MEASUREMENT 11
BQS2001
BASEMENT
1 Removal of trees
2 Site clearance
3 Top soil excavation
4 Bulk excavation-Basement
5 Disposal of excavated material
6 E.o for pickable material
7 E.o for rock
8 Foundation trench excavation
9 Scarifying and compacting
10 Planking and struting
11 Keeping excavations free from water
12 Surface treatment
13 Hardcore
14 Sand blinding
15 Asphalt tanking: horizontally
16 Cement: sand screed
17 Concrete to floating slab + reinforcement + striking off and curing
18 Concrete to basement wall + reinforcement
19 Concrete to ground beam + reinforcement
20 Formwork to the floating slab : soffits edge
21 Formwork to sides of beams
22 Formwork to one side of concrete wall
23 Concrete to slab + reinforcement + striking off and curing
24 20mm mastic asphalt laid vertically
25 50mm angle fillet
26 115 mm brickwork
27 115mm brickforce
MEASUREMENT 11
BQS2001
10.20
Top soil excavation to a average depth of
150mm below the natural ground level
and retaining of excavated material on
site on temporary spoil heaps, maximum Scarifying and compacting bottom of trench
of 100m from excavation 10.20 to specified density
5.20 53.04 5.20 53.04
Height 10200
2900 less 2/280 560
add 100 9640
add 50
3050 5200
less 460 less2/230 560
2570 4640