u = A p∗( 0. 5 DγN γ + Pd N q ) + ∑ KP di tan δA si +α CA S
i =1
) (As per IS2911 Part I/Sec 2)

Length of Pile below Ground Level L = 47.5 m


Dia of Pile D = 1.2 m
Effective Unit weight of soil at Pile Tip γ = 0.920 t/m3
Bearing Capacity Factor Nq = 35.00
Bearing Capacity Factor Nγ = 37.77
Depth of Pile Cap = 0m
Area of Pile Ap = 1.1310 m2
Earth Pressure Coefficient k = 1 (As per ODC Clause - 7.17a)
Overburden Considered for a depth of = 15 times the dia of pile (As per ODC Clause - 7.17a)
Overburden Pdi = 14.8 t/m2
Overburden Pd = 14.8 t/m2
Angle of Internal Friction at toe Φ = 33.00 deg (As per GIR)
DepthOveral γsub d*γsub Pdi As Σ K x Pdi x Corrected
layer Φ δ tanδ C α α x C x As
m Depth t/m3 t/m2 t/m2 m2 tan (δ) x Asi N Value
- 7.5 7.5 ### 6.00 3.00 28.27 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 6 13.5 ### 5.11 8.55 22.62 0 0 0.00 0.00 5.3 0.4 47.95 7.00
I 1.5 15 ### 1.42 11.81 5.65 0 0 0.00 0.00 5.3 0.4 11.99 7.00
II 3 18 ### 2.25 13.65 11.31 0 0 0.00 0.00 2.8 0.5 15.83 4.00
II 2.5 20.5 ### 1.88 14.77 9.42 0 0 0.00 0.00 2.8 0.5 13.19 4.00
IIIA 2 22.5 ### 1.78 14.77 7.54 0 0 0.00 0.00 11.2 0.3 25.33 9.00
IIIA 12 34.5 ### 11.47 14.77 45.24 0 0 0.00 0.00 11.2 0.3 152.00 9.00
IIIA 6 40.5 ### 5.88 14.77 22.62 0 0 0.00 0.00 11.2 0.3 76.00 9.00
IIIB 6 46.5 ### 6.18 14.77 22.62 0 0 0.00 0.00 15 0.3 101.79 22.00
IV 1 47.5 ### 0.92 14.77 3.77 33 33 0.65 36.16 0 0.3 0.00
36.16 444.10
= %
End Bearing Component for Sand layer = 608.32 T
Friction Bearing Component for Sand layer = 36.16 T
End Bearing Resistance for Clay Layer = 0 T
Friction Bearing Resistance for Clay Layer = 444.10 T
Total End Bearing Resistance = 608.32 T
Total Friction Bearing Resistance = 480.26 T
Total Bearing Resistance including both cohessive & granular so = 1088.58 T
Factor of safety = 2.5 (As per IS2911 Part I/Sec 2)
Safe Bearing Capacity = 435.43 T
Pile Cut Off level from GL = 2.5 m
Length of Pile below Cut-off Level Level = 45.0 m
PROJECT RAIL VIKAS NIGAM LIMITED
CALCULATIONS
DesignFOR
& Construction of Viaduct and Stations (Extension of North South Corridor) from Naupura to Dakshineswar.
Description MGC FILE NO. BH-C17 Rev.D-1
VERTICAL CAPACITY OF PILES Cal By BPH DATE 9/3/2016 SHEET
Checked By MSP DATE 9/3/2016 OF
Sec. Reference
n
I
(
Q u = A p∗( 0. 5 DγN γ + Pd N q ) + ∑ KP di tan δA si +α CA S
i =1
) (As per IS2911 Part I/Sec 2)

Length of Pile below Ground Level L = 42.0 m


Dia of Pile D = 1.2 m
Effective Unit weight of soil at Pile Tip γ = 1.000 t/m3
Bearing Capacity Factor Nq = 35.00
Bearing Capacity Factor Nγ = 37.77
Depth of Pile Cap = 0m
Area of Pile Ap = 1.1310 m2
Earth Pressure Coefficient k = 1 (As per ODC Clause - 7.17a)
Overburden Considered for a depth of = 15 times the dia of pile (As per ODC Clause - 7.17a)
Overburden Pdi = 14.9 t/m2
Overburden Pd = 14.9 t/m2
Angle of Internal Friction at toe Φ = 33.00 deg (As per GIR)
DepthOveral γsub d*γsub Pdi As Σ K x Pdi x Corrected
layer Φ δ tanδ C α α x C x As
m Depth t/m3 t/m2 t/m2 m2 tan (δ) x Asi N Value
- 4.5 4.5 ### 3.60 1.80 16.96 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 0.5 5 ### 0.41 3.81 1.88 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 5.5 10.5 ### 4.52 6.27 20.73 0 0 0.00 0.00 3.6 0.5 37.32 4.00
I 4.5 15 ### 4.06 10.56 16.96 0 0 0.00 0.00 3.6 0.5 30.54 4.00
II 3 18 ### 2.29 13.73 11.31 0 0 0.00 0.00 2.8 0.5 15.83 4.00
IIIA 9 27 ### 8.43 14.88 33.93 0 0 0.00 0.00 7.6 0.4 103.14 7.00
IIIA 6 33 ### 5.84 14.88 22.62 0 0 0.00 0.00 7.6 0.4 68.76 7.00
IIIB 7.5 40.5 ### 7.58 14.88 28.27 0 0 0.00 0.00 12 0.3 101.79 9.00
IV 1.5 42 ### 1.50 14.88 5.65 33 33 0.65 54.63 0 0 0.00
54.63 357.39
= %
End Bearing Component for Sand layer = 614.46 T
Friction Bearing Component for Sand layer = 54.63 T
End Bearing Resistance for Clay Layer = 0 T
Friction Bearing Resistance for Clay Layer = 357.39 T
Total End Bearing Resistance = 614.46 T
Total Friction Bearing Resistance = 412.02 T
Total Bearing Resistance including both cohessive & granular so = 1026.48 T
Factor of safety = 2.5
Safe Bearing Capacity = 410.59 T
Pile Cut Off level from GL = 2.5 m
Length of Pile below Cut-off Level Level = 39.5 m
(As per IS2911 Part I/Sec 2)
PROJECT RAIL VIKAS NIGAM LIMITED
CALCULATIONS
DesignFOR
& Construction of Viaduct and Stations (Extension of North South Corridor) from Naupura to Dakshineswar.
Description MGC FILE NO. BH-C18 Rev.D-1
VERTICAL CAPACITY OF PILES Cal By BPH DATE 9/3/2016 SHEET
Checked By MSP DATE 9/3/2016 OF
Sec. Reference
n
I
(
Q u = A p∗( 0. 5 DγN γ + Pd N q ) + ∑ KP di tan δA si +α CA S
i =1
) (As per IS2911 Part I/Sec 2)

Length of Pile below Ground Level L = 33.5 m


Dia of Pile D = 1.2 m
Effective Unit weight of soil at Pile Tip γ = 0.900 t/m3
Bearing Capacity Factor Nq = 32.00
Bearing Capacity Factor Nγ = 35.22
Depth of Pile Cap = 0m
Area of Pile Ap = 1.1310 m2
Earth Pressure Coefficient k = 1 (As per ODC Clause - 7.17a)
Overburden Considered for a depth of = 15 times the dia of pile (As per ODC Clause - 7.17a)
Overburden Pdi = 15.1 t/m2
Overburden Pd = 15.1 t/m2
Angle of Internal Friction at toe Φ = 32.50 deg (As per GIR)
DepthOveral γsub d*γsub Pdi As Σ K x Pdi x Corrected
layer Φ δ tanδ C α α x C x As
m Depth t/m3 t/m2 t/m2 m2 tan (δ) x Asi N Value
- 3 3 ### 2.40 1.20 11.31 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 2 5 ### 1.68 3.24 7.54 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 4 9 ### 3.36 5.76 15.08 0 0 0.00 0.00 4.4 0.5 33.18 6.00
I 3 12 ### 2.77 8.82 11.31 0 0 0.00 0.00 4.4 0.5 24.88 6.00
II 4 16 ### 3.06 11.73 15.08 0 0 0.00 0.00 2.9 0.5 21.87 4.00
IIIA 2 18 ### 1.82 14.18 7.54 0 0 0.00 0.00 7 0.4 21.11 8.00
IIIA 1 19 ### 0.91 15.09 3.77 0 0 0.00 0.00 7 0.4 10.56 8.00
IIIA 2 21 ### 1.92 15.09 7.54 0 0 0.00 0.00 7 0.4 21.11 8.00
IIIB 7.5 28.5 ### 7.45 15.09 28.27 0 0 0.00 0.00 11.5 0.4 130.06 10.00
IV 5 33.5 ### 4.50 15.09 18.85 32.5 32.5 0.64 181.16 0 0 0.00
181.16 262.76
= %
End Bearing Component for Sand layer = 567.49 T
Friction Bearing Component for Sand layer = 181.16 T
End Bearing Resistance for Clay Layer = 0 T
Friction Bearing Resistance for Clay Layer = 262.76 T
Total End Bearing Resistance = 567.49 T
Total Friction Bearing Resistance = 443.92 T
Total Bearing Resistance including both cohessive & granular so = 1011.41 T
Factor of safety = 2.5
Safe Bearing Capacity = 404.56 T (As per IS2911 Part I/Sec 2)
Pile Cut Off level from GL = 2.5 m
Length of Pile below Cut-off Level Level = 31.0 m
Project #REF!

Calculations Descritpion NEI File #REF!


Cal. By BPH Date #REF! Sheet No.
#REF!
Checked By ### Date #REF!
Sec. Reference

0.75 BH-C1

Fill Materials
2.50

Firm grey silty clay with brown spots

6.00

Soft/firm grey silty clay with traces of


semi-decomposed / decomposed wood

10.50

Firm to very stiff grey to bluish grey silty


clay with traces of yellow / brown spots

15.00

Medium dense greyish yellow clayey


sandy silt

25.50
Pile
Toe Level Medium dense / dense yellowish grey
26.50m silty fine sand with occasional traces of
kankars.
33.00
Project #REF!

Calculations Descritpion NEI File #REF!


Cal. By BPH Date #REF! Sheet No.
#REF!
Checked By ### Date #REF!
Sec. Reference
PROJECT RAIL VIKAS NIGAM LIMITED
CALCULATIONS
DesignFOR
& Construction of Viaduct and Stations (Extension of North South Corridor) from Naupura to Dakshineswar.
Description MGC FILE NO. BH-C19 Rev.D-1
VERTICAL CAPACITY OF PILES Cal By BPH DATE 9/3/2016 SHEET
Checked By MSP DATE 9/3/2016 OF
Sec. Reference
n
I
(
Q u = A p∗( 0. 5 DγN γ + Pd N q ) + ∑ KP di tan δA si +α CA S
i =1
) (As per IS2911 Part I/Sec 2)

Length of Pile below Ground Level L = 30.0 m


Dia of Pile D = 1.2 m
Effective Unit weight of soil at Pile Tip γ = 1.000 t/m3
Bearing Capacity Factor Nq = 35.00
Bearing Capacity Factor Nγ = 37.77
Depth of Pile Cap = 0m
Area of Pile Ap = 1.1310 m2
Earth Pressure Coefficient k = 1 (As per ODC Clause - 7.17a)
Overburden Considered for a depth of = 15 times the dia of pile (As per ODC Clause - 7.17a)
Overburden Pdi = 14.5 t/m2
Overburden Pd = 14.5 t/m2
Angle of Internal Friction at toe Φ = 33.00 deg (As per GIR)
DepthOveral γsub d*γsub Pdi As Σ K x Pdi x Corrected
layer Φ δ tanδ C α α x C x As
m Depth t/m3 t/m2 t/m2 m2 tan (δ) x Asi N Value
- 3 3 ### 2.40 1.20 11.31 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 2 5 ### 1.70 3.25 7.54 0 0 0.00 0.00 0 0 0.00 (As per ODC Clause - 7.17a)
I 2.5 7.5 ### 2.13 5.17 9.42 0 0 0.00 0.00 2.6 0.7 17.15 4.00
II 4.5 12 ### 2.70 7.58 16.96 0 0 0.00 0.00 2.4 0.7 28.50 4.00
IIIA 4 16 ### 3.64 10.75 15.08 0 0 0.00 0.00 5.1 0.5 38.45 6.00
IIIB 2 18 ### 1.91 13.52 7.54 0 0 0.00 0.00 8.3 0.4 25.03 10.00
IIIB 1 19 ### 0.95 14.47 3.77 0 0 0.00 0.00 8.3 0.4 12.52 10.00
IV 1 20 ### 0.93 14.47 3.77 31 31 0.60 32.78 0 0 0.00
IV 4 24 ### 3.80 14.47 15.08 33 33 0.65 141.72 0 0 0.00
IV 6 30 ### 6.00 14.47 22.62 33 33 0.65 212.58 0 0 0.00
387.07 121.66
= %
End Bearing Component for Sand layer = 598.47 T
Friction Bearing Component for Sand layer = 387.07 T
End Bearing Resistance for Clay Layer = 0 T
Friction Bearing Resistance for Clay Layer = 121.66 T
Total End Bearing Resistance = 598.47 T
Total Friction Bearing Resistance = 508.73 T
Total Bearing Resistance including both cohessive & granular so = 1107.20 T
Factor of safety = 2.5
Safe Bearing Capacity = 442.88 T (As per IS2911 Part I/Sec 2)
Pile Cut Off level from GL = 2.5 m
Length of Pile below Cut-off Level Level = 27.5 m
PROJECT RAIL VIKAS NIGAM LIMITED
CALCULATIONS
DesignFOR
& Construction of Viaduct and Stations (Extension of North South Corridor) from Naupura to Dakshineswar.
Description MGC FILE NO.
LATERAL CAPACITY OF PILES Cal By AKD DATE 9/3/2016 SHEET
Checked By MSP DATE 9/3/2016 OF
Sec. Reference

II Grade of Concrete of Pile fck = 35 N/mm2


Grade of Steel of Pile fy = 500 N/mm2
Dia of Pile d = 1.2 m
Young's Modulus of Pile Material E = 295804.0 kg/cm2
Moment of Inertia of Pile Cross Section I = 10178760 cm4
UNCONFINED COMPRESSIVE STRENGTH = 0.61
K2 = 28.6 kg/cm2 The K2 value has been considered from table
(From Table-2 of
Appendix C of IS 2911 Part 1 Sec 2 1979. IS:2911 (Part-1/Sec-2))
Depth of Fixity The code is silent for K2 value at UCS = 0.4
For Piles Embedded in Dense Sand

Free Length of Pile in Soil


R=

EI
4
K2
R

L1
=

=
569.72 cm

0 cm
hence linear interpretation has been done

L1 = 0.00
R
For Free Head Piles Lf = 1.6 From Fig. 2 of
R Appendix-C of IS:2911
(Part-1 / Sec-2)
Hence, Length of Fixity for a free head pile Lf = 911.56 cm

For Fixed Head Piles Lf = 1.95


R
Hence, Length of Fixity for a fixed head pile Lf = 1110.96 cm

Pile Head Deflection/Lateral Capacity of Pile


Lateral Capacity of Pile (load in kg reqd for 0.5cm deflect Y = 0.5 cm
3
Q ( L1 + L f )
For a free head pile Y= Q (free head) = 5.96 T
3 EI
For a fixed head pile Q ( L1 + Lf )3 Q = ### T
Y= (fixed head)

12 EI
ANNEXURE - 1
SOIL REPORT -
BORE HOLE DAT
ANNEXURE - 4
TEST PILE DESIGN
ANNEXURE - 2
GEOTECH PROFILE
OF BORELOGS
ANNEXURE - 5
GA & RC DRAWING OF TEST PILE
CAPACITY CALCULATIONS
ANNEXURE - 3
TYPICAL LOAD ON PILE CALCULATION

You might also like