GURU GOBIND SINGH REFINERY LIMITED, BATHINDA

165 MW Captive Power Plant


Training Session Evaluation Sheet
Training Code : Training Subject : Date:

Faculty Emp Code :_______ Faculty : Dept.: Total Marks : 10


Participant’s Emp. Marks
Participant : Desg. :
Code :___________
Obtained :____

1. What is set-point of over speed trip?

a.6300 c. 3950
b. 7000 d. 6930

2. What is set-point of trip oil hdr pr V.low ?

a. 2 kg/cm2 c. 5 kg/cm2
b. 4.5 kg/cm2 d. 1.5 kg/cm2

3. when both vibration increases upto trip set point in same bearing then STG trip

a. False c. nothing happen

b. True d. none of this

4. What is alarm set-point of axial displacement high

a. -+0.5MM c. -+0.7MM
b. -+0.6MM d. -+0.9MM

5. If STG fire protection acted then turbine trip ?

a. no c. generator trip
b. none of this d. yes

6. What is alarm set-point of lube oil Pressure low

a. 9.5 Kg/cm2 c. 4.5 Kg/cm2


b. 1.5 Kg/cm2 d. 1 Kg/cm2

7. Which type of instrument used to measure turbine bearing temperature?


a. J type RTD c. K T/C
b. TC D PT100 RTD

8. What is trip set-point of turbine VIB V.high?


a. 166 mm C none of this
b. 240 MICRON d. 166 MICRON

9. What is rated Speed of STG?

a 6300 RPM c. 6700 RPM


b. 7300 RPM d. 6000 RPM

10. If anyone press EPB then?


a. Turbine trip without any delay c. Turbine trip with 60 Sec delay

b. all a,c and d d. none of this

Technical Cell-Steag Page 1 of 2


GURU GOBIND SINGH REFINERY LIMITED, BATHINDA
165 MW Captive Power Plant
Training Session Evaluation Sheet
Training Code : Training Subject : Date:

Faculty Emp Code :_______ Faculty : Dept.: Total Marks : 10


Participant’s Emp. Marks
Participant : Desg. :
Code :___________
Obtained :____

Technical Cell-Steag Page 2 of 2

You might also like