Professional Documents
Culture Documents
Project Report
Demo Site
9 0
In Progress Late
5 0
Completed Not Started
14 0 0
Tasks Updated Issues Created Attendance Logs
ALL UPDATES
11 Aug, 2021
Budgeting
Progress Total Workers
Task Name Remarks
Total Today's Work Skilled Unskilled Total
Budgeting
100% 100% -- -- -- -- --
Start: 10 Aug | End: 20 Aug
Painting
Progress Total Workers
Task Name Remarks
Total Today's Work Skilled Unskilled Total
Electrical
Progress Total Workers
Task Name Remarks
Total Today's Work Skilled Unskilled Total
Site Surveying
100% 100% -- -- -- 6 --
Start: 01 Aug | End: 10 Aug
Ceiling
Progress Total Workers
Task Name Remarks
Total Today's Work Skilled Unskilled Total
Roof Installation
Progress Total Workers
Task Name Remarks
Total Today's Work Skilled Unskilled Total
Design
Progress Total Workers
Task Name Remarks
Total Today's Work Skilled Unskilled Total
Plumbing
Progress Total Workers
Task Name Remarks
Total Today's Work Skilled Unskilled Total
Landscaping
Task Name Progress Total Workers Remarks
Work
Total Today's Skilled Unskilled Total
4th Floor M Bedroom Plastering Work - 27% 4th Floor M Bedroom Plastering Work - 28%
5th floor corridor painting - 33% Slab Electrical Work ( Piping & Conducting) -
38%
Slab Electrical Work ( Piping & Conducting) - c block ground-floor flooring pcc - 20%
32%
Column RCC work above 8th slab - 37% Column RCC work above 8th slab - 63%
Site Surveying - 36% Site Surveying - 42%
Roof Steel Binding And Concrete - 40% Temple design for 1st floor in kitchen - 100%
Final deep Cleaning - 10% Tower-B of 2nd floor internal plumbing work -
68%
Tower-B of 2nd floor internal plumbing work - Excavation For landscape - 15%
32%
Window sill and pelmet - 45% Window sill and pelmet - 45%