ENGINEERING COMPLIANCE

REPORT FOR MAYFAIR

4TH MAR – 10TH MAR 2024


WEEKLY HIGHLIGHT SUMMARY
ACHIEVEMENT IMPROVEMENT IN PROGRESS ACTION REQUIRED
Training Compliance @ 100% Continuous Improvement in 3 containers and packing lists are received.
capturing and closing of WO. No confirmation of additional ordered spares and the
QA/QC @ 100% delivery thereof.

No update on available stock & Annual Consumption


of spares.
Weekly planning and schedule 2x FELs on long-standing breakdowns:
communicated. CAT 988G down with an engine for 3 months.
Negotiations are ongoing with Mantrac. Not yet
ordered.

Liebherr L550 Engine misfiring – Solenoid ordered for


further fault-finding. ETA 11/03/24 (for the Solenoid).
ETC for the equipment TBC (further fault finding
required).
PM compliance @ 100% Update on additional Manpower and ordering and
supply of PPE (maintenance teams working without
WO Compliance is 100%. correct PPE).

1
O VERALL E QUIPMENT P ERFORMANCE

Front End Loaders 35T Trucks


L550 – Engine misfiring. Solenoid required/ordered for TK010 – Axle Failure. Parts on order – No ETA.
further fault-finding. ETA 11/03/24 for the Solenoid. ETC
for the equipment TBC (further fault finding required).
988G– Engine Block Cracked (Negotiation ongoing with
Mantrac). No ETA yet.

2
C OMPLIANCE

3
SPARES STATUS