Professional Documents
Culture Documents
7 Design of Slab
Here,
Grade of concrete = M20
𝑓𝑐𝑘 = 20 N/mm2
𝑓𝑦 = 415 N/mm2
250
Shorter dimension of slab (𝑑𝑥) = 4000 + × 2 = 4250 mm
2
250
Longer dimension of slab (𝑑𝑦) = 8230 + × 2 = 8480 mm
2
𝑑𝑦 8480
So, 𝑑𝑥 = 4250 = 2.1 > 2, hence one-way slab.
Then,
Trial depth:
𝑑𝑥
From deflection criteria: Basic = 26
𝑑
1 𝑡ℎ
Width < (12)
27.981×106
𝑑 = √0.138×20×1000 = 100.687 𝑚𝑚 < 150 𝑚𝑚 (OK)
𝐴𝑠𝑡 ×𝑓𝑦
Then, 𝑀𝑢 = 0.87 × 𝑓𝑦 × 𝐴𝑠𝑡 × 𝑑 [1 − 𝑓 ]
𝑐𝑘 ×𝑏×𝑑
𝐴 ×415
or, 27.921 × 106 = 0.87 × 415 × 𝐴𝑠𝑡 × 130 [1 − 20×1000×130
𝑠𝑡
]
Using 8𝜙 𝑏𝑎𝑟𝑠,
82
𝜋× ×1000
4
c/c spacing = = 279.25
100
Now,
Modification factor:
“SEISMIC VULNERABILITY EVALUATION AND RETROFITTING OF EXISTING RCC STRUCTURE”
By [Sandesh, Shiyam, Shlok, Sonam, Subash, Swastik] | 130
568.74
𝑓𝑠 = 6.58 × 415 × 595.249
= 230 N/mm2
Modification factor from Fig. 4 of IS 456:2000 = 1.46
So,
𝑙
(𝑑 ) = 1.46 × 26 = 37.96
𝑚𝑜𝑑𝑖𝑓𝑖𝑒𝑑
𝑙 4250
(𝑑 ) = = 28.333
𝑎𝑐𝑡𝑢𝑎𝑙 150
𝑙 𝑙
∴ (𝑑 ) < (𝑑 ) [OK]
𝑎𝑐𝑡𝑢𝑎𝑙 𝑚𝑜𝑑𝑖𝑓𝑖𝑒𝑑
Here,
Grade of concrete = M20
𝑓𝑐𝑘 = 20 N/mm2
Grade of steel = Fe415
𝑙𝑦
< 2. Hence, two-way slab.
𝑙𝑥
Now,
0.068−0.064
Negative moment at continuous-edge (𝛼𝑥− ) = 0.064 + × (1.8 − 1.75) =
2−1.75
0.0648
Negative moment at continuous edge (𝛼𝑦− ) = 0.037
Positive moment at mid-span (𝛼𝑥+ ) = 0.0488
Positive moment at mid-span (𝛼𝑦+ ) = 0.028
Now,
Design moment calculation:
(a) Along-shorter span:
𝑀𝑥+ = 𝛼𝑥+ × 𝑊𝑢 × (𝑙𝑥 )2 = 3.535 kN-m
𝑀𝑥− = 𝛼𝑥− × 𝑊𝑢 × (𝑙𝑥 )2 = 4.6944 kN-m
(b) Along-longer span:
𝑀𝑦+ = 𝛼𝑦+ × 𝑊𝑢 × (𝑙𝑥 )2 = 2.028 kN-m
𝑀𝑦− = 𝛼𝑦− × 𝑊𝑢 × (𝑙𝑥 )2 = 2.68 kN-m
Then,
Maximum bending moment = 𝑀𝑥− = 4.69444 kN-m
Then,
𝑥
For Fe415: (𝑑 ) = 0.48
𝑙𝑖𝑚
4.6944×108
𝑑 = √0.138×20×1000 = 41.241 𝑚𝑚 < 𝑑𝑝𝑟𝑜𝑣 (𝑑𝑥, 𝑑𝑦). Hence, OK
Provide 8 𝜙 bars @ 270 mm c/c in both short and long span direction in the edge strip.
𝜏𝑐 = 0.28 N/mm2
For depth = 150 mm, 𝑘 = 1.3 (Clause 40.2.1.1 of IS 456:2000)
𝜏𝑐′ = 𝑘 × 𝜏𝑐 = 0.364 N/mm2
𝜏𝑣 < 𝜏𝑐 ′ (OK)
Check for deflection:
193.328
𝑝𝑡 = 1000×125 × 100 = 0.155% At support in short span direction.
𝑙
(𝑑 ) = 𝛼𝛽𝛾𝛿𝜆
𝑎𝑙𝑙𝑜𝑤
𝛼 = 20, 𝛽 = 1
79.372
𝑓𝑠 = 415 × × 0.58 = 98.82 N/mm2
193.328
𝛾 = 2, 𝛿 = 1, 𝜆 = 1
Now,
𝑙
(𝑑 ) = 2 × 20 = 40
𝑎𝑙𝑙𝑜𝑤𝑎𝑏𝑙𝑒
𝑙 2285
(𝑑 ) = = 18.28
𝑎𝑐𝑡𝑢𝑎𝑙 125
𝑙 𝑙
(𝑑 ) < (𝑑 ) [OK]
𝑎𝑙𝑙𝑜𝑤𝑎𝑏𝑙𝑒 𝑎𝑐𝑡𝑢𝑎𝑙
> 125 𝑚𝑚
Length of embedment available = 230 − clear cover
= 230 − 20 = 210 mm (OK)
𝑀1
(2) 𝐿𝑑 ≤ 1.3 + 𝐿0
𝑉
𝑦 𝑠𝑡 𝑓 𝐴
𝑀1 = 0.87 × 𝑓𝑦 × 𝐴𝑠𝑡 × 𝑑 [1 − 𝑏𝑑 𝑓 ]
𝑐𝑘
415×96.664
= 0.87 × 415 × 96.664 × 125 [1 − 1000×125×20]
= 4.292 kN-m
For 90° bend: 𝐿0 = 8 𝜙
𝑀1
𝐿𝑑 ≤ 1.3 + 𝐿0
𝑉
4.292×106
𝐿𝑑 ≤ 1.3 × 15.852×103 + 8 𝜙
47 𝜙 ≤ 415.98
𝜙 ≤ 8.85 mm (OK)
Hence, the development length is adequate and bond stress doesn't exceed the design
value.
[figure]
𝑓𝑦 = 415 N/mm2
𝑓𝑐𝑘 = 20 N/mm2
𝑙𝑦
< 2; Hence, two-way slab.
𝑙𝑥
𝑑𝑦 = 125 − 5 − 5 = 115 mm
Now,
𝐿𝑥 = 2.16 + 0.125 or 2.16 + 0.25
= 2.285 m
𝐿𝑦 = 4.125 m
(b) Calculating load on slabs:
Similar to previous:
Total factored load (𝑊𝑢 ) = 13.875 kN/m2
(c) Bending Moment coefficients:
𝐿𝑦 4.125
= 2.285 = 1.805 < 2
𝐿𝑥
Now,
0.065−0.06
Negative moment at continuous edge (𝛼𝑥− ) = × (1.805 − 1.75) = 0.0611
2−1.75
415×𝐴𝑠𝑡
or, 4.4263 × 106 = 0.87 × 415 × 𝐴𝑠𝑡 × 125 [1 − ]
1000×125×20
𝜏𝑐 = 0.28 N/mm2
𝑘 = 1.3
𝜏𝑐′ = 𝑘 × 𝜏𝑐 = 0.364 N/mm2 > 𝜏𝑣 (OK)
𝛼 = 20, 𝛽 = 1
193.328
𝑝𝑡 = = 0.154 %
1000×125
107.704
𝑓𝑠 = 0.58 × 415 × = 134 N/mm2
193.328
𝛾 = 2, 𝛿 = 1,
𝑙
So, ( ) = 2 × 20 = 40
𝑑 𝑎𝑙𝑙𝑜𝑤𝑎𝑏𝑙𝑒
𝑙 2285
( ) = = 18.28 (OK)
𝑑 𝑎𝑐𝑡𝑢𝑎𝑙 125
> 125 𝑚𝑚
Length of embedment available = 230 − clear cover
= 230 − 20 = 210 mm (OK)
(figure)
Hence,
Grade of concrete = M20
Grade of steel = Fe415
(1) Load calculation:
Superimposed load = 1.75 kN/m2 → Factored = 2.625 kN/m2
Finishing load = 1 kN/m2
150
Self-weight of slab = 25 kN/m3 × 1000 = 3.75 kN/m2
1 𝑡ℎ
(12) of clear span < width of support
So,
Effective span = Clear span between supports
𝐿𝑥 = 2.16 m
𝐿𝑦 = 24 m
Sample calculation:
Bending Moment = 4.6848 kN-m
𝑥
For Fe415; (𝑑 ) = 0.48
lim
4.6848×103
or, 𝑑 = √0.138×20×1000 = 41.199 mm
Now,
𝐴𝑠𝑡 𝑓𝑦
𝑀𝑢 = 0.87 × 𝑓𝑦 × 𝐴𝑠𝑡 × 𝑑 [1 − ]
𝑏𝑑 𝑓𝑐𝑘
𝜏𝑣 (𝑏𝑑𝑢 )
𝑉 0.01 N/mm2 0.0142 0.0136 N/mm2 0.01302 N/mm2
N/mm2
𝑝𝑡 0.0703% 0.14% 0.143% 0.141%
𝜏𝑐 0.28 N/mm2 0.28 N/mm2 0.28 N/mm2 0.28 N/mm2
( 𝜏𝑐 × 𝑘 ) 0.364 N/mm2 0.364 N/mm2 0.364 N/mm2 0.364 N/mm2
(𝑘 = 1.3) > 𝜏𝑣 > 𝜏𝑣 > 𝜏𝑣 > 𝜏𝑣
𝜏𝑐,𝑚𝑎𝑥
And, 𝜏𝑣 < (OK)
2
𝛼 = 26, 𝛽 = 1
86.306
𝛾: − 𝑓𝑠 = 0.58 × 415 × 182.783 = 113.65 N/mm2
𝑝𝑡 = 0.1406%
So, 𝛾 = 2, 𝛿 = 1, 𝜆 = 1
𝑃 = −1266.4061 kN
𝑉𝑦 = −24.7465
𝑉𝑥 = −0.0088 ≈ 0
𝑀𝑢𝑥 = 0
𝑀𝑢𝑦 = 0
Now, Soil bearing capacity 𝑞 = 150 kN/m2
Unit weight of soil (𝛾) = 17 𝑘𝑁/𝑚3
Angle of friction (𝜙) = 30°
Grade of Concrete = M20, Grade of steel = Fe415
Take 15% axial compression as self-weight,
Design load, 𝑃𝑢 = 1.15 × 𝑃 = 1.15 × 1266.4061 = 1387.36 kN
1387.36
Service load = = 924.906 kN
1.5
i) Depth of foundation,
150 1−sin 30° 2
𝐷= (1+sin 30° ) = 0.9803 ≈ 1
7
Now,
i) Size of footing,
𝑃 924.906
𝐴=𝑞= = 6.166 𝑚2
150
Now,
1.655
Pressure at critical section = 117.53 + × (127.53 − 117.53) = 123.54 kN/m2
2.75
Now,
Bending Moment at the face of column,
1.095 1 2
𝑀 = (123.54 × 1.095 × + 2 × 3.99 × 1.095 × 3 × 1.095) × 2.75 = 208.06 kN-m
2
Minimum edge depth = 150 mm (But in our case we provide 200 mm)
Now,
The BM in the direction will be same for square footing. However effective depth will be
different.
From IS 456:2000, Annex G, Clause 1.1.(b)
𝑓𝑦 ×𝐴𝑠𝑡
𝑀max = 0.87 𝑓𝑦 𝐴𝑠𝑡 × 𝑑 × (1 − 𝑓 ′ ×𝑑 )
𝑐𝑘 ×𝑏
415×𝐴
or, 208.06 × 106 = 0.87 × 415 × 𝐴𝑠𝑡 × 35 × (1 − 20×760×350
𝑠𝑡
)
= 1029.6 mm2
Assuming the resisting width as 𝑏′ = 500 𝑚𝑚 and 𝑑 = 694 𝑚𝑚, the reinforcement
required is calculated and is distributed over entire width.
Assuming 𝜙 = 12 mm
𝑊𝑖𝑑𝑡ℎ 𝑜𝑓 𝑠𝑒𝑐𝑡𝑖𝑜𝑛 2750
𝐴𝑟𝑒𝑎 𝑜𝑓 𝑠𝑡𝑒𝑒𝑙 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑑 1940.68
Spacing required = = 162
= 284.99 mm
𝐴𝑟𝑒𝑎 𝑜𝑓 𝑟𝑒𝑏𝑎𝑟 𝜋×
4
Now,
1
Nominal shear 𝑉𝑢 = (124.82 + 127.52) × 2 × 0.745 × 2.75 = 258.50 𝑘𝑁
Now,
Depth at critical section = ?
𝜙 745
𝑑𝑐𝑟𝑖𝑡𝑖𝑐𝑎𝑙 = (𝑑0 − 𝐶𝑙𝑒𝑎𝑟 𝑐𝑜𝑣𝑒𝑟 − 𝜙 − 2 ) + 1095 × (1424 − 200)
745
= (200 − 50 − 16 − 8) + 1095 × 224 = 278.401 mm
0 𝐷−𝑑 424−200
Now, tan 𝛽 = 𝐿−𝑜𝑓𝑓𝑠𝑒𝑡 = 1095−100 = 0.22
Now,
0.745 1
𝑀𝑢 = Moment at critical section = 2.75 × (124.82 × 0.745 × + 2 × 2.71 × 0.745 ×
2
2
0.745 × 3) = 35.140 × 2.75 = 96.63 kN-m
Now,
𝑀𝑢 96.63
𝑉𝑢 − tan 𝛽 258.5− ×0.22
𝑑𝑐𝑟𝑖𝑡𝑖𝑐𝑎𝑙 0.278
𝜏𝑣 = = = 519.67 kN/m2 = 0.511 N/mm2
𝑏×𝑑𝑐𝑟𝑖𝑡𝑖𝑐𝑎𝑙 1.260×0.278
Now,
2764.60
% of steel provided for one way shear = 1260×278.401 × 100% = 0.78%
𝑑 𝑑 𝑑 𝑑
Resisting perimeter = 2 × ((0.56 + 2 + 2 ) × ( 0.56 + 2 + 2 ))
Now,
𝜏𝑐 = 0.25 √𝑓𝑐𝑘 = 0.25 × √20 = 1.118 N/mm2
Since, 𝜏𝑣 = 𝐾 𝜏𝑐 = 1 × 1.118 N/mm2
Since, 𝜏max < 𝜏𝑣 . It is safe against two way shear.
Available length = 1595 − 𝐶𝑙𝑒𝑎𝑟 𝑐𝑜𝑣𝑒𝑟 𝑎𝑡 𝑏𝑎𝑠𝑒 𝑠𝑖𝑑𝑒 + 𝐶𝑙𝑒𝑎𝑟 𝑐𝑜𝑣𝑒𝑟 𝑎𝑡 𝑐𝑜𝑙𝑢𝑚𝑛 𝑠𝑖𝑑𝑒
= 1095 > 752, OK.
6.8.6 Check for Bearing Capacity,
𝐴 𝐴
Allowable bearing stress = 0.45 × 𝑓𝑐𝑘 × √(𝐴1 ) But, √𝐴1 ≥ 2.0
2 2
The project was completed abiding by the Earthquake Resistant Design codes (IS 1983
(Part-I):2016), Seismic Design of Buildings in Nepal (NBC 105:2020), FEMA 310 and
FEMA 273. Also, the guidelines provided by Department of Urban Development and
Building Construction (DUDBC) – Seismic Vulnerability Evaluation Guideline for Private
and Public Building (2011), and Seismic Retrofitting Guidelines of Buildings in Nepal
(2016) were followed for various practical implications.
With the knowledge from the available resources and valuable guidelines from our
supervisor Prof. Dr. Hari Darshan Shrestha sir, we performed the preliminary evaluation
followed by the detailed analysis and retrofitting of a structure. We hope that the report
meets the requirements of our respected supervisor sir, concerned teachers and fellow
students, who have taken an interest upon the subject matter.