Professional Documents
Culture Documents
Item
Description Quantity Unit Unit Cost Amount
No.
I Earthworks
1 Demolition
2 Excavation cu.m
3 Staking
4 Backfilling cu.m
5 Gravel Bedding
V Roofing
VI Carpentry Works
VII Doors And Windows
1 Doors
D1 Panel Door 1.00 set/s 3200 3200.00
D2 Panel Door 5.00 set/s 3800 19000.00
D3 Panel Door 2.00 set/s 1200 2400.00
2 Windows
W1 Sliding Window 4.00 set/s 11000 44000.00
W2 Fixed Window 6.00 set/s 1200 7200.00
W3 Sliding Window 6.00 set/s 7800 46800.00
W4 Awning Window 2.00 set/s 700 1400.00
Sub-Total Material Cost 124000.00
Labor Cost 37200.00
OCM 16120.00
TOTAL-VII 177320.00
Item
Description Quantity Unit Unit Cost Amount
No.
I Earthworks
1 Demolition
2 Excavation 64.01 cu.m 91.65 5866.48
3 Staking
4 Backfilling 119.046875 cu.m 791.99 94283.72
Sub-Total I 100150.19
II Structural Concrete Works
1 Footing 4.75 cu.m 9464.40 44955.90
2 Wall Footing 3.11 cu.m 9546.32 29734.40
3 Column
4 Stairs
Sub-Total II 74690.30
III Formwoks and Scaffolding
IV Masonry Works
1 Exterior Wall 339.87 sq.m 505.28 171728.37
2 Interior Wall 145.61 sq.m 160.43 23360.26
Sub-Total IV 195088.63
V Roofing Works
VI Carpentry Works
1 Ceiling 65.00 sq.m 459.99 29899.41
Sub-Total VI 29899.41
VII Doors And Windows
1 Doors 8 SETS 4573.80 36590.4
2 Windows 18 SETS 7768.44 139832
Sub-Total VII 176422.4
VIII Metal Works
Stair
IX Plumbing Works
X Electrical Works
XI Finishing
1 Plastering cu.m
2 Tile Works sq.m
3 Paint Works
Sub-Total XI
XII General Works
DETAILED UNIT PRICE ANALYSIS (DUPA)
LABOR COST
Item No. of No. of
Description Unit Cost Amount
No. Workers Hours
1 Engineer 1 3 125 375
2 Foreman 1 3 87.5 262.5
3 Laborer 1 3 43.5 130.5
4 H.E.O 1 3 81.25 243.75
Sub-Total 1011.75
EQUIPMENT COST
Item Description No. of No. of Unit Cost Amount
No. Equipment Hours
Back Hoe 1 3 1250 3750
Sub-Total 3750
MATERIAL COST
Item Description Quantity Unit Unit Cost Amount
No.
- - - - - -
Sub-Total 4761.75
LABOR COST
Item Description No. of No. of Unit Cost Amount
No. Workers Hours
Sub-Total 8503
EQUIPMENT COST
Item Description No. of No. of Unit Cost Amount
No. Equipment Hours
Sub-Total 0
MATERIAL COST
Item Description Quantity Unit Unit Cost Amount
No.
1 Common Soil 119.05 cu.m 250 29762.5
Sub-Total 29762.50
Sub-Total 38265.50
TOTAL DIRECT COST 76531.00
INDIRECT COST (OCM + CP) 7653.10
VAT 10102.09
GRAND TOTAL 94286.19
UNIT COST 791.99
LABOR COST
Item Description No. of No. of Unit Cost Amount
No. Workers Hours
1 Engineer 1.00 24.00 125.00 3000.00
2 Foreman 1.00 24.00 87.50 2100.00
3 Laborer 3.00 24.00 43.75 3150.00
4 Mason 1.00 24.00 62.50 1500.00
Sub-Total 9750.00
EQUIPMENT COST
Item No. of No. of
Description Unit Cost Amount
No. Equipment Hours
1 Bagger Concrete Mixer 1.00 16.00 18.75 300.00
Sub-Total 300.00
MATERIAL COST
Item
Description Quantity Unit Unit Cost Amount
No.
1 Portland Cement 43.00 Bag 210.00 9030.00
2 Sand 2.38 cu.m 500.00 1187.50
3 Gravel 9.50 cu.m 530.00 5035.00
4 12mm dia. Deformed Bar 244.72 kg 44.00 10767.68
5 GI Wire #16 4.00 kg 105.00 420.00
Sub-Total 26440.18
LABOR COST
Item Description No. of No. of Unit Cost Amount
No. Workers Hours
1 Engineer 1.00 16.00 125.00 2000.00
2 Foreman 1.00 16.00 87.50 1400.00
3 Laborer 4.00 16.00 43.75 2800.00
4 Mason 1.00 16.00 62.50 1000.00
Sub-Total 7200.00
EQUIPMENT COST
Item No. of No. of
Description Unit Cost Amount
No. Equipment Hours
-- -- -- -- -- --
MATERIAL COST
Item Description Quantity Unit Unit Cost Amount
No.
1 Portland Cement 27.00 Bag 210.00 5670.00
2 Sand 1.56 cu.m 500.00 778.69
3 Gravel 6.23 cu.m 530.00 3301.64
4 10mm dia. Deformed Bar 153.74 kg 44.00 6764.74
5 GI Wire #16 4.00 kg 105.00 420.00
Sub-Total 16935.06
LABOR COST
Item Description No. of No. of Unit Cost Amount
No. Workers Hours
1 Engineer 1.00 88.00 125.00 11000.00
2 Foreman 1.00 88.00 87.50 7700.00
3 Laborer 4.00 88.00 43.75 15400.00
4 Mason 4.00 88.00 62.50 22000.00
Sub-Total 56100.00
EQUIPMENT COST
Item No. of No. of
Description Unit Cost Amount
No. Equipment Hours
-- -- -- -- -- --
MATERIAL COST
Item
Description Quantity Unit Unit Cost Amount
No.
1 CHB(6") 4,249 pcs 17.00 72233.00
2 Portland Cement 179.00 Bag 210.00 37590.00
3 Sand 19.89 cu.m 500.00 9944.44
4 10mm dia. Deformed Bar 786.37 kg 44.00 34600.47
5 GI Wire #16 11.00 kg 105.00 1155.00
Sub-Total 83289.91
LABOR COST
Item Description No. of No. of Unit Cost Amount
No. Workers Hours
1 Engineer 1.00 8.00 125.00 1000.00
2 Foreman 1.00 8.00 87.50 700.00
3 Laborer 1.00 8.00 43.75 350.00
4 Mason 1.00 8.00 62.50 500.00
Sub-Total 2550.00
EQUIPMENT COST
Item Description No. of No. of Unit Cost Amount
No. Equipment Hours
-- -- -- -- -- --
MATERIAL COST
Item
Description Quantity Unit Unit Cost Amount
No.
1 CHB(6") 92 pcs 17.00 1564.00
2 Portland Cement 4.00 Bag 210.00 840.00
3 Sand 0.44 cu.m 500.00 222.22
4 10mm dia. Deformed Bar 336.91 kg 44.00 14824.03
5 GI Wire #16 5.00 kg 105.00 525.00
Sub-Total 16411.25
ITEM NUMBER: VI
ITEM DESCRIPTION: Carpentry Works - Ceiling
UNIT: sq.m
QUANTTITY: 65.00
LABOR COST
Item No. of No. of
Description Unit Cost Amount
No. Workers Hours
1 Engineer 1.00 16.00 125.00 2000.00
2 Foreman 1.00 16.00 87.50 1400.00
3 Laborer 3.00 16.00 43.75 2100.00
4 Carpenter 3.00 16.00 62.50 3000.00
Sub-Total 8500.00
EQUIPMENT COST
Item Description No. of No. of Unit Cost Amount
No. Equipment Hours
-- -- -- -- -- --
MATERIAL COST
Item
Description Quantity Unit Unit Cost Amount
No.
1 Marine Plywood 1/4" 23 pcs 450.00 10350.00
2 Metal Furring 33.00 m 143.00 4719.00
3 Rivet 2.00 box 350.00 700.00
Sub-Total 15769.00
LABOR COST
Item Description No. of No. of Unit Cost Amount
No. Workers Hours
1 Engineer 1 8 125 1000
Foreman 1 8 87.5 700
Carpenter 2 8 62.5 1000
Laborer 4 8 43.75 1400
Sub-Total 4100
EQUIPMENT COST
Item No. of No. of
Description Unit Cost Amount
No. Equipment Hours
Light Equipment 2 8 62.5 1000
Sub-Total 1000
MATERIAL COST
Item
Description Quantity Unit Unit Cost Amount
No.
1 D1 Panel Door 1.00 set/s 3200 3200.00
2 D2 Panel Door 5.00 set/s 3800 19000.00
3 D3 Panel Door 2.00 set/s 1200 2400.00
Sub-Total 24600.00
LABOR COST
Item No. of No. of
Description Unit Cost Amount
No. Workers Hours
1 Engineer 1 8 125 1000
Foreman 1 8 87.5 700
Carpenter 2 8 62.5 1000
Laborer 4 8 43.75 1400
Sub-Total 4100
EQUIPMENT COST
Item No. of No. of
Description Unit Cost Amount
No. Equipment Hours
Light Equipment 2 8 12.5 200
Sub-Total 200
MATERIAL COST
Item
Description Quantity Unit Unit Cost Amount
No.
W1: Analok Type Windows
1 4.00 set/s 10000 40000.00
(Sliding)
LABOR COST
Item Description No. of No. of Unit Cost Amount
No. Workers Hours
1 Engineer 1.00 16.00 125.00 2000.00
2 Foreman 1.00 16.00 87.50 1400.00
3 Laborer 4.00 16.00 43.75 2800.00
4 Mason 1.00 16.00 62.50 1000.00
Sub-Total 7200.00
EQUIPMENT COST
Item No. of No. of
Description Unit Cost Amount
No. Equipment Hours
-- -- -- -- -- --
MATERIAL COST
Item
Description Quantity Unit Unit Cost Amount
No.
1 Portland Cement 27.00 Bag 210.00 5670.00
2 Sand 0.00 cu.m 500.00 0.00
3 Gravel 0.00 cu.m 530.00 0.00
4 10mm dia. Deformed Bar 0.00 kg 44.00 0.00
5 GI Wire #16 4.00 kg 105.00 420.00
Sub-Total 6090.00
LABOR COST
Item No. of No. of
Description Unit Cost Amount
No. Workers Hours
1 Engineer 1.00 125.00 0.00
2 Foreman 1.00 87.50 0.00
3 Laborer 1.00 43.75 0.00
4 Mason 1.00 62.50 0.00
Sub-Total 0.00
EQUIPMENT COST
Item No. of No. of
Description Unit Cost Amount
No. Equipment Hours
-- -- -- -- -- --
MATERIAL COST
Item
Description Quantity Unit Unit Cost Amount
No.
1 pcs 17.00 0.00
2 Bag 210.00 0.00
3 cu.m 500.00 0.00
4 kg 44.00 0.00
5 kg 105.00 0.00
Sub-Total 0.00
TOTAL 39.51
TOTAL AREA
A= 1.5x3.5
A= 5.25
Depth= 0.55 Volume of excavation to be backfill
Depth= 0.4
A4(service)= 1.624
Naturtal
Grade to F.F.L
Depth= 0.4
A4(service)= 1.624
Volume 4.75
Deformed Bar
12 pcs/footing
.85m >> 1.2m
228 5
46 pcs
GI Wire
760
3.8
Second Floor
Interiior Exterior W1 3 2.16
3.5 10.00 W2 1 2.52
3.50 6.50 W3 1 1.44
3.50 10.00 W4 1 0.36
2.50 6.50
4.50 1.00 D2 1 1.68
Length 17.50 34.00
Height 5.92 5.92
Area 103.60 201.28
Reinforcement
Horizontal Bars Vertical Bars
730.72 543.79
1274.51
212.42 pcs
GI Wire
10.2228647625
First Floor
Interiior Exterior
3.5 6.5
3 10
2 10
2.03 3.5
1.5 5.5
1.5 3 D2 2 1.68
D3 1 1.26
Second Floor
Interiior Exterior
3.5 10
3.5 6.5
3.5 10
2.5 6.5
4.5 1 D2 3 1.68
D3 1 1.26
Length 17.5 34
Height 5.92 5.92
Area 103.6 201.28
Reinforcement
Horizontal Bars Vertical Bars
313.0658 232.9792
546.045
91.0075 pcs
Area
65
Labor Capacity
1.46 sq.m/hr
4.38
14.8401826484
Rivet = 100pcs/box
195 pcs
Marine Plywood
2.88 Sq.m/ board
22.57
First Floor
Area
floor 10.5
H
4.48
2.03
1.5
3
3..5
11.01
cavation to be backfill
Correction
Vol= 95.2375x25%
Compation= 23.809375
cu.m
8 = 1 day
days
4 = 4 laborers
days for 4
laborers
4 = 4 laborers
days for 4
laborers
2.16
5.04
7.2
0.36
0
1.89
1.68
18.33
6.48
2.52
1.44
0.36
1.68
12.48
3.36
1.26
4.62
5.04
1.26
6.3