Attendees:
Client: SDC Infrastructure Pvt. Ltd. (SDC) Structural Consultant: JW Consultants (JW)
Mr. Avijit Upadhyay Ms. Pratibha
Ms. Namrata Bhandari Mr. Ghanshyam
Ms. Madhavi Patade MEP Consultant: D. G. Bhave Consultants (DGB)
Liason Architect: Vision Architect PMC: Dongre PMC Pvt. Ltd. (DPMC)
No representation Mr. Uday Chandorikar
Page 1 of 3
Minutes:
Sr. No. Description Action By Original Revised Status on 17-Mar-22
Due Date Due Date
1 Design
1.1 Podium Drawing P1 & P2 Level details to be revised by JW JW 17.03.2022 24.03.2022 Waiting for feedback
and resubmit to PGP for approval and issuance GFC
drawing
1.2 Ventilator Size to be reconfirm by DGB to PGP DGB 17.03.2022 24.03.2022 Waiting for feedback
1.3 JW to confirm the Beam depth B82,B35 for Stack Parking JW 17.03.2022 24.03.2022 Waiting for feedback
to PGP
1.4 Fin Details in Elevation to confirm by JW to PGP for JW 17.03.2022 24.03.2022 Waiting for feedback
loading Conditions
1.5 Column Schedule to provided by JW JW 17.03.2022 24.03.2022 Waiting for details
1.6 Revised IOD drawings to be checked SDC 17.03.2022 24.03.2022 Waiting for details
2 Approvals
3 Procurement
4 Construction
5 Schedule
6 Budget & Cost
7 Others
7.1 No meeting conducted