Audit - Project
Construction of 3 Projects in Al-Ain Zoo- Package 3
Details
Non-compliance with Musanada HSE Requirements for OHS Inspection by Consultant & Contractor are not processed adequately &
sufficiently to be Frequent and to be including appropriate records of Inspection observations and close-out reports. Major NCR
Root Cause
Target Date Owner Closed Date Closed By
2/8/2021 0:00 Eng. Basim
Details
Non-compliance with Musanada HSE Requirements for OHS Inspection by Consultant & Contractor are not processed adequately &
sufficiently to be Frequent and to be including appropriate records of Inspection observations and close-out reports. Major NCR
Actions
Number Owner Target Date Completed Date
Details Response
Corrective Action
Target Date Owner Closed Date Closed By
2/8/2021 12:00 Eng. Basim
Details
Musanada contractual HSE Requirement
Actions
Number Owner Target Date Completed Date
Details Response
Approval
Target Date Owner Closed Date Closed By
2/8/2021 12:00 Eng. Basim
Details
By approving the Process Owner is confirming the suitability of the corrective action and verifying its implementation.
Actions
Number Owner Target Date Completed Date
Details Response
Follow Up
Target Date Owner Closed Date Closed By
6/8/2021 0:00 Omer El Madih
Details
Actions
Number Owner Target Date Completed Date
Details Response
Page 1 of 1
Details
Number Status NC/CA Owner Raised Date
NCR - 02 Open Eng. Basim 14/7/2021
Audit - Project
Construction of 3 Projects in Al-Ain Zoo- Package 3
Details
Non-compliance with Musanada Procedures for Consultant HSE Plan Approval, last approval obtained by Consultant on Jun 2019, as
is required to be submitted to Musanada every three-month as minimum to get Musanada Approval. Major NCR
Root Cause
Target Date Owner Closed Date Closed By
2/8/2021 0:00 Eng. Basim
Details
Non-compliance with Musanada Procedures for Consultant HSE Plan Approval, last approval obtained by Consultant on Jun 2019, as
is required to be submitted to Musanada every three-month as minimum to get Musanada Approval. Major NCR
Actions
Number Owner Target Date Completed Date
Details Response
Corrective Action
Target Date Owner Closed Date Closed By
2/8/2021 12:00 Eng. Basim
Details
Musanada contractual HSE Requirement
Actions
Number Owner Target Date Completed Date
Details Response
Approval
Target Date Owner Closed Date Closed By
2/8/2021 12:00 Eng. Basim
Details
By approving the Process Owner is confirming the suitability of the corrective action and verifying its implementation.
Actions
Number Owner Target Date Completed Date
Details Response
Follow Up
Target Date Owner Closed Date Closed By
6/8/2021 0:00 Omer El Madih
Details
Actions
Number Owner Target Date Completed Date
Details Response
Page 1 of 1
Details
Number Status NC/CA Owner Raised Date
NCR - 03 Open Eng. Basim 14/7/2021
Audit - Project
Construction of 3 Projects in Al-Ain Zoo- Package 3
Details
Non-compliance with Musanada Procedures for Contractor HSE Plan Approval, last approval obtained by Contractor on May 2019, as
is required to be submitted to Musanada every three-month as minimum to get Musanada Approval. Major NCR.
Root Cause
Target Date Owner Closed Date Closed By
2/8/2021 0:00 Eng. Basim
Details
Non-compliance with Musanada Procedures for Contractor HSE Plan Approval, last approval obtained by Contractor on May 2019, as
is required to be submitted to Musanada every three-month as minimum to get Musanada Approval. Major NCR.
Actions
Number Owner Target Date Completed Date
Details Response
Corrective Action
Target Date Owner Closed Date Closed By
2/8/2021 12:00 Eng. Basim
Details
Musanada contractual HSE Requirement
Actions
Number Owner Target Date Completed Date
Details Response
Approval
Target Date Owner Closed Date Closed By
2/8/2021 12:00 Eng. Basim
Details
By approving the Process Owner is confirming the suitability of the corrective action and verifying its implementation.
Actions
Number Owner Target Date Completed Date
Details Response
Follow Up
Target Date Owner Closed Date Closed By
6/8/2021 0:00 Omer El Madih
Details
Actions
Number Owner Target Date Completed Date
Details Response
Page 1 of 1
Details
Number Status NC/CA Owner Raised Date
NCR - 04 Open Eng. Basim 14/7/2021
Audit - Project
Construction of 3 Projects in Al-Ain Zoo- Package 3
Details
Non-compliance with OSHAD requirement for SRA registration, Consultant is not complying with OSHAD requirements. Major NCR.
Root Cause
Target Date Owner Closed Date Closed By
2/8/2021 0:00 Eng. Basim
Details
Non-compliance with OSHAD requirement for SRA registration, Consultant is not complying with OSHAD requirements. Major NCR.
Actions
Number Owner Target Date Completed Date
Details Response
Corrective Action
Target Date Owner Closed Date Closed By
2/8/2021 12:00 Eng. Basim
Details
Musanada contractual HSE Requirement
Actions
Number Owner Target Date Completed Date
Details Response
Approval
Target Date Owner Closed Date Closed By
2/8/2021 12:00 Eng. Basim
Details
By approving the Process Owner is confirming the suitability of the corrective action and verifying its implementation.
Actions
Number Owner Target Date Completed Date
Details Response
Follow Up
Target Date Owner Closed Date Closed By
6/8/2021 0:00 Omer El Madih
Details
Actions
Number Owner Target Date Completed Date
Details Response
Page 1 of 1