CONDITION REPORT
From Ambagahayaya Junction to 8
mile post Mahayaya Road
(PRDA-5.860Km)
Road No. 34
(Chainage 0+000 to 05+860km)
1
1.1 Introduction
This condition Report has been prepared for road no 34 From Ambagaha
yaya to 8 mile post to Via Mahayaya Road. The purpose of this Report is to
understand the actual road conditions including all the existing structures
and all the designs will be finalized based on this report.
2
This road has macadam area, concrete area and gravel area.
3
CHAINAGE 0+120
1. 600mm Dia. Hume pipe 1. Head walls and parapet 1. Existing head wall demolishes
culvert walls both sides are and constructs new head wall
damaged and parapet wall.
LHS RHS
CHAINAGE 1+361
1. 600mm Dia. Hume pipe 1. Culvert is good condition. 1. Lead way should be
culvert prepared.
4
CHAINAGE 2+500
LHS
RHS
LHS
RHS
1. 900mm Dia. Four Hume pipe 1. Function of culvert is ok 1. Lead way should be prepared.
culvert
5
CHAINAGE 2+730
RHS
OUTLET
LHS INLET
CHAINAGE 3+340
CHAINAGE 3+578
6
DETAIL OF PHOTO ACTUAL SITUATION PROPOSALS
CHAINAGE 3+710
7
LHS RHS
CHAINAGE 3+770
8
CHAINAGE 3+920
LHS RHS
CHAINAGE 4+738
LHS RHS
1 .300 mm dia. Hume pipe 1.Head walls and parapet 1.Existing head wall
culvert. walls both sides are demolishes and constructs
damaged new head wall and parapet
wall
CHAINAGE 5+410
9
LHS RHS
1 .600 mm dia. Hume pipe 1.Head walls and parapet 1.Existing head wall
culvert. walls both sides are demolishes and constructs
damaged. Culvert was new head wall and parapet
silted. wall. Culvert should be
cleaned
CHAINAGE 0+020
RHS
10
DETAIL OF PHOTO ACTUAL SITUATION PROPOSALS
1.There is a light post at the 1.The light post is very 1. Light post need to be
right hand side of the road close to the road. off set replaced.
2.5m
CHAINAGE 0+063
RHS
1.There is a light post at the 1.The light post is very 1. Light post need to be
right hand side of the road close to the road. Offset replaced.
2.3m
CHAINAGE 0+076
RHS
11
DETAIL OF PHOTO ACTUAL SITUATION PROPOSALS
1.There is a light post at the 1.The light post is very 1. Light post need to be
right hand side of the road close to the road. Offset shifted.
2.3m.
CHAINAGE 0+108
LHS
1.There is a light post at the 1.The light post is very 1. Light post need to be
left hand side of the road close to the road. Offset shifted
2.5m.
CHAINAGE 0+290
LHS
12
DETAIL OF PHOTO ACTUAL SITUATION PROPOSALS
1.There is a light post at the 1.The light post is very 1. Light post need to be
left hand side of the road close to the road .Offset shifted.
2.5m
CHAINAGE 0+655
LHS
1.There is a light post at the 1.The light post is very 1. Light post need to be
left hand side of the road close to the road. Offset shifted
2.2m.
CHAINAGE 1+254
RHS
13
1. There is a Lunumiddella 1. The tree is very close to 1.The Tree needs to be
tree at the right hand side the road. Offset 2.5m. shifted.
of the road.
CHAINAGE 2+058
RHS
CHAINAGE 2+204
RHS
14
DETAIL OF PHOTO ACTUAL SITUATION PROPOSALS
1.There is a light post at the 1. The light post is very 1. Light post need to be
right hand side of the road close to the road.. Offset shifted.
2.5m .
CHAINAGE 2+586
LHS
1.There is a light post at the 1.The light post is very 1. Light post need to be
left hand side of the road close to the road 2.5m. shifted.
CHAINAGE 2+704
LHS
15
1.There is a light post at the 1.The light post is very 1. Light post need to be
left hand side of the road close to the road shifted.
CHAINAGE 2+864
LHS
1.There is a light post at the 1. The light post is very 1. Light post need to be
left hand side of the road close to the road. Offset shifted.
1.5m.
CHAINAGE 2+910
RHS
16
1.There is a light post at the 1.The light post is very close 1. Light post need to be
right hand side of the road to the road. Offset 2.5m. shifted.
CHAINAGE 2+985
LHS
1.There is a light post at the 1.The light post is very 1. Light post need to be
left hand side of the road close to the road. Offset shifted
1.8m.
CHAINAGE 3+058.5
RHS
17
1.There is a light post at the 1. The light post is very 1. Light post need to be
right hand side of the road close to the road. Offset shifted.
2.2m.
CHAINAGE 3+095
RHS
1.There is a light post at the 1.The light post is very 1. Light post need to be
right hand side of the road close to the road. Offset shifted
2.5m.
CHAINAGE 3+216
RHS
1.There is a light post at the 1.The light post is very 1. Light post need to be
right hand side of the road close to the road .Offset shifted.
2.4m.
18
CHAINAGE 3+332
RHS
1.There is a light post at the 1.The light post is very close 1. Light post need to be
right hand side of the road to the road. Offset 2.0m shifted.
CHAINAGE 3+449
RHS
1.There is a light post at the 1.The light post is very close 1. Light post need to be
right hand side of the road to the road. Offset 2.5m. shifted.
19
CHAINAGE 4+033
LHS
1.There is a light post at the 1.The light post is very 1. Light post need to be
left hand side of the road close to the road .Offset shifted.
1.8m.
CHAINAGE 4+292
LHS
1.There is a Thekka tree at 1.The Thekka tree is very 1. Thekka tree need to be
the left hand side of the close to the road shifted.
road
CHAINAGE 4+506
20
LHS
1.There is a Pulun tree at 1.The Pulun tree is very 1. Pulun tree need to be
the left hand side of the close to the road, Offset shifted.
road 2.5m.
CHAINAGE 4+742
LHS
1.There is a at Thekka tree 1.The is Thekka tree very 1. Thekka tree need to be
the left hand side of the close to the road shifted.
road
CHAINAGE 4+748
LHS
21
DETAIL OF PHOTO ACTUAL SITUATION PROPOSALS
1.There is a Thekka tree at 1.The Thekka tree is very 1. Thekka tree need to be
the left hand side of the close to the road shifted.
road
CHAINAGE 5+333
LHS
1.There is a light post at the 1.The light post is very 1. Light post need to be
left hand side of the road close to the road. Offset shifted.
2.3m.
22