RA BILL -O2
NOTE : All dimensions are in METRE
CONCRETE WORK
Note:In All reinforced concrete works, Flyash is permitted to be added as per relevant IS Codes.However
the fly ash shall confirm to the I.S Code specifications.
60.72 Cum 4192.80 रु 254,586.82
All work up to plinth level
M25 - footings
For Footings
F1 4 2.87 2.87 0.45 14.83
F2 10 2.45 2.45 0.35 21.01
F3 4 1.83 1.83 0.25 3.35
F4 7 1.07 1.07 0.15 1.20
40.39
M25 - Plinth beam
PB1,2,3 3 21.38 0.23 0.45 6.64
1
PROJECT: PROPOSED MULTI - FUNCTIONAL COMPLEX AT HYDERABAD STATION
RA BILL -O2
NOTE : All dimensions are in METRE
B.3.2 5.37A Providing and laying in position ready mixed concrete manufactured in fully automatic batching plant and
transported to site of work in transit mixer for lead upto 10Kms having continuous agitated
mixer,manufactured as per mix design of specified grade for reinforced cement concrete work including
puming of RMC from transit mixer to site of laying, excluding the cost of centering ,shuttering, finishing and
reinforcement. including admixtures in recommended proportions as per IS 9103 to accelerate, retard
setting of concrete , improve workability without imparing strength and durability as per direction of
Engineer - in - Charge.M-25 grade reinforced cement concrete by using minimum Ordinary portland cement
content of 380. Kg of cement per Cum of concrete .All works above Plinth level upto floor V level.
Note:In All reinforced concrete works, Flyash is permitted to be added as per relevant IS Codes.However
the fly ash shall confirm to the I.S Code specifications.
107.25 Cum 4192.80 रु 449,669.97
B.3.2 All work up to floor V level.
M25 - in Column
In Ground floor
C1 4 0.30 0.30 3.15 1.13
C2 10 0.30 0.23 3.15 2.17
C3 4 0.30 0.23 3.15 0.87
C4 7 0.23 0.23 3.15 1.17
5.34
In First floor
C1 4 0.30 0.30 3.15 1.13
C2 10 0.30 0.23 3.15 2.17
C3 4 0.30 0.23 3.15 0.87
C4 7 0.23 0.23 3.15 1.17
5.34
10.69
Roundup 11.00 Cum
2
PROJECT: PROPOSED MULTI - FUNCTIONAL COMPLEX AT HYDERABAD STATION
RA BILL -O2
NOTE : All dimensions are in METRE
B3.3 5.39 Extra for carriage of R.M.C beyond the initial lead of 10km 167.97 10.00 K.m 1679.68 Cum/Km 20.90 रु 35,105.34
FORM WORK
C.1 5.90 Centering and shuttering including strutting,
propping etc and removal of form for
C.1.1 5.9.1 Foundations, footings, bases of columns, etc for
mass concrete 103.90 Sqm 119.25 रु 12,390.08
For PCC
F1 4 12.08 0.15 7.25
F2 10 10.40 0.15 15.60
F3 4 7.92 0.15 4.75
F4 7 4.88 0.15 5.12
32.72
For RCC footings
F1 4 12.08 0.45 21.74
F2 10 10.40 0.35 36.40
F3 4 7.92 0.25 7.92
F4 7 4.88 0.15 5.12
71.18
61.87
In First floor
C1 4 1.20 3.15 15.12
C2 10 1.06 3.15 33.39
C3 4 1.06 3.15 13.36
61.87
3
PROJECT: PROPOSED MULTI - FUNCTIONAL COMPLEX AT HYDERABAD STATION
RA BILL -O2
NOTE : All dimensions are in METRE
196.98
For Round off 197.00 Sqm
C.1.5 5.9.30 Suspended floors, roofs, landings, balconies, and
access platform 774.14 Sqm 187.35 रु 145,035.41
For Sunshades
In Ground floor
Sunshades 7 2.26 0.60 9.49
7 1.20 0.08 0.63
2 1.06 0.60 1.27
2 1.20 0.08 0.18
11.57
M25 - in Roof beams
In Ground floor
Hr. RB3 4 21.38 0.64 54.73
Hr. RB4 1 21.38 0.64 13.68
Ver. RB1,RB2 13 4.90 0.64 40.77
Ver. CB1 6 0.97 0.64 3.72
Ver. CB1 6 0.67 0.64 2.57
115.48
In First floor
Hr. RB3 4 21.38 0.64 54.73
Hr. RB4 1 21.38 0.64 13.68
Ver. RB1,RB2 13 4.90 0.64 40.77
Ver. CB1 6 0.97 0.64 3.72
Ver. CB1 6 0.67 0.64 2.57
115.48
230.96
4
PROJECT: PROPOSED MULTI - FUNCTIONAL COMPLEX AT HYDERABAD STATION
RA BILL -O2
NOTE : All dimensions are in METRE
BLOCK MASONARY
E.1 6.1.1 Masonary walls exposed brick work with ‘Autoclaved
Fly Ash Sand Lime Bricks of Class designation 75 in
foundation and plinth in cement mortar 1:6 (1
cement : 6 coarse sand). All worrk up to floor V
54.96 Cum 2293.40 रु 126,054.28
level.
5
PROJECT: PROPOSED MULTI - FUNCTIONAL COMPLEX AT HYDERABAD STATION
RA BILL -O2
NOTE : All dimensions are in METRE
6
Swarnaa Techno Construction Pvt Ltd, Hubli
RUNNING BILL No.8 and FINAL BILL FOR THE MONTH OF ……………
Name of Work :- Construction of Multi-Functional Complex at Hubli Railway Station Premises,Karnataka State.
Sub:- RA Bill No: 08 and FINAL
Agreement No:- IRCON/CIVIL/7004/MFC/Hubli/10/100 Dt:31.03.2010
Date Of Commencement: 31 /03/2010 Date of Completion:
Date Of Measurement:………………….
Quantity Amount in Rs.
DSR BOQ Rate
Sl No Description Unit Upto Last Since Last
Item No in Rs. Upto date Upto date Upto Last certificate Since Last Certificate
certificate Certificate
A DISMANTLING AND DEMOLISHING
A.1 15.6 Demolishing C.C / RCC work by mechanicla means and stockpiling at designated
locations and disposal of dismantelled materials upto a lead of 100 m, stacking
serviceable and unserviceable material seperately including cutting reinforcement
bars. Cum 731.05 49.23 49.23 0.00 35989.59 35989.59 0.00
A.2 15.7.4 Demolishing brick work manually / by mechanicla means including stackingof
serviceable material and disposal of unserviceqble material within 50 meters less as
peer direction of Engineer-in-charge. In Cement Mortar Cum 310.75 193.25 193.25 0.00 60052.44 60052.44 0.00
B EARTH WORK
B.1 2.6.1 Earth work in excavation by mechnical means (Hydraulic excavator)/manual means
over areas (exceeding 30cm in depth,1.5m in width as well as 10 sqm on plan)
including disposal of excavated earth, lead upto 50m and lift upto 1.5m, disposed
earth to be levelled and neatly dressed.
All Kinds of soil
Cum 101.85 4620.45 4579.34 41.11 470592.83 466405.78 4187.05
C Brick Work
C.1 6.1.1 Brick work with cement mortar 1:4… Cum 2293.40 51.75 51.75 0.00 118683.45 118683.45 0.00
C.2 4.7.2 Providing and fixing upto floor five precast CC Block in 1:3:8… Cum 5093.95 104.72 0.00 104.72 533418.07 0.00 533418.07
Deduct for not doing plastering work Item No.13.5.1 Sqm 62.15 -1047.16 0.00 (1047.16) (65080.99) 0.00 (65080.99)
D CONCRETE WORK
D.1 4.1.8 Providing and laying in postion plain cement concrete of specified grade excluding
the cost of centering and shuttering - All work up to plinth level.
1:4:8 (1 Cement : 4 coarse sand : 8 graded stone aggregate 40mm nominal size ) Cum 2449.00 172.89 162.53 10.36 423407.61 398035.97 25371.64
DESIGN MIX CONCRETE
D.2 5.33 Providing and laying in position machine batched , machine mixed and machine
vibrated design mix cement concrete of specified grade for reinforced cement
concrete work including pumping of concrete to site of laying but excluding the cost
of centering ,shuttering, finishing and reinforcement. including admixtures in
recommended proportions as per IS 9103 to accelerate, retard setting of concrete ,
improve workability without imparing strength and durability as per direction of
Engineer - in - Charge.M-25 grade reinforced cement concrete by using minimum
Ordinary portland cement content of 380. Kg of cement per Cum of concrete .All
works above plinth level upto floor V level.
Page 7
Quantity Amount in Rs.
DSR BOQ Rate
Sl No Description Unit Upto Last Since Last
Item No in Rs. Upto date Upto date Upto Last certificate Since Last Certificate
certificate Certificate
D.3 5.37 Providing and laying in position ready mixed concrete manufactured in fully
automatic batching plant and transported to site of work in transit mixer for lead upto
10Kms having continuous agitated mixer,manufactured as per mix design of
specified grade for reinforced cement concrete work including puming of RMC from
transit mixer to site of laying, excluding the cost of centering ,shuttering, finishing
and reinforcement. including admixtures in recommended proportions as per IS
9103 to accelerate, retard setting of concrete , improve workability without imparing
strength and durability as per direction of Engineer - in - Charge.M-25 grade
reinforced cement concrete by using minimum Ordinary portland cement content of
380. Kg of cement per Cum of concrete .All works upto Plinth level.
Page 8
Quantity Amount in Rs.
DSR BOQ Rate
Sl No Description Unit Upto Last Since Last
Item No in Rs. Upto date Upto date Upto Last certificate Since Last Certificate
certificate Certificate
G PLASTERING
13.15.1 6 mm cement plaster in ceiling Sqm 62.15 605.00 605.00 0.00 37600.75 37600.75 0.00
14.4.1 12 mm cement plaster 1:4 mix Sqm 82.55 437.88 400.00 37.88 36146.99 33020.00 3126.99
H
1.21.2 Supply and fixing of PVC conduit
25 mm Mtr 47.00 3400.00 3400.00 0.00 159800.00 159800.00 0.00
Total Amount = A Rs. 22,033,513.16 Rs. 21,448,626.37 Rs. 584,886.79
Gross Amount (A)+Adding quoted (+22%) above DSR 2007 rates Rs. 26,880,886.06 Rs. 26,167,324.17 Rs. 713,561.88
Total RA Bill-No.8 & Final Bill Amount Say Rs. 713,562
Page 9
Certified that:
1.Work billed has been executed satisfactorily as per contract specifications and site conditions.
2.Certified that no materials the cost of which has not been recovered have been issued to the Contractor except such as specifically
provided for in the agreement/Work order.
3. Quantity billed does not exceed the quantity executed at site.
4. No departmental tools and plant have been issued to the Contractor other than those for which hire charges have been recovered in the bill.
5.The measurements were made by me on …………………………. and are recorded at abstract of measurements in measurement
Book No 306 from page No ………… to …………
Date of Measuerement ……………..
HUSSAIN T M
Date:…………………………. Manager/Civil
Certified that:
1. The labour engaged by us for the work have been paid as per extant labour laws:
2. The measurements as billed are accepted;
3. Seinorage charges, Cess,etc., due to the Govt on the materials used for this work have been fully paid & no payment due to them is outstanding.
Date………………. Contractor
Certified that the foregoing claim is correct, that the necessary measurements were taken by Mr.Hussain T M Manager/civil
on 15.06.2011 and Technical check has done by me on…………………..and are recorded in MB at pages ……………..
of MB Booklet No 306 and Abstract of Measurements in Measurement book no 306 at page No …………………….and that
the work has been satisfactorily performed.
Total Rs.
Memo of payments made Upto Date Upto last bill Since last bill
DEDUCTIONS:
Received Rs.(……………………….)……………………………………………………………
………………………..as per details above on account of this work.