PROJECT: PROPOSED MULTI - FUNCTIONAL COMPLEX AT HYDERABAD STATION

RA BILL -O2
NOTE : All dimensions are in METRE

Total Executed Amount as per DSR-2007 रु 2,532,675.31


DSR
SL.NO
Code No DESCRIPTION NOS L B D CONT QTY UNIT Rate Executed Qty Amount
EARTH WORK

CONCRETE WORK

DESIGN MIX CONCRETE


B.3 5.33A Providing and laying in position machine batched , machine mixed and machine vibrated design mix cement
concrete of specified grade for reinforced cement concrete work including pumping of concrete to site of
laying but excluding the cost of centering ,shuttering, finishing and reinforcement. including admixtures in
recommended proportions as per IS 9103 to accelerate, retard setting of concrete , improve workability
without imparing strength and durability as per direction of Engineer - in - Charge.M-25 grade reinforced
cement concrete by using minimum Ordinary portland cement content of 380. Kg of cement per Cum of
concrete .All works above plinth level upto floor V level.

In All reinforced concrete works, Flyash is permitted


to be added as per relevant IS Codes.However the
fly ash shall confirm to the I.S Code specifications.
6.32 Cum 3983.75 रु 25,175.25
M25 - in Lintel.
In Ground floor
Continous lintel LB1 (Grid A1-F1) 5 3.93 0.23 0.20 0.90
Cut lintel LB1 (Grid A3-F3) 5 2.26 0.23 0.20 0.52
Continous lintel LB1 (A3-A1,F3-F1) 2 10.63 0.23 0.20 0.98
Continous lintel LB2 (F2-F1) 1 4.83 0.23 0.20 0.22
Continous lintel LB3 (A1-B1) 2 3.97 0.23 0.15 0.27
Continous lintel LB2 (B1-C1,D1-E1,E1-F1) 3 3.93 0.23 0.20 0.54
Continous lintel LB3 (A3'-C'3') 1 8.85 0.23 0.15 0.31
Continous lintel LB3 (C'3'-E'3') 1 5.52 0.23 0.15 0.19
Continous lintel LB3 (C'3'-C'3,D'3-D'3') 2 3.10 0.23 0.15 0.21
All cut lintels LB2 2 2.03 0.23 0.20 0.19
@ Toilet Portion LB3 2 2.00 0.23 0.15 0.14
LB3 1 2.19 0.23 0.15 0.08
LB4 1 2.23 0.12 0.15 0.04
4.59
M25 - in Sunshades
In Ground floor
Sunshades 5 2.29 0.60 0.08 0.52
2 1.06 0.60 0.08 0.10
0.61
M25 - Stair case steps
In Ground floor
Internal 22 1.43 0.28 0.08 0.65
23 1.00 0.28 0.08 0.47
1.12
6.32 Cum 3983.75
B.3.1 5.37 Providing and laying in position ready mixed concrete manufactured in fully automatic batching plant and
transported to site of work in transit mixer for lead upto 10Kms having continuous agitated
mixer,manufactured as per mix design of specified grade for reinforced cement concrete work including
puming of RMC from transit mixer to site of laying, excluding the cost of centering ,shuttering, finishing and
reinforcement. including admixtures in recommended proportions as per IS 9103 to accelerate, retard
setting of concrete , improve workability without imparing strength and durability as per direction of
Engineer - in - Charge.M-25 grade reinforced cement concrete by using minimum Ordinary portland cement
content of 380. Kg of cement per Cum of concrete .All works upto Plinth level.

Note:In All reinforced concrete works, Flyash is permitted to be added as per relevant IS Codes.However
the fly ash shall confirm to the I.S Code specifications.
60.72 Cum 4192.80 रु 254,586.82
All work up to plinth level
M25 - footings
For Footings
F1 4 2.87 2.87 0.45 14.83
F2 10 2.45 2.45 0.35 21.01
F3 4 1.83 1.83 0.25 3.35
F4 7 1.07 1.07 0.15 1.20
40.39
M25 - Plinth beam
PB1,2,3 3 21.38 0.23 0.45 6.64

1
PROJECT: PROPOSED MULTI - FUNCTIONAL COMPLEX AT HYDERABAD STATION
RA BILL -O2
NOTE : All dimensions are in METRE

Total Executed Amount as per DSR-2007 रु 2,532,675.31


DSR
SL.NO
Code No DESCRIPTION NOS L B D CONT QTY UNIT Rate Executed Qty Amount
12 4.40 0.23 0.45 5.46
PB3 2 4.00 0.23 0.45 0.83
2 4.62 0.23 0.45 0.96
2 4.62 0.23 0.45 0.96
1 4.00 0.23 0.45 0.41
PB 4 1 2.77 0.23 0.40 0.25
1 1.07 0.23 0.40 0.10
1 3.10 0.23 0.40 0.29
1 3.10 0.23 0.40 0.28
1 2.46 0.23 0.40 0.23
1 2.47 0.23 0.40 0.23
PB5 3 2.00 0.23 0.40 0.55
2 1.57 0.23 0.40 0.29
17.48
57.87
Roundup 58.00 Cum
M20 - Col up to Plinth level
C1 4 0.30 0.30 1.73 0.62
C2 10 0.30 0.23 1.83 1.26
C3 4 0.30 0.23 1.83 0.51
C4 7 0.23 0.23 1.23 0.46
2.85
Roundup 3.00 Cum

B.3.2 5.37A Providing and laying in position ready mixed concrete manufactured in fully automatic batching plant and
transported to site of work in transit mixer for lead upto 10Kms having continuous agitated
mixer,manufactured as per mix design of specified grade for reinforced cement concrete work including
puming of RMC from transit mixer to site of laying, excluding the cost of centering ,shuttering, finishing and
reinforcement. including admixtures in recommended proportions as per IS 9103 to accelerate, retard
setting of concrete , improve workability without imparing strength and durability as per direction of
Engineer - in - Charge.M-25 grade reinforced cement concrete by using minimum Ordinary portland cement
content of 380. Kg of cement per Cum of concrete .All works above Plinth level upto floor V level.

Note:In All reinforced concrete works, Flyash is permitted to be added as per relevant IS Codes.However
the fly ash shall confirm to the I.S Code specifications.
107.25 Cum 4192.80 रु 449,669.97
B.3.2 All work up to floor V level.
M25 - in Column
In Ground floor
C1 4 0.30 0.30 3.15 1.13
C2 10 0.30 0.23 3.15 2.17
C3 4 0.30 0.23 3.15 0.87
C4 7 0.23 0.23 3.15 1.17
5.34
In First floor
C1 4 0.30 0.30 3.15 1.13
C2 10 0.30 0.23 3.15 2.17
C3 4 0.30 0.23 3.15 0.87
C4 7 0.23 0.23 3.15 1.17
5.34
10.69
Roundup 11.00 Cum

M25 - in Roof beams


In Ground floor
Hr. RB3 4 21.38 0.23 0.32 6.29
Hr. RB4 1 21.38 0.23 0.32 1.57
Ver. RB1,RB2 13 4.90 0.23 0.32 4.69
Ver. CB1 6 0.97 0.23 0.32 0.43
Ver. CB1 6 0.67 0.23 0.32 0.30
13.28
In First floor
Hr. RB3 4 21.38 0.23 0.32 6.29
Hr. RB4 1 21.38 0.23 0.32 1.57
Ver. RB1,RB2 13 4.90 0.23 0.32 4.69

2
PROJECT: PROPOSED MULTI - FUNCTIONAL COMPLEX AT HYDERABAD STATION
RA BILL -O2
NOTE : All dimensions are in METRE

Total Executed Amount as per DSR-2007 रु 2,532,675.31


DSR
SL.NO
Code No DESCRIPTION NOS L B D CONT QTY UNIT Rate Executed Qty Amount
Ver. CB1 6 0.97 0.23 0.32 0.43
Ver. CB1 6 0.67 0.23 0.32 0.30
13.28
26.56
M25 - in Roof slabs
In Ground floor 1 21.38 12.59 0.13 34.99
Deduct Stair Case Portion -1 3.10 4.15 0.13 -1.67
33.32

In First floor 1 21.38 12.59 0.13 34.99


Deduct Stair Case Portion -1 3.10 4.15 0.13 -1.67
33.32
In Internal Stair Case
First flight 1 3.13 1.43 0.15 0.67
Second flight 1 3.76 1.43 0.15 0.81
Landing 1 3.10 1.33 0.15 0.62
External Stair Case 1 7.20 1.00 0.15 1.08
Landing 1 1.00 1.20 0.15 0.18
3.36
70.00
Roundup 71.00 Cum

B3.3 5.39 Extra for carriage of R.M.C beyond the initial lead of 10km 167.97 10.00 K.m 1679.68 Cum/Km 20.90 रु 35,105.34

FORM WORK
C.1 5.90 Centering and shuttering including strutting,
propping etc and removal of form for
C.1.1 5.9.1 Foundations, footings, bases of columns, etc for
mass concrete 103.90 Sqm 119.25 रु 12,390.08
For PCC
F1 4 12.08 0.15 7.25
F2 10 10.40 0.15 15.60
F3 4 7.92 0.15 4.75
F4 7 4.88 0.15 5.12
32.72
For RCC footings
F1 4 12.08 0.45 21.74
F2 10 10.40 0.35 36.40
F3 4 7.92 0.25 7.92
F4 7 4.88 0.15 5.12
71.18

Roundup 103.90 Sqm

C.1.3 5.9.6 Columns, Pillars, piers, Abutments, posts, and


struts. 167.11 Sqm 238.40 रु 39,840.07
Col up to basement level
C1 4 1.20 1.73 8.30
C2 10 1.06 1.83 19.40
C3 4 1.06 1.83 7.76
C4 7 0.92 1.23 7.92
43.38
In Ground floor
C1 4 1.20 3.15 15.12
C2 10 1.06 3.15 33.39
C3 4 1.06 3.15 13.36

61.87
In First floor
C1 4 1.20 3.15 15.12
C2 10 1.06 3.15 33.39
C3 4 1.06 3.15 13.36

61.87
3
PROJECT: PROPOSED MULTI - FUNCTIONAL COMPLEX AT HYDERABAD STATION
RA BILL -O2
NOTE : All dimensions are in METRE

Total Executed Amount as per DSR-2007 रु 2,532,675.31


DSR
SL.NO
Code No DESCRIPTION NOS L B D CONT QTY UNIT Rate Executed Qty Amount
167.11
For Round off 168.00 Sqm
C.1.4 5.9.21 Lintels,beams, plinthbeams, girders, bressumers
and cantilevers 196.98 Sqm 319.10 रु 62,856.00
For Plinth beam
PB1,2,3 3 21.38 2.00 0.45 57.73
12 4.40 2.00 0.45 47.52
PB3 2 4.00 2.00 0.45 7.20
2 4.62 2.00 0.45 8.32
2 4.62 2.00 0.45 8.31
2 4.00 2.00 0.45 7.20
2 3.42 2.00 0.45 6.16
PB 4 1 2.77 2.00 0.40 2.21
1 1.07 2.00 0.40 0.86
1 3.10 2.00 0.40 2.48
1 3.10 2.00 0.40 2.48
1 2.46 2.00 0.40 1.96
1 2.47 2.00 0.40 1.97
PB5 3 2.00 2.00 0.40 4.80
4 1.57 2.00 0.40 5.02
164.22
For Lintel.
In Ground floor
Continous lintel LB1 (Grid B3-E3) 3 3.93 2.00 0.25 5.90
Continous lintel LB2 (A3-B3,E3-F3) 2 3.97 2.00 0.20 3.17
Continous lintel LB3 (A3-A2,A2-A1,F3-F2) 3 4.83 2.00 0.15 4.35
Continous lintel LB2 (F2-F1) 1 4.83 2.00 0.20 1.93
Continous lintel LB3 (A1-B1) 2 3.97 2.00 0.15 2.38
Continous lintel LB2 (B1-C1,D1-E1,E1-F1) 3 3.93 2.00 0.20 4.72
Continous lintel LB3 (A3'-C'3') 1 8.85 2.00 0.15 2.65
Continous lintel LB3 (C'3'-E'3') 1 5.52 2.00 0.15 1.65
Continous lintel LB3 (C'3'-C'3,D'3-D'3') 2 3.10 2.00 0.15 1.86
All cut lintels LB2 2 2.03 2.00 0.20 1.62
@ Toilet Portion LB3 2 2.00 2.00 0.15 1.20
LB3 1 2.19 2.00 0.15 0.66
LB4 1 2.23 2.00 0.15 0.67
32.76
196.98

196.98
For Round off 197.00 Sqm
C.1.5 5.9.30 Suspended floors, roofs, landings, balconies, and
access platform 774.14 Sqm 187.35 रु 145,035.41
For Sunshades
In Ground floor
Sunshades 7 2.26 0.60 9.49
7 1.20 0.08 0.63
2 1.06 0.60 1.27
2 1.20 0.08 0.18
11.57
M25 - in Roof beams
In Ground floor
Hr. RB3 4 21.38 0.64 54.73
Hr. RB4 1 21.38 0.64 13.68
Ver. RB1,RB2 13 4.90 0.64 40.77
Ver. CB1 6 0.97 0.64 3.72
Ver. CB1 6 0.67 0.64 2.57
115.48
In First floor
Hr. RB3 4 21.38 0.64 54.73
Hr. RB4 1 21.38 0.64 13.68
Ver. RB1,RB2 13 4.90 0.64 40.77
Ver. CB1 6 0.97 0.64 3.72
Ver. CB1 6 0.67 0.64 2.57
115.48
230.96
4
PROJECT: PROPOSED MULTI - FUNCTIONAL COMPLEX AT HYDERABAD STATION
RA BILL -O2
NOTE : All dimensions are in METRE

Total Executed Amount as per DSR-2007 रु 2,532,675.31


DSR
SL.NO
Code No DESCRIPTION NOS L B D CONT QTY UNIT Rate Executed Qty Amount
M25 - in Roof slabs
In Ground floor 1 21.38 12.59 269.17
Deduct Stair Case Portion -1 3.10 4.15 -12.85
256.32

In First floor 1 21.38 12.59 269.17


Deduct Stair Case Portion -1 3.10 4.15 -12.85
256.32
530.80
In Internal Stair Case
Landing 1 3.10 1.33 0.15 0.62
External Stair Case
Landing 1 1.00 1.20 0.15 0.18
0.80
774.14
For Round off 775.00 Sqm

C.1.6 5.9.7 Stairs, (excluding landings) exceptspiral staircases.


32.71 Sqm 182.70 रु 5,975.97
For stairs flights In Ground Floor only
In Internal Stair Case
First flight 1 3.13 1.43 4.46
Second flight 1 3.76 1.43 5.37
Steps 22 1.43 0.15 4.72
External Stair Case 24 1.00 0.15 3.60
18.15
For stairs flights In Ground Floor only
In Internal Stair Case
First flight 1 3.13 1.43 4.46
Second flight 1 3.76 1.43 5.37
Steps 22 1.43 0.15 4.72
14.55
32.71
For Round off 33.00 Sqm

C.1.7 5.11.1 Extra for additional height in centering,shuttering


where ever required with adequate bracing,proping
etc. including cost of de-shuttering and decenetring
at all levels ,over a height of 3.5m for every
additional height of 1m or part there of (Plan area to
be measured)
1025.30 Sqm 70.20 रु 71,975.98
Suspended floors,roofs,landing,beams and balconies
In First floor for upto 4.5m height 1 21.38 12.59 269.17
Deduct Stair Case Portion -1 3.10 4.15 -12.85
In First floor for upto 5.5m height 1 21.38 12.59 269.17
Deduct Stair Case Portion -1 3.10 4.15 -12.85
In First floor for upto 6.5m height 1 21.38 12.59 269.17
Deduct Stair Case Portion -1 3.10 4.15 -12.85
In First floor for upto 7.5m height 1 21.38 12.59 269.17
Deduct Stair Case Portion -1 3.10 4.15 -12.85
1025.30

IRON & STEEL WORK


D.1 5.22 Reinforcement steel for RCC work including
straightening, cutting, bending, placing in position
and binding all complete in all levels.(SAIL, TISCO,
RINL)

D.1.1 5.22.1 Mild steel and medium tensile steel bars.


D.1.2 5.22.6 Thermo - Mechanically Treated bars. 29213.02 kg 42.70 रु 1,247,395.95

BLOCK MASONARY
E.1 6.1.1 Masonary walls exposed brick work with ‘Autoclaved
Fly Ash Sand Lime Bricks of Class designation 75 in
foundation and plinth in cement mortar 1:6 (1
cement : 6 coarse sand). All worrk up to floor V
54.96 Cum 2293.40 रु 126,054.28
level.
5
PROJECT: PROPOSED MULTI - FUNCTIONAL COMPLEX AT HYDERABAD STATION
RA BILL -O2
NOTE : All dimensions are in METRE

Total Executed Amount as per DSR-2007 रु 2,532,675.31


DSR
SL.NO
Code No DESCRIPTION NOS L B D CONT QTY UNIT Rate Executed Qty Amount
In Ground floor
All round walls 2 21.38 0.23 3.14 30.91
2 11.03 0.23 3.14 15.95
Inner walls 1 8.85 0.23 3.45 7.02
1 5.52 0.23 3.45 4.38
2 3.33 0.23 3.45 5.28
2 7.70 0.23 3.45 12.22
1 5.12 0.23 3.45 4.06
1 2.00 0.23 3.45 1.59
1 5.63 0.23 3.14 4.07
1 3.10 0.23 3.14 2.24
87.71 Cum
In First floor
All round walls 2 21.38 0.23 3.14 30.91
2 11.93 0.23 3.14 17.25
Inner partitions walls
1 6.90 0.23 3.45 5.48
1 3.10 0.23 3.14 2.24
55.88 Cum
Gross 143.59
Less
Columns 10.69
Lintels 65.52
Joineries 1 54.00 0.23 12.42
88.62
54.96 60.00 Cum
E.3 6.13.2 Masonry walls of 115mm thick with ‘Autoclaved Fly
Ash Sand Lime Bricks of Class designation 75 in
superstructure above plinth and up to floor V level.
78.63 Sqm 302.80 रु 23,808.21
All work floor V level
In Ground floor
1 2.00 3.45 6.90
In OTS & Ducts 2 1.06 3.45 7.31
3 0.45 3.45 4.66
18.87 Sqm
In First floor
Partition walls 5 4.12 3.45 70.98
For Ducts 1 4.92 3.45 16.97
87.96 Sqm
For all floors 106.83
Less Doors 28.20
Roundup 78.63 78.63 Sqm

7.1.1 Random Rubble Masonary 17.84 Cum 1838.90 रु 32,805.98


In foundation and basement
For PB below RR Masonry
Grid B1-F1 4 3.93 0.45 0.77 5.45
Grid F1-F3 2 4.90 0.45 0.95 4.19
Grid B3-F3 4 3.93 0.45 0.66 4.67
Grid A3-B3 1 3.78 0.45 0.38 0.65
Grid A3-A1 2 4.86 0.45 0.47 2.06
Grid A1-B1 1 3.38 0.45 0.54 0.82
17.84

6
Swarnaa Techno Construction Pvt Ltd, Hubli
RUNNING BILL No.8 and FINAL BILL FOR THE MONTH OF ……………
Name of Work :- Construction of Multi-Functional Complex at Hubli Railway Station Premises,Karnataka State.
Sub:- RA Bill No: 08 and FINAL
Agreement No:- IRCON/CIVIL/7004/MFC/Hubli/10/100 Dt:31.03.2010
Date Of Commencement: 31 /03/2010 Date of Completion:
Date Of Measurement:………………….
Quantity Amount in Rs.
DSR BOQ Rate
Sl No Description Unit Upto Last Since Last
Item No in Rs. Upto date Upto date Upto Last certificate Since Last Certificate
certificate Certificate
A DISMANTLING AND DEMOLISHING
A.1 15.6 Demolishing C.C / RCC work by mechanicla means and stockpiling at designated
locations and disposal of dismantelled materials upto a lead of 100 m, stacking
serviceable and unserviceable material seperately including cutting reinforcement
bars. Cum 731.05 49.23 49.23 0.00 35989.59 35989.59 0.00
A.2 15.7.4 Demolishing brick work manually / by mechanicla means including stackingof
serviceable material and disposal of unserviceqble material within 50 meters less as
peer direction of Engineer-in-charge. In Cement Mortar Cum 310.75 193.25 193.25 0.00 60052.44 60052.44 0.00
B EARTH WORK
B.1 2.6.1 Earth work in excavation by mechnical means (Hydraulic excavator)/manual means
over areas (exceeding 30cm in depth,1.5m in width as well as 10 sqm on plan)
including disposal of excavated earth, lead upto 50m and lift upto 1.5m, disposed
earth to be levelled and neatly dressed.
All Kinds of soil
Cum 101.85 4620.45 4579.34 41.11 470592.83 466405.78 4187.05
C Brick Work
C.1 6.1.1 Brick work with cement mortar 1:4… Cum 2293.40 51.75 51.75 0.00 118683.45 118683.45 0.00
C.2 4.7.2 Providing and fixing upto floor five precast CC Block in 1:3:8… Cum 5093.95 104.72 0.00 104.72 533418.07 0.00 533418.07
Deduct for not doing plastering work Item No.13.5.1 Sqm 62.15 -1047.16 0.00 (1047.16) (65080.99) 0.00 (65080.99)
D CONCRETE WORK
D.1 4.1.8 Providing and laying in postion plain cement concrete of specified grade excluding
the cost of centering and shuttering - All work up to plinth level.
1:4:8 (1 Cement : 4 coarse sand : 8 graded stone aggregate 40mm nominal size ) Cum 2449.00 172.89 162.53 10.36 423407.61 398035.97 25371.64
DESIGN MIX CONCRETE
D.2 5.33 Providing and laying in position machine batched , machine mixed and machine
vibrated design mix cement concrete of specified grade for reinforced cement
concrete work including pumping of concrete to site of laying but excluding the cost
of centering ,shuttering, finishing and reinforcement. including admixtures in
recommended proportions as per IS 9103 to accelerate, retard setting of concrete ,
improve workability without imparing strength and durability as per direction of
Engineer - in - Charge.M-25 grade reinforced cement concrete by using minimum
Ordinary portland cement content of 380. Kg of cement per Cum of concrete .All
works above plinth level upto floor V level.

In All reinforced concrete works, Flyash is permitted to be added as per relevant IS


Codes.However the fly ash shall confirm to the I.S Code specifications. Cum 3983.75 409.10 409.10 0.00 1629752.13 1629752.13 0.00

Page 7
Quantity Amount in Rs.
DSR BOQ Rate
Sl No Description Unit Upto Last Since Last
Item No in Rs. Upto date Upto date Upto Last certificate Since Last Certificate
certificate Certificate
D.3 5.37 Providing and laying in position ready mixed concrete manufactured in fully
automatic batching plant and transported to site of work in transit mixer for lead upto
10Kms having continuous agitated mixer,manufactured as per mix design of
specified grade for reinforced cement concrete work including puming of RMC from
transit mixer to site of laying, excluding the cost of centering ,shuttering, finishing
and reinforcement. including admixtures in recommended proportions as per IS
9103 to accelerate, retard setting of concrete , improve workability without imparing
strength and durability as per direction of Engineer - in - Charge.M-25 grade
reinforced cement concrete by using minimum Ordinary portland cement content of
380. Kg of cement per Cum of concrete .All works upto Plinth level.

Note:In All reinforced concrete works, Flyash is permitted to be added as per


relevant IS Codes.However the fly ash shall confirm to the I.S Code specifications.
Cum 4192.80 166.905 166.905 0.00 699799.28 699799.28 0.00
D.4 5.37A Providing and laying in position ready mixed concrete manufactured in fully
automatic batching plant and transported to site of work in transit mixer for lead upto
10Kms having continuous agitated mixer,manufactured as per mix design of
specified grade for reinforced cement concrete work including puming of RMC from
transit mixer to site of laying, excluding the cost of centering ,shuttering, finishing
and reinforcement. including admixtures in recommended proportions as per IS
9103 to accelerate, retard setting of concrete , improve workability without imparing
strength and durability as per direction of Engineer - in - Charge.M-25 grade
reinforced cement concrete by using minimum Ordinary portland cement content of
380. Kg of cement per Cum of concrete .All works above Plinth level.

Note:In All reinforced concrete works, Flyash is permitted to be added as per


relevant IS Codes.However the fly ash shall confirm to the I.S Code specifications. Cum 4192.80 1122.73 1105.00 17.73 4707382.34 4633044.00 74338.34
D.5 5.8 Reinforcement cement concrete work vertical and horizontal fins…. Cum 3928.75 5.52 4.55 0.97 21694.56 17875.81 3818.75
E FORM WORK
5.90 Centering and shuttering including strutting, propping etc and removal of form
E.1 5.9.2 ………..
Walls (any thickness) including attached pilasters, butteresses,plinth and string Sqm 180.40 744.54 744.54 0.00 134315.02 134315.02 0.00
E.2 5.9.3 course etc. floors, roofs, landings, balconies, and access platform
Suspended Sqm 187.35 4800.04 4800.04 0.00 899287.49 899287.49 0.00
E.3 5.9.5 Lintel, Beams,plinth beams, girder, bressumers and cantilivers Sqm 162.65 3500.00 3500.00 0.00 569275.00 569275.00 0.00
E.4 5.9.6 Columns, Pillars, piers, Abutments, posts, and struts. Sqm 238.40 1461.15 1461.15 0.00 348338.16 348338.16 0.00
E5 5.9.7 Stairs,( excluding landing) .. Sqm 204.00 64.00 64.00 0.00 13056.00 13056.00 0.00
F IRON & STEEL WORK
5.22 Reinforcement steel for RCC work including straightening, cutting, bending, placing
in position and binding all complete in all levels.(SAIL, TISCO, RINL)
F.1 5.22.A6 Thermo - Mechanically Treated bars. Kg 42.70 261842.68 261709.03 133.65 11180682.44 11174975.50 5706.94
F.1 9.48.2 Providing and fixing MS grill….Fixed to openings / wooden frames with rawl plugs /
screws / concrete blocks etc. Kg 64.40 300.00 300.00 0.00 19320.00 19320.00 0.00

Page 8
Quantity Amount in Rs.
DSR BOQ Rate
Sl No Description Unit Upto Last Since Last
Item No in Rs. Upto date Upto date Upto Last certificate Since Last Certificate
certificate Certificate
G PLASTERING
13.15.1 6 mm cement plaster in ceiling Sqm 62.15 605.00 605.00 0.00 37600.75 37600.75 0.00
14.4.1 12 mm cement plaster 1:4 mix Sqm 82.55 437.88 400.00 37.88 36146.99 33020.00 3126.99
H
1.21.2 Supply and fixing of PVC conduit
25 mm Mtr 47.00 3400.00 3400.00 0.00 159800.00 159800.00 0.00
Total Amount = A Rs. 22,033,513.16 Rs. 21,448,626.37 Rs. 584,886.79
Gross Amount (A)+Adding quoted (+22%) above DSR 2007 rates Rs. 26,880,886.06 Rs. 26,167,324.17 Rs. 713,561.88
Total RA Bill-No.8 & Final Bill Amount Say Rs. 713,562

Total Value of work done Rs. 26,880,886.06

Amount certified in this bill Rs. 713,562

Signature Contractor Signature IRCON

Page 9
Certified that:

1.Work billed has been executed satisfactorily as per contract specifications and site conditions.
2.Certified that no materials the cost of which has not been recovered have been issued to the Contractor except such as specifically
provided for in the agreement/Work order.
3. Quantity billed does not exceed the quantity executed at site.
4. No departmental tools and plant have been issued to the Contractor other than those for which hire charges have been recovered in the bill.
5.The measurements were made by me on …………………………. and are recorded at abstract of measurements in measurement
Book No 306 from page No ………… to …………
Date of Measuerement ……………..

HUSSAIN T M
Date:…………………………. Manager/Civil

Certified that:

1. The labour engaged by us for the work have been paid as per extant labour laws:
2. The measurements as billed are accepted;
3. Seinorage charges, Cess,etc., due to the Govt on the materials used for this work have been fully paid & no payment due to them is outstanding.

Date………………. Contractor

Certified that the foregoing claim is correct, that the necessary measurements were taken by Mr.Hussain T M Manager/civil
on 15.06.2011 and Technical check has done by me on…………………..and are recorded in MB at pages ……………..
of MB Booklet No 306 and Abstract of Measurements in Measurement book no 306 at page No …………………….and that
the work has been satisfactorily performed.

Date…………… Contractor Dy.Manager Deputy General Manager(Civil)

Chargeable to ………………………………………………And to be included in the account for…………………………………..


for ……………………………………………………………

To be paid at ………………………. In the presence of …………………………………by cheque on ……………………..Bank.

Jt. General Manager


RECOVERIES :
1 Retention Money Rs.

2 Income Tax @ Rs.

3 VAT tax Rs.

4 Any other recovery Rs.

Total Rs.

Memo of payments made Upto Date Upto last bill Since last bill

Total value of work done

Amount of previous payments from Last Certificate No.

Payment to be made now

DEDUCTIONS:

Received Rs.(……………………….)……………………………………………………………
………………………..as per details above on account of this work.

Passed for Rs……………………………………………………………………………………………………………………………………

Less Deduction Rs. ……………………………………………………………………………….

Nett Amount Payable Rs. ………………………………………………………………………..

Cheque No. ………………………. Date…………………

Rupees…………………………………………………………………………………………………………………………………………………

Paid in my presence

Signature and Designation of witnessing officer Signature of Contractor


with stamp
Page 10 of 12
ORIGINAL
TAX / VAT INVOICE
For Buyer
Valid for Input Tax

To, Tax InvoiceNo: Dt:

M/S IRCON INTERNATIONAL LIMITED,B'LORE. LOA No: IRCON/CIVIL/7004/MFC/HUBLI/10/100 Dt:31.12.2010


Name of Work :- Construction of Multi-Functional Complex at Hubli Your TIN : 29700137173
Railway Station Premises,
Our TIN: 29940825838

Service Tax Reg. No.:AAM CS09 80 LXM 001

Description of Goods Unit Qty Rate Amount


A. Base Cost
Rs. 679,583.00
=(( Gross Amount)/1.05)
Add:
1 Service Tax on 25% value of A @10% = B ill -NA-
o f B ely
ct at
2 Educational Cess on Service Tax @ 3% of B s tra per -NA-
Ab S e
p er ited Rs. 0.00
3 VAT @ 4% of A As bmm Rs. 27,183.00
Su
Rs. 0.00
4 Labour Cess @ 1% of A Rs. 6,796.00

TOTAL/GROSS AMOUNT RECEIVABLE Rs. 713,562.00

Note:- Service Tax Not Applicable

For Swarnaa Techno Construction Pvt Ltd


Annexure-I

ORIGINAL
TAX/VAT INVOICE
For Buyer
Valid for Input Tax

To, Tax InvoiceNo: Date:13/05/2011


M/S IRCON INTERNATIONAL LIMITED Work Order No: IRCON/SZ/MFCs/330/BLDG/02/Phase-1/6876 Date:01.02.2010
Name of Work :- Construction of Multi-Functional Complex at Alleppey Your TIN :
Railway Station Premises,Kerala State.
Our TIN:

Sl No Description of Goods Unit Qty Rate Amount Total Amount


Base Cost
A
=(( Gross Amount)/1.05) 100.0% Rs. 679583.00
Add:
Service Tax on 25% value of (A) bill
1
@10% 0.000% Rs. 0.00

Educational Cess on Service Tax @


2
3% 0.000% Rs. 0.00
0.00
3 VAT @ 4% of (A) 4% Rs. 27183.00
0.00
4 Labour Cess @ 1% of (A) 1% Rs. 6796.00

Total 5.000% Rs. 713562.00

Page 12 of 12