CONTINGENCY PLANNING

Sr. Type of contingency Alternate


Current status
No. reviewed arrangements
1 utility intermptions

no power failures on any working 450 kva DG set installed


power failures
day. with 125 kva dg installed

which can be used to run


2hrs failure every staggering day all production machines In
case of power failuer

i-e. our weekly off at present.


overhead crane wheel failure once in 6months wheel kept in stock

if not can be procured


other failures generlly observed
locally max loss in 3hrs
labours are arranged by 1)contractors whenever
2 labour shortage
contractors required with

no shortage of labours observed


one day advance
affections production.

3 setters are available per shift

frequent mechanical & electrical


3 key equipments failure
failures observed in furnace

mechanical failure mainly due to currect the problem &


conveyor drive starts the machines

electrical failure once in 3 months alternative pump & motor


due to pumpmotor installed

4 field returns no field returns till date

PREPARED BY: CHECKED BY: APPROVED BY:


Y PLANNING
Responsibility/ Action completion
Action plan
Target date status

provide sleeve over s.s sleves provided in


(work manager by
conveyor chain to avoid conveyor chain by aug-
aug-10)
problems 10 end

spare motors to be made


(head of ele )by four motor of 7.5HP by
available as standby
aug-10 aug-10 1st week
(7.5HP 2880rpm)